All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.


Aug 2026

 For reference purposes the website carries here the following tenders:
 8Design, supply, installation and commissioning of aggregated 33KW capacity on grid rooftop SPV power plants Details
 8Design, supply, installation and commissioning of aggregated 182KW capacity on grid rooftop SPV power plants Details
 8Tender for construction of 2x40 MVA 132kV S/S Jagdishpur Details
 8Tender for construction of 2x40 MVA 132kV S/S Naseerpur Details
 8Tender for construction of 2x40 MVA 132kV S/S Details
 8Tender for construction of 2x63 MVA 132kV S/S Details
 8Tender for major repairing and overhauling of tunnel gate Details
 8Tender for construction of 01 Nos. 132kV GIS line bays (outdoor) at 400kV GIS substation Details
 8Tender for consultancy services to carry out due diligence and bid advisory to NML for coal Details
 8Tender for upgradation of connectivity of CEMS EQMS installed stations Details
 8Tender for biennial contract for maintenance of CW discharge canal Details
 8Tender for annual maintenance support services works for all types of civil works Details
 8Tender for construction of additional UG 11kV feeder Details
 8Tender for purchase and delivery of portland pozzolana cement confirming Details
 8Tender for PCC flooring with gravel spreading and drainage system in the switch yard Details
 8Tender for extension of control room at 132 kV S/Stn Details
 8Tender for construction of new SHB and allied civil work at 33 kV Sub Stn Details
 8Tender for augmentation of existing 34 nos 33 kV substations along Details
 8Tender for repair and maintenance of control room at 132/33 kV GSS Details
 8Tender for procurement of ACSR Zebra ACSR panther and ACSR moose conductor Details
 8Tender for treatment of slope stability measures on upstream side Details
 8Tender for construction of protection wall along the right bank of reservoir Details
 8Tender for procurement of consumable electrical items Details
 8Tender for construction of 33kV line and installation of 33/0.4kV, 1x1000KVA sub-station Details
 8Tender for construction of 220kV D/C transmission line Details
 8Design, manufacturing, testing at works and supply of 200 SQ MM, 132 kV single core XLPE cable Details
 8Tender for erection, testing and commissioning work of LILO of 132kV line Details
 8Tender for annual contract for the work of complete operation maintenance and housekeeping of coal handling plant Details
 8Tender for supply of spares for the 210MW BHEL make generator Details
 8Tender for requirement of various types of switches Details
 8Tender for annual contract routine breakdown and annual maintenance of HT switchgear HT motors DG sets hydrogen plant and generators and its auxiliaries Details
 8Tender for supply of valves (gate, globe and check valves) installed in turbine and boiler Details
 8Tender for annual contract for routine breakdown and capital maintenance of LT switchgear LT motors motorized Details
 8Tender for supply of GTC sleeves for various shaft of pumps Details
 8Tender for supply of spares of journal housing of HP-1103 bowl mills Details
 8Tender for miscellaneous balance works of plant and non plant Details
 8Tender for annual contract for repairing/reconditioning of components of pumps, drum sub assembly of clinker grinder and different types and sizes of valves Details
 8Tender for requirement of spares for premium transmission make gearbox installed Details
 8Tender for requirement for supply, erection, testing and commissioning of 1100 Ah and 425 Ah battery banks with dismantling and buyback of existing battery banks Details
 8Tender for annual contract for routine, breakdown maintenance work and providing assistance in operation of ash handling system Details
 8Tender for annual contract for routine breakdown and capital maintenance of 400kV switchyard power transformers Details
 8Tender for annual contract of routine, breakdown maintenance work of compressed air system Details
 8Tender for supply of battery charger suitable for 30 V 100AH battery Details
 8Tender for supply of cable end termination kit suitable for 70 sqmm Details
 8Tender for estimate of new 33/11 kV s/s Details
 8Tender for work for 33 kV bare conductor to covered Details
 8Tender for procurement & commissioning of battery bank/cells along with buy back of old batteries Details
 8Tender for procurement for miscellaneous items for IMD-I, 2X600MW, of SSTPP Details
 8Tender for procurement for motor operated 200 NB 8 gate valve with actuator for steam inverting line of coal mills Details
 8Tender for procurement for spares for ESP boiler Details
 8Tender for procurement for various size of gland packing rope for high pressure valve, packing rope for coal mill Details
 8Tender for excavation, transportation and spreading of excavated spoil on the dry ash surface Details
 8Tender for construction of additional hydrogen cylinder storage room Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects Kapadwanj Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects Nadiad Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects Ranasan Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects Narol Details
 8Tender for procurement of bag filter of dust collector of unit Details
 8Tender for procurement of hydrogen gas along with cylinder, testing and maintenance Details
 8Tender for biennial service contract for maintenance of electrical and C&I parts Details
 8Tender for rewinding and repairing of 4MW BFP motor Details
 8Tender for conversion of existing overhead portion to underground system of the 33 kV line Details
 8Tender for procurement of advanced diagnostic tool for predictive maintenance of various transmission lines Details
 8Tender for work of turfing in 132kV and 33kV switchyard at 132kV S/s Details
 8Tender for annual/capital maintenance of machine Details
 8Tender for procurement of miscellaneous consumable items Details
 8Tender for procurement of miscellaneous general consumable and safety items Details
 8Tender for construction of LT/HT line & transformers Details
 8Tender for capital overhaul of 210 MW LMW TG set and Re RLA study on turbine components Details
 8Tender for supply of 11kV AB switch with PT insulator Details
 8Tender for Bi-annual work contract for the work of dismantling, erection and winching of power transformers/ICTs Details
 8Tender for balanced work of supply, erection, testing and commissioning of additional 1 x 25MVA, 132/33 kV T/F along Details
 8Tender for miscellaneous civil works for 500kV substations and switchyards Details
 8Tender for work of annual maintenance contract for various make air compressor for 132/220kV CBs at various Details
 8Tender for annual maintenance contract for weed control work at 400kV, 220kV, 33kV switchyard Details
 8Tender for work of providing and fixing of high voltage busbar insulation tape, and heat shrinkable busbar insulating tubing at various Details
 8Tender for work of augmentation by replacement of 2x315 MVA, to 2X 500MVA 400/220kV ICT’s Details
 8Tender for work of annual contact for loading, unloading & transportation various S/Stn Details
 8Tender for repairs to miscellaneous work in switchyard Details
 8Tender for construction of RCC compound wall around the peripheri of sub-station Details
 8Tender for procurement of inhibited high grade type-A insulating oil for HVDC converter transformer & smoothing reactor Details
 8Tender for annual maintenance contract for attending emergency/ breakdown maintenance work of various 400kV lines Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Gotri Details
 8Tender for work for repairing of raincuts for bund protection Details
 8Tender for misc. civil work Details
 8Tender for supply of various size valves for boiler Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Godhra Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Dahod Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Kheralu Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Bodeli Details
 8Tender for supply of various consumables, measuring instruments, tools tackles, CPVC and fasteners items Details
 8Tender for work of overhauling of ESP pass Details
 8Tender for erection, testing & commissioning work of 66kV equipments Details
 8Tender for supply of tubes, end plates & baffles and work Details
 8Tender for erection, testing & commissioning work of 66kV equipments, structures, control wiring, yard lighting Details
 8Tender for supply of tarpaulin sheet for covering of coal Details
 8Tender for erection, testing & commissioning work of 66kV equipments, structures Details
 8Tender for erection, testing & commissioning work of 66kV equipments, structures, control wiring, yard lighting Details
 8Tender for supply of riser duct liners of beater wheel mill Details
 8Tender for work of routine, preventive, overhauling and breakdown maintenance of Air conditioning systems Details
 8Tender for Bi-annual work contract of job work related to operation & related to maintenance works Details
 8Tender for supply of fire system pumps Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8States' Revenue From Mining, Coal Sectors Surged Significantly Since 2014-15: Govt Data Details
 
8Documents show Modi government pushed coal reforms despite internal criticism, benefiting major mining firms Details
 
8Coal India, L&T, NEO Performance among 20 bidders under Rs 7,280-crore rare earth magnet scheme: MHI Details
 
8Overhaul India's power sector strategy, shift to decentralised systems, insists policy analyst Details
 
8Naidu pushes pumped storage, solar power to cut electricity costs in Andhra Pradesh Details
 
8Vedanta Power, Adani, RIL: Why India's power giants are turning to nuclear Details
 
8Hydrogen Technology Marks India’s Transition to Global Power Details
 
8PFC Consulting Invites Bids for J&K Transmission Infrastructure Details
 
8Kalpataru Projects International bags new orders worth Rs 3526 crore Details
 
8India: Secondary steel sector finds commercially viable pathway to decarbonisation through renewable power Details
 
8Which is the Largest Thermal Power Station in India Details
 
8India’s Decade of Transition: Building Global Power Through Strategic Partnership Details
 
8From Air India dope test to Solar Mission Aditya-L1, what’s the latest global headlines about India Details
 
8India’s Solar Manufacturing Ambitions: The Role of AI Details
 
8CEA Cyber Security Regulations 2026 Set New Power Sector Protection Standards Details
 
8India Embraces Cluster-Based Manufacturing to Become a Global Powerhouse Details
 
8Anti-Dumping as Industrial Policy: India's Solar Ascent Details
 
8Vedanta Power, Adani, RIL: Why India's power giants are turning to nuclear Details
 
8How India Energy Stack aims to turn power sector digital — like UPI for electricity Details
 
8Solar Industries Shares Correct After Hitting All-Time Highs Details
 
8Assam: Solar power push for govt health facilities in Udalguri district Details
 
8India Solar Capacity Hits 50 GW Record, Faces Price Risks Details
 
8Inside Rajasthan’s Sustainable Hospitality: Solar Power, Water Recycling And Local Sourcing Details
 
8Defence sector stocks today, August 14: Unimech Aerospace jumps 5%, Paras Defence gains 3.5%; MTAR, Solar Industries fall Details
 
You can also click on Newsclips for more Details
 For reference purposes the website carries here the following tenders:
8Tender for work of new 33 kV line from 132/33 kV EHV substation Details
8Tender for construction of 33/11 kV S/s Details
8Tender for procurement of spares for pneumatic actuators and power cylinders Details
8Tender for procurement of spares for boiler super heater and reheater control and block valve actuator Details
8Tender for availing services of design and development, implementation, demonstration and testing work Details
8Tender for procurement of spares for APH model 27.5VITM 2000 72 degree PA of 2X250MW Details
8Tender for procurement of bearings for BFP drive turbine Details
8Tender for supply, installation and commissioning of breakers for LT feeders Details
8Tender for replacement of Stg-1 LT switchgears Details
8Tender for procurement of HT motor Details
8Tender for chain link fencing work in phase-II Details
8Tender for supply of ventilation system for 2X660 MW Details
8Tender for supply of 220 kV circuit breaker Details
8Tender for supply, installation and commissioning of tower/floor mount split air conditioners Details
8Tender for procurement of 01 no. battery operated self-articulated boom lift Details
8Tender for dismantling of CTs, CVTs, LA, CVTs, and CTs/CVTs junction boxes Details
8Tender for BMC maintenance of water supply & drainage systems Details
8Tender for complete replacement of CW hot basin pipeline of cooling towers along Details
8Tender for assistance in maintenance of 6.6 kV and 440 V indoor switchgear Details
8Tender for manufacture, testing, supply & delivery of 11kV RVTs Details
8Tender for extension of switch house of 66 kV sub-station Details
8Tender for renewal and replacement of damaged wood door shutters and chowkats of various Details
8Tender for seat replacement of HP bypass valves Details
8Tender for repair of old U-fencing at 220kV s/s Details
8Tender for strengthening of existing pile type foundation by open pit foundation for 220kV transmission line Details
8Tender for repair of old U-fencing and at 132kV s/s Details
8Tender for extension of switch house at 66 kV S/Stn Details
8Tender for procurement of 20 position test benches Details
8Design, manufacturing supply and commissioning of latest technology LT ACB 415 volt AC circuit breakers Details
8Tender for new 66 kV line Details
8Tender for procurement of surface air coolers for the 37.5 MW hydro electric generator stator winding Details
8Tender for upgradation of 33kV substation Details
8Design, fabrication, supply, installation, testing, commissioning with remote monitoring system (RMS) of total 453 kW grid connected solar PV power plant Details
8Tender for procurement of battery bank and float cum boost battery charger for 220V and 48V DC systems Details
8Tender for procurement of EHV grade transformer oil for different transmission Details
8Tender for work of laying 40 mm thick gravel above the ground in 400kV, 33kV switchyard Details
8Tender for underwater inspection of the water conductor system of 4X30 MW Khodri hydroelectric project Details
8Tender for underwater inspection of the water conductor system of 4X60 MW chibro hydroelectric project Details
8Tender for construction of LT line for street light and shifting of HT/ LT line including De- centralized material Details
8Tender for diversion of 132kV line Details
8Tender for supply of various instruments Details
8Tender for work of ash lifting of ESP all 04 pass for boiler Details
8Tender for rate contract for work of rewinding and repairing of various rating of LT motor, submersible pump and various Details
8Tender for procurement of various type of control transformers Details
8Tender for supply of plumbing, electrical and carpentry material for maintenance Details
8Tender for supply of ESP spares Details
8Tender for supply of 3-D anti wear SS corrugated double expansion bellows Details
8Tender for empanelment of electrical contractors for supply installation, testing commissioning of 33 kV lines, 33/ 11 kV power transformers and all other allied material required Details
8Tender for strengthening/laying of earth mat at 132 kV substation Details
8Tender for day to day electrical defect attending work, preventive, breakdown maintenance & overhauling work at ESP Details
8Tender for construction of new borewell at 132 kV GSS Details
8Tender for const. of 01 No. 132 kV solar bay Details
8Tender for civil work for augmentation of 31.50 MVA transformer at 132 kV GSS Details
8Tender for const. of civil foundation for 02 Nos 33 kV feeder bay Details
8Tender for augmentation works of 132/33 kV 50 MVA transformer at 220 kV GSS Details
8Tender for construction of civil foundation and other civil works for 20/25 MVA Tr III At 132 kV GSS Details
8Tender for construction of civil foundation and other misc civil works in yard Details
8Tender for supply of spares of level gauge and complete level gauge assembly Details
8Tender for supply, installation and commissioning of 75-inch video wall panels and associated accessories Details
8Tender for procurement of spares for LT switchgear and CHP system Details
8Tender for procurement of voltage transformers (PT) and current transformers (CT) for river water system and construction supply panels Details
8Tender for supply of coal concentrator for boiler, 2X600 MW Details
8Tender for supply, installation and commissioning of flame scanners with accessories Details
8Tender for supply and commissioning of complete electrical wire rope hoist Details
8Tender for work contract for rebabbitting and machining of white metal bearings turbine bearing Details
8Tender for annual contract for routine, breakdown and capital maintenance works of protection system, AVR, excitation system and DC system Details
8Tender for annual contract for routine, breakdown and capital maintenance works of LT switchgear, LT motors and electrical operated motorized valve, dampers and soot blowers etc. Details
8Tender for annual maintenance contract for routine, breakdown and capital maintenance of C&I equipments and instruments Details
8Tender for annual work contract for routine and breakdown Mtc. of turbine, heat exchangers, TDBFP turbine and their auxiliaries Details
8Tender for annual work contract for the work of condition monitoring and vibration analysis and dynamic balancing of ID/FD/PA fans installed Details
8Tender for external painting along with associated civil works Details
8Tender for annual contract for the work of services for high-pressure jet cleaning for removal of boiler clinker using straight imported nozzle and UHP pump Details
8Tender for annual work contract for routine preventive and breakdown mtc works of water treatment plant cooling water system cooling towers and associated system Details
8Tender for complete overhauling, assembly, testing, and supply of repair kits for two stage liquid ring vacuum pump Details
8Tender for fabrication work of weather protective shed/canopy on foundations of boiler side HT & LT motors Details
8Tender for procurement of 10000 nos. of LT three phase 20-100 Amps static meters Details
8Tender for repair and maintenance of front side of 132/33 kV grid sub station Details
8Tender for carrying routine patrolling, preventive/breakdown maintenance of 220kV SC transmission line Details
8Tender for procurement of 33kV HT XLPE cable 400 sqmm armored Details
8Tender for procurement of 20.0 KL liquid ammonia Details
8Tender for renovation work for 220 kV and 132 kV bays of 160MVA siemens auto tranaformer and 25MVA reserve transformer Details
8Tender for supply of various size H/S jointing kit used for 33/11 kV S/S Details
8Tender for carrying out the shift operation works by assisting the AE JE shift in boiler turbine and generator Details
8Tender for Bi-annual transportation of various EHV equipment's/ it’s allied materials Details
8Tender for work of providing & fixing of additional jumpers on tension towers of the various lines Details
8Tender for work of bi-year rate contract for the maintenance of 400/220/132/110 kV EHV lines Details
8Tender for various regular preventative maintenance / emergency and breakdown works of various 220kV & 100kV substations Details
8Tender for annual maintenance contract (AMC) for overhauling, repairing & servicing of 33 kV & 11kV CGL make circuit breakers at various Details
8Tender for rate contract for the work of overhauling and servicing of 420 kV, 245 kV & 145 kV circuit breaker Details
8Tender for procurement of indoor DC bushings for smoothing reactor (500kv,360mH) Details
8Tender for supply, installation, testing & commissioning of 250kVA diesel generator (DG) set Details
8Tender for work of providing and fixing of additional 33kV PT set along with bussection isolator Details
8Tender for work of AMC for work of refilling / reconditioning and servicing of fire extinguishers of various types and capacity installed Details
8Tender for ARC of work of erection, testing & commissioning of 66kV feeder bay, transformer bay Details
8Tender for construction of store shed platform with ramp Details
8Tender for work of comprehensive operation & maintenance for 5 years of a 1 MW grid connected solar photovoltaic power plant Details
8Tender for comprehensive running maintenance of bore well pump-motor sets Details
8Tender for work of attending routine, shut down & breakdown defects & preventive maintenance of electrical auxiliaries Details
8Tender for annual work contract for work of online routine, preventive shut down & breakdown maintenance of beater wheel mills and its associated equipment’s of 1X75MW boiler Details
8Tender for work of dismantling replacement / repairing of PF pipe, orifice & PF bend of coal mills Details
8Tender for supply and installation of an energy efficient lubricated rotary screw air compressor Details
8Tender for work of preventive maintenance, shutdown & emergency maintenanc of IAC/SAC compressor, air washery fan/pump motor, ACW/FCW motor Details
8Tender for work of comprehensive base flow study Details
8Tender for requirement of various size and types of conveyor belt rollers Details
You can also click on Tenders for more
8Juniper Green Energy Commissions 167 MW Wind Capacity Details
8Motilal Oswal commits Rs 1,500 crore investment in Inox Clean Energy platform Details
8Majority of professionals expect renewables to pip coal-based power production by 2035: Survey Details
8Hinduja Group commits INR 2,500 crore to renewables and new mobility solutions in Tamil Nadu Details
8Better Economics: Rental power solutions, applications and cost benefits Details
8India Drives Global Surge in Planned Coal Mining Capacity, Defying Renewable Energy Transition Details
8India nearly doubles planned coal mining capacity Details
8India’s Floating Solar Push: Beyond Subsidies and Incentives Details
8India's Manufacturing Mission 2047: NITI Aayog Names Chemicals, Textiles, Telecom and Solar PV as Key Sectors Details
8Chemicals, textiles, telecom, solar PV sector key to India's global manufacturing push: NITI Aayog Details
8India Solar Installations to Hit Record 50 GW in 2026 Details
8C&I Solar Plus Storage Success: Maharashtra Facility Case Study Details
8Solex Energy lists on BSE, targets 10 GW module capacity by 2030 Details
8Oswal Pumps secures Rs 78 crore rooftop solar project in Bihar Details
8Nagaland seeks investment, joint ventures to address power generation deficit Details
8MSMEs in India's secondary steel sector can reduce their power bills by up to 34 pc per year: Report Details
8Ratul Puri: Beyond Low-Cost Power to Clean Energy Reliability Details
8Chandigarh power privatisation: 9,257 billing complaints, Centre skips bill comparison Details
8Decarbonising Industries: Government mandates accelerate the implementation of energy efficiency initiatives Details
8Amol Babulal Taori Appointed as POWERGRID Director (Finance) Details
8Cosmic Solar EPC secures Rs 574 crore solar orders Details
8Renewable Energy Could Cut Secondary Steel MSMEs’ Power Costs By 34%: Report Details
8Karnataka opens power transmission sector for private companies through BOOT model Details
8Bangladesh faces 10-hour power cuts:Govt orders markets to shut by 8pm, seeks increased diesel supply from India amid crisis Details
8Parliament passes Mines and Minerals Amendment Bill Details
8Coal generation falls for first time since 1970s Details
8Bangladesh Battles Worst Power Crisis, Turns To India For Help Details
8Gujarat Inject Kerala Ltd's Renewable Energy Bet Puts It on Investors' Radar; Market Sees Up to 30% Upside Details
You can also click on Newsclips for more Details
8OPTCL's Rs 138.15 crore Panikoili package leaves the cost-opening date to be defined later A 2x200 MVA 220/132 kV and 2x100 MVA 220/33 kV substation is bundled with a 220 kV LILO off the New Duburi-Paradeep line and a 132 kV LILO off Jajpur Road-Kendrapada, in one turnkey contract. Route lengths, bay counts, shutdown windows and interface milestones are not quantified anywhere in the tender header. PBG quantum, LD ceiling, escalation and arbitration sit in the contract sections. A reverse-auction annexure applies after two-stage qualification.

8NTPC invites domestic competitive bids for work its own scope assigns to CSIR-SERC by name Tender fee, bid security, SD, LD, PBG and defect liability are all inapplicable, and 100% of the preliminary-inspection fee is payable in advance without a bank guarantee. No contract agreement will be executed because an NTPC-CSIR-SERC MOU already exists. SCC item 11 puts PPE on the contractor, Section V puts it on NTPC, and GCC 4.2 ranks SCC above the technical specification. Four extension records state no replacement dates.

8GETCO said the Tharad date would not be extended under any circumstances, then extended it three times Online closing moved 66 days and physical EMD 68. The rating reference went from 20°C to 50°C ambient, ride-through at 0.15 pu fell from five seconds to 0.3 second, and the guaranteed loss ceiling rose from below 1% to below 1.5%. Requests for an interest-free advance, 90% dispatch payment and a 5% LD cap were answered "as per tender terms & conditions" on a Rs 244.54 crore estimate.

8NTPC's Barauni fly ash package supplied the geotechnical data it had said would come later, and named the foundation Amendment 02 attached Annexure-P and rewrote civil clause 1.02.00 to open/pile foundations with stone-column ground improvement. Amendment 01 deleted the scheme and general layout drawings in favour of Part-E and made construction power the bidder's arrangement. Railway-track installation is excluded while simultaneous five-wagon loading across three silos remains contractual. Delay LD is Rs 6.09 lakh per day, capped at 5%.

8KSEBL's Rs 24.72 lakh cable job carries three years of defects liability on a six-month execution period Two corrigenda moved submission 17 days and opening 18, the second issued on the day the revised opening was due, neither stating a reason. Percentage rates hold even where quantities vary considerably after detailed survey, and unlisted but necessary items are deemed included. The NIT prints reference 2026-276 against 2026-27 everywhere else; the fee reads Rs 5,900 in the NIT and Rs 6,667 on the portal.

8GETCO's Rs 245.27 crore Sagapara STATCOM offers a 10% advance at MCLR against a 110% bank guarantee Taking it drops progressive supply payment from 80% to 70%. GCC 38 describes a 10% execution guarantee followed by a separate 10% warranty guarantee, while SCC 19 describes a single 10% security-cum-performance guarantee held two years and one month past charging. Third-party radio-interference complaints run five years beyond the guarantee period. Prolongation cost and geopolitical adjustment were both declined. Two extensions, 53 days.

8NEEPCO's fifth corrigendum is dated 21 July and supersedes everything; the recorded bid closing is 7 July C5 overwrites all previous buyer-added conditions while the tender-detail record retains the original date. ATC 19.5 makes necessary deviations non-compensable, TOR 5.0 pays for change of scope at mutually accepted rates, and the GeM 25% option requires consent, with no threshold separating the three. Payment reads 45 days on GeM and 30 days in ATC 19.2(e). One scored band prints "≥ 60000 Cum/month < 60000 Cum/month".

8GSECL rules that where ET-6250 duplicates itself, the most stringent clause applies to all bidders The same corrigendum inserts 4.0 sq.mm-or-higher CT cabling while amending clause 7.03.01(b) from 4 sq.mm to 2.5 sq.mm per lead. Busbar protection moves from 16 bays with four zones to 12 existing plus six future bays with two zones, and four protection groups leave the minimum function list without a stated destination. Supply delivery extends four months to six. The NIT prints GST of Rs 27,000 on a Rs 15,000 fee totalling Rs 17,700.

8KSEBL defers the low-voltage switchgear SLD to detailed engineering and wants a lump-sum price now BOQ quantities do not cap the physical obligation and additional quantities required for completion carry no extra payment. Hybrid GIS at 245 kV was refused as equivalent experience and a seven-year alternative to the ten-year operating history was refused; a panel-layout change to 11,060 mm was accepted, a 0.5 VA burden against the specified 10 VA was not. Corrigendum 5 added 21 days to a Rs 106.64 crore package.

8RPCL repriced its coal from G8 grade to GCV 5050 kcal/kg ARB after bidders attacked the label Addendum 2 substituted the ARB figure in clauses 9.1, 9.12, 23.15, the price schedule and the mine declaration. The referee-sample objection window fell from 14 days to seven. Quantity is expressly non-firm and reducible without compensation, while delay costs 2.5% of landed cost per 30 days to a 10% ceiling. Post-award mine substitution is permitted only if the applicable rate does not exceed the quoted rate.

8UJVNL deleted its comparable-contract value thresholds and set a Rs 260 crore turnover test in their place That applies where a bidder relies on manufacturer credentials, against Rs 77.88 crore for one qualifying alone, on a Rs 259.60 crore estimate. Permitted manufacturers rose from one to two, named makes gave way to functional requirements, and the switchyard was corrected from GIS to AIS after issue. Sixteen extensions moved the deadline 162 days; Corrigendum 04 sets technical opening on 28 February against submission on 23 March.

8UJVNL's Rs 87.90 crore Tankul notice moved its dates five times and specifies nothing else EMD, PBG, bid validity, security validity, qualification thresholds, LD, escalation, variation valuation and geological-risk allocation are all absent, routed to the state portal. Closing has moved from 10 July to 17 August, 38 days, across three corrigenda and two date-extension notices. The scope — trench weir, intake, desilting tank, feeder pipe, tunnel, surge shaft, powerhouse and hydro-mechanical works — is unchanged throughout.

8UJVNL prices Kulhal's performance security by how the bidder qualifies: 10% alone, 15% on manufacturer credentials A further 5% can attach to the value of manufacturer-authorised equipment. The 10% advances carry PNB three-year MCLR plus 150 bps compounded monthly against 115% security. Escalation activates only beyond 2%, is capped at 20%, excludes foreign exchange, and stops rising for contractor-attributable delay while downward adjustment continues. Four corrigenda moved closing 53 days without reopening any of it.

8NHPC raised experience, turnover, working capital and bid capacity by about 2.1% each after issuing Link-3 Corrigendum 8 took bid capacity to Rs 2,301.20 crore and turnover to Rs 813 crore, deleted the trash-rack cleaning machine requirement and relaxed TBM availability by one month inside an unchanged 36-month completion. NHPC could not confirm grid power availability, and roads to quarry and disposal areas stay with the contractor. Seven extensions moved closing 80 days, with a 42-page technical corrigendum landing on 11 August.

8NHPC cut the Salal variation markup from 20% to 18.63% and replaced the BOQ while the portal estimate held at Rs 267.94 crore Employer-supplied materials and rented equipment attract 8.63%. Corrigendum 1 rewrote insurance across definitions, claims reporting, proceeds, deductibles and reinstatement, preserving employer recovery for contractor negligence regardless of any payout. Equipment data sheets still carry a "Lot-1 Package: Sawalkot H.E. Project" heading. Closing moved 88 days; the reverse auction triggers only above 105% of the estimate.

8KPCL's Rs 192.32 crore coal tender sits behind a portal page reading "Setting up of Computer Lab" The same page names Karnataka State Electronics Development Corporation as procuring entity and 90-day validity against the tender's 180. Clause 23.12 applied both 18% and 5% GST to railway freight before correction, and DC-1 was rewritten from G8 grade to GCV 5050 kcal/kg ARB. The referee window fell to seven days. Imported-coal, group-company, JV and logistics-only credentials were all refused. Details
8Revenue from operations increased to Rs 3.20 crore from Rs 3.06 crore in Q1 FY27, while total income declined to Rs 3.59 crore from Rs 3.77 crore.
8Profit before tax fell to Rs 0.50 crore from Rs 0.90 crore and profit after tax fell to Rs 0.44 crore from Rs 0.61 crore; the prior-year comparison included an exceptional item. Details
8Daily output reached 1,062.70 MU against a 979.40 MU programme across 60,007.23 MW of monitored capacity.
8The Southern Region beat its year-to-date programme by 2,634.12 MU, while the Northern, Western and Eastern regions remained below their cumulative programmes. Details
8A fresh tender was scheduled to open on 21 August after the High Court set aside the earlier procurement, returning the metering programme to the bidding stage.
8PSERC granted the utility six weeks in Petition 46/2024 but did not close the show-cause proceeding or record completed deployment of any meters. Details
8KSERC found insufficient intermediary economy for an additional distribution licensee where the Perumbavoor park had one identified consumer, Kaynes.
8The Commission rejected KPUPL's application and directed incumbent KSEBL to provide 24-hour supply, leaving the proposed private distribution arrangement without approval. Details
8BRPL claimed 31.64%, BYPL 24.02% and TPDDL 23.71% after power-purchase costs rose against the base used in the prevailing tariff order.
8DERC relaxed the 10% billing-cycle cap by allowing additional FPPAS of 7.94%, 7.43% and 8.50%, respectively, while leaving all other tariff provisions in force. Details
8POWERGRID has commissioned three 1,500 MVA ICTs, two 500 MVA ICTs and associated lines and bays at Bikaner-III, including five renewable-energy bays covering 1,467 MW.
8Two connected projects totalling 490 MW were expected to declare commercial operation on 22 August 2026, while land and substation dependencies hold back the Neemrana link. Details
8Approved interconnection work at Ishanagar was assessed to reduce Northern Region import ATC and TTC by 1,900 MW, while Fatehpur-Sasaram work carried another 900 MW effect.
8The figures are prospective system assessments rather than realised curtailment, but they narrow the transfer envelope when the approved outages are taken. Details
8The Northern Region agenda linked repeated conductor failures on the Ballabgarh-Agra line to ageing hardware and proposed reconductoring the circuit.
8The line's cited loading makes renewal consequential, but the source records no completed tender, award or replacement work. Details
8Since the Koteshwar-Rishikesh double-circuit line was energised in December 2025, the 315 MVA and 240 MVA ICTs at Rishikesh have overloaded under changing hydro conditions.
8The grid operator has opened intra-state lines and run substations radially; equipment lead times may delay the additional 315 MVA ICT and its bays beyond the Kumbh requirement. Details
8The daily average was 49.993 Hz, yet frequency was below 49.90 Hz for 8.252% of the day and above 50.05 Hz for 17.998%.
8The maximum reached 50.254 Hz at 13:02 and the minimum fell to 49.718 Hz at 19:24:10, showing why a daily average can conceal control excursions. Details
8Gas and liquid-fuel plants had 11,232.53 MW unavailable out of 20,122.42 MW, an outage rate of 55.82%, leaving 8,889.89 MW online.
8Coal plants had 35,658.51 MW unavailable out of 224,157.51 MW, or 15.91%, while maximum net output reached 172,510.36 MW. Details
8The evening requirement was 84,059 MW, while daily energy shortage was 8.13 MU across a region that consumed about 1,899 MU.
8At 22:25 the maximum assessed requirement reached 86,746 MW with a 1,448 MW shortage; Punjab and Uttarakhand reported large state-level gaps. Details
8The auditors recorded negative net worth of Rs 2.83 crore and said the resulting material uncertainty cast significant doubt on the company's ability to continue as a going concern.
8They also said Rs 13.46 lakh of June-quarter interest had not been provided, understating the loss and liabilities, while cumulative unprovided interest had reached Rs 80.96 lakh. Details
8Consolidated profit declined from Rs 2.58 crore to Rs 2.11 crore, while the limited-review report carried multiple qualifications affecting receivables, advances and legacy claims.
8The qualified amounts included a Rs 90.83 crore arbitration claim, Rs 14.94 crore of advance lacking adequate audit evidence and Rs 74.55 crore of goodwill without recorded impairment. Details
8Profit after tax increased to Rs 52.55 crore in the June quarter from Rs 31.61 crore a year earlier, while total income was almost flat at Rs 340.57 crore.
8The executable backlog fell to Rs 1,545.4 crore from Rs 2,635.3 crore after the termination of two flue-gas-desulphurisation contracts worth Rs 774.9 crore. Details
COAL-GASIFICATION FUNDING REOPENED BEFORE ANY NEW PROJECT WON SUPPORT

8Coal gasification Category III enters a separate competition for the same remaining scheme pool

TWO KARNATAKA SUBSTATIONS ENTER LICENCE SCRUTINY BEFORE DELIVERY CLOCKS START

8Karnataka's proposed Mekhali substation enters licence scrutiny before a 24-month delivery clock can start
8Hampapura's proposed 2x500 MVA GIS project faces the same licence gate in a separate case Details
CURRENT OPERATING ACCOUNTS EXPOSED SCHEDULE, SETTLEMENT AND AVAILABILITY GAPS

8Purulia pumped storage generated 2.58 MU after consuming 3.06 MU in pumping - the daily record proves cycling, not round-trip efficiency
8Northeastern supply fell 45 MW short at a 4,151 MW maximum requirement - the regional report records the gap without assigning a cause
8Motihari slipped outside its voltage band for 0.62% of the day as Godda improved by 4.23 percentage points
8PVVNL planned two-to-four-hour interruptions across named Meerut urban feeders - consumers received a time window, not a restoration guarantee
8Andhra Pradesh recorded 11.092 MU of free agricultural electricity sales in Bapatla - delivery data alone cannot prove subsidy payment or service quality
8Two 400 kV Ramagundam-Telangana STPP circuits remained on the southern outage register after first tripping in March 2023
8A 132 kV Andhra circuit tripped on an R-N fault - the report gave no restoration time or consumer-impact figure Details
SETTLEMENTS AND DISPATCH DATA PUT A PRICE ON DAILY GRID BALANCING

8Northern deviation settlement created a Rs 141.91 crore WR-NR payable inside a larger two-way weekly account
8Northern reactive-energy charges left receivables above payables for the week
8July SCED produced almost twice as much decrement as increment in the Northern Region

PROTECTION AND CONNECTION CHANGES MOVE FORWARD, BUT DELIVERY STILL DEPENDS ON FIELD WORK

8Northern under-frequency relief must be recalibrated feeder by feeder
8Ladakh's Taru and Phey renewable projects reach the grid-connection gate before a December target

THERMAL OUTAGES AND REVIVALS CHANGED AVAILABLE CAPACITY UNIT BY UNIT

8Bhadadri Unit 3 lost 80 MW of available rating late on 13 August
8Neyveli Unit 3 returned after a four-hour 25-minute outage
8Vallur Unit 4's 800 MW outage remained unresolved in the cited daily report
8Two southern thermal-unit revivals restored 710 MW of rating during the day

GENERATION, TRANSFER AND HYDRO DATA SHOWED DIFFERENT OPERATING CONSTRAINTS

8SCUC called 5,646 MWh more upward than downward energy on 13 August
8Coal generation beat programme by 409.85 MU on the day and 9,906.90 MU year to date
8Tripura spent almost the entire day beyond reported transfer capability
8Odisha's hydro fleet averaged 742.8 MW while reservoir and outage rows explain the operating boundary Details
LARGE CAPACITY PROPOSALS REACHED APPRAISAL; NONE CROSSED THE APPROVAL GATE

8ONGC's 65-well Gujarat amendment enters appraisal across 18 mining-lease blocks
8ONGC's separate 12-well Cambay proposal also reaches the EAC agenda
8BPCL's Mumbai refinery seeks to expand CDU-4 from 6 to 10 MMTPA
8Mirzapur's proposed distillery doubling begins at the scoping gate
8TruAlt's 400 KLPD multi-feedstock ethanol project awaits environmental-clearance appraisal
8Sentini's 300 KLPD distillery expansion remains conditional on appraisal
8BPCL's 9 MMTPA Nellore refinery reaches fresh-EC appraisal, not construction
8Atharv seeks linked sugar, distillery and 35 MW cogeneration expansion
8Koderma's proposed 100,000 TPA coal-tar plant enters environmental review
8Karimganj's distillery seeks to double to 600 KLPD with 6 MW cogeneration Details
RESERVED PUNJAB ORDERS LEAVE CONNECTIONS AND RULE CHANGES INOPERATIVE

8Sunny Enclave's permanent power connection awaits PSERC's reserved order
8Preet City's 100.96-acre development also remains without a final connection ruling
8Punjab's proposed FPPAS amendment remains inoperative until PSERC issues its reserved order
8Punjab's existing rooftop-solar portal duties remain in force while PSERC decides PSPCL's proposed amendment

JHARKHAND PROCEEDINGS FIXED PLEADING AND NOTICE DEADLINES WITHOUT MERITS RELIEF

8JSERC gives JREDA a final chance to answer Rungta Mines Case 01/2026 before the 29 September hearing
8JREDA's unanswered pleading keeps Rungta Mines Case 02/2026 open until 29 September
8Rungta Mines Case 04/2026 advances only because JREDA gets one last opportunity to respond
8JSERC keeps Rungta Mines Case 05/2026 alive while JREDA gets a final pleading opportunity
8Rungta Mines Case 06/2026 reaches the 29 September gate without a tariff or monetary ruling
8DVC HT consumers' review moves to final hearing after the remaining document window closes
8DVC's Case 23/2026 against Jharkhand HT consumers reaches final hearing without a merits decision
8Inland Power's review receives notice and a 15 September hearing Details
CESC'S RENEWABLE, ACQUISITION AND CASH-RETURN EVENTS REMAIN AT DIFFERENT LIFECYCLE STAGES

8CESC put 435 MWp of solar into operation - but disclosed no generation or earnings contribution from the new capacity
8CESC secured a 175 MW wind award at Rs 3.85 per kWh - but the project is still short of a PPA, construction and commissioning
8CESC signed to acquire 1.4 GWp of operating solar assets - the Rs 4,859 crore transaction still awaits closure
8CESC will pay an interim dividend of Rs 6 per share - a direct shareholder return despite lower quarterly EBITDA
8Veer Energy more than doubled quarterly revenue and raised PAT 63% - but the small base makes the next result the durability test Details
COAL-GASIFICATION FUNDING REOPENED BEFORE ANY NEW PROJECT WON SUPPORT

8Coal-gasification Category II reopens Rs 1,866.94 crore of unallocated support - bidders still have to clear capacity and funding gates Details
COMPARABLE DATA REVEALED MOVEMENT THAT STATIC SNAPSHOTS WOULD MISS

8India's monitored generation rose 2.39% in a day and beat programme by 318.84 MU - but the total excludes renewable output
8Twenty-two of 31 hydro reservoirs were below last year's level - the national count hides eight that were higher
8Green day-ahead buyers sought 144,477.63 MWh, but only 31,242.27 MWh cleared - sell offers covered less than a quarter of demand bids
8Renewable generation rose 46.18 MU in a day as wind jumped 11% - solar and other renewable output both fell
8Voltage control worsened sharply at Cuddapah while three western nodes improved - one national average would hide the divergence
8Telangana reservoirs gained 66.4 TMCft in eight days - but remained 186.7 TMCft below last year's storage

CURRENT OPERATING ACCOUNTS EXPOSED SCHEDULE, SETTLEMENT AND AVAILABILITY GAPS

8Northern SCUC and ancillary settlements left Rs 32.66 crore payable from the pool - decrement energy exceeded increment energy
8APNRL declared 74,400 MWh for July while WBSEDCL surrendered 34,792.5 MWh - Haryana also scheduled below its periphery declaration
8GMR Kamalanga's larger July capacity account left 12,611.07 MWh unscheduled - its peak account was almost fully matched
8Eastern forced generation outages reached 5,842.5 MW, more than twice the planned 2,770 MW - fresh coal trips outweighed a 250 MW revival Details
BILLING AND POLICY ORDERS CHANGED WHAT CONSUMERS MAY BE CHARGED OR KEEP

8Bihar closes a billing-compliance case after a Rs 20,167 correction - the waived surcharge cannot return in later bills
8Punjab withdrew its 2026 industrial-policy circular - existing electricity-duty and IDF benefits are protected from refunds for now

FEES, VERIFICATION AND RECONCILIATION NOW STAND BETWEEN CLAIMANTS AND FINAL RELIEF

8Haryana treats three green-access challenges as counterclaims - each applicant must pay Rs 45,000 before September arguments
8UPERC orders verification of split electricity and maintenance payments - a Wave City household still has no restoration ruling
8Nabha Power and PSPCL get six more weeks to reconcile mega-power benefits - no tariff adjustment is yet fixed Details
POWER MARKETS CLEARED LARGE VOLUMES, BUT SCARCITY AND EMPTY ORDER BOOKS EXPOSED THE LIMITS

8Day-ahead electricity trading cleared more than 180,000 MWh - repeated Rs 10,000/MWh hours exposed scarcity inside a liquid market
8High-price day-ahead sellers offered 305,546 MWh across eight days - buyers did not clear a single unit
8Integrated day-ahead buyers offered for 5,050 MWh across eight days - sellers offered nothing and every session cleared zero
8Real-time trading cleared 183,621 MWh - repeated Rs 10,000/MWh intervals exposed scarcity inside the balancing market Details
CESC'S HIGHER SALES AND PROFIT DID NOT RESTORE OPERATING EARNINGS

8CESC's revenue and PAT rose while EBITDA fell - the quarter delivered growth without stronger operating profit

ORDER BOOKS AND TECHNOLOGY DEALS MUST BECOME REVENUE, MARGIN OR COMMISSIONED CAPACITY

8Solar Industries' Rs 21,350 crore order book sets the delivery base for its Rs 14,000 crore FY27 revenue guidance
8Genus Power's Q1 profit rose 27% - but Rs 22,183 crore of its Rs 24,020 crore order book depends on joint-venture execution
8Engineers India's Q1 PAT rose 141% even as total income fell 5.4% - its JV and associate share swung from loss to profit
8Kirloskar Electric booked a record first-quarter Rs 184 crore of orders - conversion must repair a quarter that ended in loss
8BHEL adds Hystar's PEM electrolyser route after an alkaline tie-up - local manufacturing still has to be built
8Premier Energies' Rs 15,000 crore order book extends into FY28 - its new 7 GW cell line must now turn trials into revenue Details
8NPCIL's riser insulation package lists one set against four pipe sizes and 24 riser positions The bidder must fund detailed engineering, mock-ups, radiation qualification, five installation trials and site training before any payment falls due. ATC clause 13.0 ties 100% payment to final acceptance and completion of training, on a firm price held over 364 days. The GeM summary marks arbitration "No" while ATC clause 24.0 sets a three-arbitrator tribunal.

8NTPC Mining asks developers for indicative tariffs while holding the land lease rate back to the RFP The 50 MWp splits evenly across two mines, but one sits on an overburden dump and the other carries mandatory levelling plus a developer-scope 33 kV line on a shorter schedule. Penalties, payment security, deemed generation and curtailment treatment are all still open to market input. A later limited tender may be confined to those who respond now.

8WAPCOS's Rs 1 crore mandate says no pre-bid meeting will be held; GeM scheduled one with a Teams link The GeM field records 10:00 against a description reading 10:30-12:30, validity reads 90 days in one document and 120 in the other, and MSE relaxation is "No" in one and 50% in the other. Basic turnover eligibility starts at Rs 50 lakh while scored turnover starts at Rs 50 crore. Arbitration is expressly waived even though the 1996 Act appears in the same document's regulatory framework.

8AEGCL's Rs 6.72 lakh Narengi consultancy buys PLS CADD tower spotting and states no completion period Two lump-sum items cover bay feasibility and full route survey with profile drawings, with forest proposal and tree enumeration expressly carved out. Corridor width, accuracy tolerances, route alternatives and permitted iterations are undefined. The whole cycle from launch to close runs eight days.

8Tata Power's one-year final-checking agreement for a 765 kV line gives bidders 10 days and no quantities Tower counts, line length, inspection formats, acceptance authority, manpower and reporting protocol are all absent from the notice. So are EMD, PBG, payment cycle, LD and liability caps. For a year-long framework, minimum workload and call-off frequency are the terms that matter, and neither is stated.

8TGTRANSCO's Rs 60.71 crore package keeps negative escalation running after positive escalation stops Delay attributable to the contractor removes upward price protection while leaving downward adjustment enforceable, on top of milestone and post-completion penalties. Section 1.2 deems unlisted but necessary components into bidder supply, closing the variation route. A bid 20% below estimate draws additional security of 10% of the estimated cost by the document's own worked example.

8KPTCL's Rs 108.02 crore Ayyanahalli package deleted its 25% consortium floor after a pre-bid nobody attended The line qualification can now sit entirely with one partner, with a three-year electrical-works test replacing it for the other. The proceedings record nil bidder representatives; the queries that produced the change arrived by email. Underlying kilometre thresholds are unchanged.

8APGENCO reserves the right to amend its metering cubicle tender after its own submission window shuts Bids close at 14:00, technical opening is 15:00, and modifications are permitted up to 15:00. Validity reads 180 days in the NIT and 120 in the attached general conditions, while the covering enquiry gives a third set of times. Manufacturer-site QA inspection is marked "Not Required", moving conformity onto supplier certificates.

8NHPC's Sawalkot Lot-1 added Rs 287.91 crore, deleted a qualification route and moved its deadline eleven times The estimate reset from Rs 5,129.03 crore to Rs 5,416.94 crore carried turnover, working capital and bid capacity up with it, while the quantity-based dam alternative disappeared, leaving only an 80 m concrete dam. Project capacity was corrected from 1856 MW to 1800 MW without explanation. No reason is recorded against any of the 161 days of extensions.

8MPPGCL's 30 MWac solar tender moved its query-response date three times, ending seven days before bids close Responses now land after the deadline they were originally meant to precede, leaving one week to absorb them across engineering, vendor quotes, generation modelling and O&M pricing. Evaluation runs on Rs/kWh combining capex, discounted five-year O&M and accepted NEEGG. Omitted-but-necessary equipment is deemed included and prices stay firm.

8NHPC's Kamala amendment moved HM qualification into execution, then needed an errata to fix the clause it cited The same corrigendum cut muck disposal from four zones to two, removing both sites nearest the dam and leaving two shared 50/50 with the adjacent lot. Adverse climate moved from employer risk "Nil" to EOT, and earthquake gained express compensation. Grid power is tentative at two years out, with captive generation and compulsory later uptake both on the contractor.

8THDC's Kalai-II package moved 216 days and rewrote shotcrete from "no extra payment" to Rs 180 per kg Eight extensions ran alongside two substantive amendments and a notice refusing further queries — followed by another date revision. The 31.5-month clock now starts after a 30-day mobilisation period rather than on the seventh day from LOA. The road tunnel is carved out of the milestone-damage waiver every other milestone enjoys.

8AEGCL's Sonapur extension notice pushes bids to 2026 and schedules the opening for 2023 The same package records an NIT date in the pre-bid minutes that post-dates both the NIT and portal publication. A pre-bid meeting materialised where the portal fields read "NA", drawing nine firms. Prices stay fixed for 24 months and the request for conductor and cable escalation was refused.

8MPMKVVCL narrowed its type-test waiver to one rating and readmitted a disqualified bidder after opening The concession originally covered a new bidder lacking reports for any rating; it now covers only the 10 MVA unit. EMD is Rs 1 lakh against post-award security of 1% plus 9% on a 66-month instrument. A bidder rejected as a medium enterprise returned on the MSME notification preserving previous-category benefits for three years.

8NHPC's Salal award is 8.7% below estimate, or 1.5% above it, depending which estimate applies The benchmark rose 11.1% late in the cycle, taking experience, turnover, working capital and bid capacity up with it after an earlier corrigendum had widened technical eligibility. One of three bidders failed qualification, leaving a two-bid contest 3.4% apart. The NIT provides for reverse auction; the comparative statement shows only two values.

8WBSEDCL cut its retesting charge 90% and drew 188 bids in which L2 sits 44.0% above L1 EMD fell 30.0% and 16.7% across categories at pre-bid, while the charge per repeat inspection went from Rs 50,000 to Rs 5,000. Of 188 bids, 148 cleared technically, many only partially by capacity or transformer type. A bidder removed from the restricted-opening table after a corrigendum resurfaced in the price ranking at L22. Details
 For reference purposes the website carries here the following tenders:
 8Tender for work of annual/routine testing of various equipments installed at 400 kV GIS S/S Details
 8Tender for civil works for construction of 01 No. 63 MVA transformer plinth and related 132/33 kV bay Details
 8Tender for civil maintenance and upkeeping work at various volts transmission sub stations Details
 8Tender for diversion of submerged tower 400 kV line Details
 8Tender for supply of cross patrolling of transmission lines Details
 8Tender for supply of LT three phase channel cross arm and angle cross arm Details
 8Tender for procurement of transformer structure materials double pole Details
 8Tender for procurement LT GI pins Details
 8Tender for providing pile foundation for various tower Details
 8Tender for construction of control room foundations, cable trench Details
 8Tender for procurement of spares for SAM make sludge disposal pump model Details
 8Tender for construction work for new proposed 33/11 kV line Details
 8Tender for construction of new borewell at 132 kV GSS Details
 8Tender for construction of civil foundation and other misc civil works in yard for 20/25 MVA Tr At 132 kV GSS Details
 8Tender for construction of civil foundation and other misc civil works in yard Details
 8Tender for levelling and gravelling work of 132 kV switch yard at 132 kV GSS Details
 8Tender for procurement of 220V-600AH lead acid tubular type battery sets Details
 8Tender for procurement of non ferric alum Details
 8Tender for repairing/retrofitting/renovation of raw water pump house Details
 8Tender for supply of CPVC pipe & fittings Details
 8Tender for supply and application of epoxy glass flake coating with UV resistance PU top coat on various external surfaces Details
 8Tender for work of preventive maintenance of various 220 kV switchyard Details
 8Tender for supply of GI coated heavy duty MS grill Details
 8Tender for EPC package for ash handling system package Details
 8Tender for work of RCC revetment/protection wall work at various Details
 8Tender for procurement of furnace oil Details
 8Tender for construction of 132 kV sub-station Details
 8Tender for extension of control room construction of 02 No. 66kV bays Details
 8Tender for supply of wireless LCM kit for 220kV and 66kV class switchyard Details
 8Tender for supply of C&S electric make ACB & panel spares Details
 8Tender for procurement 22 kV, 200A AB switch Details
 8Tender for supply of LT three phase X arm channel Details
 8Tender for supply of T.C.fuse wire 12,14,16 SWG Details
 8Tender for supply of transformer structure materials Details
 8Tender for construction of new 11 kV, LT lines and 11/0.4 kV DTR Details
 8Tender for construction and shifting of existing 33kV/11kV/LT OH/UG lines Details
 8Tender for Re-construction of existing 33 kV UG line Details
 8Tender for construction of new 33 kV line from 33/11 kV DSS Details
 8Design, fabrication, supply, installation, testing, commissioning of on grid solar ground mounted project with net meter and remote monitoring system, capacity of 46 kW Details
 8Design, fabrication, supply, installation, testing, commissioning of on grid solar ground mounted project with net meter and remote monitoring system, capacity of 83 kW Details
 8Design, fabrication, supply, installation, testing, commissioning with RMS of total 156 kW grid connected solar PV power plant Details
 8Tender for supply and erection of 50TR capacity air cooled DX condensing unit for 400kV switchyard Details
 8Tender for supply, retrofit commissioning of 90 kW and above LT air contactor modules (DK21) with LT vacuum contactors Details
 8Tender for supply and replacement of LTG and HTG tubes Details
 8Tender for empanelment of contractors to award a rate contract award RCA for DTR renovation work of 63 KVA, 100 KVA, 200 KVA and 315 KVA substation Details
 8Tender for empanelment of contractors to award a rate contract award RCA for work for aug/conversion of LT line 3x95 Sqmm and 3 X 150sq.mm.XLPE cable Details
 8Tender for augmentation of 33 kV line on H-Beam using ACSR Dog conductor Details
 8Tender for empanelment of contractors to award a rate contract award RCA for work of aug conversion LT cable Details
 8Tender for work of aug of existing 11 kV line to ACSR Dog/Raccoon with 13Mtr H beam/PCC pole Details
 8Tender for procurement of lighting items for power houses Details
 8Tender for annual maintenance work of railway siding for power house Details
 8Tender for supply and running out of ballast for railway maintenance work Details
 8Tender for construction of new hydrogen shed for 1x210 MW unit Details
 8Tender for work contract of transportation of the ash from ash dyke II Details
 8Tender for construction of precast RCC cover and stone Details
 8Tender for procurement of spares of electromagnetic flow meter and SWAS spares installed Details
 8Tender for manufacture, testing, supply, delivery and operational training/ commissioning of three phase transformer turns ratio test sets Details
 8Tender for manufacturing, testing, supply and delivery of 50 Nos. 220V/100AH and 30 Nos.24V/100AH DC distribution boards and 80 Nos. 415V, 11 circuit, AC distribution boards Details
 8Tender for work related to construction and electrification of line and shifting of lines and poles Details
 8Tender for replacement of defective meters Details
 8Tender for maintenance and repair of 11 kV HT/LT line Details
 8Tender for replacement of defective meters Details
 8Tender for work of installation of one (01) No. 12.5 MVA power transformer Details
 8Tender for erection, testing & commissioning work of 66kV equipments, structures Details
 8Tender for erection, testing & commissioning work of 66kV equipments, structures, control wiring Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Karamsad Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Borsad Details
 8Tender for procurement of MS pipes 550 NB for replacement Details
 8Tender for thorough interior civil renovation and allied work Details
 8Tender for work of atactic polypropylene APP treatment to arrest leakages Details
 8Tender for supply loading at factory and transportation of LT distribution box Details
 8Tender for supply and delivery of different local materials Details
 8Tender for construction of 1 No 33 kV bay, 2 Nos. 11 kV feeder bay and providing transformer plinth Details
 8Tender for laying of 11kV 3x300sq.mm XLPE UG cable Details
 8Tender for laying of 11kV 3x300sq.mm XLPE UG cable for erection of new 11 kV feeder Details
 8Tender for supply of stay set complete Details
 8Tender for work of providing & fixing of 33kV numerical backup relay with non-directional three phase over current (3 O/C) & earth fault (E/F) protection Details
 8Tender for AMC for CTR make nitrogen injection fire protection system (NIFPS) for ICTs & transformer Details
 8Tender for annual maintenance contract (AMC) for the work of attending emergency breakdown works & planned maintenance works in various 220/132 kV EHV S/Stn Bhandara Details
 8Tender for annual maintenance contract (AMC) for the work of attending emergency breakdown works & planned maintenance works in various 220/132 kV EHV S/Stn Details
 8Tender for biennial maintenance contract of replacement of installed smoothing reactor by spare smoothing reactor Details
 8Tender for supply of pressure relay of converter transformer Details
 8Tender for annual maintenance contract (AMC) for the work of attending emergency breakdown work & planned maintenance works in various 220/132kV EHV S/S Details
 8Tender for refilling, servicing & maintenance, supply of spares for fire extinguishers at various substations Details
 8Tender for annual maintenance contract (AMC) for work of underground cables at various Details
 8Tender for attending emergency breakdown work & annual routine maintenance of 220/132/110kV various EHV lines Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Mehsana Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Patan Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Himatnagar Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Chhatral Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Dhansura Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Jamla Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Vijapur Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Agiyol Details
 8Tender for supply of pre engineering shed Details
 8Design, engineering, manufacture, supply, erection, testing & commissioning of 6.6 kV indoor metalClad draw-outtype VCB panels Details
 8Tender for supply, installation commissioning, & testing of soft starter with major/minor modification in existing panels for various motors Details
 8Tender for supply of assorted size of MS grill for repairing of platform of ash slurry line Details
 8Tender for supply of mill discharge first piece after MPO for coal mill Details
 8Tender for purchase of standard toolkit bag Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8Hinduja Renewables Bets On BESS, Pumped Storage To Make Renewables More Dispatchable Details
 
8Maharashtra Floats EOI for 170 MW Floating Solar & BESS Project Details
 
8NVVN Invites EOI for 263 MW Solar Open Access Power Details
 
8ACME Solar Refinances Rs 21.5 Billion Debt for 450 MW Portfolio Details
 
8MNRE Approves INR 258.83 Crore HRD Programme To Strengthen India’s Renewable Energy Workforce Details
 
8Rooftop solar installations soar in India Details
 
8CIL, ArcelorMittal sign MoU to explore syn-gas usage from a coal gasification plant at Paradip Details
 
8DNHDDPCL Invites Bids for 5 MW Rooftop Solar Program Details
 
8India’s small steelmakers could save money and cut emissions with switch to renewable power Details
 
8How India can get its BESS projects right Details
 
8India on e-wheels: There are hardly any electric cars on Srinagar’s roads; here is why Details
 
8H2 Innovation eyes collaboration with universities, government to develop green hydrogen in India Details
 
8Power Ministry Urges States: Accelerate Smart Meter Rollout Details
 
8Dr Jitendra shares in LS India’s Thorium driven indigenous Nuclear strategy Details
 
8Siemens Energy India to attend Motilal Oswal investor meet Details
 
8Gentari Explores Sale of India EV Charging Network With 3,000 Chargers Details
 
8Data Centre Power Boom: Why renewable developers are demanding a Rs 3,000 crore relief package Details
 
8Stocks to Watch: Solar Industries, LG, Tata Motors PV and 7 Other Stocks Announcing Q1 Results Today Details
 
8SJVN Commissions 75 MW Jamui Solar Power Project in Bihar, Expands Renewable Energy Portfolio Details
 
8India’s Solar Surge Highlights 50 GW Power Gap Challenge Details
 
8India's Planned Coal Mining Capacity Hits 638 MTPA Details
 
83 Best-Performing Mutual Funds With High Holdings in NTPC, Adani Power & Tata Power in 2026 Details
 
8Demand aggregation of renewable electricity can cut power costs for India’s secondary steel MSME clusters by 34 percent Details
 
8Bajel Projects Bags Rs 400 Crore Order From Power Grid for 765kV Transmission Line Details
 
8Power sector stocks today, August 12: TD Power Systems jumps 15.87%, Gujarat Industries up 7.40%, Diamond Power rises 4.36% Details
 
8India’s solar power cuts coal use in the day, but evening demand keeps fossil fuel running Details
 
8El Niño drives India's July power demand to a record high: Crisil report Details
 
8India nearly doubles proposed coal mine capacity as global pipeline expands: Report Details
 
8CEA Proposes New 2026 Grid Connectivity Technical Standards For Power Sector Entities Details
 
8How the Indian Railways moves closer to becoming net-zero carbon emitter by 2030 Details
 
You can also click on Newsclips for more Details
8PLI awards and private investment have expanded module capacity much faster than cells, wafers and raw materials. The result is a larger domestic manufacturing base with a narrowing-but still material-upstream dependence. Details
8IRENA expects the solar fleet to expand from 2,383 GW in 2025 to more than 5 TW by 2030 under its 1.5°C scenario. The same build-out could create more than 25 million tonnes of panel waste a year by 2050, while most markets still lack solar-specific end-of-life rules. Details
8Haldia Energy recovered its fixed charges in FY26, but cash conversion is being held back by delayed tariff true-ups and an appealed refund direction. The pressure is visible in debtors of Rs 2,939 crore and leverage close to the rating agency's stated guardrail. Details
8The approved procurement runs from October 2026 to March 2027 and varies by hour and month, rather than providing round-the-clock supply. Bidders cut some offers from Rs 12.99/kWh to Rs 9.98/kWh, but the final tariff still embeds a premium for firm peak-period availability. Details
8The 12 August exchange report shows a seven-fold gap between purchase and sell bids in the real-time market. Clearing at the ceiling does not mean every purchase bid was served; it shows scarce offered volume was absorbed at the maximum permitted price. Details
8The 8 August event involved fire, smoke and oil spillage at the 400/220 kV station, with both interconnecting transformers going out together. The operating record identifies protection and restoration questions, but the final forensic cause is still under investigation. Details
8NRLDC's resource-adequacy study finds that daily or aggregate surpluses can coexist with shortages after solar output fades. Punjab, Delhi, Uttarakhand and Himachal Pradesh also show uncovered periods, while Rajasthan and Haryana did not provide usable data for the study. Details
8The gap between allocation and output is concentrated in clearances, mining leases, land and development work. Even among 23 blocks described as operational, eight had not reached the source's separate producing category at 30 June. Details
8POWERGRID has charged four transformers and a Bikaner line loop-in, but the 682 km Bikaner-III-Neemrana-II corridor remains the schedule driver. The delay limits full Rajasthan renewable-zone evacuation without meaning that the entire scheme is unavailable. Details
8Government data show national scale in rooftop and solar-pump programmes alongside very uneven capacity and beneficiary outcomes. The same tables also mix broad renewable additions with scheme-specific delivery, so the numbers cannot be treated as one programme total. Details
8The regulator accepted post-facto approval because 90% central support and project deadlines were at stake, but warned the utility over procedural lapses. If delayed awards cause grant refusal or conversion to a loan, the resulting cost stays outside the consumer tariff. Details
8The expert committee recommended amended terms of reference for the Basania multipurpose project, not environmental clearance or construction approval. Its energy and irrigation case will now be tested against land, forest and social impacts at appraisal. Details
8Fifty-eight eligible units have requested about Rs 932 crore under a Rs 1,500 crore incentive scheme. The oversubscription signals capacity appetite, but the government will disburse only against eligible investment, commercial production and specified milestones. Details
8KABIL obtained permission for invasive exploration in April and selected a drilling contractor, but final local concurrence remains pending. Feasibility is now scheduled for March 2029, leaving production dependent on exploration results rather than the ownership of five blocks alone. Details
8CESC's Malegaon distribution franchise continues to depend on equity and inter-corporate funding while it invests in the local network. The exposure is measurable, but the rating report does not establish a completed turnaround or a regulator-backed recovery path. Details
8Government contests reports of a major coal-depot fire - but supplies no independent incident record
8Gita Renewable seeks a Rs 200 crore borrowing ceiling - after reporting no quarterly operating revenue
8Monthly averaging preserved frequency-response eligibility - despite zero response in two events
8CERA's open-access refund claim failed on limitation - not on the disputed formula
8Intraday buyers found no sellers on 12 August
8High-price sellers offered 41,078.4 MWh - no buyer entered
8A 101 MW solar developer withdrew its extension case - its Rs 10.10 crore guarantee remains exposed
8SJVN's 75 MW Jamui solar plant entered commercial operation, adding contracted Bihar supply at Rs 2.96/kWh
8JSW and Druk Green's agreement creates a joint-development vehicle for Bhutan's 920 MW Punatsangchhu-III hydro project
8EAC recommended study terms for Gandikota's proposed expansion from 1,000 MW to 1,800 MW, putting the larger design into environmental appraisal
8India completed 4,081 ckm by July, adding part of the 16,554 ckm transmission network planned for FY27
8UPERC opened tariff scrutiny for seven thermal stations totalling 4,190 MW Details
8Western-region outage reports listed 6,646 MW unavailable on 12 August, cutting supply available to western-region grid users
8Yadadri, Vallur and SEPC outages removed 1,825 MW from the southern stack, reducing supply available to Telangana and Tamil Nadu grid users
8Eastern-region outage report listed 4,895 MW unavailable on 12 August, with flood-damaged Teesta III alone withholding 1,200 MW from regional supply
8Southern-region report listed 2,040 MW unavailable on 12 August as valve, emissions-control, fire and fuel-handling failures removed ten units Details
8National grid frequency stayed outside its prescribed band for 6.93 hours on 12 August, extending the control-quality deviation recorded across July
8Northern import interfaces breached transfer limits for 12.75 hours in July, narrowing secure interregional transfer headroom
8Five substations spent 51–78 hours outside voltage bands in July, constraining secure operation at persistent problem points Details
8Fifteen collapsed towers kept the Gadag-Koppal double-circuit line constrained, limiting renewable evacuation until permanent restoration
8Telangana’s reservoir energy fell to 1,047.7 MU from 2,054.3 MU, reducing hydro headroom at the 13 August snapshot
8Assam and Tripura exceeded available transfer capability for 44.2% and 91.2% of 11 August, tightening secure import headroom for both state systems Details