All content in this website is sourced legitimately

Rs 287.59 crore hydroelectric project: Civil work package-1 in Q2, 2020.  Rs 885.25 crore greenfield hydroelectric project: Civil works package in Q3, 2020.  Download Tenders and Newsclips.  Our Take.  Our Take.  Download Tenders and Newsclips.  Download Tenders and Newsclips.  Our Take.  Software update: Power projects.  Rs 31,000 crore power plant: Switchyard package coming up .  Greenfield Super Thermal Power Project: Cooling tower requirement coming up.  Greenfield Standalone Pump Storage Project: EIA consultant RFQ ahead.  Advanced Ultra-Super-critical Thermal Power Demonstration Project: RFQs ahead.  Our Take.  Download Tenders and Newsclips.  Our Take.  Download Tenders and Newsclips.  Our Take.  Download Tenders and Newsclips.  Greenfield Hydroelectric project: Civil work package in Q2, 2020.  

Rs 287.59 crore hydroelectric project: Civil work package-1 in Q2, 2020

Jan 17: Project Name: Hydroelectric Greenfield Project
8Project Cost: Rs 287.59 crores
8Project Description: The promoter's 52 MW (2x26 MW) greenfield hydroelectric plant has been held up on account of a delay in signing of the power purchase agreement. EIA and EMP studies under progress by a consultant R.S Enviro Technology Pvt. Ltd. The preparation of DPR is also under progress. EC has not been granted yet . Forest clearance is pending at DFO. RFQ for civil work package-1 is likely to be floated in Q2 2020.
Click here for more details
Details

Rs 885.25 crore greenfield hydroelectric project: Civil works package in Q3, 2020

Jan 17: Project Name: Greenfield Hydroelectric Project
8Project Cost: Rs 885.25 crores
8Project Description: EIA and EMP study completed by AFC Consultant PVT Ltd and the report has submitted. EC is not granted yet. Techno-economic clearance has been granted by CEA. Drilling and drifting works are in progress. Civil works package -2 is likely to be floated in Q3 2020.
Click here for more details
Details

Download Tenders and Newsclips

Jan 17: For reference purposes the website carries here the following tenders: 
 
8Tender for Procurement of LT cables & aerial bunched cables Details
 
8Tender for Supply of complete set of rotor pole keys Details
 
8Tender for Procurement of 315 MVA, 400/220/33 KV Auto Transformer Details
 
8Tender for Replacement of ACSR Bare Conductor by A.B. Cable Details
 
8Tender for Procurement Of 300 mm ERW pipes Details
 
8Tender for Procurement of Transformer Oil Details
 
8Tender for work of Replacement of condenser tubes Details
 
8Tender for Procurement of spares for Dryer Details
 
8Tender for Supply & Installation of Flue Gas Desulphurisation (FGD) and Auxiliary System Details
 
8Tender for Procurement of Various type of valves installed in AHP Details
 
8Tender for supply of 33kV lattis structure Details
 
8Tender for Construction Of 4x33 kV bays at 132 kV S/Stn by dismantling of 2x33 kV bays Details
 
8Tender for supply & delivery of 02 Nos. transformer Details
 
8Tender for Biennial Maintenance Contract for Regular & Running Maintenance of all Electrical Equipments Details
 
8Tender for Carrying out operation of DG Sets, Submersible Pumps, Station Service Boards and Cooling Water System Details
 
8Design, manufacture, testing, delivery of 3 phase Oil filled transformers Details
 You can also click on Tenders
for more
For reference purposes the website carries here the following Newsclips: 
8Adani, Azure top bidders for manufacturing-linked solar tender Details
8Mercedes-Benz set to roll out its first fully-electric vehicle in April 2020 Details
8SC seeks Centre's reply on implementation of policy to convert public transport vehicle to EVs Details
8Adani Solar retail distribution in Karnataka soon Details
8"Undue favour" given to "disqualified" Adani Enterprises in award of coal supply contract: CBI Details
8India will have 225 GW of renewable energy capacity by 2022, including large hydro: MNRE Secy Details
8EV startup BattRE launches entry-level electric scooter LoEV Details
8Punjab CM to target SAD over controversial power agreements Details
8Maharashtra: Mahavitaran seeks 6 per cent increase in power tariff Details
8Deutsche Bank-led group a step closer to Jindal India deal Details
8Govt's proposed discom scheme positive measure for the power sector Details
8We are investing to build the solar agriculture market: Saravanan Paneer Selvam, Grundfos India Details
8Electricity Act may be amended to ensure discoms honour power pacts Details
8Electrical industry expects Rs 30,000 cr biz at flagship showcase event ELECRAMA Details
8Maharashtra: Pawar, Nagpurians want power plants shifted to Nashik Details
You can also click on Newsclips for more
Details

Our Take

Jan 17: 8SKS Power Generation (Chhattisgarh) Limited: The company’s cash flows will remain sensitive to variation in short-term power tariff levels Details
8P & R Gogripur Hydro Power Pvt. Ltd: Ratings withdrawn Details
8Shifting to renewables could grow the world economy by 1% a year until 2050: An analysis Details
8What are the implications of climate change investments? Details
8Adani Power Jharkhand Ltd: Pushing debt levels up for group company Details
You can also click on Reports
for more Details

Our Take

Jan 16: 8GRIDCO Ltd.: Improved financials and operational performance Details
8India will be the first such economy that has not depended upon a high level of fossil fuel burning per dollar of GDP: An analysis Details
8Arhyama Solar Power Private Limited: Under non-cooperating category with rating agency Details
8Business Opportunity: Setting up of 1200MW Wind-Solar Hybrid power projects Details
8FGD implementation schedule for thermal units in India: An update Details
8Lanco Solar Private Limited: Non-Cooperating with rating agency Details
You can also click on Reports
for more Details

Download Tenders and Newsclips

Jan 16: For reference purposes the website carries here the following tenders: 
 
8Tender for Annual Overhauling of Boiler Pressure part Details
 
8Tender for Rate Contract for maintenance of milling system Details
 
8Tender for Overhauling of steam generator auxiliaries Details
 
8Tender for procurement of LT power & control cable Details
 
8Tender for AMC of Turbine Aux. valve and heat exchanger Details
 
8Tender for AMC of ESP wet ash handling system Details
 
8Tender for Procurement of pneumatic cylinders & its spare kit for TPP Details
 
8Tender for Annual work contract for maintenance of 200 kV & 400 KV Switchyard equipments Details
 
8Tender for rate contract for erection and dismantling of emergency restoration system Details
 
8Supply, Erection, Modification, Testing & Commissioning of LT Switchgear with Breaker retrofitting Details
 
8Design, Supply, Erection, Testing and Commissioning of Mechanical BOPs like Drainage & Dewatering System Details
 
8Tender for Supply of equipments & Work of replacement of Various existing EHV equipments Details
 
8Tender for Supply, Civil, Erection, Testing & Commissioning of 110kV level creation Details
 
8Tender for work of Repairing/Overhauling & providing of spares for Air compressors Details
 
8Tender for supply of Imported Non-coking coal Details
 
8Tender for work of RLA Study in 2 Nos. boilers Details
 
8Tender for supply of Plante type battery banks Details
 
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips: 
8German Officials Agree Plan to Exit Coal-Fired Power by 2038 Details
8Andhra plans to transfer power assets to APPFCL Details
8Kalpataru Power Q3 PAT seen up 37.1% YoY to Rs. 126.1 cr: ICICI Direct Details
8With divestment target under pressure, Centre fast-tracks strategic sales process Details
8KEC International Q3 PAT seen up 36.7% YoY to Rs. 153.6 cr: ICICI Direct Details
8India's thermal coal imports at major ports down by 17 per cent this fiscal Details
8Centre begins commercial coal auction process Details
8Coal companies must make extra voluntary contribution to staff pension fund: CMPFO Details
8Soon, Goa’s colleges will generate their own power Details
8Maharashtra: MSEDCL proposes astronomical GSC for solar rooftop Details
8Rajasthan: Bylaw breather for 1,500 rooftop restaurants in Jaipur Details
8Honda, Isuzu power up fuel cell partnership for heavy-duty trucks Details
8Cong leader seeks judicial probe into high rates of electricity supplied by private firms in Punjab Details
8Maharashtra: MSEDCL residents tariff may be steepest after 5-8 per cent hike Details
8Government proposes grant of Rs 1.1 lakh crore for state discoms Details
You can also click on Newsclips for more
Details

Download Tenders and Newsclips

Jan 15: For reference purposes the website carries here the following tenders: 
8Tender for HM Works comprising, Design, preparation of detailed fabrication subassembly Details
8Tender for Electromechanical Works for HEP Details
8Tender for Annual Comprehensive O&M Contract for 50 MW Grid Connected Details
8Tender for Supply of LT Transformers Details
8Tender for work of assembly of 33kV Isolator Details
8Tender for Insulation of Pipe, Valve & Equipment Details
8Tender for procurement Spares for ESP controllers Details
8Tender for Supply & replacement of suspension string insulators Details
8Tender for Constructing of 600M OH Line Details
8Tender for Constructions of 11kV OH line Details
8Tender for Supplying and drawing 11kV covered conductor Details
8Tender for supply of HT ABC Details
8Tender for supply of dry type transformer Details
8Tender for supply of bushing installed guidevane operating system Details
8Tender for the Procurement of 4944 metres of cast basalt lined MS pipes Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8Coal auction rules: 4 per cent revenue share, affiliate companies not allowed Details
8By 2030, 57% of global power demand should be met by renewables: IRENA Details
8Global green tech revolution at risk, India can play role in reforming mining practices: Experts Details
8 Maharashtra: MERC withdraws compulsory gross metering for solar power Details
8 Chandigarh: 300 govt houses to get solar panels in Crest’s Rs 15cr project Details
8Tamil Nadu: Bright spot eludes solar powered agri income plan Details
8India’s renewable energy capacity reaches 86 GW in 2019; wind takes biggest share Details
8 Adani in early talks to acquire Reliance Power's troubled unit Details
8 Jaiprakash Power Ventures to exit insolvency process Details
8More than 400,000 German jobs at risk in switch to electric cars: Handelsblatt Details
8Tariff hike: KERC wants Bescom to justify expenses Details
8 Best Power Equipments appoints Anurag Mathur as Regional Director Details
8 Shapoorji Pallonji Group needs 5,000-6,000 cr Details
8Andhra Pradesh: Power connection for 50k ryots soon Details
8Yes Bank invokes pledged shares to acquire 30 per cent in Reliance Power's UP unit Details
8 Goa: Domestic power tariffs not hiked, power minister clarifies Details
8GE T&D India appoints Pitamber Shivnani as CEO & President Details
You can also click on Newsclips for more Details

Our Take

Jan 15: 8Unitech Power Transmission Ltd: The company’s operating and net profit margins are thin due to the nature of industry Details
8Meghalaya Energy Corporation Ltd: Collection Efficiency and High AT&C losses Details
8Power distribution sector debt pile of 4 trillion is a huge barrier for reform and low carbon transition: An analysis Details
8Safeguard duty on Chinese solar power equipment will make RE industry uncompetitive: An analysis Details
8Government to roll out one nuclear-reactor: Rolling out one nuclear-reactor each year will increase production of zero carbon energy: An analysis Details
8How Climate Change Affects the Building Energy Consumptions Due to Cooling, Heating, and Electricity Demands?  Details
You can also click on Reports for more Details

Software update: Power projects

Jan 15: Project Name: North Karanpura greenfield thermal power plant
8Project Cost: Rs 14336.00crores
8Project EventRFQ for supply, erection, installation, testing, and commissioning of ESP for unit-3 is likely to be floated in March 2020
Click here for more details
Project Name: Barh super thermal power project stage-II - FGD Addition

8Project Cost: 330.00 Crores
8Project Event: RFQs for the award of the FGD installation package is expected by March 2020. Further bids are expected soon.
Click here for more details
Project Name: Bhusawal brownfield thermal power station

8Project Cost: Rs 4500 crore
8Project Event:RFQ for the erection, testing, and commissioning of natural draught cooling towers is expected by Q2 2020.
Click here for more details
Project Name: Patratu superthermal greenfield power plant

8Project Event: RFQ for supply, erection, installation testing and commissioning of FGD for Units-1,2,3 is likely to be floated on Q2 2020.
Click here for more details Details

Rs 31,000 crore power plant: Switchyard package coming up

Jan 13: Project Name: Greenfield Thermal Power Station
 
8Project Cost: Rs 31000.00crores
8Project Description:
Erection and commissioning of the first four units of SG and TG 4x800 MW are in progress. Civil works of SG for fifth units are yet to start. Erection and commissioning of TG for the first fourth units are also in progress. Bids for natural draught cooling tower for all 5 units will be opened on 20th January 2020. BHEL has also floated tenders for single steel flue RCC chimney for unit -5 and twin steel flue RCC chimney for all units except unit -5. Bids will be opened later this month. RFQ for the switchyard package for all units is likely to be floated in Q2 2020.
Click here for more details
Details

Greenfield Super Thermal Power Project: Cooling tower requirement coming up

Jan 13: Project Name: Greenfield Super Thermal Power Project
8Project Cost: Rs 12772.00 crores
8Project Description: The BTG contractor BHEL has completed the piling works in the boiler area for TANGEDCO's greenfield 1600 MW (2x800 MW) supercritical thermal power plant. The work got delayed due to issues connected with balance land acquisition issues. The civil works for the main plant area are in progress. Currently, BHEL has floated tenders for the erection, testing, commissioning and trial operation of the boiler and its auxiliary for unit -1. Bids will be opened on 30th January 2020. RFQ for the civil, structural, architectural, mechanical work including testing, commissioning and trial operation of the natural draught cooling tower is likely to be floated in Q2 2020.
Click here for more details
Details

Greenfield Standalone Pump Storage Project: EIA consultant RFQ ahead

Jan 13: Project Name: Greenfield Standalone Pump Storage Project
8Project Cost: 1347.63 crores
8Project Description: Pre- Feasibility report is completed and it is prepared by in house resources. Detailed topographical surveys and geotechnical investigations will be initiated during the feasibility studies. TOR is prepared and it is submitted. RFQ for EIA consultant is likely to be floated on Q2 2020. Further bids are expected soon.
8Project Event: RFQ for EIA consultant is likely to be floated on Q2 2020.
8Expenditure Approval: Q3:2020.
8RFQ Date: Q2:2020
8Release Date: Q2: 2020
8Start Date: 2021
8Completion Date: 2025
Click here for more details
Details

Advanced Ultra-Super-critical Thermal Power Demonstration Project: RFQs ahead

Jan 13: Project Name: Advanced Ultra-Super-critical Thermal Power Demonstration Project, Stage-III
8Project Cost: 9484.00 crores
8Project Description: The terms of reference have been granted in February 2019. A consortium of NTPC, BHEL, and IGCAR has carried out R&D activities consisting of several analytical investigations including field tests for the development of Advanced Ultra-supercritical (AUSC) Technology. The project envisages the development of indigenous technology for steam parameters of 310 Kg/cm2 and 710 °C / 720 °C temperature under the Development of Clean Coal (Carbon) Technologies Mission. No additional land is proposed to be acquired for the project. EIA study has been  completed. But EC is not granted yet. BHEL will be selected as an EPC Contractor.
8Project EventRFQ for coal handling plant is likely to be floated by Q3 2020.
 Click here for more details, including key contacts Details

Our Take

Jan 13: 8CESC: Company is expected to report weak Q3FY20E results on back of lower generation in the base business Details
8NTPC: Better hydro generation and LC payment mechanisms issues for SEB's has hurt the operational performance for Q3FY20E Details
8Annual investments in renewables must double by 2030 to ensure a sustainable future Details
8India's Energy efficiency improves, but needs to accelerate: An analysis Details
8Kalpataru Power: KPTL is expected to report strong revenue which is expected to grow by 16.4% to Rs 2007.6 crore in Q3FY20E Details
8Business Opportunity in Coal mining project Details
You can also click on Reports for more Details

Download Tenders and Newsclips

Jan 13: For reference purposes the website carries here the following tenders: 
 
8Tender for the work of Annual Maintenance of Hydro Turbine & Generating assemblies Details
 
8Tender for Procurement of Sulphuric Acid for TPS Details
 
8Tender for Procurement of Conveyor belt textile-steel cord for coal handling plant Details
 
8Tender for Round the clock operation, routine, preventive & breakdown maintenance of C&I system Details
 
8Tender for Procurement of complete set of IPC nozzle for LMZ Turbine Details
 
8Tender for Procurement of 415V LT switchgear Details
 
8Tender for Overhauling of ESP of TPS Details
 
8Tender for Procurement of Spare Parts of Wagon Tippler, Side Arm Charger & Rotary Breaker for CHP Details
 
8Tender for Procurement of spares for KWU Steam Turbines Details
 
8Tender for procurement of 220 V nickel cadmium battery banks Details
 
8Tender for replacement of defected & damaged LT panels Details
 
8Tender for the work of R&M of electrical installation Details
 
8Tender for operation of 132/33/11kV substation and maintenance of 33/11KV substation Details
 
8Tender for Maintenance of 33 KV, 11 KV & LT Lines Details
 
8Tender for Biennial Maintenance Contract for Electrical Operation & Running Maintenance and regular electrical maintenance Details
 
8Tender for maintenance contract for boiler pressure parts Details
 
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips: 
8Govt plans to restrict coal supply to Andhra Pradesh Details
8Odisha power reforms model for States’ Details
8Coal sector gets a fresh lease of life. India has to do more Details
8Siemens will back controversial Australian coal project: CEO Joe Kaeser Details
8Solar power association writes to Nitin Gadkari against NTPC’s tender conditions Details
8Coal India will remain dominant player: Union coal minister Pralhad Joshi Details
8In Talks With Mongolia, Russia to Import Coking Coal: Pradhan Details
8Germany's Siemens to fulfill Australia coal mine contract Details
8Punjab: Ludhiana Smart City Mission to begin phase II of solar project soon Details
8Panasonic's India aims to expand EV charging offerings Details
8Abu Dhabi-based agency calls for clean energy investments to double Details
8Tata Power Solar bags Rs 1,505 crore project from NTPC under CPSU scheme Details
85-year power tariffs for home users: BEST, Tata seek hikes, Adani cuts Details
8Adani seeks 1 per cent cut, Tata 9 per cent hike in power tariffs Details
8Matter of pride for Haryana to score first rank in State Energy Efficiency Index 2019, says Khattar Details
8Major shift: PMO mulls to open gates for FDI in nuclear power Details
8China says no significant cut in new energy vehicle subsidies in 2020 Details
8Chandigarh: UT asks power regulator to fix T&D losses at 13.3 per cent Details
8Chandigarh to induct EVs; evaluated as progressive UT in energy efficiency index Details
You can also click on Newsclips for more
Details

Our Take

Jan 10: 8Renewable energy sector makes rapid strides in 2019: A report
8PM's office proposes waiving carbon tax on coal:An analysis Details
8India plans $35 bn reforms to revive struggling power retailers: Bailing out power retailers will reward excessive risk taking: An analysis Details
8Why not use natural gas or coal with carbon capture? Details
8Business Opportunity: Many outage programmes of generating units and transmission lines are coming soon Details
You can also click on Reports for more Details

Download Tenders and Newsclips

Jan 10: For reference purposes the website carries here the following tenders: 
 
8Tender for Supply and retrofitting of 800A 3 Pole ACB Details
 
8Tender for Procurement of Spares parts of Paddle Feeder installed at CHP Details
 
8Tender for Annual Work Contract for Routine Maintenance of Boiler fluid systems Details
 
8Tender for Procurement of solenoid valves with coils for various pneumatic system Details
 
8Tender for E&M work including technological structures for CHP R&M work Details
 
8Tender for procurement of Economiser coils Details
 
8Tender for procurement of 200V, 990AH nickel cadmium battery banks Details
 
8Tender for construction of 11kV feeders Details
 
8Tender for the work of overhauling & servicing of various make 22kV Circuit breakers Details
 
8Tender for Rate Contract for supply of HT/LT ABC Hardware Items Details
 
8Tender for the supply of items for testing and maintenance equipments Details
 
8Tender for the supply of hydrochloric acid Details
 
8Tender for Job of complete removal of damaged V-bars and Grid materials and refitting with new V-bars and Grid materials Details
 
8Tender for the work of Flue Gas Desulphurisation (FGD) Project Management & Engineering consultancy services Details
 
8Tender for Procurement of Battery charger Details
 
8Tender for Procurement of copper control cable Details
 
8Tender for ARC for attending Boiler Tube Leakage and other allied works Details
 
You can also click on Tenders for more
 For reference purposes the website carries here the following Newsclips:
 
8Coal India resources get a boost of 8.3 BT after Centre’s allocation of 16 blocks Details
 
8EESL electric vehicle tender failed as vehicles were not for personal use: Pawan Goenka Details
 
8Installed Renewable Energy Capacity Crosses 84GW Details
 
8Indian power ministry seeks more time for coal-fired plants to install emission cutting equipment Details
 
8Ease of mining coal needs to be accompanied by regulatory overhaul Details
 
8India’s energy choices are critical for the world Details
 
8No financial and technical yardstick for coal auctions Details
 
8Commercial mining could be limited by a move towards clean energy: Care Ratings Details
 
8Indian Railways to procure 1,000 Mw solar power by 2021-22 Details
 
8Green developers in AP lost Rs 1,400 cr since August Details
 
8Sterling and Wilson must be held liable for failure to protect minority shareholders: InGovern Details
 
8India not to be a significant player in offshore wind energy anytime soon: Alexander Fløtre, Rystad Energy Details
 
8Loom Solar launches world's first IoT-based solar AC module Details
 
8Electric Vehicles: ABB, Ashok Leyland join hands to develop flash-charging bus Details
 
8NHPC likely to deliver a better Q3 on growth in generation Details
 
8Power ministry launches portal to track states' energy efficiency performance Details
 
You can also click on Newsclips for more
Details

Our Take

Jan 09: 8Tuppadahalli Energy India Pvt Ltd: The company remains exposed to counterparty credit risks due to exposure to a single buyer Details
8What are the global perspective on electric vehicle 2020? Details
8Coal import demand is expected to be subdued in coming months: A report
8International Grid Integration: What are the strategic implications in Asia? Details
8Business Opportunity in Capital power plant Details
You can also click on Reports for more Details

Download Tenders and Newsclips

Jan 09: For reference purposes the website carries here the following tenders: 
 
8Tender for AMC for attending preventive work of 220kV & 132kV EHV transmission lines Details
 
8Tender for Work of online, routine, preventive, breakdown, AOH & COH maintenance of AHP silo system Details
 
8Tender for Supply of Caustic Soda Lye TPP Details
 
8Tender for Annual Work Contract for Routine Maintenance of Boiler Fuel System Details
 
8Tender for Design, engineering and supply of 220/132kV single core XLPE cable Details
 
8Supply, Installation, Commissioning and Comprehensive Annual Maintenance Contract of CAAQMS Details
 
8Tender for fixing and termination jobs of various size LT UG cable Details
 
8Tender for Replacement of 68 nos pendent re-heater coils Details
 
8Tender for construction of 33kV ring lines on panther conductor Details
 
8Tender for BRC for the work of spray insulation of various turbine modules Details
 
8Tender for Work Contract for the work of Chemical Washing of disc insulator strings Details
 
8Tender for Annual rate contract for maintenance work of various 132kV, and 220kV EHV Substations Details
 
8Tender for operation and maintenance for lignite handling system Details
 
8Tender for AMC for Coal Mill auto rejection system Details
 
8Tender for supply & delivery of ring and ball sets Details
 
8Tender for Attending breakdown works in Bottom Ash Hopper Details
 
You can also click on Tenders for more
 For reference purposes the website carries here the following Newsclips:
 
8Emission controlling systems: Don’t bundle coal and renewable power Details
 
8Coal blocks in India no longer ‘captive’; Steel, power firms may bid for mines Details
 
8India in talks with World Bank for Modi’s global electricity grid plan Details
 
8SoftBank in talks to sell stake in India's renewable energy venture: Report Details
 
8Cabinet okays Ordinance removing end-use restrictions in coal mine auctions Details
 
8SAD alleges undue benefit to pvt power plants by Cong-led Pb govt Details
 
8Supreme Court stays HC order, lets DRI pursue case against Adani firms Details
 
8Supreme Court seeks centre's response on plea challenging Coal Mines Act provisions Details
 
8Environment Ministry clears 10 coal mining projects Details
 
8India to ease mining rules from March to spur investment Details
 
8Cabinet approves India-UK MoU for energy self-sufficiency in railways Details
 
815 lakh power sector employees, engineers on strike: AIPEF Details
 
8Lithium completes acquisition of 1000 Mahindra EVs in its fleet Details
 
8Banks seeing credit demand from solar, oil & gas and road: SBI Chairman Details
 
8Kerala: Kozhikode to get 26 electric vehicle charging stations Details
 
You can also click on Newsclips for more
Details

Greenfield Hydroelectric project: Civil work package in Q2, 2020

Jan 08: Project Name: Greenfield Hydroelectric Power Project
8Project Cost: 1994.74 crores
8Project Description: The land survey for the project is in process and a Nodal Officer has been appointed by state government for processing the work for the land acquisition, but the progress of work has been slow. The socio-economic survey and public hearings were carried out by the consultant and the report has been submitted to the higher authority. SIA studies had been completed. Drilling and drifting works are in progress. RFQ for the civil work package -2 is likely to be floated in Q2 2020.
Click here for more details, including key contacts
Details

Rs 287.59 crore hydroelectric project: Civil work package-1 in Q2, 2020

Jan 17: Project Name: Hydroelectric Greenfield Project
8Project Cost: Rs 287.59 crores
8Project Description: The promoter's 52 MW (2x26 MW) greenfield hydroelectric plant has been held up on account of a delay in signing of the power purchase agreement. EIA and EMP studies under progress by a consultant R.S Enviro Technology Pvt. Ltd. The preparation of DPR is also under progress. EC has not been granted yet . Forest clearance is pending at DFO. RFQ for civil work package-1 is likely to be floated in Q2 2020.
Click here for more details
Details

Rs 885.25 crore greenfield hydroelectric project: Civil works package in Q3, 2020

Jan 17: Project Name: Greenfield Hydroelectric Project
8Project Cost: Rs 885.25 crores
8Project Description: EIA and EMP study completed by AFC Consultant PVT Ltd and the report has submitted. EC is not granted yet. Techno-economic clearance has been granted by CEA. Drilling and drifting works are in progress. Civil works package -2 is likely to be floated in Q3 2020.
Click here for more details
Details

Download Tenders and Newsclips

Jan 17: For reference purposes the website carries here the following tenders: 
 
8Tender for Procurement of LT cables & aerial bunched cables Details
 
8Tender for Supply of complete set of rotor pole keys Details
 
8Tender for Procurement of 315 MVA, 400/220/33 KV Auto Transformer Details
 
8Tender for Replacement of ACSR Bare Conductor by A.B. Cable Details
 
8Tender for Procurement Of 300 mm ERW pipes Details
 
8Tender for Procurement of Transformer Oil Details
 
8Tender for work of Replacement of condenser tubes Details
 
8Tender for Procurement of spares for Dryer Details
 
8Tender for Supply & Installation of Flue Gas Desulphurisation (FGD) and Auxiliary System Details
 
8Tender for Procurement of Various type of valves installed in AHP Details
 
8Tender for supply of 33kV lattis structure Details
 
8Tender for Construction Of 4x33 kV bays at 132 kV S/Stn by dismantling of 2x33 kV bays Details
 
8Tender for supply & delivery of 02 Nos. transformer Details
 
8Tender for Biennial Maintenance Contract for Regular & Running Maintenance of all Electrical Equipments Details
 
8Tender for Carrying out operation of DG Sets, Submersible Pumps, Station Service Boards and Cooling Water System Details
 
8Design, manufacture, testing, delivery of 3 phase Oil filled transformers Details
 You can also click on Tenders
for more
For reference purposes the website carries here the following Newsclips: 
8Adani, Azure top bidders for manufacturing-linked solar tender Details
8Mercedes-Benz set to roll out its first fully-electric vehicle in April 2020 Details
8SC seeks Centre's reply on implementation of policy to convert public transport vehicle to EVs Details
8Adani Solar retail distribution in Karnataka soon Details
8"Undue favour" given to "disqualified" Adani Enterprises in award of coal supply contract: CBI Details
8India will have 225 GW of renewable energy capacity by 2022, including large hydro: MNRE Secy Details
8EV startup BattRE launches entry-level electric scooter LoEV Details
8Punjab CM to target SAD over controversial power agreements Details
8Maharashtra: Mahavitaran seeks 6 per cent increase in power tariff Details
8Deutsche Bank-led group a step closer to Jindal India deal Details
8Govt's proposed discom scheme positive measure for the power sector Details
8We are investing to build the solar agriculture market: Saravanan Paneer Selvam, Grundfos India Details
8Electricity Act may be amended to ensure discoms honour power pacts Details
8Electrical industry expects Rs 30,000 cr biz at flagship showcase event ELECRAMA Details
8Maharashtra: Pawar, Nagpurians want power plants shifted to Nashik Details
You can also click on Newsclips for more
Details

Our Take

Jan 17: 8SKS Power Generation (Chhattisgarh) Limited: The company’s cash flows will remain sensitive to variation in short-term power tariff levels Details
8P & R Gogripur Hydro Power Pvt. Ltd: Ratings withdrawn Details
8Shifting to renewables could grow the world economy by 1% a year until 2050: An analysis Details
8What are the implications of climate change investments? Details
8Adani Power Jharkhand Ltd: Pushing debt levels up for group company Details
You can also click on Reports
for more Details

Our Take

Jan 16: 8GRIDCO Ltd.: Improved financials and operational performance Details
8India will be the first such economy that has not depended upon a high level of fossil fuel burning per dollar of GDP: An analysis Details
8Arhyama Solar Power Private Limited: Under non-cooperating category with rating agency Details
8Business Opportunity: Setting up of 1200MW Wind-Solar Hybrid power projects Details
8FGD implementation schedule for thermal units in India: An update Details
8Lanco Solar Private Limited: Non-Cooperating with rating agency Details
You can also click on Reports
for more Details

Download Tenders and Newsclips

Jan 16: For reference purposes the website carries here the following tenders: 
 
8Tender for Annual Overhauling of Boiler Pressure part Details
 
8Tender for Rate Contract for maintenance of milling system Details
 
8Tender for Overhauling of steam generator auxiliaries Details
 
8Tender for procurement of LT power & control cable Details
 
8Tender for AMC of Turbine Aux. valve and heat exchanger Details
 
8Tender for AMC of ESP wet ash handling system Details
 
8Tender for Procurement of pneumatic cylinders & its spare kit for TPP Details
 
8Tender for Annual work contract for maintenance of 200 kV & 400 KV Switchyard equipments Details
 
8Tender for rate contract for erection and dismantling of emergency restoration system Details
 
8Supply, Erection, Modification, Testing & Commissioning of LT Switchgear with Breaker retrofitting Details
 
8Design, Supply, Erection, Testing and Commissioning of Mechanical BOPs like Drainage & Dewatering System Details
 
8Tender for Supply of equipments & Work of replacement of Various existing EHV equipments Details
 
8Tender for Supply, Civil, Erection, Testing & Commissioning of 110kV level creation Details
 
8Tender for work of Repairing/Overhauling & providing of spares for Air compressors Details
 
8Tender for supply of Imported Non-coking coal Details
 
8Tender for work of RLA Study in 2 Nos. boilers Details
 
8Tender for supply of Plante type battery banks Details
 
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips: 
8German Officials Agree Plan to Exit Coal-Fired Power by 2038 Details
8Andhra plans to transfer power assets to APPFCL Details
8Kalpataru Power Q3 PAT seen up 37.1% YoY to Rs. 126.1 cr: ICICI Direct Details
8With divestment target under pressure, Centre fast-tracks strategic sales process Details
8KEC International Q3 PAT seen up 36.7% YoY to Rs. 153.6 cr: ICICI Direct Details
8India's thermal coal imports at major ports down by 17 per cent this fiscal Details
8Centre begins commercial coal auction process Details
8Coal companies must make extra voluntary contribution to staff pension fund: CMPFO Details
8Soon, Goa’s colleges will generate their own power Details
8Maharashtra: MSEDCL proposes astronomical GSC for solar rooftop Details
8Rajasthan: Bylaw breather for 1,500 rooftop restaurants in Jaipur Details
8Honda, Isuzu power up fuel cell partnership for heavy-duty trucks Details
8Cong leader seeks judicial probe into high rates of electricity supplied by private firms in Punjab Details
8Maharashtra: MSEDCL residents tariff may be steepest after 5-8 per cent hike Details
8Government proposes grant of Rs 1.1 lakh crore for state discoms Details
You can also click on Newsclips for more
Details

Download Tenders and Newsclips

Jan 15: For reference purposes the website carries here the following tenders: 
8Tender for HM Works comprising, Design, preparation of detailed fabrication subassembly Details
8Tender for Electromechanical Works for HEP Details
8Tender for Annual Comprehensive O&M Contract for 50 MW Grid Connected Details
8Tender for Supply of LT Transformers Details
8Tender for work of assembly of 33kV Isolator Details
8Tender for Insulation of Pipe, Valve & Equipment Details
8Tender for procurement Spares for ESP controllers Details
8Tender for Supply & replacement of suspension string insulators Details
8Tender for Constructing of 600M OH Line Details
8Tender for Constructions of 11kV OH line Details
8Tender for Supplying and drawing 11kV covered conductor Details
8Tender for supply of HT ABC Details
8Tender for supply of dry type transformer Details
8Tender for supply of bushing installed guidevane operating system Details
8Tender for the Procurement of 4944 metres of cast basalt lined MS pipes Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8Coal auction rules: 4 per cent revenue share, affiliate companies not allowed Details
8By 2030, 57% of global power demand should be met by renewables: IRENA Details
8Global green tech revolution at risk, India can play role in reforming mining practices: Experts Details
8 Maharashtra: MERC withdraws compulsory gross metering for solar power Details
8 Chandigarh: 300 govt houses to get solar panels in Crest’s Rs 15cr project Details
8Tamil Nadu: Bright spot eludes solar powered agri income plan Details
8India’s renewable energy capacity reaches 86 GW in 2019; wind takes biggest share Details
8 Adani in early talks to acquire Reliance Power's troubled unit Details
8 Jaiprakash Power Ventures to exit insolvency process Details
8More than 400,000 German jobs at risk in switch to electric cars: Handelsblatt Details
8Tariff hike: KERC wants Bescom to justify expenses Details
8 Best Power Equipments appoints Anurag Mathur as Regional Director Details
8 Shapoorji Pallonji Group needs 5,000-6,000 cr Details
8Andhra Pradesh: Power connection for 50k ryots soon Details
8Yes Bank invokes pledged shares to acquire 30 per cent in Reliance Power's UP unit Details
8 Goa: Domestic power tariffs not hiked, power minister clarifies Details
8GE T&D India appoints Pitamber Shivnani as CEO & President Details
You can also click on Newsclips for more Details

Our Take

Jan 15: 8Unitech Power Transmission Ltd: The company’s operating and net profit margins are thin due to the nature of industry Details
8Meghalaya Energy Corporation Ltd: Collection Efficiency and High AT&C losses Details
8Power distribution sector debt pile of 4 trillion is a huge barrier for reform and low carbon transition: An analysis Details
8Safeguard duty on Chinese solar power equipment will make RE industry uncompetitive: An analysis Details
8Government to roll out one nuclear-reactor: Rolling out one nuclear-reactor each year will increase production of zero carbon energy: An analysis Details
8How Climate Change Affects the Building Energy Consumptions Due to Cooling, Heating, and Electricity Demands?  Details
You can also click on Reports for more Details

Software update: Power projects

Jan 15: Project Name: North Karanpura greenfield thermal power plant
8Project Cost: Rs 14336.00crores
8Project EventRFQ for supply, erection, installation, testing, and commissioning of ESP for unit-3 is likely to be floated in March 2020
Click here for more details
Project Name: Barh super thermal power project stage-II - FGD Addition

8Project Cost: 330.00 Crores
8Project Event: RFQs for the award of the FGD installation package is expected by March 2020. Further bids are expected soon.
Click here for more details
Project Name: Bhusawal brownfield thermal power station

8Project Cost: Rs 4500 crore
8Project Event:RFQ for the erection, testing, and commissioning of natural draught cooling towers is expected by Q2 2020.
Click here for more details
Project Name: Patratu superthermal greenfield power plant

8Project Event: RFQ for supply, erection, installation testing and commissioning of FGD for Units-1,2,3 is likely to be floated on Q2 2020.
Click here for more details Details

Rs 31,000 crore power plant: Switchyard package coming up

Jan 13: Project Name: Greenfield Thermal Power Station
 
8Project Cost: Rs 31000.00crores
8Project Description:
Erection and commissioning of the first four units of SG and TG 4x800 MW are in progress. Civil works of SG for fifth units are yet to start. Erection and commissioning of TG for the first fourth units are also in progress. Bids for natural draught cooling tower for all 5 units will be opened on 20th January 2020. BHEL has also floated tenders for single steel flue RCC chimney for unit -5 and twin steel flue RCC chimney for all units except unit -5. Bids will be opened later this month. RFQ for the switchyard package for all units is likely to be floated in Q2 2020.
Click here for more details
Details

Greenfield Super Thermal Power Project: Cooling tower requirement coming up

Jan 13: Project Name: Greenfield Super Thermal Power Project
8Project Cost: Rs 12772.00 crores
8Project Description: The BTG contractor BHEL has completed the piling works in the boiler area for TANGEDCO's greenfield 1600 MW (2x800 MW) supercritical thermal power plant. The work got delayed due to issues connected with balance land acquisition issues. The civil works for the main plant area are in progress. Currently, BHEL has floated tenders for the erection, testing, commissioning and trial operation of the boiler and its auxiliary for unit -1. Bids will be opened on 30th January 2020. RFQ for the civil, structural, architectural, mechanical work including testing, commissioning and trial operation of the natural draught cooling tower is likely to be floated in Q2 2020.
Click here for more details
Details

Greenfield Standalone Pump Storage Project: EIA consultant RFQ ahead

Jan 13: Project Name: Greenfield Standalone Pump Storage Project
8Project Cost: 1347.63 crores
8Project Description: Pre- Feasibility report is completed and it is prepared by in house resources. Detailed topographical surveys and geotechnical investigations will be initiated during the feasibility studies. TOR is prepared and it is submitted. RFQ for EIA consultant is likely to be floated on Q2 2020. Further bids are expected soon.
8Project Event: RFQ for EIA consultant is likely to be floated on Q2 2020.
8Expenditure Approval: Q3:2020.
8RFQ Date: Q2:2020
8Release Date: Q2: 2020
8Start Date: 2021
8Completion Date: 2025
Click here for more details
Details

Advanced Ultra-Super-critical Thermal Power Demonstration Project: RFQs ahead

Jan 13: Project Name: Advanced Ultra-Super-critical Thermal Power Demonstration Project, Stage-III
8Project Cost: 9484.00 crores
8Project Description: The terms of reference have been granted in February 2019. A consortium of NTPC, BHEL, and IGCAR has carried out R&D activities consisting of several analytical investigations including field tests for the development of Advanced Ultra-supercritical (AUSC) Technology. The project envisages the development of indigenous technology for steam parameters of 310 Kg/cm2 and 710 °C / 720 °C temperature under the Development of Clean Coal (Carbon) Technologies Mission. No additional land is proposed to be acquired for the project. EIA study has been  completed. But EC is not granted yet. BHEL will be selected as an EPC Contractor.
8Project EventRFQ for coal handling plant is likely to be floated by Q3 2020.
 Click here for more details, including key contacts Details

Our Take

Jan 13: 8CESC: Company is expected to report weak Q3FY20E results on back of lower generation in the base business Details
8NTPC: Better hydro generation and LC payment mechanisms issues for SEB's has hurt the operational performance for Q3FY20E Details
8Annual investments in renewables must double by 2030 to ensure a sustainable future Details
8India's Energy efficiency improves, but needs to accelerate: An analysis Details
8Kalpataru Power: KPTL is expected to report strong revenue which is expected to grow by 16.4% to Rs 2007.6 crore in Q3FY20E Details
8Business Opportunity in Coal mining project Details
You can also click on Reports for more Details

Download Tenders and Newsclips

Jan 13: For reference purposes the website carries here the following tenders: 
 
8Tender for the work of Annual Maintenance of Hydro Turbine & Generating assemblies Details
 
8Tender for Procurement of Sulphuric Acid for TPS Details
 
8Tender for Procurement of Conveyor belt textile-steel cord for coal handling plant Details
 
8Tender for Round the clock operation, routine, preventive & breakdown maintenance of C&I system Details
 
8Tender for Procurement of complete set of IPC nozzle for LMZ Turbine Details
 
8Tender for Procurement of 415V LT switchgear Details
 
8Tender for Overhauling of ESP of TPS Details
 
8Tender for Procurement of Spare Parts of Wagon Tippler, Side Arm Charger & Rotary Breaker for CHP Details
 
8Tender for Procurement of spares for KWU Steam Turbines Details
 
8Tender for procurement of 220 V nickel cadmium battery banks Details
 
8Tender for replacement of defected & damaged LT panels Details
 
8Tender for the work of R&M of electrical installation Details
 
8Tender for operation of 132/33/11kV substation and maintenance of 33/11KV substation Details
 
8Tender for Maintenance of 33 KV, 11 KV & LT Lines Details
 
8Tender for Biennial Maintenance Contract for Electrical Operation & Running Maintenance and regular electrical maintenance Details
 
8Tender for maintenance contract for boiler pressure parts Details
 
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips: 
8Govt plans to restrict coal supply to Andhra Pradesh Details
8Odisha power reforms model for States’ Details
8Coal sector gets a fresh lease of life. India has to do more Details
8Siemens will back controversial Australian coal project: CEO Joe Kaeser Details
8Solar power association writes to Nitin Gadkari against NTPC’s tender conditions Details
8Coal India will remain dominant player: Union coal minister Pralhad Joshi Details
8In Talks With Mongolia, Russia to Import Coking Coal: Pradhan Details
8Germany's Siemens to fulfill Australia coal mine contract Details
8Punjab: Ludhiana Smart City Mission to begin phase II of solar project soon Details
8Panasonic's India aims to expand EV charging offerings Details
8Abu Dhabi-based agency calls for clean energy investments to double Details
8Tata Power Solar bags Rs 1,505 crore project from NTPC under CPSU scheme Details
85-year power tariffs for home users: BEST, Tata seek hikes, Adani cuts Details
8Adani seeks 1 per cent cut, Tata 9 per cent hike in power tariffs Details
8Matter of pride for Haryana to score first rank in State Energy Efficiency Index 2019, says Khattar Details
8Major shift: PMO mulls to open gates for FDI in nuclear power Details
8China says no significant cut in new energy vehicle subsidies in 2020 Details
8Chandigarh: UT asks power regulator to fix T&D losses at 13.3 per cent Details
8Chandigarh to induct EVs; evaluated as progressive UT in energy efficiency index Details
You can also click on Newsclips for more
Details

Our Take

Jan 10: 8Renewable energy sector makes rapid strides in 2019: A report
8PM's office proposes waiving carbon tax on coal:An analysis Details
8India plans $35 bn reforms to revive struggling power retailers: Bailing out power retailers will reward excessive risk taking: An analysis Details
8Why not use natural gas or coal with carbon capture? Details
8Business Opportunity: Many outage programmes of generating units and transmission lines are coming soon Details
You can also click on Reports for more Details

Download Tenders and Newsclips

Jan 10: For reference purposes the website carries here the following tenders: 
 
8Tender for Supply and retrofitting of 800A 3 Pole ACB Details
 
8Tender for Procurement of Spares parts of Paddle Feeder installed at CHP Details
 
8Tender for Annual Work Contract for Routine Maintenance of Boiler fluid systems Details
 
8Tender for Procurement of solenoid valves with coils for various pneumatic system Details
 
8Tender for E&M work including technological structures for CHP R&M work Details
 
8Tender for procurement of Economiser coils Details
 
8Tender for procurement of 200V, 990AH nickel cadmium battery banks Details
 
8Tender for construction of 11kV feeders Details
 
8Tender for the work of overhauling & servicing of various make 22kV Circuit breakers Details
 
8Tender for Rate Contract for supply of HT/LT ABC Hardware Items Details
 
8Tender for the supply of items for testing and maintenance equipments Details
 
8Tender for the supply of hydrochloric acid Details
 
8Tender for Job of complete removal of damaged V-bars and Grid materials and refitting with new V-bars and Grid materials Details
 
8Tender for the work of Flue Gas Desulphurisation (FGD) Project Management & Engineering consultancy services Details
 
8Tender for Procurement of Battery charger Details
 
8Tender for Procurement of copper control cable Details
 
8Tender for ARC for attending Boiler Tube Leakage and other allied works Details
 
You can also click on Tenders for more
 For reference purposes the website carries here the following Newsclips:
 
8Coal India resources get a boost of 8.3 BT after Centre’s allocation of 16 blocks Details
 
8EESL electric vehicle tender failed as vehicles were not for personal use: Pawan Goenka Details
 
8Installed Renewable Energy Capacity Crosses 84GW Details
 
8Indian power ministry seeks more time for coal-fired plants to install emission cutting equipment Details
 
8Ease of mining coal needs to be accompanied by regulatory overhaul Details
 
8India’s energy choices are critical for the world Details
 
8No financial and technical yardstick for coal auctions Details
 
8Commercial mining could be limited by a move towards clean energy: Care Ratings Details
 
8Indian Railways to procure 1,000 Mw solar power by 2021-22 Details
 
8Green developers in AP lost Rs 1,400 cr since August Details
 
8Sterling and Wilson must be held liable for failure to protect minority shareholders: InGovern Details
 
8India not to be a significant player in offshore wind energy anytime soon: Alexander Fløtre, Rystad Energy Details
 
8Loom Solar launches world's first IoT-based solar AC module Details
 
8Electric Vehicles: ABB, Ashok Leyland join hands to develop flash-charging bus Details
 
8NHPC likely to deliver a better Q3 on growth in generation Details
 
8Power ministry launches portal to track states' energy efficiency performance Details
 
You can also click on Newsclips for more
Details

Our Take

Jan 09: 8Tuppadahalli Energy India Pvt Ltd: The company remains exposed to counterparty credit risks due to exposure to a single buyer Details
8What are the global perspective on electric vehicle 2020? Details
8Coal import demand is expected to be subdued in coming months: A report
8International Grid Integration: What are the strategic implications in Asia? Details
8Business Opportunity in Capital power plant Details
You can also click on Reports for more Details

Download Tenders and Newsclips

Jan 09: For reference purposes the website carries here the following tenders: 
 
8Tender for AMC for attending preventive work of 220kV & 132kV EHV transmission lines Details
 
8Tender for Work of online, routine, preventive, breakdown, AOH & COH maintenance of AHP silo system Details
 
8Tender for Supply of Caustic Soda Lye TPP Details
 
8Tender for Annual Work Contract for Routine Maintenance of Boiler Fuel System Details
 
8Tender for Design, engineering and supply of 220/132kV single core XLPE cable Details
 
8Supply, Installation, Commissioning and Comprehensive Annual Maintenance Contract of CAAQMS Details
 
8Tender for fixing and termination jobs of various size LT UG cable Details
 
8Tender for Replacement of 68 nos pendent re-heater coils Details
 
8Tender for construction of 33kV ring lines on panther conductor Details
 
8Tender for BRC for the work of spray insulation of various turbine modules Details
 
8Tender for Work Contract for the work of Chemical Washing of disc insulator strings Details
 
8Tender for Annual rate contract for maintenance work of various 132kV, and 220kV EHV Substations Details
 
8Tender for operation and maintenance for lignite handling system Details
 
8Tender for AMC for Coal Mill auto rejection system Details
 
8Tender for supply & delivery of ring and ball sets Details
 
8Tender for Attending breakdown works in Bottom Ash Hopper Details
 
You can also click on Tenders for more
 For reference purposes the website carries here the following Newsclips:
 
8Emission controlling systems: Don’t bundle coal and renewable power Details
 
8Coal blocks in India no longer ‘captive’; Steel, power firms may bid for mines Details
 
8India in talks with World Bank for Modi’s global electricity grid plan Details
 
8SoftBank in talks to sell stake in India's renewable energy venture: Report Details
 
8Cabinet okays Ordinance removing end-use restrictions in coal mine auctions Details
 
8SAD alleges undue benefit to pvt power plants by Cong-led Pb govt Details
 
8Supreme Court stays HC order, lets DRI pursue case against Adani firms Details
 
8Supreme Court seeks centre's response on plea challenging Coal Mines Act provisions Details
 
8Environment Ministry clears 10 coal mining projects Details
 
8India to ease mining rules from March to spur investment Details
 
8Cabinet approves India-UK MoU for energy self-sufficiency in railways Details
 
815 lakh power sector employees, engineers on strike: AIPEF Details
 
8Lithium completes acquisition of 1000 Mahindra EVs in its fleet Details
 
8Banks seeing credit demand from solar, oil & gas and road: SBI Chairman Details
 
8Kerala: Kozhikode to get 26 electric vehicle charging stations Details
 
You can also click on Newsclips for more
Details

Greenfield Hydroelectric project: Civil work package in Q2, 2020

Jan 08: Project Name: Greenfield Hydroelectric Power Project
8Project Cost: 1994.74 crores
8Project Description: The land survey for the project is in process and a Nodal Officer has been appointed by state government for processing the work for the land acquisition, but the progress of work has been slow. The socio-economic survey and public hearings were carried out by the consultant and the report has been submitted to the higher authority. SIA studies had been completed. Drilling and drifting works are in progress. RFQ for the civil work package -2 is likely to be floated in Q2 2020.
Click here for more details, including key contacts
Details
  • Jan 08: Greenfield Hydroelectric project: Civil work package in Q2, 2020:Details
  • Jan 08: WFGD and DeNOx system: Equipment RFQs ahead:Details
  • Jan 08: Download Tenders and Newsclips:Details
  • Jan 07: Our Take:Details
  • Jan 07: Download Tenders and Newsclips:Details
  • Jan 06: Our Take:Details