MPPTCL invites bids for five 500 MVA, 400/220/33 kV autotransformers under a pass-fail loss regime
8Loss ceilings of 90 kW no-load and 500 kW load carry no capitalisation, yet a first-unit 2% exception and penalties at double the evaluation cost apply.
8A 14th-month versus March 2027 delivery illustration and a 5% versus 10% guarantee keep schedule and security risk with manufacturers.
OMC tenders feasibility study and DPR for the 4.5 km Sasubohumali ghat road on a lump-sum fee
8Only panel firms with greenfield hill-road credentials can bid, yet the contract form makes the consultant answerable for executants' completion and payments.
8A 20% site-verification payment with no deadline and guarantee tails of three, four and 12 months keep liability and cash-flow risk with the consultant.
NHPC puts its 50 MW Lakhmana wind farm up for sale through a forward auction at a Rs 177 crore reserve
8Generation has averaged 30.2% below estimate, the PPA expired in 2019 and the incumbent O&M contract ends on 30 November 2026.
8A BOQ note seeking 25 years of O&M and a tax-inclusive quote, against an SCC that says otherwise, leaves bids on unequal bases.
BSPGCL tenders 491.903 MW of feeder-level solar across 206 substations with a contested 5 MWh battery clause
8Bid sheet Item 34(b) mandates storage from 2.5 MW while the RFP says the project excludes it, and the 60% minimum share leaves residual capacity unfillable at 52 of 60 qualifying sites.
8PBG encashment windows of six and 15 months keep pricing and security risk with developers.
APCPL awards Rs 350.67 crore Jharli coal supply to Tirupati Minerals at Rs 7,013.45 per tonne among six bids
8The GCV band cut to 3,550–4,000 kcal/kg matches the pricing base, and payment falls to 88.8% at 3,550 and 44.4% at 3,549.
8Station-end testing, adjusted tonnage for freight and a Rs 1 per tonne clause keep quality and working-capital risk with the supplier.
SECL bundles mine development, overburden removal and coal dispatch at Chhal into a Rs 2,703 crore, 4,018-day contract
8Bid dates slipped 22 days, 43.814 Ha of the first 50.06 Ha awaits resettlement, and 20% of the fleet must run on electric, CNG or LNG with no price variation.
8Lowest-of-three lead rules, steel-contamination recoveries and a 135- versus 122-month ePBG gap keep access, billing and guarantee risk with the contractor.
BHEL splits Raghunathpur boiler erection into two packages worth Rs 218.72 crore after L4 accepts a counteroffer
8Termico won Package A at Rs 109.4665 crore, while Indwell and Bhavani declined before P.E. Erectors took Package B at Rs 109.2488 crore.
8Four extensions, a B.1 qualification rewrite and an award 246 days after close keep validity and shared-facility risk with bidders.
GSECL seeks a 45 MLD effluent treatment EPC with two years of O&M at Ukai, ranked partly on power use
8Each extra kWh/day of guaranteed consumption adds Rs 18,055 to the evaluated price over a 15-year horizon.
8A 5% versus 10% guarantee, 46,920 m³/day of inflow against a 45 MLD plant and trial acceptance at 22.5 MLD keep design and security risk with the contractor.
RVPN admits nine bids for the Rs 143.63 crore Hathi Bhata 132/33 kV GIS after six deadline extensions
8Cable losses priced at Rs 2.96 lakh per kW, a fixed 1,800 m HDD quantity and item-rate deductions on overruns can reorder bids.
8An additional-security trigger below roughly Rs 122.09 crore and a 62-month kit guarantee keep civil and financing risk with the contractor.
IOC, HPCL and BPCL tie at Rs 86.0043 crore for NTPC North Karanpura's 6,000 KL LDO supply
8All three oil marketing companies quoted identical totals, triggering an equal-rate quantity split for 365-day supply paid by 100% lot-wise advance with no EMD or CPG.
8A payment comparator written "between two Vendors", no split ratio, firm freight and a 7-day versus 15-day delivery clock keep margin and LD risk with suppliers.
MPMKVVCL splits Rs 94.00 crore transformer rate contract across seven makers, leaving 31 units of 5 MVA unplaced
8The award covers 86 of 117 5 MVA units at Rs 63.80 lakh each, 36.8% above the implied estimate, and all 46 10 MVA units after Suman Electricals cut its quote by 11.9%.
8Cancellation for convenience before inspection, upward price variation lost after supplier delay and 45-day payment without interest keep inventory and working-capital risk with manufacturers.
UPPTCL opens a rejected bidder's price bid for Prayagraj GIS substation 19 days late under High Court orders
8Safety Controls & Devices' packet for the Rs 102.16 crore 220/33 kV, 4×60 MVA package was opened on 17 November, after nine qualified bids were opened on 29 October.
8Feeder-bay counts of one, three and two, leftover Agra site references and a 3-month versus 45-day CPBG tail keep scope and guarantee risk with the EPC contractor.
UPPTCL seeks Rs 4 lakh survey and layout study for Gomti Nagar 220/132 kV GIS/AIS and bus conversion
8The very short e-tender closes on 25 November for layouts of a proposed 2×160 MVA installation and a double-main conversion of the existing yard, with a Rs 10 lakh turnover floor.
8A 24 versus 25 November deadline, three months versus 45 days for execution and undefined drawing-acceptance criteria keep redraw and working-capital risk with the consultant.
PFC invites Category A law firms to paper Rs 477.78 crore loan for Mahathi's Cuddalore port
8The limited GeM bid closes on 23 November for least-cost selection of lender's counsel on an 8.88 MTPA seaport whose concession bars mortgaging the site and facilities.
840% of an all-inclusive fee tied to the closing opinion, conflicting tests at exactly five assignments and rival tie-break rules keep fee and eligibility risk with bidders.
RECPDCL pushes YEIDA 400/220 kV GIS deadline to 25 November and squeezes the post-auction window
8Amendment III adds eight days to submission, moving the reverse auction to 8 December and SPV transfer to 28 December with the Rs 5.28 crore bid bond and Rs 13.20 crore guarantee unchanged.
8Three days to deliver originals after the auction, a 12-day LoI-to-transfer gap against a 10-day clause and commercial operation tied to Aligarh bays keep closing risk with bidders.
KPTCL reports Rs 241.47 crore secure-infrastructure award to ITI with no bid count or estimate
8The open, two-cover lump-sum package covers design, supply, integration and commissioning across substations and centralised locations, with 17 November shown as an indicative contract date.
8No stated contract period, site count, acceptance criteria or payment milestones keep integration and working-capital risk with the contractor.
RRECL clears 11 of 19 bids for Rs 99.77 crore PM E-Drive charging rollout after easing the revenue-share rule
8The seven-package tender covers 236 locations on a 10-year term, with H1 selection on revenue share per kWh and financial opening scheduled for 16 November.
8Escrow settlement left to contract signing, no subsidy timetable, no carve-out for DISCOM delays and a 150- versus 180-day bid-security mismatch keep liquidity risk with operators.
KPTCL awards Hanur 220 kV substation package at Rs 209.08 crore on a single bid, 24.3% above estimate
8The 24-month package for 2×150 MVA transformation, a 13.458 km 220 kV DC line and 58.733 km of 66 kV links went to M T Kumar after Amendment-I let bidders qualify through a tower-design consultant.
8An unclear GST basis for the award, conflicting time-extension clauses, ceiling-based tower payments and contractor-funded ROW compensation keep pricing and cash-flow risk with the contractor.
GUVNL's 1,500 MW RTC auction fills the requirement in only two of eight months
8The tender for 1,500 MW of RTC and 1,500 MW of non-solar power from 16 November 2026 to 30 June 2027 drew RTC tariffs of Rs 8.90–10.00/kWh, with volumes ranging from 75 MW in November to 1,500 MW in February and March.
8Anonymous "XX" entries, unreconciled overnight delivery windows, no recorded acceptance or PPA quantities and an unclear LC mechanism keep supply-adequacy risk with GUVNL.
GUVNL's non-solar power auction draws just 50 MW at Rs 29–35/kWh against a 1,500 MW requirement
8November and January drew no non-solar bids, and the other six periods recorded 50 MW each at up to 293.3% above the lowest RTC tariff, while RTC drew sources from Ambitious, Jindal, Tata, NVVN and PTC.
8Single-offer periods that need GERC consent, unidentified suppliers behind every non-solar price and no explanation of the weak response keep procurement risk with GUVNL.
PSPCL awards Kapurthala RDSS package to SKS Infra at Rs 88.94 crore after the auction flips the ranking
8SKS moved from L2 to L1 by undercutting ABI's Rs 89.24 crore opening bid by a single 0.1% decrement, leaving the award 28.8% above the Rs 69.06 crore estimate for HT/LT loss-reduction works in three divisions.
8An unexplained Rs 20.88 lakh post-auction cut, 3% versus 10% performance-security clauses, no steel-structure escalation and GIS-linked final payments keep working-capital risk with the contractor.
PSPCL awards Nawanshahar RDSS package to ABI Energy at Rs 101.38 crore with no fresh auction bids
8Package 14's three ranked offers clustered 29.2–32.8% above the Rs 78.74 crore estimate, and the 730-day award came in Rs 34.46 lakh below ABI's evaluated L1 for reasons the record does not give.
8Conflicting 3% and 10% security terms, a "sixty-five (60) days" payment clause, lot-rejection penalties and a 473-day gap between the NoA and the portal contract date keep cash-flow and compliance risk with the contractor.
Kashmirilal overtakes ABI by Rs 9.46 lakh to win PSPCL's Rs 94.47 crore Mahilpur package
8The reverse auction cut Kashmirilal's own bid by 4.4% but improved on the best opening offer by only 0.1%, leaving the Package 12 award 27.1% above the Rs 74.33 crore estimate.
8Quality penalties of up to 5% of contract price, 10-year latent-defect liability, conflicting 3% and 10% security clauses and GIS-linked final payments keep execution and liquidity risk with the contractor.
RECPDCL pushes YEIDA 400/220 kV GIS deadline to 25 November but keeps the 18-month schedule
8Amendment III adds eight days to the previous deadline for the UPPTCL project, 23 days later than the original, moving the reverse auction to 8 December and SPV transfer to 28 December with the Rs 5.28 crore bid bond and Rs 13.20 crore CPG unchanged.
8No stated reason, a 12-day LoI-to-transfer window against clause 2.15.3's ten days and payment tied to simultaneous commissioning keep revenue-timing and execution risk with bidders.
PSPCL awards Jalandhar-2 RDSS package to ABI Energy at 28% above estimate
8The Rs 87.10 crore award against a Rs 68.04 crore estimate is Rs 19 lakh below ABI's evaluated bid, with Mangal and Vindhya 7.4% and 8.3% higher.
8An unexplained price cut, conflicting award dates and steel left out of price adjustment keep margin and timeline risk with the contractor.
DVC clears GE Vernova, Siemens and Techno Electric for Rs 133.63 crore Durgapur switchyard rebuild after eight extensions
8The DTPS GIS bids closed 75 days late, after escalation caps were removed for power transformers and R. S. Infraprojects was rejected over its surety bond.
8A 92-month security period, no payment for extra cable trays and gaps between drawings and the BOQ keep engineering risk with contractors.
CSPDCL gives contractors a six-month exit in its Rs 1,193 crore fault-restoration tender
8The corrigendum raises the vehicle odometer limit from 30,000 km to 1 lakh km, and a separate amendment moves submission to 25 November.
8A wrong incentive example, conflicting penalty start dates and uncapped CSERC compensation keep performance and payroll risk with contractors.
CCL's Rs 467.16 crore Amrapali–Shivpur coal evacuation tender says no ePBG but demands 5% performance security
8The three-year GeM package for 32,000 TPD of loading, haulage and wagon loading carries a Rs 50 lakh EMD and 3% retention.
8Payment on railway weighment, ±30% volume swings and a draft work order that bars escalation keep utilisation and cash-flow risk with transporters.
NTPC's Rs 200 crore Kudgi ash-haul panel guarantees no work orders
8Up to five AST-01 contractors must match the L1 rate to haul ash up to 300 km, with each capped at Rs 40 crore of work.
8A minus 100% variation clause, measurement-linked payment and extra security for deep discounts keep volume and liquidity risk with transporters.
JPDCL draws 14 bidders for Rs 159.46 crore Kathua Rural RDSS package after cutting performance security to 6%
8Bids for the Billawar, Basohli and Ramkote package opened on 14 November after an eight-day extension, with security now accepted as BG or surety bond.
8Price-variation bills tied to available funds and dismantling with no extra payment keep cash-flow and pricing risk with contractors.
JPDCL's Kathua Urban RDSS opening lists a bid stamped after the deadline
8Ten bidders were admitted for the Rs 239.60 crore package, but Vijai Electricals' entry is timed at 16:41, after the 14:00 closing.
8Price-variation billing tied to available funds and a vendor list disclosed only after award keep execution and recovery risk with contractors.
GUVNL's short-term power auction draws only 50 MW at Rs 29/kWh for non-solar hours
8Offers met the full 1,500 MW RTC requirement only in February and March, with lowest quotes of Rs 8.90–9.66/kWh.
8Unnamed "XX" sources behind 900 MW and PPAs not yet signed keep supply-firmness risk with GUVNL.
MPPTCL invites bids for five 500 MVA, 400/220/33 kV autotransformers under a pass-fail loss regime
8Loss ceilings of 90 kW no-load and 500 kW load carry no capitalisation, yet a first-unit 2% exception and penalties at double the evaluation cost apply.
8A 14th-month versus March 2027 delivery illustration and a 5% versus 10% guarantee keep schedule and security risk with manufacturers.
OMC tenders feasibility study and DPR for the 4.5 km Sasubohumali ghat road on a lump-sum fee
8Only panel firms with greenfield hill-road credentials can bid, yet the contract form makes the consultant answerable for executants' completion and payments.
8A 20% site-verification payment with no deadline and guarantee tails of three, four and 12 months keep liability and cash-flow risk with the consultant.
NHPC puts its 50 MW Lakhmana wind farm up for sale through a forward auction at a Rs 177 crore reserve
8Generation has averaged 30.2% below estimate, the PPA expired in 2019 and the incumbent O&M contract ends on 30 November 2026.
8A BOQ note seeking 25 years of O&M and a tax-inclusive quote, against an SCC that says otherwise, leaves bids on unequal bases.
BSPGCL tenders 491.903 MW of feeder-level solar across 206 substations with a contested 5 MWh battery clause
8Bid sheet Item 34(b) mandates storage from 2.5 MW while the RFP says the project excludes it, and the 60% minimum share leaves residual capacity unfillable at 52 of 60 qualifying sites.
8PBG encashment windows of six and 15 months keep pricing and security risk with developers.
APCPL awards Rs 350.67 crore Jharli coal supply to Tirupati Minerals at Rs 7,013.45 per tonne among six bids
8The GCV band cut to 3,550–4,000 kcal/kg matches the pricing base, and payment falls to 88.8% at 3,550 and 44.4% at 3,549.
8Station-end testing, adjusted tonnage for freight and a Rs 1 per tonne clause keep quality and working-capital risk with the supplier.
SECL bundles mine development, overburden removal and coal dispatch at Chhal into a Rs 2,703 crore, 4,018-day contract
8Bid dates slipped 22 days, 43.814 Ha of the first 50.06 Ha awaits resettlement, and 20% of the fleet must run on electric, CNG or LNG with no price variation.
8Lowest-of-three lead rules, steel-contamination recoveries and a 135- versus 122-month ePBG gap keep access, billing and guarantee risk with the contractor.
BHEL splits Raghunathpur boiler erection into two packages worth Rs 218.72 crore after L4 accepts a counteroffer
8Termico won Package A at Rs 109.4665 crore, while Indwell and Bhavani declined before P.E. Erectors took Package B at Rs 109.2488 crore.
8Four extensions, a B.1 qualification rewrite and an award 246 days after close keep validity and shared-facility risk with bidders.
GSECL seeks a 45 MLD effluent treatment EPC with two years of O&M at Ukai, ranked partly on power use
8Each extra kWh/day of guaranteed consumption adds Rs 18,055 to the evaluated price over a 15-year horizon.
8A 5% versus 10% guarantee, 46,920 m³/day of inflow against a 45 MLD plant and trial acceptance at 22.5 MLD keep design and security risk with the contractor.
RVPN admits nine bids for the Rs 143.63 crore Hathi Bhata 132/33 kV GIS after six deadline extensions
8Cable losses priced at Rs 2.96 lakh per kW, a fixed 1,800 m HDD quantity and item-rate deductions on overruns can reorder bids.
8An additional-security trigger below roughly Rs 122.09 crore and a 62-month kit guarantee keep civil and financing risk with the contractor.
IOC, HPCL and BPCL tie at Rs 86.0043 crore for NTPC North Karanpura's 6,000 KL LDO supply
8All three oil marketing companies quoted identical totals, triggering an equal-rate quantity split for 365-day supply paid by 100% lot-wise advance with no EMD or CPG.
8A payment comparator written "between two Vendors", no split ratio, firm freight and a 7-day versus 15-day delivery clock keep margin and LD risk with suppliers.
MPMKVVCL splits Rs 94.00 crore transformer rate contract across seven makers, leaving 31 units of 5 MVA unplaced
8The award covers 86 of 117 5 MVA units at Rs 63.80 lakh each, 36.8% above the implied estimate, and all 46 10 MVA units after Suman Electricals cut its quote by 11.9%.
8Cancellation for convenience before inspection, upward price variation lost after supplier delay and 45-day payment without interest keep inventory and working-capital risk with manufacturers.
UPPTCL opens a rejected bidder's price bid for Prayagraj GIS substation 19 days late under High Court orders
8Safety Controls & Devices' packet for the Rs 102.16 crore 220/33 kV, 4×60 MVA package was opened on 17 November, after nine qualified bids were opened on 29 October.
8Feeder-bay counts of one, three and two, leftover Agra site references and a 3-month versus 45-day CPBG tail keep scope and guarantee risk with the EPC contractor.
UPPTCL seeks Rs 4 lakh survey and layout study for Gomti Nagar 220/132 kV GIS/AIS and bus conversion
8The very short e-tender closes on 25 November for layouts of a proposed 2×160 MVA installation and a double-main conversion of the existing yard, with a Rs 10 lakh turnover floor.
8A 24 versus 25 November deadline, three months versus 45 days for execution and undefined drawing-acceptance criteria keep redraw and working-capital risk with the consultant.
PFC invites Category A law firms to paper Rs 477.78 crore loan for Mahathi's Cuddalore port
8The limited GeM bid closes on 23 November for least-cost selection of lender's counsel on an 8.88 MTPA seaport whose concession bars mortgaging the site and facilities.
840% of an all-inclusive fee tied to the closing opinion, conflicting tests at exactly five assignments and rival tie-break rules keep fee and eligibility risk with bidders.
RECPDCL pushes YEIDA 400/220 kV GIS deadline to 25 November and squeezes the post-auction window
8Amendment III adds eight days to submission, moving the reverse auction to 8 December and SPV transfer to 28 December with the Rs 5.28 crore bid bond and Rs 13.20 crore guarantee unchanged.
8Three days to deliver originals after the auction, a 12-day LoI-to-transfer gap against a 10-day clause and commercial operation tied to Aligarh bays keep closing risk with bidders.
KPTCL reports Rs 241.47 crore secure-infrastructure award to ITI with no bid count or estimate
8The open, two-cover lump-sum package covers design, supply, integration and commissioning across substations and centralised locations, with 17 November shown as an indicative contract date.
8No stated contract period, site count, acceptance criteria or payment milestones keep integration and working-capital risk with the contractor.
RRECL clears 11 of 19 bids for Rs 99.77 crore PM E-Drive charging rollout after easing the revenue-share rule
8The seven-package tender covers 236 locations on a 10-year term, with H1 selection on revenue share per kWh and financial opening scheduled for 16 November.
8Escrow settlement left to contract signing, no subsidy timetable, no carve-out for DISCOM delays and a 150- versus 180-day bid-security mismatch keep liquidity risk with operators.
KPTCL awards Hanur 220 kV substation package at Rs 209.08 crore on a single bid, 24.3% above estimate
8The 24-month package for 2×150 MVA transformation, a 13.458 km 220 kV DC line and 58.733 km of 66 kV links went to M T Kumar after Amendment-I let bidders qualify through a tower-design consultant.
8An unclear GST basis for the award, conflicting time-extension clauses, ceiling-based tower payments and contractor-funded ROW compensation keep pricing and cash-flow risk with the contractor.
GUVNL's 1,500 MW RTC auction fills the requirement in only two of eight months
8The tender for 1,500 MW of RTC and 1,500 MW of non-solar power from 16 November 2026 to 30 June 2027 drew RTC tariffs of Rs 8.90–10.00/kWh, with volumes ranging from 75 MW in November to 1,500 MW in February and March.
8Anonymous "XX" entries, unreconciled overnight delivery windows, no recorded acceptance or PPA quantities and an unclear LC mechanism keep supply-adequacy risk with GUVNL.
GUVNL's non-solar power auction draws just 50 MW at Rs 29–35/kWh against a 1,500 MW requirement
8November and January drew no non-solar bids, and the other six periods recorded 50 MW each at up to 293.3% above the lowest RTC tariff, while RTC drew sources from Ambitious, Jindal, Tata, NVVN and PTC.
8Single-offer periods that need GERC consent, unidentified suppliers behind every non-solar price and no explanation of the weak response keep procurement risk with GUVNL.
PSPCL awards Kapurthala RDSS package to SKS Infra at Rs 88.94 crore after the auction flips the ranking
8SKS moved from L2 to L1 by undercutting ABI's Rs 89.24 crore opening bid by a single 0.1% decrement, leaving the award 28.8% above the Rs 69.06 crore estimate for HT/LT loss-reduction works in three divisions.
8An unexplained Rs 20.88 lakh post-auction cut, 3% versus 10% performance-security clauses, no steel-structure escalation and GIS-linked final payments keep working-capital risk with the contractor.
PSPCL awards Nawanshahar RDSS package to ABI Energy at Rs 101.38 crore with no fresh auction bids
8Package 14's three ranked offers clustered 29.2–32.8% above the Rs 78.74 crore estimate, and the 730-day award came in Rs 34.46 lakh below ABI's evaluated L1 for reasons the record does not give.
8Conflicting 3% and 10% security terms, a "sixty-five (60) days" payment clause, lot-rejection penalties and a 473-day gap between the NoA and the portal contract date keep cash-flow and compliance risk with the contractor.
Kashmirilal overtakes ABI by Rs 9.46 lakh to win PSPCL's Rs 94.47 crore Mahilpur package
8The reverse auction cut Kashmirilal's own bid by 4.4% but improved on the best opening offer by only 0.1%, leaving the Package 12 award 27.1% above the Rs 74.33 crore estimate.
8Quality penalties of up to 5% of contract price, 10-year latent-defect liability, conflicting 3% and 10% security clauses and GIS-linked final payments keep execution and liquidity risk with the contractor.
RECPDCL pushes YEIDA 400/220 kV GIS deadline to 25 November but keeps the 18-month schedule
8Amendment III adds eight days to the previous deadline for the UPPTCL project, 23 days later than the original, moving the reverse auction to 8 December and SPV transfer to 28 December with the Rs 5.28 crore bid bond and Rs 13.20 crore CPG unchanged.
8No stated reason, a 12-day LoI-to-transfer window against clause 2.15.3's ten days and payment tied to simultaneous commissioning keep revenue-timing and execution risk with bidders.
PSPCL awards Jalandhar-2 RDSS package to ABI Energy at 28% above estimate
8The Rs 87.10 crore award against a Rs 68.04 crore estimate is Rs 19 lakh below ABI's evaluated bid, with Mangal and Vindhya 7.4% and 8.3% higher.
8An unexplained price cut, conflicting award dates and steel left out of price adjustment keep margin and timeline risk with the contractor.
DVC clears GE Vernova, Siemens and Techno Electric for Rs 133.63 crore Durgapur switchyard rebuild after eight extensions
8The DTPS GIS bids closed 75 days late, after escalation caps were removed for power transformers and R. S. Infraprojects was rejected over its surety bond.
8A 92-month security period, no payment for extra cable trays and gaps between drawings and the BOQ keep engineering risk with contractors.
CSPDCL gives contractors a six-month exit in its Rs 1,193 crore fault-restoration tender
8The corrigendum raises the vehicle odometer limit from 30,000 km to 1 lakh km, and a separate amendment moves submission to 25 November.
8A wrong incentive example, conflicting penalty start dates and uncapped CSERC compensation keep performance and payroll risk with contractors.
CCL's Rs 467.16 crore Amrapali–Shivpur coal evacuation tender says no ePBG but demands 5% performance security
8The three-year GeM package for 32,000 TPD of loading, haulage and wagon loading carries a Rs 50 lakh EMD and 3% retention.
8Payment on railway weighment, ±30% volume swings and a draft work order that bars escalation keep utilisation and cash-flow risk with transporters.
NTPC's Rs 200 crore Kudgi ash-haul panel guarantees no work orders
8Up to five AST-01 contractors must match the L1 rate to haul ash up to 300 km, with each capped at Rs 40 crore of work.
8A minus 100% variation clause, measurement-linked payment and extra security for deep discounts keep volume and liquidity risk with transporters.
JPDCL draws 14 bidders for Rs 159.46 crore Kathua Rural RDSS package after cutting performance security to 6%
8Bids for the Billawar, Basohli and Ramkote package opened on 14 November after an eight-day extension, with security now accepted as BG or surety bond.
8Price-variation bills tied to available funds and dismantling with no extra payment keep cash-flow and pricing risk with contractors.
JPDCL's Kathua Urban RDSS opening lists a bid stamped after the deadline
8Ten bidders were admitted for the Rs 239.60 crore package, but Vijai Electricals' entry is timed at 16:41, after the 14:00 closing.
8Price-variation billing tied to available funds and a vendor list disclosed only after award keep execution and recovery risk with contractors.
GUVNL's short-term power auction draws only 50 MW at Rs 29/kWh for non-solar hours
8Offers met the full 1,500 MW RTC requirement only in February and March, with lowest quotes of Rs 8.90–9.66/kWh.
8Unnamed "XX" sources behind 900 MW and PPAs not yet signed keep supply-firmness risk with GUVNL.
For daily newsletters and other free services, fill in your details: