All content in this website is sourced legitimately

MNRE extends the ALMM solar-cell exemption to 31 December 2026, sparing rooftop and open-access projects.  Daily Power Sector Tenders Excel update.  POWER MARKETS DAILY.  GRID OPERATIONS DAILY.  OUTAGE & MAINTENANCE REGISTER.  FUEL & COAL LEDGER.  HYDRO & RESERVOIR LEDGER.  CERC DOCKET.  STATE REGULATORY ROUNDUP.  GREEN MARKETS & RE PROGRAMME WATCH.  CORPORATE WIRE.  COMMITTEES, PEOPLE & SYSTEM ADMINISTRATION.  Methane blast kills at least 20 at NHPC's under-construction Teesta-VI tunnel in Sikkim.   IEX day-ahead sat at the Rs 10,000 ceiling in 54% of 21 July's blocks yet crashed to Rs 1,618 at noon.  The grid paid Western generators Rs 80 crore in one week to stay on the site as monsoon load slumped.  Half of India's inter-state transmission build is late - Rajasthan and Khavda solar links slip up to six years.  Adani Energy Solutions' Q1 profit doubles to Rs 1,237 crore on a Rs 71,779 crore transmission pipeline.  The North-East grid is going blind as its control-system bill jumps Rs 167 crore on AI-driven hardware prices.  Twenty-seven thermal plants run coal-critical in mid-monsoon - Andhra's Damodaram Sanjeevaiah down to 2%.  Jharkhand's discom posts a Rs 1,839 crore half-year loss as its accumulated deficit nears Rs 18,330 crore.  India's under-construction coal fleet swells to 42,700 MW even as this year's additions collapse to 2,260 MW.  Contracting news for the day: Part-1.  Download tenders and news clips.  Hydro & Reservoir Ledger.  Eastern thermal earned about Rs 112 crore in June for running part-loaded - the same stations were also failing their frequency duty.  Day-ahead power hit the Rs 10 ceiling overnight and at dusk on 20 July - yet the grid met a ~239 GW peak nearly shortage-free.  The North met a 93,981 MW summer peak nearly shortage-free - but a single wind trip cost Rajasthan 1,290 MW.  Jaiprakash Power’s Q1 profit jumps 69% to Rs 469 crore as NARCL files insolvency over a Rs 1,239 crore guarantee.  MERC lets Adani’s Mumbai discom adopt Rs 6.38 a unit for 750 MW of round-the-clock renewable power.   India’s pumped-storage build-out reaches 15,870 MW under construction as SECI awards another 1,344 MW.  Twenty-six thermal plants sit critical on coal in mid-monsoon - Andhra’s Damodaram Sanjeevaiah down to 2%.  Punjab’s power employees and pensioners strike for two days, forcing PSPCL to draft engineers to man substations.  Maharashtra’s new RE policy blocks MERC from ordering MSEDCL to buy Waterfront’s small-hydro - even after fixing its Rs 6.18 tariff.  About 40 GW sat on outage on 20 July as North Chennai lost 800 MW and Rajpura 700 MW to boiler and ESP faults.  Power Markets Daily.  Grid Operations Daily.  Outage & Maintenance Register.  Fuel & Coal Ledger.  Daily Power Sector Tenders Excel update.  CERC Docket.  State Regulatory Roundup.  Green Markets & RE Programme Watch.  Corporate Wire.  Committees, People & System Administration.  Contracting news for the day: Part-1.  Download tenders and news clips.  The West runs a surplus while the North and South ration - July's squeeze is a delivery problem, not a generation shortfall.  POWER MARKETS DAILY.  GRID OPERATIONS DAILY.  OUTAGE & MAINTENANCE REGISTER.  FUEL & COAL LEDGER.  HYDRO & RESERVOIR LEDGER.  CERC DOCKET.  STATE REGULATORY ROUNDUP.  GREEN MARKETS & RE PROGRAMME WATCH.  CORPORATE WIRE.  COMMITTEES, PEOPLE & SYSTEM ADMINISTRATION.  Nearly 30,000 MW has sat out of the grid for over a fortnight - flood, fire, tower collapse, GLOF and bankruptcy, some of it dead for years.  The West ran as a deviation conduit between East and South last week - settling a net Rs 51 crore, with Khavda solar the single biggest mover.  MNRE grants its sixth solar-cell reprieve in eight weeks and Delhi rewrites net-metering - a quiet admission that domestic cell supply still cannot carry distributed solar.  Tata Power lands a 40-year storage tolling contract from SECI - Rs 351 crore a year for a 324 MW pumped-storage plant, about Rs 14,000 crore over its life.  CERC forgives NTPC a 22.5-month captive-mine delay as force majeure, then fences the money - Rs 4,340 crore recast, Rs 136 crore stripped, Rs 59 crore clawed from the mining contractor.  A monsoon flood knocks out the 765/400 kV Champa hub in Chhattisgarh - all three transformers trip and the operator logs the situation "out of control".  The grid's designated shock-absorbers are its worst responders: NR's big hydro fleet scores near zero on governor response while NTPC thermal scores perfect.  Southern coal stocks fall to single digits - Damodaram Sanjeevaiah at 2%, and Telangana's Yadadri backs an 800 MW unit off the grid for want of coal.  Kerala's regulator adopts Rs 5.96/unit round-the-clock power and openly rebukes its own utility, ordering fixed day-ahead load-shedding as reservoirs fall to 28%.  Day-ahead and real-time power pinned the Rs 10,000/MWh ceiling through every peak block, 17–19 July.  Contracting news for the day: Part-1.  Contracting news for the day: Part-2.  Download tenders and news clips.  Daily Power Sector Tenders Excel update.  Contracting news for the day: Part-1.  Download tenders and news clips.  Power Markets Daily.  Grid Operations Daily.  

MNRE extends the ALMM solar-cell exemption to 31 December 2026, sparing rooftop and open-access projects

Jul 22: 8The renewable-energy ministry has pushed the deadline for mandatory use of listed domestic solar cells to 31 December 2026, from 31 May, for rooftop, net-metering and open-access projects. Utility-scale projects stay bound by the mandate, and everything must comply from 1 January 2027. Details

Daily Power Sector Tenders Excel update

Jul 22: 8Daily Excel covering new tenders and all published updates including corrigendum, amendment, addendum, clarification and status revisions, along with technical and financial bid opening, evaluation completion and final award actions including AOC and LOA issuance.
Click on Reports for more Details

POWER MARKETS DAILY

Jul 22: 8IEX day-ahead averaged Rs 6,617 on 21 July but held the Rs 10,000 ceiling in 54% of blocks
8Real-time power took the day's biggest volume - 192.70 MU - at a weekly-low Rs 4,143
8The green day-ahead cleared Rs 6,755 and term strips settled flat at Rs 6,350 - no green discount
8PXIL cleared nothing and HPX drew no buyers, so IEX carried the entire cleared market on 21 July
8DVC-style peak buying returns as GUVNL and UPPCL float HPX reverse auctions for evening blocks
8Rajasthan's merit order runs from Rs 0.99 at NLC Barsinghsar to Rs 27.87 for liquid-fuel peaking Details

GRID OPERATIONS DAILY

Jul 22: 8India met a 235,132 MW evening peak and a 237,218 MW day-max on 21 July with zero shortage
8The grid ran high a quarter of 21 July and the operators backed generation down by 51,305 MWh
8The North-East to Tripura corridor sat over its transfer limit for 51.9% of 21 July
8Gujarat alone curtailed 922 MW of solar and 353 MW of wind for grid security on 21 July
8The Northern grid switched out about 25 of its 765 kV bus reactors at dawn to hold voltage up
8India imported 51 MU from Bhutan and 22 MU from Nepal while wheeling power to Bangladesh Details

OUTAGE & MAINTENANCE REGISTER

Jul 22: 8About 43 GW of generation sat on outage on 21 July, the West carrying 18 GW of it
8Fresh 21 July trips took out Sasan 660 MW, Rihand-II 500 MW and a clutch of 200 MW units
8Yadadri's coal-starved 800 MW unit came back on 21 July; Ropar and Ghatampur stayed coal-hit
8North Chennai's 800 MW and Rajpura's 700 MW units stayed out on ESP and boiler faults
8Two Southern 400 kV corridors remain down two months after tower collapses in May
8Much of the 'outage' is economic reserve-shutdown - 2,700 MW of Western gas parked idle Details

FUEL & COAL LEDGER

Jul 22: 8Twenty-seven thermal plants ran coal-critical on 20 July; Damodaram Sanjeevaiah at 2%
8Coal ministry says 42 mines have been scientifically closed - a first since independence
8Fly-ash use hit 98.3% in 2024-25, but barely 1% of it moves by rail Details

HYDRO & RESERVOIR LEDGER

Jul 22: 8Telangana's Krishna reservoirs sit about 92% below last year deep into the monsoon
8Odisha's hydro fleet ran about 350 MW with several OHPC units forced out and reservoirs below last year
8Sikkim generated zero units on 21 July with the 1,200 MW Teesta-III still out since 2023 Details

CERC DOCKET

Jul 22: 8CERC proposes to grant PI Green Consulting a Category-V inter-state trading licence
8CERC clears POWERGRID's Mahan-Rewa transmission licence and rebukes Mahan Energen for non-compliance Details

STATE REGULATORY ROUNDUP

Jul 22: 8Uttarakhand's regulator clears a Kedarnath feeder after the fact and rebukes UPCL for jumping the gun
8Uttarakhand's ombudsman quashes a Rs 11 lakh back-bill and orders recovery from erring UPCL officers
8Bihar reserves one Section-142 order, lists two more and opens a supply code for sugar mills
8UP's regulator admits an Ayesha Steel removal-of-difficulty plea for a 20 August hearing
8Chhattisgarh's regulator takes up Jindal Steel's captive Raigarh ARR with a Rs 48 crore true-up gap
8Assam opens a public hearing on paying interest on consumers' security deposits
8Punjab's regulator advertises five deputation posts, including a secretary to the chairperson Details

GREEN MARKETS & RE PROGRAMME WATCH

Jul 22: 8MNRE extends the ALMM solar-cell exemption to 31 December 2026 for rooftop and open-access
8India's renewable capacity reaches 288.58 GW, four times its 2014 level, MNRE tells Parliament
8The power ministry halts two Tamil Nadu offshore-wind transmission projects
8India's battery-cell scheme has awarded 40 GWh but drawn zero incentive and Rs 5,180 crore of investment
8ACME Solar signs its 300 MW SECI hybrid PPA at Rs 3.25, lifting signed capacity to 6,870 MW
8Tripura's ADB-funded distribution plan pairs a 120 MW gas revamp with rooftop solar for weavers Details

CORPORATE WIRE

Jul 22: 8Adani Energy Solutions' Q1 profit doubles to Rs 1,237 crore
8Jharkhand's discom posts a Rs 1,839 crore half-year loss
8JSW Energy lifts its Toshiba-turbine stake to 20.7% as its GE Power India merger clears the vote
8BHEL's Trichy unit carries a Rs 43,927 crore order book as it lifts capex and nuclear supply
8Servotech's Q1 revenue jumps 66% to Rs 208 crore on solar, chargers and storage
8Viviana Power Tech commissions a 400 kV wind-evacuation line and carries a Rs 1,340 crore book
8REC floats a Maharashtra transmission SPV for a 400 kV Solapur switching station
8Kirloskar Electric flags going concern even as it turns a small profit and raises Rs 40 crore
8NLC India raises Rs 150 crore of commercial paper as the July results run fills the diary
8Ratings Watch - ICRA assigns 'A' to Blupine's 50 MW Karnataka solar group; reaffirms AA+ for Adani Energy Solutions Details

COMMITTEES, PEOPLE & SYSTEM ADMINISTRATION

Jul 22: 8The North-East's control-system bill jumps Rs 167 crore as its grid loses visibility
8Three regions' weekly settlements paid generators Rs 100 crore-plus of must-run
8Three inter-state lines were charged in June, but 54 of 86 remain behind schedule
8PSPCL ties promotions to strike-regularisation as its establishment churns through 50-plus officers
8Rajasthan's RVPN reopens employee pay-fixation and amends its 1964 service regulations
8SJVN's state-nominee director ceases office as PSU board seats turn over Details

Methane blast kills at least 20 at NHPC's under-construction Teesta-VI tunnel in Sikkim

Jul 22: 8A sudden burst of methane deep inside the head-race tunnel of NHPC's 500 MW Teesta Stage-VI project at Samardung touched off an explosion and toxic fumes shortly after 1 pm on 20 July, trapping 25 workers and project officers. By the morning of 22 July at least 20 were confirmed dead and a handful still missing, as rescue teams battled the same gas that caused the blast. Details

IEX day-ahead sat at the Rs 10,000 ceiling in 54% of 21 July's blocks yet crashed to Rs 1,618 at noon

Jul 22: 8The day-ahead market averaged Rs 6,617.61 a MWh on 21 July but sat pinned at the Rs 10,000 ceiling through the overnight and evening blocks, then collapsed to Rs 1,617.91 in the solar-flooded early afternoon. None of it was scarcity - the grid met a 235,132 MW evening peak with zero shortage; the crunch is the shape of the day, not a shortage of power. Details

The grid paid Western generators Rs 80 crore in one week to stay on the site as monsoon load slumped

Jul 22: 8The Western load-despatch centre’s security-constrained unit-commitment account for 6–12 July shows Rs 80.17 crore paid to keep coal and gas units committed and run up, led by Rs 14.98 crore to NTPC’s Khargone. In the same week the Eastern pool paid a further Rs 21 crore of must-run, Farakka alone drawing Rs 15.6 crore - the cost of holding thermal ready while midday solar forces it down. Details

Half of India's inter-state transmission build is late - Rajasthan and Khavda solar links slip up to six years

Jul 22: 8The CEA’s June progress report shows 54 of 86 under-construction inter-state transmission lines awarded through competitive bidding running behind schedule, many of them the very lines meant to evacuate Rajasthan and Khavda solar. Sterlite’s Goa–Tamnar link has slipped almost six years; a cluster of renewable-zone corridors is 12 to 24 months late. Details

Adani Energy Solutions' Q1 profit doubles to Rs 1,237 crore on a Rs 71,779 crore transmission pipeline

Jul 22: 8Adani Energy Solutions reported a consolidated first-quarter net profit of Rs 1,236.56 crore, up 129%, on income of Rs 9,852 crore and EBITDA of Rs 3,178 crore. It is carrying a Rs 71,779 crore under-construction transmission pipeline and has agreed to buy the IntelliSmart smart-metering platform outright for Rs 3,050 crore. Details

The North-East grid is going blind as its control-system bill jumps Rs 167 crore on AI-driven hardware prices

Jul 22: 8The North-Eastern committee’s papers for its 23 July meeting show the region’s new SCADA and energy-management build re-costed to Rs 688.61 crore from Rs 521.67 crore, a Rs 167 crore jump the committee blames on server and memory prices inflated by AI data-centre demand. At the same time real-time visibility of the grid has collapsed - Nagaland is telemetering under 30% of its data to the regional despatch centre. Details

Twenty-seven thermal plants run coal-critical in mid-monsoon - Andhra's Damodaram Sanjeevaiah down to 2%

Jul 22: 8National coal stock at power plants held about 40.75 million tonnes, roughly 13 days’ cover, on 20 July - but 27 individual plants were running critical, one more than a week earlier. Andhra’s Damodaram Sanjeevaiah was at 2% of its normative stock and JSW’s two Torangallu units were out of coal altogether. Details

Jharkhand's discom posts a Rs 1,839 crore half-year loss as its accumulated deficit nears Rs 18,330 crore

Jul 22: 8Jharkhand Bijli Vitran Nigam’s unaudited results, filed ten months late under the distribution-reform scheme, show a Rs 746.70 crore loss for the September quarter and Rs 1,839.02 crore for the half-year. Its accumulated deficit is close to Rs 18,330 crore and its power-purchase bill alone exceeds its revenue from selling electricity. Details

India's under-construction coal fleet swells to 42,700 MW even as this year's additions collapse to 2,260 MW

Jul 22: 8The CEA’s June thermal status report shows 42,700 MW of coal capacity under construction, all supercritical, against a further 21,380 MW stalled or stressed. Yet only 2,260 MW of a 7,300 MW target has been commissioned this year - and most fleet growth now comes through insolvency buyers, not greenfield builds. Details

Contracting news for the day: Part-1

Jul 22: 81. PSTCL floats 90-day civil works tender for 160 MVA transformer at 220 kV Bathinda substation
PSTCL has published a notice inviting tender for civil works connected with a 160 MVA transformer at its 220 kV GNDTP Bathinda substation, with a compressed 90-day completion window and quoted rates valid for 120 days. Tender documents will be issued only to firms the corporation considers adequately experienced, though no qualification formula is disclosed. A striking drafting anomaly sits inside the notice: the document-issue deadline falls after the bid-submission deadline. Unless corrected, the timetable is internally unworkable and could undermine competitive participation.

 

82. UJVNL packages river diversion, tunnelling and powerhouse into single Rs 87.90 crore Tankul hydro contract
UJVN Limited has invited online bids for constructing the 12 MW Tankul small hydro project in Pithoragarh, combining trench weir, intake, river diversion, desilting tank, tunnel, surge shaft, powerhouse and hydro-mechanical works in one mandate. The submission deadline has moved by 25 days through two extensions alongside two corrigenda, signalling the package required correction before closure. Bidders must price geological uncertainty, river behaviour and remote Himalayan logistics into a compact contract value. The project's execution complexity far exceeds its modest installed capacity.

 

83. BSPGCL couples 150 MW solar with 75 MW/300 MWh battery in tariff-based bid with capacity-linked EMD
Bihar State Power Generation Company has issued an NIT to develop 150 MW of solar PV integrated with a four-hour battery system through tariff-based competitive bidding followed by e-reverse auction. The EMD scales at Rs 14.24 lakh per MW quoted, discouraging speculative capacity offers, while the original bid-security instrument must physically reach BSPGCL despite an otherwise digital process. Battery degradation, augmentation and charging rules — central to project economics — are left to the detailed documents. The outcome could set an early state benchmark for solar-plus-storage pricing.

 

84. HPSEBL seeks Rs 3.72 crore project management consultant under QCBS — then adds a reverse auction
HPSEBL has floated an RFP for a project management agency to support its reforms-linked distribution scheme, deploying 246 expert man-months across engineering review, field monitoring and funding-claim support, with the deadline extended by ten days. Selection follows a 70:30 quality-cost formula, yet the notice simultaneously announces an e-reverse auction — an unresolved structural clash. A Rs 70 crore annual turnover threshold towers over the modest assignment value, favouring large national consultancies. HPSEBL also retains the right to double expert deployment in every category, shifting staffing risk onto the consultant.

 

85. OCPL hands one consultant the entire blueprint for its 5 MTPA Manoharpur coal washery
Odisha Coal and Power Limited is appointing a single adviser to prepare the DPR, washability study, CAPEX-OPEX-IRR modelling and the complete EPC tender architecture for a proposed 5 MTPA coal washery, with the deadline extended by 18 days after the original schedule lapsed. The washability study must run through one of six named institutions, tying a core milestone to external laboratories. Joint ventures are barred, concentrating all credentials in one entity, while least cost selection meets a strict abnormally-low-bid clause that can exclude aggressive quoters from retenders. The 120-day programme leaves little slack for approval cycles.

 

86. GSECL's Rs 4.73 crore covered-conductor retrofit at Ukai TPS carries a 36-month owner-controlled execution horizon
GSECL has floated an open three-stage e-tender to replace 16 km of exposed 11 kV conductors at Ukai Thermal Power Station with medium-voltage covered conductors, including eight double-pole air-break switch structures and dismantling of old lines, as an indivisible supply-plus-works package. Supply must finish in six months, but the work order stays valid for 36 months — extendable by six more at unchanged prices. Thirty per cent of supply value remains locked until successful charging, tying contractor cashflow to shutdown availability. With no guaranteed work-release schedule, bidders are pricing a long-duration call-off obligation, not a fixed-schedule job.

 

87. MSEDCL extends commencement window but holds commercial line on Rs 130.38 crore STAR-II transformer buy
MSEDCL has issued Amendment No. 1 with pre-bid clarifications on its tender for 200 kVA STAR-II CRGO distribution transformers, extending the commencement period from two to three months while keeping the nine-month delivery schedule intact. Manufacturer requests for revised estimated cost, IEEMA price variation, relaxed experience thresholds and softer security terms were all rejected, while BEE certification was confirmed as not required for 22 kV units. The amendment signals selective operational flexibility without commercial concession. Certification-heavy entry barriers remain firmly in place for smaller suppliers.

 

88. POWERGRID engages exclusive land valuer for 219 km transmission corridor in Morbi under package-wise GeM bid
POWERGRID has invited a two-packet GeM bid to appoint a land valuer for transmission-line corridors in Morbi district under Package-7, covering roughly 219 km, with the consultant certifying survey-number-wise market rates for compensation and acquisition. The valuer must work exclusively for POWERGRID and is barred from representing any other project stakeholder — a stronger conflict-management measure than routine consultancy tenders carry. The district-wise package model spreads work across Gujarat while limiting how many packages one bidder can secure. The tender treats land valuation as project-critical infrastructure work rather than conventional advisory service.

 

89. NREDCAP offers 22-year DBFOT concession for Rs 324.70 crore Vijayawada waste-to-energy plant
NREDCAP, acting for Vijayawada Municipal Corporation and participating urban bodies, has issued an RFP for a private concessionaire to design, build, finance, operate and transfer a 15 MW municipal-waste-based power plant under a 22-year concession including two years of construction. The Rs 3.24 crore EMD and qualification framework point toward experienced infrastructure developers rather than general EPC contractors. Financing strategy and long-term operating assumptions will matter more than EPC pricing in determining competitiveness. The structure reflects a policy preference for private lifecycle ownership of complex municipal processing assets.

 

810. NTPC Ramagundam to double transformer capacity with 500 MVA units under integrated 30-month contract
NTPC has invited domestic bids to replace two 250 MVA auto transformers at Ramagundam with 500 MVA interconnecting units, bundling design, manufacture, transport, oil treatment, erection and commissioning into one accountability chain over 30 months. An unusual clause forces installation pricing into a 10–15% band of supply value, blocking payment-structure engineering. Loss penalties reach Rs 10 lakh per kW for no-load deviation — with no reward for overperformance — while the variable-price contract offers only narrow escalation relief. A Rs 1 crore bid security applies with no MSE exemption.

 

811. BHEL's 400 kV GIS package for Yamuna Nagar loads firm pricing, reverse auction and long-tail liabilities onto suppliers
BHEL is procuring a complete 400 kV gas-insulated switchgear installation for HPGCL's 800 MW ultra-supercritical expansion at Yamuna Nagar, with the deadline extended twice after a technical corrigendum rewrote testing, transport, packing and scope-boundary provisions. Prices stay firm across a 12-month supply cycle, while the 18-month warranty starts only after project trial operation — a milestone outside the supplier's control. Entire specification clauses were deleted without replacement, creating interpretation gaps, and packing must survive 24 months of outdoor monsoon exposure. Impact recorders must trace every shock from factory to site, with a reverse auction awaiting qualified vendors.

 

812. NTPC Talcher Kaniha's Rs 84.81 crore ash-backfilling contract pays only the lower of two measurements
NTPC has floated a GeM bid restricted to its enlisted ash-transport vendors for excavating, hauling and compacting ash from Talcher Kaniha into quarries and mine voids 50–100 km away, under a 12-month contract splittable 50:50 between two bidders. Payment follows the lower of dispatch-end or filling-site measurement, and every truck movement needs weighbridge, GPS, FASTag, toll and geotagged photo evidence uploaded daily — incomplete records mean withheld payment. A quantity mismatch between the scope figure and doubled BOQ entries demands careful reconciliation. Regulatory penalties on NTPC flow back entirely to the contractor, converting a transport job into a full land-reclamation obligation.

 

813. AEGCL's fixed-price 220 kV line for TATA semiconductor plant transfers all design-modification costs to the contractor
Assam Electricity Grid Corporation has published a turnkey tender for a 220 kV Sonapur-TSAT double-circuit line providing redundant power to the TATA semiconductor facility, spanning overhead line, underground cable, optical fibre and commissioning under single-point responsibility within 24 months. There is no advance payment and no escalation: AEGCL supplies the base design, but site-driven modifications — special towers, pile foundations, raised chimneys — must be executed at zero additional cost. The warranty runs five years from supply or four-and-a-half from commissioning, whichever is later, with liquidated damages at 1% per week up to 10%. Payments can take 60 days, subject to fund availability.

 

814. Powergrid caps land valuers at one package each across ten-district Gujarat valuation drive
Powergrid has issued a GeM bid for an IBBI-recognised land valuer covering 246 tower locations across 91.74 km spanning three transmission SPVs in Vadodara district, one of ten sequentially opened packages, with every assignment due within 15 days of intimation. A "one agency, one package" rule prevents any single firm from dominating, while packages with three or fewer bidders jump the price-opening queue. No escalation applies, quantities can swing 25% either way, and the bid summary denies arbitration even as attached conditions prescribe a full arbitration regime. Consistency across multiple independent valuers remains the unaddressed governance risk.

 

815. JREDA opens Jharkhand's 16-site hydro pipeline to solar, wind and thermal players through eligibility rewrite
JREDA has issued an EOI to identify developers for small hydro projects across 16 Jharkhand sites under the BOOT model, beginning with surveys and DPRs before full development, financing and long-term operation. Corrigendum-I broke the hydro-only entry barrier: any 5 MW DISCOM PPA — solar, wind or thermal — now qualifies, provided the bidder operates a plant in the supplying state, with the deadline extended by 14 days. A Rs 50 crore turnover floor screens for balance-sheet depth over technical pedigree. Concession terms, tariffs and free-power obligations are deferred entirely to the RfP stage, making second-stage evaluation the critical safeguard.

 

816. UJVNL's Sirkari Bhyol hydro tender swells 53% to Rs 243 crore through twenty corrigenda
UJVN Limited's EPC tender for the electromechanical works of the 3x40 MW Sirkari Bhyol Rupsiabagar project has been transformed through twenty corrigenda and seven addenda: the estimated value jumped 53% to Rs 243.05 crore, the EMD rose to Rs 4.87 crore, and every qualification threshold was rewritten upward. Technical access simultaneously widened through a fifteen-year experience window, more approved component makes and flexible efficiency testing, even as financial entry tightened. Himalayan logistics, construction power and site utilities stay contractor-facing despite repeated bidder requests for relief. Bidders must hold prices for 270 days on a package still being stabilised months after publication.

Details

Download tenders and news clips

Jul 22:  For reference purposes the website carries here the following tenders:
 8Tender for supply and installation of digital type loadcell based overload and slack protection me chanism for various hoists gantry cranes installed Details
 8Tender for work of supply of T and P (tools and plants) materials Details
 8Tender for work of providing and erection of additional poles Details
 8Tender for work of replacement of old PVC cable with new PVC armoured cable Details
 8Tender for R&M works including supply and installation of 11 kV indoor VCB panel Details
 8Tender for erection, dismantaling and maintenance of HT/LT and transformer Details
 8Tender for annual rate contract (ARC) for LED lights & related spares items Details
 8Tender for annual rate contract for various types of structural steel items. Details
 8Tender for NDCT overhauling works Details
 8Tender for procurement of CW pump mechanical seals Details
 8Tender for procurement of galvanized gratings and end bar Details
 8Tender for hot line stringing of 66 kV line Details
 8Tender for dismantling of existing fencing and installation of new main gate along Details
 8Tender for procurement of cable termination kit Details
 8Tender for material handling and management including receipt, unloading, verifying, shifting, stacking, preservation, handling and handing over of components of boiler with auxiliaries Details
 8Tender for modification of steam generator (boiler) of 210 MW for comprehensive work Details
 8Tender for replacement work of old main switch, fuse unit etc. Details
 8Tender for renovation of control room at 110 kV substation Details
 8Tender for shifting of electrical utilities in connection Details
 8Tender for supply of 3 nos digital insulation resistance tester Details
 8Tender for procurement of 180KW, 3.3kV HT motors Details
 8Tender for R and M of existing fire detection and protection system Details
 8Tender for replacement of existing 250MVA auto transformers with 500MVA transformer Details
 8Tender for housekeeping work of 2x150 MVA 220/ 132kV grid sub station Details
 8Tender for supply of wall soot blower and oil gun spares for boiler Details
 8Tender for supply, erection and commissioning of various accessories of conveyor belt Details
 8Tender for construction of yard work and misc. civil works at 33kV S/S Details
 8Tender for construction of control room, cable trench, water supply arrangement at 33 kV s/s Details
 8Tender for purchase of spares for 420kV, 3150A, TP, HCB isolators with earth switches Details
 8Tender for procurement of spares for BHEL make DVAR Details
 8Tender for supply, erection & commissioning of 11 kV lines with MVCC conductor & dismantling of existing Details
 8Tender for supply, erection, testing and commissioning of 220 V DC, 63 AH, KPH 63P, Ni-Cd type battery set Details
 8Tender for biennial rate contract for motor or heavy equipment lifting or shifting or placement and motor coupling fitting works Details
 8Tender for execution erection work for effecting the 33kV bulk NSC by laying UG 33 kV 3CX400 SQMM XLPE cable Details
 8Tender for execution of erection work by erection of 11KV RMU, laying of 11kV XLPE UG cable, laying of HDPE pipe Details
 8Tender for round the clock maintenance for routine breakdown and preventive maintenance of 4 x 9 MW and 2 x 4 MW TG sets with all auxiliaries 66 kV switchyard Details
 8Tender for electrical work for construction of 2X5 MVA 33/11 kV S/S Details
 8Tender for construction of 26 KM.33kV line Details
 8Tender for providing and fixing of insulated sheet for ST pole Details
 8Tender for work of replacement of old PVC cable with new PVC armoured cable Details
 8Tender for work of installation of one No. 5 MVA power transformer at 33/11 kV sub-station Details
 8Tender for providing and fixing of insulated sheet Details
 8Tender for providing and fixing of insulated sheet for ST pole Details
 8Tender for work of overhauling, servicing & repairing work of 400kV circuit breaker Details
 8Tender for work of bi-annual maintenance contract for the work of servicing, repairing of various size and capacities battery sets and chargers Details
 8Tender for supply of 5nos spare numerical distance protection relay Details
 8Tender for refilling, servicing & maintenace, supply of spares for fire extinguishers at various substations Details
 8Tender for work of feeder re-orientation at 110kV & 220kV substation Details
 8Tender for work of supply & installation of advance cable transit system by passive fire screen Details
 8Tender for work of fabrication and supply of 50 kL empty oil tank Details
 8Tender for AMC for battery sets maintenance work (220 volts & 48 volts) and charger Details
 8Tender for annual maintenance contract for repairs, overhauling of 33 kV VCB installed Details
 8Tender for work of providing & fixing of maintenance free earthing at 220 kV line Details
 8Tender for supply of pressure relay of converter transformer Details
 8Tender for work of supply and installation of bird diverters (BFD) on 132kV DC transmission line Details
 8Tender for conversion of existing indoor SF6 & VCB AIS switchgear panels pertaining Details
 8Tender for rate contract of excavation and laying of new power / control / telephone cables Details
 8Tender for supply and application of epoxy glass flake coating with UV resistance PU top coat on various external surfaces Details
 8Tender for supply of control panel spares of pump house Details
 8Tender for R&M work of erection, commissioning of new feeder bay HV & LV equipment’s, testing ,earthing,control wiring etc. of 220/66kV 160 MVA transformer Details
 8Tender for erection and maintenance of HT/LT & TC work Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8
India’s Coal Mine Closure Report and GIZ Agreement Explained Details
 
8Bharat Coking Coal shares drop over 7% after Q1 net loss, lower offtake Details
 
8India’s Coal Self-Reliance Push: Govt Takes Major Steps to Boost Production and Reduce Imports Details
 
8Coal Ministry to Sign MoUs for Sustainable Mine Closure, Jharia Rehabilitation and Skill Development Details
 
8SECL Plants 3.20 Lakh Saplings in a Day, Builds Bilaspur’s First Miyawaki Forest for Greener Future Details
 
8Pumped hydro storage of 16 GW capacity under construction: Power Ministry Details
 
8Core sector growth reaches five-month high in June, lifted by iron ore and power Details
 
8PM-KUSUM's Missing Link: Why India's Solar Pump Success Isn't Yet an Agricultural Energy Revolution Details
 
8Power discoms await revival as structural reform delays persist in India Details
 
8Major Boost to Island Energy Security as 50 MW LNG Power Project Moves Forward Details
 
8Why Storage Hydropower Must Become Nepal's Next National Priority Details
 
8India Reaches 548.85 GW Power Capacity As Renewables Account For 43.09%, And Solar Hits 162 GW Details
 
8Tata Power wins 324 MW SECI pumped hydro project Details
 
8India tunnel collapse at a hydropower project kills 10 as 17 remain missing Details
 
8Transformers & Rectifiers India Reports 8% Q1 FY27 Revenue Growth, Order Book Reaches Record INR 6,630 Crore Details
 
8MAHLE Unveils Range Extender and Magnet-Free Motor for Heavy Commercial Vehicles Details
 
8India’s clean energy boom: Why the City of London should be paying attention Details
 
8India’s Renewable Energy Generation Crosses 100 GW for the First Time Details
 
8Stocks to Watch: Adani Power, Eternal, and 6 Other Stocks Announcing Q1 Results Today Details
 
8India’s renewable energy capacity jumps nearly to 288.58 GW Details
 
8Kolkata Power Network Eyes Digital Meter Expansion Details
 
8EAC-PM Report Flags India's Power Grid Vulnerability Details
 
8NLC India Raises Rs 150 Crore Through Commercial Paper Issue to Boost Liquidity and Support Growth Plans Details
 
8India Allows 4 Chinese-Linked Firms to Bid on Power Projects Details
 
8India Signs Major Nuclear Technology MoU: NPCIL and ECIL to Develop Critical Systems Details
 
8ACME Solar signs PPA with SECI for 300MW ISTS-connected Wind-Solar Hybrid Renewable Energy Project Details
 
8REC Signs Agreement with RITES to Ensure Quality Checks of Power Transformers Under RDSS Details
 
8J&K Readies 1,624 MW Hydropower Units by December 2026 Details
 
You can also click on Newsclips for more Details

Hydro & Reservoir Ledger

Jul 21: 8Telangana’s Krishna-basin storage has collapsed about 92% year on year, Srisailam and Nagarjunasagar near-empty
8Odisha hydro ran about 528 MW on 19–20 July with several OHPC units forced out and reservoirs below last year Details

Eastern thermal earned about Rs 112 crore in June for running part-loaded - the same stations were also failing their frequency duty

Jul 21: 8Beneficiary states under-requisitioned below 85% of their entitlement, forcing nine Eastern-region thermal stations to run at part load, and the compensation bill for it reached about Rs 111.9 crore for the fiscal year to June. The stations that ran part-loaded also posted the region’s weakest frequency-response scores, so the pool is paying twice - once in compensation, once in lost grid support. Details

Day-ahead power hit the Rs 10 ceiling overnight and at dusk on 20 July - yet the grid met a ~239 GW peak nearly shortage-free

Jul 21: 8The day-ahead market averaged Rs 6,801 a MWh on 20 July but sat at the Rs 10,000 ceiling through the overnight hours and again in the evening, then collapsed to about Rs 1,815 in the solar-flooded middle of the day. None of this was scarcity - the grid met a roughly 239 GW peak with barely a megawatt-hour of shortage; the crunch is the shape of the day, not a shortage of power. Details

The North met a 93,981 MW summer peak nearly shortage-free - but a single wind trip cost Rajasthan 1,290 MW

Jul 21: 8The Northern Region’s peak demand climbed through the June quarter to 93,981 MW and was met with under half a percent of shortage, with Uttar Pradesh the only state left short. Yet the quarter also shows how thin the margins are: single elements swung a gigawatt at a time. Details

Jaiprakash Power’s Q1 profit jumps 69% to Rs 469 crore as NARCL files insolvency over a Rs 1,239 crore guarantee

Jul 21: 8Jaiprakash Power Ventures reported a standalone Q1 profit of Rs 468.95 crore, up 69% year on year, even after absorbing a Rs 193.63 crore exceptional loss. In the same disclosure it flagged that NARCL has filed a Section 7 insolvency petition against it over a Rs 1,239 crore corporate guarantee - the overhang that now prices the stock. Details

MERC lets Adani’s Mumbai discom adopt Rs 6.38 a unit for 750 MW of round-the-clock renewable power

Jul 21: 8The Maharashtra commission allowed Adani Electricity Mumbai’s distribution arm to adopt a Rs 6.38 a unit tariff for 750 MW of round-the-clock renewable power under a ten-year deal, undercutting MSEDCL’s own effective benchmark. It is a signal on where firm-renewable pricing is settling. Details

India’s pumped-storage build-out reaches 15,870 MW under construction as SECI awards another 1,344 MW

Jul 21: 8The power ministry told Parliament that 11 pumped-storage projects totalling 15,870 MW are under construction, with a further 24,010 MW in the pipeline. In the same week SECI’s first pumped-storage tender awarded 1,344 MW of a 1,500 MW offer, confirming the shift from policy to procurement. Details

Twenty-six thermal plants sit critical on coal in mid-monsoon - Andhra’s Damodaram Sanjeevaiah down to 2%

Jul 21: 8National coal stock at power plants held about 41 million tonnes, or roughly 21 days, on 19 July - but 26 individual plants were running critical, with Andhra’s Damodaram Sanjeevaiah at just 2% of its normative stock. The average hides a distribution problem, not comfort. Details

Punjab’s power employees and pensioners strike for two days, forcing PSPCL to draft engineers to man substations

Jul 21: 8PSPCL’s own management circulated an order on 20 July confirming that a joint front of power employees and pensioner bodies will hold a statewide protest and mass leave on 21–22 July, with pensioners threatening a “jail bharo” agitation. Chief engineers have been told to ensure every substation is manned through the stoppage. Details

Maharashtra’s new RE policy blocks MERC from ordering MSEDCL to buy Waterfront’s small-hydro - even after fixing its Rs 6.18 tariff

Jul 21: 8MERC determined a tariff of Rs 6.18 a unit for Waterfront’s 3 MW small-hydro project but refused to direct MSEDCL to sign a power-purchase agreement, because Maharashtra’s March 2026 renewable-energy policy dropped the procurement mandate. The regulator fixed the price and then found it could not compel the sale. Details

About 40 GW sat on outage on 20 July as North Chennai lost 800 MW and Rajpura 700 MW to boiler and ESP faults

Jul 21: 8Generation outages ran to about 40 GW across the northern, western and southern registers on 20 July, and the day added fresh forced trips - North Chennai’s 800 MW unit hand-tripped on an ESP problem and Rajpura’s 700 MW unit on a boiler-tube leak. This parked baseload is the other half of the day’s price story. Details

Power Markets Daily

Jul 21: 8Day-ahead power averaged Rs 6,801 a MWh on 20 July but sat at the Rs 10,000 ceiling overnight and at dusk
8Real-time power cleared just 3.34 MU at the Rs 10,000 ceiling; the green, intraday and ancillary segments did not clear
8Term and green contracts settled around Rs 7,500 a MWh as the high-price exchange (HPX) day-ahead did not clear on 20 July
8DVC floats an August reverse auction for two 100 MW thermal bands across the exchanges, e-auction 22 July Details

Grid Operations Daily

Jul 21: 8All-India peak of about 239,106 MW was met on 20 July with roughly 1 MU of shortage
8The grid ran high 28% of 20 July - 6.75 hours outside the IEGC band, peaking at 50.251 Hz
8Rajasthan and the NR–ER corridor breached their transfer limits about 20% and 17% of 20 July
8Maharashtra shed about 0.195 MU on 20 July when a 132 kV line overloaded and grid-security load-shedding operated
8The Northern grid met a 93,981 MW June-quarter peak nearly shortage-free Details

Outage & Maintenance Register

Jul 21: 8About 40 GW sat on outage on 20 July; North Chennai 800 MW and Rajpura 700 MW tripped
8Further 20 July trips took out KSTPS 500 MW, Meenakshi 350 MW, Paras, Neyveli, Ukai and Tuticorin units
8Yadadri’s 800 MW unit has been out on coal shortage since 9 July; ACBIL 135 MW out on coal since 12 June
8The 765 kV Ariyalur–North Chennai line was still out late on 20 July after a fault; a Gadarwara 765 kV line faulted
8Champa’s 400 kV bays were out on station flooding and Vindhyachal HVDC Pole-1 had tripped in the West
8The northern and western transmission registers ran to 538 and 422 elements on 20 July, storm-collapse lines still standing Details

Fuel & Coal Ledger

Jul 21: 8Twenty-six thermal plants ran coal-critical on 19 July; Damodaram Sanjeevaiah at 2%
8The Ministry of Coal advances a Rs 37,500 crore gasification scheme, applications closing 7 September
8Thermal plants held 42.8 MT of coal and 14 days’ cover as coal supplied 69.5% of Q1 power, the ministry told Parliament
8Delhi’s Pragati gas plant ramped spot RLNG offtake about six-fold into the summer, its bill reaching Rs 85.9 crore a fortnight Details

Daily Power Sector Tenders Excel update

Jul 21: 8Daily Excel covering new tenders and all published updates including corrigendum, amendment, addendum, clarification and status revisions, along with technical and financial bid opening, evaluation completion and final award actions including AOC and LOA issuance.
Click on Reports for more Details

CERC Docket

Jul 21: 8CERC cut NTPC’s decommissioned Talcher 460 MW annual charge to Rs 475 crore and disallowed most residual capex
8CERC shielded SJVN Green’s 860 MW connectivity from CTUIL revocation and barred encashment of its bank guarantees
8CERC reserved orders on THDC’s water-tax change-in-law claim for the Tehri and Koteshwar hydro stations
8NEEPCO sought a cut in its Tripura gas station’s availability norm to 70% as ONGC gas supply more than halved
8PSPCL and Pragati Power head to a 13 August hearing over a Rs 82.99 crore Pragati-III billing dispute
8CERC reserved a ruling on whether it can hear the TNPDCL–PTC 150 MW pilot-power dispute at Rs 3.26 a unit
8CERC admitted six NLDC and RLDC fee truing-up petitions for 2019-24 and issued notices
8Trading-licence moves: CERC reserved Infinite Voltx’s Category V grant and sought RPG Power Trading’s accounts
8CERC docket calendar - Kishtwar Transmission security interest admitted, UPPCL water-tax amendment allowed, ISTS-charge batch adjourned
8APTEL’s Court-I and Court-II carried 257 and 27 short matters and over 1,670 final appeals as on 17 July
8GERC cleared VMS TMT’s 11.88 MW solar connectivity but refused Iran-conflict force majeure; adjourned Gujarat discoms’ net-metering plea Details

State Regulatory Roundup

Jul 21: 8MERC let Adani’s Mumbai discom adopt Rs 6.38 a unit for 750 MW round-the-clock renewables
8MERC suspended MSEDCL’s power to seize an under-used consumer feeder and ordered Rs 45 lakh compensation
8MERC ordered MSEDCL to pay Vena Energy Rs 11.42 crore in late-payment surcharge and interest on wind dues
8MERC cleared a provisional tariff for Adani’s Rs 6,888 crore 1,000 MW HVDC link, trimming the claimed cost
8Maharashtra’s RE policy blocked MERC from ordering MSEDCL to buy Waterfront’s small-hydro
8MERC dismissed about 1,959 MW of NOPL solar change-in-law claims for non-appearance and closed a settled Talf Solar guarantee dispute
8Bihar’s regulator set FY27 biomass and bagasse tariffs and restored them retrospectively to 1 April
8CSERC let Shree Cement raise its Chhattisgarh contract demand to 51 MVA at a 5% energy surcharge
8Assam’s regulator holds a public hearing on the 8th amendment to its electricity supply code
8Tamil Nadu’s electricity ombudsman part-voided a Rs 2.73 lakh back-billing on a defective meter Details

Green Markets & RE Programme Watch

Jul 21: 8Renewables met about 38% of demand at midday on 20 July, solar peaking at 69.1 GW
8SECI awarded 1,344 MW of pumped storage as the national build-out reached 15,870 MW
8BNC Power won SECI’s 10 MW Odisha solar tender at Rs 2.60 a unit with zero viability-gap funding
8ACME Solar signed a 300 MW hybrid PPA at Rs 3.25 and commissioned 160.5 MWh of Rajasthan battery storage
8KPI Green commissioned 200 MW of Coal India’s 300 MW Khavda solar and won charging nod for a 100 MW Maharashtra plant
8MNRE sanctioned a Rs 436.93 crore renewable R&D programme with a Rs 200 crore perovskite pilot line
8SECI opened an EOI to aggregate bulk renewable off-takers and set a 3 August site visit for a 45.6 MW wind EPC Details

Corporate Wire

Jul 21: 8Jaiprakash Power’s Q1 profit rose 69% to Rs 469 crore as NARCL filed insolvency over a Rs 1,239 crore guarantee
8Transformers & Rectifiers’ order book hit a record Rs 6,630 crore as Q1 inflows surged 218%
8GE Power India’s shareholders and creditors met to clear its absorption into JSW Energy
8ICICI Direct rated BHEL a Buy at Rs 575 on a record Rs 2.6 lakh crore order book
8Nava lifted its FY26 dividend to a record Rs 8.50 as Zambia arrears fell to US$28 million
8Corporate diary - JK Cement Q1 profit slips 12% to Rs 291 crore; Premier Roadlines books Rs 182 crore of power orders
8Smaller filings - CLN Energy reprices a promoter issue to Rs 423; Pace Digitek’s Lineage ties up AI-data-centre power; L&T bags mega metals EPC
8Results and board diary - Waaree Renewable, Indosolar and RattanIndia Power report over 23–24 July Details

Committees, People & System Administration

Jul 21: 8Punjab’s power employees and pensioners strike on 21–22 July, forcing PSPCL to man substations
8The Eastern committee’s June settlement run put about Rs 112 crore of part-load compensation across nine stations
8The Eastern frequency scorecard ranked PVUNL (0.33) and JIPL (0.41) the region’s weakest responders in June
8PSPCL reshuffled 16 senior officers and about 25 substation engineers and sanctioned posts for a new 66 kV grid
8PSPCL’s CMD leads a team to POWERGEN India as the utility revises induction and training rosters
8Mahatransco named 28 apprentices for its 2026-27 intake at Nagpur Details

Contracting news for the day: Part-1

Jul 21: 81) APGENCO's Dr NTTPS meter tender carries three conflicting reference numbers and four different bid-closing times The portal cites M100030900/P41 while the NIT and enquiry use P211 and a longer CE/O&M reference. Submission deadlines shift across 12:00, 13:00, 14:00 and 15:00 hrs depending on the document read. Latest: price-bid opening has been fixed, following the enquiry letter's own submission and opening timing.

 

82) OPTCL's Rs 256.29 crore Pahala tender makes one EPC contractor own a new GIS, a 9.94-km line and two live-station bay extensions The turnkey scope stitches the new GIS to Balianta through one integrated commissioning obligation. EMD is Rs 97.23 lakh. Latest: bids have closed and techno-commercial opening has taken place, with the price-bid date still pending.

 

83) A second APGENCO filing recasts the same NTTPS meter package as a straightforward digital-metering upgrade Scope bundles Secure-make ABT meters, RS-485/Modbus communication, HMI software and full commissioning into one contract. Eligibility favours manufacturers/dealers with PSU or utility metering experience. Latest: presented under a single, unconflicted P211 reference.

 

84) TGGENCO's 42-lakh-tonne coal haulage tender keeps daily quantity unguaranteed while penalising monthly shortfalls Bidders must move ~15,000 tonnes/day with GPS-fitted, dual-end-weighed tippers. Only 30% of the rate is diesel-linked; 70% stays fixed. Latest: the tender has opened, with pre-qualification bid opening due ahead of the price-bid opening.

 

85) MSEDCL's Rs 215.89 crore transformer tender softens qualification but holds firm on price and delivery 33/11 kV experience now counts toward the rarer 33/22 kV and 22/11 kV variants, and their type-test reports can follow bid submission. The nine-month delivery and 66-month warranty stay unchanged. Latest: Amendment No. 1 has been issued, extending the bid deadline.

 

86) POWERGRID gates its 765kV Bikaner substation package behind a mandatory NDA before releasing bid documents The package supports the Rajasthan REZ Phase IV evacuation corridor. Bidders must clear an eligibility and confidentiality screen before seeing specifications or pricing. Latest: the Invitation for Bids has been published, with bid submission and opening still ahead.

 

87) NTPC extends bidding on its Farakka generator-transformer replacement without touching scope or terms The 250 MVA transformer package covers design through commissioning under one 30-month contract. Bid security is Rs 50 lakh with a mandatory Integrity Pact. Latest: an extension notice has revised the bid submission and opening schedule, with scope and terms unchanged.

 

88) AEGCL's Sonapur–TSAT line for TATA Semiconductor pushes site-driven design changes into the contractor's fixed price The Rs 1.57 crore-EMD, 24-month turnkey package spans towers, pile foundations, 220 kV cable and underground OFC. Warranty runs 60 months from supply or 54 from commissioning. Latest: the tender has been published, with bid submission, closing and technical opening still ahead.

 

89) NHPC's Sawalkot dam package jumps 5.6% in value after a capacity correction and 123 days of deadline extensions The estimate rose from Rs 5,129.03 crore to Rs 5,416.94 crore after fixing capacity from 1,856 MW to 1,800 MW. Turnover and working-capital thresholds rose in step. Latest: Corrigendum 10 has fixed the online submission date, with hard-copy submission and techno-commercial opening following shortly after.

 

810) NTPC's Pudimadaka green-urea plant links a Simhadri CO2 unit to five process blocks across two sites under one lump-sum price Carbon capture at Simhadri feeds hydrogen, ammonia and urea production 25 km away at Pudimadaka, all under one lump-sum contract. Bid security is Rs 20 crore, shareable among consortium partners. Latest: Date Corrigendum 02 has moved the submission/opening deadline forward again, following Commercial and Technical Amendments.

 

811) NHPC's Rs 5,541 crore Kamala Lot-1 bundles dam, diversion tunnels and hydro-mechanical works into one civil package The 1,720 MW project in Kamla district combines diversion tunnels, cofferdams, the dam and access roads/bridges. EMD is Rs 10 crore against a 2,372-day execution period. Latest: document download and bid submission remain open, with bid opening scheduled shortly after.

 

812) NTPC's 200,000-unit limestone GeM tender splits award among four suppliers with freight dwarfing the material cost Balajee Steel Udyog took 75,000 tonnes; three others split the remaining 25,000 tonnes. All contracts land at Rs 3,960/tonne, Rs 740 material plus Rs 3,220 freight. Latest: award has been finalised, with contracts running over a one-year supply period.

 

813) GUVNL's short-term power RFP shifts nearly all transmission and sourcing risk onto generators and traders The tender seeks 500–1,000 MW across monthly windows through the procurement period. Interstate bidders absorb a fixed 3.50% regional loss adjustment intrastate suppliers avoid. Latest: the RFP has been published, with bids due shortly before the IPO opening and e-reverse auction on DEEP.

Details

Download tenders and news clips

Jul 21:  For reference purposes the website carries here the following tenders:
 
8Tender for establishment of 765/ 400 kV transmission scheme Details
 
8Tender for supply of 245 kV RIP/RIS bushing for various substations Details
 
8Tender for supply of 420 kV draw rod/lead RIP/RIS bushing for various substation Details
 
8Tender for packing forwarding insurance, transportation supply delivery unloading on for destination of 400 kV bushings Details
 
8Tender for packing forwarding insurance, transportation supply delivery unloading on for destination of 245 kV and below bushings Details
 
8Tender for supply of ferric alum Details
 
8Tender for supply of 360kW HT motor Details
 
8Tender for work of complete overhauling of carious pumps installed for T-G set & BOP auxiliaries Details
 
8Tender for strengthening of exit lane of the existing bituminous coal Details
 
8Tender for construction of 33 kV bay Details
 
8Tender for work of transportation of erection and commissioning of emergency restoration system on 132 kV line Details
 
8Tender for incrasing capacity of (2X63 MVA to 3X63 MVA) T/F and related civil work Details
 
8Tender for supply and repairing of various duct of Ventilation system and overhauling of various air centrifugal fan Details
 
8Tender for work of removal & laying of 6.6/11kV (E), 1C X 1000Sq.mm, aluminum cables along Details
 
8Tender for supply, installation, commissioning and testing of vibration monitoring system for continuous vibration measurement Details
 
8Tender for supply of heating element baskets for air pre-heater of PH IV Details
 
8Tender for supply of heating element baskets for air pre-heater of PH III Details
 
8Tender for supply of seals fo rotary air pre heater Details
 
8Tender for supply of single pole str materials spare Details
 
8Tender for supply of 110KW 10 pole condenser vacuum pump motor Details
 
8Tender for ancillary work required for smooth operation of belt conveyors Details
 
8Tender for construction of foundations for various electrical equipments VCB, CTPT, cable trenches Details
 
8Tender for supply of equipment / material , design, erection, testing , commissioning for system improvement scheme for replacement of old/obsolete switchgear equipment at 33/11 kV sub-stations Details
 
8Tender for construction of 33/11 kV, 2x10MVA GIS sub-station Details
 
8Tender for turnkey construction of 220 kV double circuit transmission line Details
 
8Tender for in-house outsourcing of fabrication of sub-assemblies of HP heaters, LP heaters, condensers, lube oil piping works Details
 
8Tender for supply of BWSR spares Details
 
8Tender for annual maintenance contract for work of on-site N2 drying out for power transformers & ICT’s for various Details
 
8Tender for supply of assorted size of MS grill for repairing of platform of ash slurry line Details
 
8Tender for supply of liquor ammonia 25 % (AR grade) for boiler water treatment Details
 
8Tender for supply of capacitance type level switches for seal oil Details
 
8Tender for supply of IE4 class LT motors Details
 
8Tender for supply of canopies for DCS panels Details
 
8Tender for supply of C&S electric make ACB & panel spares Details
 
8Tender for supply of castable refractory for ash handling plant Details
 
8Tender for supply of battery water for 220V DC & 48V DC battery banks Details
 
8Tender for supply of PLC, VFD (variable frequency drive), HMI and installation Details
 
8Tender for supply of SMF batteries Details
 
8Tender for annual maintenance contract to carry out the routine repair & maintenance of power house equipments Details
 
8Tender for procurement of EPR grade cable 1.1 kV Details
 
8Tender for protection of power house Details
 
8Tender for supply of grinding rolls (roller liners) and bull ring segments Details
 
8Tender for annual maintenance contract for carrying out works in regular outage, emergency and attending breakdown of various 400kV, 220kV, 132kV & 66kV EHV lines Details
 
8Tender for construction of transformer fencing for various Details
 
8Tender for supply of coal nozzles for burner panel of boiler 250 MW Details
 
8Tender for supply of gland packing rings, gland rope and SS 304 spiral wound gaskets etc Details
 
8Tender for supply of spares for HP bypass valves and boiler safety valves for boiler Details
 
8Tender for requirement of spares of zirconia oxygen analysers installed Details
 
8Tender for purchase of spares for 3X1750 KVA DG sets Details
 
8Tender for supply of seals and spares for air pre heater Details
 
8Tender for supply of spares for LPBP stop And control valves Details
 
8Tender for procurement of 06 numbers of grinding ring and 216 number of balls of EL 76 pulveriser Details
 
8Tender for miscellaneous structural works Details
 
8Tender for procurement of different types of steel materials Details
 
8Tender for service contract for power extension and new point wiring Details
 
8Tender for execution of unit 3 COH during overhauling Details
 
8Tender for service contract for de-insulation and re-insulation job during overhauling and various maintenance work Details
 
8Tender for annual maintenance contract of telephone exchange, telephone set and line up Details
 
8Tender for supply of miscellaneous consumables items for electrical and generator maintenance Details
 
8Tender for supply of 11kV moving contact for 200Amps 11kV AB switch (double pole) Details
 
8Tender for work of annual maintenance contract for servicing/ maintenance of battery sets and chargers, taking capacity tests of battery sets and reconditioning of 220V/110V/48V,100/200/300/500/1000 A Details
 
8Tender for AMC for work of arresting oil leakages from the various joints of power transformers Details
 
8Tender for supply of 420kV, 3150A Male Female assembly of centre break isolator Details
 
8Tender for work of replacement of insulator or SRI work of attending the fault or broken conductor Details
 
8Tender for mechanical strengthening work of S/C 66kV line Details
 
8Tender for purchase of 400Amp SMC LTDB Details
 
8Tender for work of Re-tubing of tube nests of LP heater Details
 
8Tender for dismantling of conventional lighting system at boiler, ESP, ash plant Details
 
8Tender for biennial rate contract for works of online, preventive and breakdown maintenance of coal mills XRP-1003 and its associated auxiliaries Details
 
8Tender for work of removal of existing super heater header 5 (SHH5) and erection & commissioning of new SHH 5 along with its associated field joints for boiler Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8
India's Rs 37,500 Crore Coal Gasification Scheme Sees Strong Interest Details
 
8Coal gasification projects of over 22 MT capacity under implementation Details
 
8Solar Startups Attract Over $1 Bn As Clean Energy Investments Accelerate Details
 
8The Ultimate Guide to Solar Energy: Everything You Need to Know in 2026 and Beyond Details
 
8BHEL Invites Bids For Supply Monocrystalline 625 Wp Solar PV Modules For Hyderabad R&D Division Details
 
8Growth and Future of Solar Stocks in India Details
 
8RITES and MECON sign MoU to explore business avenues Details
 
8India has adequate coal stocks, thermal power plants equipped to meet daily demand: Govt Details
 
8AI, Data Centres To Accelerate India’s Power Cycle; Transmission Remains Top Bet: Vakil Of HDFC Securities Details
 
8India has adequate coal stocks to meet power demand, says government Details
 
8Adani Power Share Price Rises Nearly 2% Ahead of Q1 FY27 Results Details
 
8THDC India Commissions 11 MW Floating Solar Plant At Khurja STPP, Boosting NTPC’s Green Capacity Details
 
8India has sufficient coal stocks to meet thermal power demand, says power ministry Details
 
8How Wind Energy in India Is Powering Rural Electrification and Grid Stability Details
 
8Karnataka govt firm on implementing Sharavathi Pumped Storage Project: CM D K Shivakumar Details
 
8Bondada Engineering Secures NTPC REL Deal For 100 MWh Battery Storage Project Details
 
8Why Jaiprakash Power Ventures Shares Surged 8% Today — Here's What Drove The Rally Details
 
8From Standard Pipes to Project-Specific Solutions, Techno India Adapting to Forward Integration Details
 
8Punjab: Power Minister Tarunpreet Singh Sondh launches distribution of 10,500 safety tool kits to PSPCL employees Details
 
8Naveen Jindal Group in talks for proposed nuclear projects, in discussion with US, French companies Details
 
8Coal Stock at Thermal Power Plants Sufficient for 14 Days, Government Assures Uninterrupted Power Supply Details
 
8Thermal Power Plants hold 42.8 MT coal stock, enough for 14 days": MoS Power Shripad Naik Details
 
8India Holds 42.8 Million Tonnes of Coal for Power Stability Details
 
8Tata Power Bags 40-Year SECI Deal Worth Rs 351 Crore Annually for Pumped Hydro Details
 
8NTPC renewable Energy awards contract for 100MWh Details
 
8NPCIL and ECIL Enter MoU to Boost Indigenous Control Systems and Nuclear Technology Solutions Details
 
8India's core sector output rises to five-month high of 5 per cent in June Details
 
You can also click on Newsclips for more Details

The West runs a surplus while the North and South ration - July's squeeze is a delivery problem, not a generation shortfall

Jul 20: 8On 18–19 July the Northern Region shed load in Punjab and Haryana even as the Western Region exported close to 300 million units a day with no shortage and no renewable curtailment. The gap is not missing megawatts - it is congested corridors and benched gas standing between surplus in one region and unmet demand in another. Details

POWER MARKETS DAILY

Jul 20: 8IEX day-ahead cleared 1.30 million MWh in the week to 20 July at a Rs 6,666/MWh average
8Term-ahead buyers locked the Rs 10,000/MWh ceiling for forward daily blocks on 17 July
8APCPDCL and RUVITL float ~1,100 MW and ~1,000 MW thermal reverse auctions on all three exchanges
8IGSTPS-Jhajjar's Rs 45.69 crore tops NRPC's ~Rs 193-crore part-load bill for April–June
8NLDC benched the entire gas fleet at Rs 14–22/kWh while coal cleared at Rs 1.2–5.7/kWh
8Grid-India backed thermal down by up to 46,660 MWh a day to absorb midday solar
8ERPC's weekly deviation pool ran a Rs 60.37-crore balance
8All-India ISTS transmission loss set at 3.95% for the week to 26 July Details

GRID OPERATIONS DAILY

Jul 20: 8All-India frequency fell to 49.596 Hz on 19 July in a synchronous evening dip
8NR import corridor was in ATC violation 11.46% of 19 July as Rajasthan sat 19.1% congested
8NER–Tripura import corridor held in transfer-capacity violation ~three-quarters of the day
8Ancillary despatch ran heavily to down-regulation - up to 46,660 MWh backed down on 19 July
8Western Region exported ~282 MU north on 19 July as the grid's balancing sink and source
8High-voltage light-load regime held Amreli above 420 kV ~90% of 18 July
8NR and WR registers carried high-fault-current trips plus a decade-long tail of dead assets
8One relay-and-reclose event cascaded through five 400 kV bays at Fatehgarh-III / Serentica on 19 July
8Two Karnataka 400 kV corridors stay un-restored since May tower collapses
8Grid-India set the all-India ISTS transmission loss at 3.95% for 20–26 July
8NRPC rates Northern hydro the worst primary-frequency responders - Parbati-III scored 0.00
8ERPC re-cut a week's reactive-energy account off one meter swap - DARLIPALI draws Rs 3,37,902
8WRLDC swapped ~a dozen interface meters to check/standby readings in DSM week-14
8Karnataka's ageing thermal posted soft June returns - RTPS ran 58.2% PLF
8Thermal availability held 85.5% on 16 July as hydro ran 11% under its YTD programme
8Bihar alone curtailed load across 17–19 July despite zero ER-wide shortage Details

OUTAGE & MAINTENANCE REGISTER

Jul 20: 8India carried 53,415 MW under maintenance on 16 July - 22,936 MW of it forced thermal trips
8Western Region ran up to 18,336.5 MW out on 18 July, led by VSTPS-V and Adani Raipur trips
8Southern Region outage climbed 1,906 MW in two days to 11,820.88 MW on 19 July
8Northern Region carried 9,138 MW out on 19 July, 4,900 MW of it forced coal
8Eastern Region held ~5.1–5.9 GW out; Teesta-III's 1,200 MW forced into a 21st month
89,230.47 MW of thermal/nuclear went off-grid on 16 July on boiler and air-preheater faults
8NTPC water-wall tube leaks hit Gadarwara U1 (800 MW) and Barh U3 (660 MW)
8Long-parked units anchor the ~29,961 MW out beyond 15 days
8Telangana's Yadadri loses both first-stage 800 MW units, U1 and U2
8Jindal Simhapuri logged four trips of two 150 MW units in a single day - a repeat-tripping signal
8NPCIL's RAPS-A Unit-1 (100 MW) is formally set for decommissioning, out since 2004
8PVVNL runs a 100-plus feeder shutdown wave across Meerut–Muzaffarnagar ahead of the Kanwar Yatra
8Chronic multi-year transmission forced outages stay open - Raigarh–Raipur FSC since 2016
8Himachal hydro units force-out on high silt as monsoon flows spike
8KPCL's newest Raichur unit (250 MW Unit-8) sat out all June on planned outage
8OHPC carries multiple hydro units out - Burla and Chipilma forced
8KSEBL replaces Idukki Unit-6 upper guide bearing in-house in nine days, saving about Rs 35 lakh Details

FUEL & COAL LEDGER

Jul 20: 8Twenty-seven thermal plants sit at critical coal stock on 18 July
8WBPDCL bills a June fuel surcharge up to 60 paise/kWh, with Kolaghat the steepest pass-through
8NRPC bills IGSTPS-Jhajjar Rs 4,569.48 lakh of part-load compensation for Apr–Jun 2026
8Coal Ministry's Rs 37,500 crore surface coal-gasification scheme moves to procurement
8Every RLNG and liquid-fuel gas station stays out of merit order at 1,395–2,223 paise/kWh
8All-India coal stock at CIL/SCCL plants holds ~16 days, nine at five days or fewer
8Yadadri U4 (800 MW) stays shut on coal shortage - the South's sole such outage
8Imported-coal dependence concentrates at Adani Kawai, Nasik, Chandrapur and North Chennai-III
8Coal-supply failures force units down at ACBIL, Kasaipalli, Ghatampur, Raichur and Tanda
8A large gas-CCPP block backs down on costly or conserved fuel; Uran and Agartala run short Details

HYDRO & RESERVOIR LEDGER

Jul 20: 8Telangana reservoir live storage collapses from 300.7 to 43.8 TMC year-on-year
8National hydro generation runs ~11% below programme YTD, Eastern and Northern fleets worst
8Odisha's OHPC fleet generates just 590.44 MW / 14.17 MU, reservoirs below year-ago
8CERC re-rates NEEPCO's Kopili Stage-II from 25 to 23 MW, rules 2022 flood force majeure
8Northern Region reservoir energy falls to 1,116 MU from 1,361 MU year-on-year
8Western Region reservoirs run mixed - Koyna and Indira Sagar down, Sardar Sarovar up
8Southern Region reservoirs sit below last year across the board; Kerala at 28%
8Idukki Unit-6 fixed in-house in nine days, saving KSEBL about Rs 35 lakh Details

CERC DOCKET

Jul 20: 8NTPC claims Rs 3,063.91/tonne Talaipalli coal for Lara STPS, 27% above its own projection
8CERC trues up NEEPCO's Kopili-II tariff, sets 2024-29 AFC rising to Rs 2,527.01 lakh
8CERC opens objections on POWERGRID Vataman's bay for 250 MW Rajasthan BESS at Bhadla-III
8PGCIL withdraws its Rs 233.96 crore OT security-operations-centre O&M claim Details

STATE REGULATORY ROUNDUP

Jul 20: 8KSERC clears KSEBL's 300 MW peak-power bid method but forces a 12-month CTUIL average
8MERC freezes MSEDCL's 12 June supplementary bills to 15 open-access consumers pending APTEL
8MERC reserves orders in 11 matters - five Pune-corridor transmission licensees plus Carbonminus
8MERC adjourns Avaada's plea to extend supply-start dates on 2,300 MW of Maharashtra solar
8PSPCL reclassifies lawyers'-chamber connections from commercial to Domestic tariff
8PSPCL sanctions a new 66 kV Bathinda substation under RDSS at Rs 641.19 lakh
8MPERC opens consultation on the Sixth Amendment to the MP Electricity Supply Code
8GERC reserves maintainability on Trambovad farmers' SKY solar complaint against MGVCL
8TN Ombudsman orders TNPDCL to implement a Coimbatore hotel's 61 kW load within 30 days Details

GREEN MARKETS & RE PROGRAMME WATCH

Jul 20: 8Avaada's 2,300 MW of Maharashtra solar risks stranding as MSETCL evacuation slips to FY2027-28
8CERC moves to add a bay for Rajasthan BESS's 250 MW at saturated Bhadla-III
8All-India renewable penetration hit 38.05% on 17 July with zero curtailment
8Kerala lines up 250 MW / 1,000 MWh of BESS and 500 MW of solar before winter
8Green day-ahead cleared near-parity to grey as wind barely traded
8Gujarat's SKY farm-solar runs a third below promise, burdening farmers with loan recovery
8Southern renewables cleared without curtailment as pumped storage and BESS cycled against the peak
8Domestic solar-glass capacity is still a fraction of demand as the anti-dumping wall thickens
8ISA has collected no interest and given no award on Haryana's Kalpana Chawla Solar prize since 2022 Details

CORPORATE WIRE

Jul 20: 8Tata Power's 40-year SECI pumped-storage tolling award
8CBI searches Reliance Infrastructure's registered office; company reports no financial impact
8NTPC board to weigh Q1FY27 results and a Rs 12,000 crore NCD/bond programme on 24 July
8POWERGRID to raise its FY27 borrowing limit from Rs 30,000 crore to Rs 35,000 crore
8Adani Power tables a fundraise alongside Q1FY27 results on 22 July; quantum undisclosed
8Three large issuers cluster Q1FY27 results on 22 July - Adani Power, Adani Energy Solutions, JSW Energy
8PFC to seek enhanced domestic and international borrowing limit on 23 July
8TD Power Systems' FY26 income rises 44% to Rs 1,878 crore on record order inflow
8Bajel Projects' FY26 PAT jumps 74% to Rs 26.95 crore even as its order book slips
8Borosil Renewables swings to Rs 86.64 crore Q1FY27 profit on pricing, not volume
8POWERGRID wins TBCB mandate for two synchronous condensers at Fatehgarh-II
8REC floats two shell SPVs for Maharashtra intra-state TBCB transmission
8Coal India advances a 187.5 MW / 750 MWh BESS at Choutuppal; AHASOLAR wins the owner's-engineer role
8VA Tech WABAG secures a "Large" BWSSB wastewater DBO order with biogas captive power
8ACME Solar rebuts "13 containers" claim over Pokhran BESS fire; four PCS units hit
8Inox Green Energy Services to consider a fundraise on 22 July; quantum undisclosed
8BF Utilities fined by NSE and BSE for delayed consolidated FY26 results after subsidiaries missed filing
8International Solar Alliance swings to a USD 3.08 million surplus for FY2025 on trebled revenue (colour)

Ratings Watch

8Orient Electric's ESG rating improves to 74 on steady year-on-year gains Details

COMMITTEES, PEOPLE & SYSTEM ADMINISTRATION

Jul 20: 8NTPC and Coal India each gain a government-nominated independent director
8Alfa Transformers adds a discom veteran as Non-Executive Non-Independent Director
8Ministry of Coal builds the governance layer for its Rs 37,500 crore surface-gasification scheme
8ISA discloses a 2024 cyber-fraud that diverted USD 357.86 thousand; recovery partial
8SRPC 67th CCM minutes flagged unreadable - retrieval flag
8Rolled-over committee action items
8PSPCL reshuffles its cadres across Punjab - ministerial and 18 technical transfers, 29 clerks relieved
8PSPCL lists ~5 electrical officers born Aug-1968 for superannuation
8PSPCL deputes 6 officers to DoPT-sponsored MGSIPA training programmes
8PSPCL publishes provisional JE/Electrical recruitment merit list - ~5,700 candidates ranked
8PSPCL creates ~8 permanent posts for the new 66 kV Focal Point Mubarakpur substation
8NBPDCL constitutes a 5-member Energy Accounting Cell for DT metering under AMISP
8Ministry of Coal to engage 18 Young Professionals and 2 Legal Consultants on contract
8KSEBL awards a Good Service Entry to 20 staff for the in-house Idukki UGB repair Details

Nearly 30,000 MW has sat out of the grid for over a fortnight - flood, fire, tower collapse, GLOF and bankruptcy, some of it dead for years

Jul 20: 8CEA's registers show almost 30 GW out of service for more than fifteen days in mid-July, much of it stranded gas but a hard core of it long-dead thermal and hydro. Sikkim's Teesta-III has been out about 21 months since a glacial flood, two Karnataka 400 kV corridors since May tower collapses, and Tamil Nadu's Tuticorin units since a March-2025 control-room fire. Details

The West ran as a deviation conduit between East and South last week - settling a net Rs 51 crore, with Khavda solar the single biggest mover

Jul 20: 8The Western committee's deviation account for the week to 5 July shows the region paying the East a net Rs 263 crore and receiving a net Rs 267 crore from the South - passing imbalance through itself rather than causing it. The largest single line in the pool is no thermal station but a Khavda solar aggregator, whose forecast error now moves more money than any coal plant. Details

MNRE grants its sixth solar-cell reprieve in eight weeks and Delhi rewrites net-metering - a quiet admission that domestic cell supply still cannot carry distributed solar

Jul 20: 8A new MNRE order lets net-metering and open-access renewable projects commission without the domestic solar-cell (ALMM List-II) requirement until 31 December 2026, superseding a stack of earlier extensions. On the same days, Delhi's regulator collapsed net-metering into a two-stage online process with hard 25- and 10-day connection deadlines. Details

Tata Power lands a 40-year storage tolling contract from SECI - Rs 351 crore a year for a 324 MW pumped-storage plant, about Rs 14,000 crore over its life

Jul 20: 8SECI has issued Tata Power a Letter of Award for pumped-storage service from a 324 MW / 2,592 MWh plant on a 40-year annuity, at an annual fixed charge of Rs 351.3 crore. It is a long-dated, availability-based storage contract rather than a merchant arbitrage bet - and the payment only starts once SECI ties up its own downstream buyers. Details

CERC forgives NTPC a 22.5-month captive-mine delay as force majeure, then fences the money - Rs 4,340 crore recast, Rs 136 crore stripped, Rs 59 crore clawed from the mining contractor

Jul 20: 8The Commission held NTPC's 22.5-month slip in commissioning its Talaipalli captive coal mine to be beyond the company's control, fixing commercial operation at 1 October 2023 over discom objections. In the same order it capped the revised cost at Rs 4,340.50 crore, disallowed Rs 136.55 crore of claimed capital cost, and recorded that terminated contractor Thriveni had paid NTPC Rs 58.83 crore. Details

A monsoon flood knocks out the 765/400 kV Champa hub in Chhattisgarh - all three transformers trip and the operator logs the situation "out of control"

Jul 20: 8On 17 July heavy flooding tripped all three inter-connecting transformers at the Champa pooling station on Buchholz protection, taking down a top-tier 765 kV evacuation hub for Chhattisgarh's coal belt. The WRLDC outage log records an operator writing that the situation was "out of control now due to continuously raining." Details

The grid's designated shock-absorbers are its worst responders: NR's big hydro fleet scores near zero on governor response while NTPC thermal scores perfect

Jul 20: 8The Northern committee's June frequency-response league table puts Parbati-III at 0.00 and a row of NHPC and SJVN hydro stations just above it, while NTPC's coal units sit at a perfect 1.00. Because the score feeds tariff, the hydro fleet that is supposed to stabilise frequency is being penalised for failing to. Details

Southern coal stocks fall to single digits - Damodaram Sanjeevaiah at 2%, and Telangana's Yadadri backs an 800 MW unit off the grid for want of coal

Jul 20: 8Twenty-seven thermal plants sat on critical coal stock in mid-July, the tightest cluster in Andhra Pradesh, Telangana and Tamil Nadu, with APPDCL's 2,400 MW Damodaram Sanjeevaiah station down to 2% of its normative stock. The squeeze stopped being a warning and became lost megawatts when TGGENCO's Yadadri Unit 4 was shut for coal shortage. Details

Kerala's regulator adopts Rs 5.96/unit round-the-clock power and openly rebukes its own utility, ordering fixed day-ahead load-shedding as reservoirs fall to 28%

Jul 20: 8KSERC cleared KSEBL to buy 200 MW of round-the-clock power for a year at Rs 5.96 a unit, but recorded that the utility's Core Committee never costed the tariff impact and took two weeks to file after bidding closed. With reservoirs at 28% against a normal 60% and a peak deficit put at 500–1,000 MW, the Commission ordered load-shedding to be fixed a day ahead and held for a week. Details

Day-ahead and real-time power pinned the Rs 10,000/MWh ceiling through every peak block, 17–19 July

Jul 20: 8IEX's day-ahead and real-time markets cleared at the Rs 10,000 per MWh price cap in the morning and evening peaks on all three days, then crashed to Rs 1,300–1,900 in the solar midday. The Rs 20,000 high-price segment woke for a single night - a market pressed hard against its ceiling but rarely through it. Details

Contracting news for the day: Part-1

Jul 20: 81) Power Grid floats 1 GWh battery framework demanding firm prices without guaranteeing a single order Power Grid has invited first-stage bids for a 250 MW/1,000 MWh four-hour BESS long-term agreement. Capacity converts into work only when it wins external tariff tenders from SECI, states or DISCOMs. The partner must hold firm prices, sustain 95% availability and 87% round-trip efficiency at its own cost. Clause 9(e) guarantees no minimum quantity despite full readiness obligations.

82) POWERGRID picks its Sunni Dam–Luhri transmission contractor before knowing whether it will win the project The TL01 pre-bid tie-up covers the Nange–Koldam 400 kV double-circuit line. Award is conditional on POWERGRID winning RECPDCL's TBCB competition. The contractor must sign an exclusivity MoU and stay out of all rival bids. A mountain-specific 50 km qualification filter and 33-month completion clock frame the package.

83) UPRVUNL's pumped hydro tender absorbs six extensions without returning any developer risk The Rs 3,953 crore, minimum 640 MW project sits between the Rihand and Obra reservoirs. The developer must identify the layout itself, arrange land and clearances, and post a Rs 79.06 crore EMD. Commissioning must fit 54 months — 18 for the DPR and only 36 for construction. Every major execution and clearance risk stays with the developer.

84) Eleven corrigenda turn BHEL's Koradi lime-and-gypsum EPC into a different tender from the one first issued Six extensions have added 45 days to the original bidding window. Capacities are now fixed at 150/165 TPH for lime and 50/55 TPH for gypsum. Weighbridges, MCC buildings and pay loaders were pushed firmly into contractor scope. Escalation relief is capped at plus or minus 20% while intermediate LD stays.

85) WAPCOS caps its Atal Park consultancy at Rs 3.31 lakh while stretching the obligation across four-plus years The Cuttack assignment runs from concept and DPR through supervision and as-built documentation. The fee stays frozen through extensions of up to three additional years. Payment is back-to-back, released only after WAPCOS receives funds from Cuttack Development Authority. A 5% guarantee, 5% retention and exclusion of arbitration complete the burden.

86) BHEL's Koradi bottom-ash package extends contractor liability past commissioning and into plant operations The 970-day, no-deviation EPC withholds equipment payments where civil pricing falls below 50% of contract value. Latent-defect liability runs 24 months beyond the defect period. Conveyor belts damaged during operation must be replaced at contractor cost. Milestone slippage triggers 10% withholding from running-account bills.

87) WBSETCL's 55 km cable tender grants technical flexibility while refusing every commercial concession on copper risk The 33 kV XLPE procurement pairs a 120-day delivery clock with firm prices and a reverse auction. Order splitting can leave L1 with only 60% of the quantity. In-house NABL test reports and steel drums were accepted at pre-bid stage. The steel-drum reply collides with the wooden-drum specification without a formal amendment.

88) GPPC rewrites its Pipavav clarifier health study but parks half the fee behind a tender it does not control Amendment No. 1 opens eligibility from Gujarat to all of India and mandates NDT at 12 locations minimum. An impossible 50%-per-week penalty has been corrected to 5%, capped at 10%. Payment splits into four 25% tranches tied partly to a separate implementation tender. The amendment arrived months after the original submission schedule, making the chronology itself a live issue.

89) SECI pairs open-global access with a Rs 8.44 crore entry ticket for its 45.6 MW Ramagiri wind EPC The single package bundles design, supply, construction, commissioning and maintenance for an ISTS-connected project. A two-envelope evaluation will be followed by an e-reverse auction. The query window closes hours before the pre-bid meeting even begins. Maintenance period, turbine configuration and performance guarantees remain undisclosed.

810) MPPMCL's four-hour battery tender slips 57 days through three corrigenda and three addenda The 282.50 MW/1,130 MWh procurement follows a build-own-operate model with viability gap funding. EMD of Rs 4.80 lakh per MW means Rs 13.56 crore for the full capacity. A Rs 15 lakh processing fee raises entry costs before evaluation begins. Projects may sit anywhere in India, importing connectivity risk into every bid.

811) NTPC REL gives Nokhra battery bidders eleven more days and not one gram less risk Corrigendum No. 01 extends bid submission while the query deadline stays shut. Bidders must deliver 1,320 MWh of nameplate for 1,200 MWh of dispatch at the point of injection. Capacity must hold at 98% across 15 years with contractor-funded augmentation. A Rs 20 crore bid security guards the reverse-auction gateway.

812) NVVN puts Varanasi's green charcoal through 65 tests, one trip and one payment before it reaches the market The GeM tender covers charcoal, ash and emission testing down to dioxins, furans and mercury. All sampling must fit a single site visit at one consolidated charge. Full payment waits for report acceptance, with competition limited to 22 approved vendors. Bids sharing an IP address face summary rejection at either stage.

813) NHPC widens entry to its Rs 379.25 crore Jalaun solar evacuation package while keeping project-wide LD intact Corrigendum-1 broadens general experience to any large electrical infrastructure work, opening the gate beyond substation-and-line contractors. Three 33/400 kV pooling substations at Orai, Madhogarh and Pathrahi must be delivered within 24 months. Delay preventing beneficial use attracts LD on the total contract price, capped at 10% plus GST. Escrow payments, an interest-bearing advance against a 110% guarantee and 5% bill retention keep cashflow risk with the contractor.

Details

Contracting news for the day: Part-2

Jul 20: 81) Power Grid floats 1 GWh battery framework demanding firm prices without guaranteeing a single order Power Grid has invited first-stage bids for a 250 MW/1,000 MWh four-hour BESS long-term agreement. Capacity converts into work only when it wins external tariff tenders from SECI, states or DISCOMs. The partner must hold firm prices, sustain 95% availability and 87% round-trip efficiency at its own cost. Clause 9(e) guarantees no minimum quantity despite full readiness obligations.

82) POWERGRID picks its Sunni Dam–Luhri transmission contractor before knowing whether it will win the project The TL01 pre-bid tie-up covers the Nange–Koldam 400 kV double-circuit line. Award is conditional on POWERGRID winning RECPDCL's TBCB competition. The contractor must sign an exclusivity MoU and stay out of all rival bids. A mountain-specific 50 km qualification filter and 33-month clock frame the package.

83) UPRVUNL's pumped hydro tender absorbs six extensions without returning any developer risk The Rs 3,953 crore, minimum 640 MW project sits between the Rihand and Obra reservoirs. The developer must identify the layout itself, arrange land and clearances, and post a Rs 79.06 crore EMD. Commissioning must fit 54 months — 18 for the DPR and only 36 for construction. Every major execution and clearance risk stays with the developer.

84) Eleven corrigenda turn BHEL's Koradi lime-and-gypsum EPC into a different tender from the one first issued Six extensions have added 45 days to the original bidding window. Capacities are now fixed at 150/165 TPH for lime and 50/55 TPH for gypsum. Weighbridges, MCC buildings and pay loaders were pushed firmly into contractor scope. Escalation relief is capped at plus or minus 20% while intermediate LD stays.

85) WAPCOS caps its Atal Park consultancy at Rs 3.31 lakh while stretching the obligation across four-plus years The Cuttack assignment runs from concept and DPR through supervision and as-built documentation. The fee stays frozen through extensions of up to three additional years. Payment is back-to-back, released only after WAPCOS receives funds from Cuttack Development Authority. A 5% guarantee, 5% retention and exclusion of arbitration complete the burden.

86) BHEL's Koradi bottom-ash package extends contractor liability past commissioning and into plant operations The 970-day, no-deviation EPC withholds equipment payments where civil pricing falls below 50% of contract value. Latent-defect liability runs 24 months beyond the defect period. Conveyor belts damaged during operation must be replaced at contractor cost. Milestone slippage triggers 10% withholding from running-account bills.

87) WBSETCL's 55 km cable tender grants technical flexibility while refusing every commercial concession on copper risk The 33 kV XLPE procurement pairs a 120-day delivery clock with firm prices and a reverse auction. Order splitting can leave L1 with only 60% of the quantity. In-house NABL test reports and steel drums were accepted at pre-bid stage. The steel-drum reply collides with the wooden-drum specification without a formal amendment.

88) GPPC rewrites its Pipavav clarifier health study but parks half the fee behind a tender it does not control Amendment No. 1 opens eligibility from Gujarat to all of India and mandates NDT at 12 locations minimum. An impossible 50%-per-week penalty has been corrected to 5%, capped at 10%. Payment splits into four 25% tranches tied partly to a separate implementation tender. The amendment arrived months after the original bid schedule, making the chronology itself a live issue.

89) SECI pairs open-global access with a Rs 8.44 crore entry ticket for its 45.6 MW Ramagiri wind EPC The single package bundles design, supply, construction, commissioning and maintenance for an ISTS-connected project. A two-envelope evaluation will be followed by an e-reverse auction. The query window closes hours before the pre-bid meeting even begins. Maintenance period, turbine configuration and performance guarantees remain undisclosed.

810) MPPMCL's four-hour battery tender slips 57 days through three corrigenda and three addenda The 282.50 MW/1,130 MWh procurement follows a build-own-operate model with viability gap funding. EMD of Rs 4.80 lakh per MW means Rs 13.56 crore for the full capacity. A Rs 15 lakh processing fee raises entry costs before evaluation begins. Projects may sit anywhere in India, importing connectivity risk into every bid.

811) NTPC REL gives Nokhra battery bidders eleven more days and not one gram less risk Corrigendum No. 01 extends bid submission while the query deadline stays shut. Bidders must deliver 1,320 MWh of nameplate for 1,200 MWh of dispatch at the point of injection. Capacity must hold at 98% across 15 years with contractor-funded augmentation. A Rs 20 crore bid security guards the reverse-auction gateway.

812) NVVN puts Varanasi's green charcoal through 65 tests, one trip and one payment before it reaches the market The GeM tender covers charcoal, ash and emission testing down to dioxins, furans and mercury. All sampling must fit a single site visit at one consolidated charge. Full payment waits for report acceptance, with competition limited to 22 approved vendors. Bids sharing an IP address face summary rejection at either stage.

Details

Download tenders and news clips

Jul 20:  For reference purposes the website carries here the following tenders:
 8Tender for architectural, structural & MEP consultancy services Details
 8Tender for supply, installation, testing and commissioning with 5 year CMC of grid connected solar photovoltaic systems of various capacity Details
 8Tender for supply of equipments/ material, erection, testing and commissioning for the work augmentation by providing additional 1 x 25 MVA, 132- 110/33 kV T/F Details
 8Tender for remodeling and restructuring of existing 09 Nos. 400kV bays Details
 8Tender for civil works for construction of 132 kV bay at 220 kV S/s Details
 8Tender for civil works for construction of 132 kV bay Details
 8Tender for supply, installation, testing and commissioning of smoke an heat extraction system Details
 8Tender for supply, installation, testing and commissioning of complete set up of emergency alternate water drain arrangement from dewatering pit Details
 8Tender for supply of LT pilfer resistant metering cubicle Details
 8Tender for miscellaneous work regarding dismantling, fabrication and erection of hopper empty out /cleaning chutes Details
 8Tender for work of servicing of TG bearing/RTDs, seal liners TE/EE, servicing/overhauling of HP/IP CV, ESV, IV and misc. AOH related activities Details
 8Tender for erection of estimate for new 5 MVA substation Details
 8Tender for appointment of dealers for fly ash bricks Details
 8Tender for preventive and breakdown maintenance of exchangers, pressure filters, phosphate transferring system Details
 8Tender for ARC for HT/LT/TC erection and maintenance work Details
 8Tender for supply of various fasteners and consumables Details
 8Tender for work of collection of fly ash, bed ash Details
 8Tender for supply and retrofitment of 245kV circuit breakers Details
 8Tender for requirement of work order for transformer Details
 8Tender for provision of chain link fencing work inside the proposed 33/11kV P/S/S Details
 8Tender for construction of approach path at proposed 33/11kV P/S/S Details
 8Tender for construction of cable trench and drain at proposed Details
 8Tender for development of yard at proposed 33/11kV P/S/S Details
 8Tender for construction of proposed 33/11kV P/S/S Details
 8Tender for framework agreement for 1 year of silver plating of 5 micron on aluminium and copper conductor Details
 8Tender for epoxy mortar treatment for repair of chute spillway Details
 8Tender for erection laying of 11 kV HT cables on overhead line Details
 8Tender for release of new service connections of new HT line Details
 8Tender for replacement of existing 11 kV bare conductor by 11 kV AAAC AL-59, 70 Sq.mm Details
 8Tender for replacement of 11 kV ACSR conductor by AAAC feeder Details
 8Tender for construction of 33kV line and installation of 33/0.4kV, 1x1000KVA sub-station Details
 8Tender for supply of numerical transformer protection differential relays high end model Details
 8Tender for ARC for HT/LT/TC erection and maintenance work Details
 8Tender for ARC for HT/LT/TC erection and maintenance works Details
 8Tender for bulk procurement of MCBs Details
 8Tender for supply and commissioning of elect. eqpt for rain water harvesting system Details
 8Tender for supply, installation and commissioning of SCADA DASHBOARD for flow transmitters Details
 8Tender for procurement of transmission tower hardware fitting material for 400kV line Details
 8Tender for painting works of transformers, panels, bus ducts, motors, electrical structures, street light poles Details
 8Tender for ARC for HT/LT/TC erection and maintenance works Details
 8Tender for turnkey based contract for conversion of existing electrical line network in to underground cable Details
 8Tender for work of erection, commissioning of equipments, testing, control wiring etc. of 1 Nos. 66kV bus coupler bay Details
 8Tender for supply of 90/10 cupronickel condenser tubes Details
 8Tender for work for replacement of various pulleys and its bearing Details
 8Tender for supply and installation of energy saving BLDC ceiling fan Details
 8Tender for work of overhauling of ESP pass Details
 8Tender for supply of tarpaulin sheet for covering of coal Details
 8Tender for work of complete servicing/ overhauling/ defect attending of various hoists and cranes Details
 8Tender for supply of various consumable & routine maintenance items Details
 8Tender for supply, erection, testing, and commissioning of 220kV & 66kV equipment and materials Details
 8Tender for reconditioning of complete rotor assembly of ring granulators Details
 8Tender for procurement of sleeve type expansion joint (modified coupling device) for wet ash disposal pipe line Details
 8Tender for repair and maintenance of balance 56 Nos rollers of under sluice gate, spillway gate and HR gates Details
 8Tender for work of annual maintenance contract of 3MT capacity elevators of boiler Details
 8Tender for dismantling of 150 kWp rooftop solar plant Details
 8Tender for outsourcing of 2 no additional PTFs with 20 MVA PTF Details
 8Tender for outsourcing work of erection testing and commissioning of new 66 kV SS with 01 No 20 MVA power transformers along Details
 8Tender for installation of 11/0.4 kV 990 KVA compact sub station Details
 8Tender for installation of 11/0.4 kV 990 KVA compact sub station at 33/11 kV S/s Details
 8Tender for installation of 11/0.4 kV 990 KVA compact sub station Details
 8Tender for replacement of bare conductor by AB cable Details
 8Tender for replacement of bare conductor by AB cable in 11 kV feeder Details
 8Tender for procurement of grinding rolls and bull ring segment for XRP883 coal mill Details
 8Tender for procurement of 1200 MM conveyor belt Details
 8Tender for biennial maintenance contract for control and instrumentation system Details
 8Tender for procurement of spares for main turbine Details
 8Tender for service contract for insulation and sheet cladding work during overhauling Details
 8Tender for replacement of 210MW LMW turbo generator defective TG rotor Details
 8Tender for supply of equipments / material, erection, testing and commissioning for the work of augmentation by replacement of existing 1x25 MVA, 132/33kV, transformer Details
 8Tender for work of annual maintenance contract (AMC) for various 400kV lines Details
 8Tender for supply of spares for 400kV SF6 breaker Details
 8Tender for repair & complete overhauling work of 298.6 MVA converter transformer & 360 mH 500 kV smoothing reactor Details
 8Tender for work of repair & upgradation of crimping tool at various substation & line Details
 8Tender for work of supply, installation and commissioning of 100% hot redundancy based continuously available Details
 8Tender for providing and fixing of 400kV & 220kV isolators spare parts and servicing Details
 8Tender for work of cold line washing of disc insulator strings of various 132kV & 220 kV lines Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8Jindal Steel Deploys Indigenous Coal Gasification in Global First for Steelmaking Details
 
8As Solar and Wind Meet A Larger Share of India’s Grid Load , Incremental Additions Come At Ever Higher Cost To Grid Details
 
8Tata Power Gets SECI Approval For 324 MW Pumped Storage Plant Services Details
 
8APTEL Rules in Favour of Wind Developer in Dispute Over Unapproved PPA Details
 
8Battery PLI norms eased as India cuts subsidy rate Details
 
8Indian Government Extends ALMM 2 Deadline for Solar Projects Details
 
8GB Solar commissions 2 GW module plant in Gujarat Details
 
8Centre extends exemption for select RE projects from sourcing solar cells from ALMM-listed manufacturers Details
 
8India's solar push hits a manufacturing hurdle. Here's why the cell mandate was delayed Details
 
8Indian Railways Invites INR 4.02 Crore Tender For 1 MW Rooftop Solar PV Plant At BLW Workshop Details
 
8Power sector growth outlook remains strong on robust demand, thermal generation; higher costs, execution risks pose offsets: Report Details
 
8A problem of when, not how much Details
 
8SECI Invites EOI From Bulk Power Consumers For Long-Term Renewable Energy Procurement Across India Details
 
8India’s power discoms are healthier than before, but subsidy dependence remains a major challenge Details
 
8Hydel projects to add 14,000 Mw by 2032-33, CEA Chairman reckons Details
 
8Delhi launches ‘Smart Power Push’ with compact substation, 'Solarise East' campaign Details
 
8Prepare for surge in power demand: Dy CM Mallu Bhatti Details
 
8Weak monsoon halves TN hydel power output, forcing costly electricity purchases Details
 
8Laser Power & Infra wins Rs 4.15 crore HPSEBL order for HTLS conductors Details
 
8Gujarat’s Rs 6 trillion data centre bet may trigger 45 GW solar surge; Nuvama explains 22% cost cut Details
 
8Adani Enterprises and 7 Other Stocks in Which Mutual Funds Increased Their Stake in Q1 Details
 
8Erratic Monsoon Risks: Impact on Food Costs and Power Demand Details
 
8The power grid must get smarter before it gets bigger’: Vera Silva, Chief Strategy & Technology Officer, Electrification Systems, GE Vernova Details
 
8India Electricity Consumption Spikes 8% During April-June Quarter Details
 
8Stock with 111% Profit CAGR Is Now Betting Rs 1,000 Crore on India’s Defence Manufacturing Opportunity Details
 
8PTC India and Bandhan Bank See Technical Upside, Says Angel One Details
 
You can also click on Newsclips for more Details

Daily Power Sector Tenders Excel update

Jul 20: 8Daily Excel covering new tenders and all published updates including corrigendum, amendment, addendum, clarification and status revisions, along with technical and financial bid opening, evaluation completion and final award actions including AOC and LOA issuance.
Click on Reports for more Details

Contracting news for the day: Part-1

Jul 18: 8SECI floats 45.6 MW ISTS-connected wind project at Ramagiri, Andhra Pradesh, with 10-year O&M
SECI has invited bids for turnkey EPC of a 45.6 MW (+5%) wind power project at Ramagiri, Sri Sathya Sai district. It follows single-stage two-envelope bidding with e-reverse auction, a Rs 25,000 + GST processing fee and an Rs 8.44 crore EMD. The scope covers design through commissioning plus 10 years of comprehensive O&M. What's happening: SECI has split its 50 MW FDRE project into two separately awarded packages — this Wind package and a separate Solar+BESS one — but the wind contractor must still integrate both into a single functioning asset, keeping design, performance and lifecycle risk with the bidder.

 

8Powergrid invites bids for 16 units of 765 kV, 80 MVAR single-phase reactors under Lot-8
Powergrid has issued a tender for the 765 kV Reactor Package 7RT-34-BULK via the PRANIT portal. It is a lump-sum contract with a Rs 25,000 tender fee and EMD shown as Nil. Bid submission closes on 14 August 2026, with technical bid opening the same day; a pre-bid meeting is set for 28 July 2026. What's happening: Powergrid is aggregating sixteen reactors into one bulk package rather than ordering substation by substation, standardising specifications and securing manufacturing capacity in advance — keeping the field limited to proven high-voltage OEMs.

 

8Powergrid opens GeM tender for 765 kV current transformers across Eastern and Western Region-I
Powergrid has launched a GeM procurement for 765 kV current transformers, including 3000A, 4000A, extended-rating and six-core variants. Deliveries go to substations in Jharkhand, Bihar and Chhattisgarh over 365 days. It carries an Rs 8.71 lakh EMD and a 5% ePBG valid 26 months, reserved for Class-I local suppliers. Bids close 6 August 2026; the online pre-bid meeting is 23 July 2026. What's happening: Powergrid is pairing reverse-auction price discovery with Class-I local-supplier reservation for a specialised product, chasing lower prices without loosening technical entry barriers — which keeps competition among a small pool of qualified OEMs.

 

8Powergrid tenders 12 units of 765 kV, 80 MVAR reactors under 7RT-35-BULK with 60-month defect liability
Powergrid has issued a specification for 12 single-phase reactors under Lot-8, published 15 July 2026, with bids closing 13 August 2026. EMD is replaced by a bid-securing declaration, and an e-reverse auction applies. Reactors carry a 60-month defect liability, a further five-year latent-defect window and a Rs 8 lakh per kW loss LD. Six units must be commissioning-ready in 23 months and the remaining six in 26 months. What's happening: Powergrid is loading heavy lifetime-performance risk onto the contractor and deferring freight and insurance pricing until after it fixes destinations — so bidders win on ex-works price but negotiate logistics costs later, with little leverage.

 

8MPUVNL invites RESCO rooftop-solar bids across nine MP districts on a 25-year PPA model
MPUVNL has invited bids for grid-connected rooftop solar at government premises across nine districts, published 16 July 2026, with bids closing 17 August 2026. The developer finances, builds, owns and operates each system for 25 years under separate PPAs with each government DDO. EMD is Rs 1 lakh per MW, with performance security of Rs 1,750 per kW for each PPA, and the first-year tariff escalates 2% annually. What's happening: MPUVNL is capping each bidder's award at the lower of its EMD-backed and financial capacity, and fragmenting district awards into multiple DDO-level PPAs — turning the tender into a distributed 25-year operating platform rather than a simple EPC job.

 

8PFC appoints lender's legal counsel for Rs 254 crore Bikaner solar-plus-BESS financing
PFC has issued a GeM tender to appoint counsel for a ~Rs 254 crore loan to Juniper Nirjara Energy for a 42 MWp solar and 234.8 MWh BESS project, plus security changes to an existing 70 MWp solar loan. It is a two-packet limited tender among 12 empanelled category-A firms, with no EMD or ePBG, closing 31 July 2026, and the lump-sum fee is paid in five 20% milestones. What's happening: PFC needs the counsel to recast security so a new loan and an existing solar financing share collateral on a first pari-passu basis — buying execution certainty, with milestone payments hinging on registries and counterparties outside the firm's control while PFC keeps termination-at-will.

 

8TGGENCO floats two-year rate contract for grinding rolls and bull ring segments with conflicting qualification clauses
TGGENCO has invited two-part bids for grinding rolls and bull ring segments used in BHEL bowl mills across its 270–800 MW units, on a two-year rate-contract basis. Bids close 17 August 2026, with a Rs 1.15 crore EMD and a 10,000-hour operating guarantee with mid-life joint inspection. What's happening: The tender contradicts itself — five versus six years' experience, and Rs 30 crore versus Rs 7.20 crore solvency, across different sections — an unresolved drafting conflict that could decide who qualifies before price bids even open, while layered securities and firm pricing shift lifecycle risk onto the supplier.

Details

Download tenders and news clips

Jul 18:  For reference purposes the website carries here the following tenders:
 8Tender for development of railway siding for loading of pond ash Details
 8Tender for interconnection of 400kV line Details
 8Tender for supply, installation testing and commissioning of differential numeric relays at various Details
 8Tender for supply of TLSA for the transmission lines Details
 8Tender for work of 33 kV new substation Details
 8Tender for construction of 33 kV UG line Details
 8Tender for civil works for construction of 132 kV bays Details
 8Tender for selection of agency for providing application management services Details
 8Tender for procurement of spares of various rating motors HT motors Details
 8Tender for work of repairing of foundation bolts of rotary breakers Details
 8Tender for procurement of HS straight joint kit, HS outdoor and HS indoor termination kit for 11 kV 3 X 120 sqmm XLPE cable Details
 8Tender for procurement of 11 kV standalone structure materials complete set Details
 8Tender for R&M of AEP gear boxs Details
 8Tender for Package- 3 engineering procurement, supply, installation, testing & commissioning of electro- mechanical components for 640MW (8X80 MW) Details
 8Tender for work of bus strengthening from single panther conductor Details
 8Tender for procurement of non ferric alum commercial grade. Details
 8Tender for erection of 3.3kV overhead line Details
 8Tender for various pipeline related jobs (installation of pump, etc) along with associated electrical works Details
 8Tender for maintenance of 11kV, 3.3kV and 550V OH line Details
 8Tender for annual miscellaneous preparatory civil works for various Details
 8Tender for civil maintenance of ash dyke Details
 8Tender for maintenance of horticulture and landscape works Details
 8Tender for supply of R-22 refrigerant gas for AC plant system Details
 8Tender for supply of various types of clamp for 220 kV switchyard Details
 8Design, fabrication, supply, installation, testing, commissioning of ongrid solar ground mounted project with net meter and RMS capacity of 140 kW Details
 8Tender for repair of damaged platform, plinth surface, drain, railing Details
 8Tender for construction of 33kV underground line Details
 8Tender for supply of ferric alum Details
 8Tender for construction of new 33 /11 kV sub station Details
 8Tender for supply, erection, installation, testing, and commissioning of materials/equipment Details
 8Tender for supply of programmable multi function digital panel meters for switchyard and protection control panels Details
 8Tender for extension of drainage at 110kV substation Details
 8Tender for construction of 11kV new feeder from 110kV S/s Details
 8Tender for shifting of electrical utilities in connection Details
 8Tender for resurfacing of road inside substation, extension of road to 11kV yard Details
 8Tender for utility shifting of transformers and RMU Details
 8Tender for procurement of spare of mechanical seal of booster pump Details
 8Tender for procurement of carb clad/Tibo. sol coated rotary segregating valve assembly for buffer hopper Details
 8Tender for procurement of spares of DMCW (TG and SG) pumps Details
 8Tender for procurement of ABT compliant energy meters of 0.2s accuracy Details
 8Tender for procurement of spares for gas analyser Details
 8Tender for renewal and replacement of damaged water supply/sanitary paint electrical wiring Details
 8Tender for procurement of special steel sail hard/TISCRAL or equipment 6mm carbon steel for gas ducts. Details
 8Tender for supply and delivery of 61 Nos. guide vane seal Details
 8Tender for procurement of 4-inch PRV for unit 5 conveying line Details
 8Tender for biennial maintenance work of of water distribution line Details
 8Tender for biennial maintenance contract for electrical maintenance including illumination system Details
 8Tender for biennial maintenance contract for overall illumination maintenance jobs Details
 8Tender for procurement of electrical spare parts items Details
 8Tender for replacement of existing 11 kV ACSR conductor with 11 kV Dog conductor Details
 8Tender for ARC for HT/LT/TC erection and maintenance works Details
 8Tender for laying, erection, testing and commissioning of 132kV 1Cx800 sq.mm XLPE cable Details
 8Tender for Bi-annual contract for work of loading, unloading, stacking of any material Details
 8Tender for work of erection dismantling of 132kV/66kV/11kV equipment’s, structures, control wiring Details
 8Tender for ARC for HT/LT/TC erection and maintenance works Details
 8Tender for work biannual AMC of repairing / refurbishing, servicing & overhauling of 400KV & 220kV isolator along Details
 8Tender for annual battery maintenance work at various substations Details
 8Tender for annual maintenance contract for attending emergency / breakdown / planned maintenance works of 220kV & 132kV sub stations Details
 8Tender for work of replacement of old battery set by new battery set Details
 8Tender for various regular preventative maintenance / emergency and breakdown works of various 220kV & 100kV substations Details
 8Tender for supply of spares and repairing, servicing & overhauling VCBs at various sub stations Details
 8Tender for annual maintenance contract for the work of repairing, overhauling, servicing, maintenance & alignment of 220/132/33kV isolators Details
 8Tender for dismantling of existing damaged compound wall & reconstruction of compound wall at 132kV S/Stn Details
 8Tender for supply, installation, testing & commissioning of 2 TR split type variable speed inverter Details
 8Tender for work of establishment of 220/22kV GIS substation Details
 8Tender for establishment of 220/33kV substation along Details
 8Tender for work of LILO of 220kV line Details
 8Tender for supply of various types of contactors for LTMCC of 500 MW Details
 8Design, supply, installation, commission and maintenance of solar PV system Details
 8Tender for Bi-annual rate contract for erection of 66 kV line feeder bay / transformer bay for various sub-stations Details
 8Tender for purchase, erection, including foundation of conductor/cable measuring machine Details
 8Tender for work of replacement of insulator or SRI work of attending the fault or broken conductor and/or snapping from tower/gantry Details
 8Tender for work of overhauling, oil leakage attending and testing of 100MVA, 11/230 kV generating transformer Details
 8Tender for rate contract for repairing of failed / damaged / distribution transformers Details
 8Tender for supply, of LED flood lights 240 Watts Details
 8Tender for work of removal, supply and application of spray insulation of steam turbines Details
 8Tender for supply of mill discharge first piece after MPO for coal mill Details
 8Tender for supply of tubes, end plates & baffles and work Details
 8Tender for work of preventive maintenance, shutdown & emergency maintenance of IAC/SAC compressor, air washery fan/pump motor, ACW/FCW motor Details
 8Tender for work of dismantling replacement / repairing of PF pipe, orifice & PF bend of coal mills Details
 8Tender for work of replacement of various spares of drive system of wagon tippler Details
 8Tender for work of fabrication/ removal/ repairing /erection of metallic expansion bellows at various Details
 8Tender for supply of various spares for SWAS system of boiler Details
 8Tender for supply of various instruments for CHP Details
 8Tender for supply and replacement of NDCT components for 1x 800 MW Details
 8Tender for procurement of 6.6/0.415 kV feeder protection numerical relays Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8ECL CMD calls for balanced energy transition, says coal remains key to India's energy security Details
 
88 core industries index to become 9 as government adds iron ore Details
 
8West Bengal Energy Transition Shapes Coal Future Details
 
8India rebases its core sector index to 2022-23 on 20 July, and the same output will print a different growth number Details
 
8Iron Ore Joins India''s Core Sector Index, Total 9 Industries Details
 
8Index of Core Industries set to get an upgrade with revised base year and weights Details
 
8India Adds 30.6 GW Renewable Energy Capacity in H1 2026, Solar Leads Growth: Pralhad Joshi Details
 
8India's renewable energy capacity additions rose 25% in H1 2026 Details
 
8India’s renewable energy sector set for ‘transformational’ growth Details
 
8Adani Group breaks into India’s Top 10 most valuable brands; Adani Power leads energy sector Details
 
8Manju Gupta: Executive Director, Power Grid Corporation of India Limited Details
 
8Industry experts flag AI skills gap in clean energy sector Details
 
8Pinarayi Vijayan warns of protests if Kerala government sets up nuclear power plant Details
 
8Unlocking Efficiency: Building a unified power market through market coupling Details
 
8Advancing India’s sustainable industrial economy through clean energy Details
 
8FM Report: Power-Generation Risks Mount as Electricity Demand Soars Details
 
8Nuclear Ambitions: Building capacity for a low-carbon future Details
 
8Aryaman Vikram Birla targets 20 GW renewable capacity in medium term; plans to back growth with battery storage Details
 
8POWERGRID Invites Bids For 250 MW/1000 MWh Battery Energy Storage System Project Across India Details
 
8India a step closer to its first demonstration-scale geothermal power project Details
 
8India to Open Thorium Sector to Private Firms Details
 
8Assam govt plans Rs 77,353 crore power push Details
 
8Sanjay Ghodawat Group and Nordstar Estates Join Forces to Power India’s High-Growth Real Estate Markets Details
 
8Laser Power & Infra secures Rs 4.15 crore HPSEBL order for HTLS conductors Details
 
8Ratul Puri on Building Integrated Energy Solutions for India’s Rising Power Demand Details
 
8NTPC Appoints Dr. Som Nath Sachdeva as Non-Official Independent Director for Three-Year Term Details
 
8Laser Power & Infra Locks in 10% Upper Circuit Again After Heavy Institutional Buying on Listing Details
 
8Walchandnagar Industries, BHEL, L&T shares in focus as NTPC-NPCIL JV floats Rs 28,000 crore tender for Rajasthan Nuclear Power Project Details
 
You can also click on Newsclips for more Details

Power Markets Daily

Jul 17: 8Day-ahead and real-time prices at fresh highs
Day-ahead cleared Rs 7,284/MWh for 17 July (Rs 7,049 for the 16th; Rs 2,490 on 12 July); real-time averaged Rs 7,723/MWh on 16 July before easing to Rs 6,911; green day-ahead firmed to Rs 7,024. Night blocks repeatedly hit the Rs 10,000 ceiling. Cleared volumes were ordinary (day-ahead 148,764 MWh for the 17th); the move is on price, driven by an evening buy-side scramble, not by volume.

8Demand near an all-time high
Maximum demand met 270,203 MW on 16 July, against the 270.8 GW national record of 21 May; energy met 6,002 MU. A monsoon peak this close to a heatwave peak is the demand signal behind the price move.

8Term-ahead and intraday markets pinned to the ceiling, clearing only in the evening
IEX term-ahead and green term-ahead contracts traded thin and mostly at the Rs 10,000 ceiling, with genuine clearing only in round-the-clock products (term-ahead round-the-clock West cleared 2,640 MWh at about Rs 7,953). The intraday segment cleared nothing all day. Real-time cleared only from about 19:30, and the PXIL deviation market only between 20:30 and 23:00 - buyers paying the ceiling, then Rs 5,500 - confirming the scarcity is a post-solar evening event.

8High-price and ancillary day-ahead segments did not clear
The high-price day-ahead market drew a sell-only book of about 72,000 MWh with no matching demand and no clearing price for a second running day; the ancillary-services day-ahead segment saw no bids and no activity all week. The unused sell-side capacity is another marker of daytime surplus.

8GUVNL floats a 400 MW reverse auction across three exchanges
Hindustan Power Exchange circular HPX_RA_01056 (16 July) sets a single-side reverse auction for Gujarat Urja Vikas Nigam - three tranches of 400 MW covering 23–31 July, August and September, ceiling Rs 10,000/MWh, energy of any type - with the e-auction on 18 July; parallel auctions run on IEX and PXIL. A large discom buying blocks two to three months out is the mirror image of the evening-peak tightness.
Details

Grid Operations Daily

Jul 17: 8Frequency ran low, not high
On 16 July the frequency was inside the 49.9–50.05 Hz band 64.3 percent of the time, but it spent almost twice as long below the band (23.3 percent) as above it (12.4 percent), touching a low of 49.508 Hz at 06:18. After weeks of running high on surplus, a day that dips low points to tighter mornings and a stretched evening ramp rather than pure oversupply.

8The grid was net backing down, with costly gas left idle
Ancillary services backed generation down by a net 4,565 MWh on 16 July (31,543 down against 26,978 up), and NLDC's unit-commitment table shows eight RLNG-gas stations committed but scheduled at zero. The system was comfortable on energy through the day; see Story 1.

8A busbar-protection event at Vemagiri cost 1,400 MW for fourteen minutes
At 11:52 on 16 July a jumper cut on a 220 kV bus-coupler at Vemagiri (Andhra Pradesh) operated the busbar protection, tripping the Vemagiri transformers and then Guddigudem's on load transfer, for a load loss of about 1,400 MW; supply was restored by 12:06. A short, sharp reminder that single-point bus faults still take large blocks off instantly.

8National corridors clean, but Tripura's import path ran over its limit for nearly 20 hours
Nationally, inter-regional transfer and N-1 criteria showed zero violations on 16 July. Inside the North-East, though, the Tripura import corridor breached its available transfer capability for 19.7 hours on 15 July (82 percent of the day) and the Assam corridor for five - the chronic evacuation constraint behind the region's defence-scheme strain (see Story 4).

8A southern bus ran persistently over-voltage at Cuddapah
The 765 kV bus at Cuddapah spent 38 percent of 16 July above 800 kV, peaking at 813 kV - the day's largest voltage deviation, with smaller high-voltage excursions at Nizamabad, Maheshwaram and two Gujarat buses. Light evening loading on a high-voltage backbone with reactive support lagging; no low-voltage violations were recorded nationally.

8Weak primary frequency response from two North-East stations
NERLDC's June frequency-response scorecard rates Doyang hydro at 0.02 and Palatana gas at 0.21 on a scale to 1.0 - near-absent governor response - while Bongaigaon and Kopili scored a full 1.0. Poor primary response from large machines is what forces the ancillary market to do more of the second-by-second balancing.

8Eastern demand was chronically under-forecast
ERLDC's day-ahead load forecast for 16 July ran a mean error of 7.5 percent and under-called actual demand by up to about 3,900 MW through the midday blocks; the intraday forecast was tight at 1.4 percent. Day-ahead under-forecasting in a rising-demand month feeds straight into next-day exchange buying.

8A CT burst at Biharsharif cascaded to a 110 MW blackout when a breaker failed to open
On 26 June a current-transformer burst at Biharsharif faulted the bus, and the bus-coupler breaker's pole failed to open mechanically - so the fault spread to the second bus and cascaded to a 110 MW blackout, with the disturbance recorder found not time-synchronised. A single CT failure turning into a station blackout is exactly the latent mechanical defect a protection audit is meant to catch.

8Santaldih lost 225 MW when a bus-shift flashed over mid-operation
On 4 June a heavy flashover during a live shift of a unit from one bus to another at Santaldih operated the busbar differential and tripped the whole switchyard, losing 225 MW of generation and 92 MW of load. The committee's lesson is blunt: finish the feeder rearrangement before splitting a bus, not during it.

8Godda and Pakur lost load twice as healthy lines tripped with the faulted ones
Two events at Godda/Pakur (17 and 25 June, 168 and 216 MW of load lost) saw faults on the Madanpur lines simultaneously trip healthy parallel circuits; the Jharkhand utility must explain why an auto-reclose did not operate and segregate its special-protection outputs. Sympathetic tripping of sound lines is the signature of a protection-coordination gap.

8A Buxar transformer tripped on a setting that breaks the region's protection rule
On 11 June a Buxar transformer tripped on a standby-earth-fault element set to a fixed one-second delay rather than the eastern region's inverse-time philosophy - a settings mismatch the operator has asked the utility to correct. Small on its own, it is the kind of non-standard setting that turns an external fault into an unnecessary trip.

8Generation ran above programme on 15 July, but hydro is lagging
CEA's daily generation report puts all-India output at 5,020 MU on 15 July against a 4,485 MU programme. Year-to-date, eastern hydro is 32 percent below target and north-eastern 12 percent below, while northern nuclear runs 18 percent short - the shortfalls that a monsoon is supposed to be curing.

8Darbhanga went dark on 29 June though the fault cleared in under 100 milliseconds
At Darbhanga on 29 June a phase-to-earth fault cleared in under a tenth of a second, yet both 220 kV lines and both 400/220 kV transformers tripped together and the station went dark. The phasor records show the fault was cleared fast, so why healthy elements tripped with it is unexplained, and the two transmission utilities' reports are still awaited - the signature of a protection-logic fault rather than the fault itself.

8A north-eastern voltage problem is now spilling into Bhutan's grid
Chronic low voltage around Rangia in Assam - worse whenever a Bongaigaon–Rangia circuit is out - has Assam pulling so much power through a 132 kV tie to Motanga that it stresses the Bhutan system, whose operator has asked to open the tie from its end. The region's voltage weakness now crosses an international border, and the fix - a 400/220 kV substation at Rangia - is still pending.

8A Nagaland protection scheme keeps shedding load with no fault to answer for
Unequal loading on two parallel 132 kV lines at Dimapur keeps pushing one phase over the special-protection-scheme pickup, shedding load three times in late June and early July with no actual fault; the root cause is still not found. A defence scheme that fires on a loading imbalance is itself a reliability risk, not a safeguard.
Details

MNRE extends the ALMM solar-cell exemption to 31 December 2026, sparing rooftop and open-access projects

Jul 22: 8The renewable-energy ministry has pushed the deadline for mandatory use of listed domestic solar cells to 31 December 2026, from 31 May, for rooftop, net-metering and open-access projects. Utility-scale projects stay bound by the mandate, and everything must comply from 1 January 2027. Details

Daily Power Sector Tenders Excel update

Jul 22: 8Daily Excel covering new tenders and all published updates including corrigendum, amendment, addendum, clarification and status revisions, along with technical and financial bid opening, evaluation completion and final award actions including AOC and LOA issuance.
Click on Reports for more Details

POWER MARKETS DAILY

Jul 22: 8IEX day-ahead averaged Rs 6,617 on 21 July but held the Rs 10,000 ceiling in 54% of blocks
8Real-time power took the day's biggest volume - 192.70 MU - at a weekly-low Rs 4,143
8The green day-ahead cleared Rs 6,755 and term strips settled flat at Rs 6,350 - no green discount
8PXIL cleared nothing and HPX drew no buyers, so IEX carried the entire cleared market on 21 July
8DVC-style peak buying returns as GUVNL and UPPCL float HPX reverse auctions for evening blocks
8Rajasthan's merit order runs from Rs 0.99 at NLC Barsinghsar to Rs 27.87 for liquid-fuel peaking Details

GRID OPERATIONS DAILY

Jul 22: 8India met a 235,132 MW evening peak and a 237,218 MW day-max on 21 July with zero shortage
8The grid ran high a quarter of 21 July and the operators backed generation down by 51,305 MWh
8The North-East to Tripura corridor sat over its transfer limit for 51.9% of 21 July
8Gujarat alone curtailed 922 MW of solar and 353 MW of wind for grid security on 21 July
8The Northern grid switched out about 25 of its 765 kV bus reactors at dawn to hold voltage up
8India imported 51 MU from Bhutan and 22 MU from Nepal while wheeling power to Bangladesh Details

OUTAGE & MAINTENANCE REGISTER

Jul 22: 8About 43 GW of generation sat on outage on 21 July, the West carrying 18 GW of it
8Fresh 21 July trips took out Sasan 660 MW, Rihand-II 500 MW and a clutch of 200 MW units
8Yadadri's coal-starved 800 MW unit came back on 21 July; Ropar and Ghatampur stayed coal-hit
8North Chennai's 800 MW and Rajpura's 700 MW units stayed out on ESP and boiler faults
8Two Southern 400 kV corridors remain down two months after tower collapses in May
8Much of the 'outage' is economic reserve-shutdown - 2,700 MW of Western gas parked idle Details

FUEL & COAL LEDGER

Jul 22: 8Twenty-seven thermal plants ran coal-critical on 20 July; Damodaram Sanjeevaiah at 2%
8Coal ministry says 42 mines have been scientifically closed - a first since independence
8Fly-ash use hit 98.3% in 2024-25, but barely 1% of it moves by rail Details

HYDRO & RESERVOIR LEDGER

Jul 22: 8Telangana's Krishna reservoirs sit about 92% below last year deep into the monsoon
8Odisha's hydro fleet ran about 350 MW with several OHPC units forced out and reservoirs below last year
8Sikkim generated zero units on 21 July with the 1,200 MW Teesta-III still out since 2023 Details

CERC DOCKET

Jul 22: 8CERC proposes to grant PI Green Consulting a Category-V inter-state trading licence
8CERC clears POWERGRID's Mahan-Rewa transmission licence and rebukes Mahan Energen for non-compliance Details

STATE REGULATORY ROUNDUP

Jul 22: 8Uttarakhand's regulator clears a Kedarnath feeder after the fact and rebukes UPCL for jumping the gun
8Uttarakhand's ombudsman quashes a Rs 11 lakh back-bill and orders recovery from erring UPCL officers
8Bihar reserves one Section-142 order, lists two more and opens a supply code for sugar mills
8UP's regulator admits an Ayesha Steel removal-of-difficulty plea for a 20 August hearing
8Chhattisgarh's regulator takes up Jindal Steel's captive Raigarh ARR with a Rs 48 crore true-up gap
8Assam opens a public hearing on paying interest on consumers' security deposits
8Punjab's regulator advertises five deputation posts, including a secretary to the chairperson Details

GREEN MARKETS & RE PROGRAMME WATCH

Jul 22: 8MNRE extends the ALMM solar-cell exemption to 31 December 2026 for rooftop and open-access
8India's renewable capacity reaches 288.58 GW, four times its 2014 level, MNRE tells Parliament
8The power ministry halts two Tamil Nadu offshore-wind transmission projects
8India's battery-cell scheme has awarded 40 GWh but drawn zero incentive and Rs 5,180 crore of investment
8ACME Solar signs its 300 MW SECI hybrid PPA at Rs 3.25, lifting signed capacity to 6,870 MW
8Tripura's ADB-funded distribution plan pairs a 120 MW gas revamp with rooftop solar for weavers Details

CORPORATE WIRE

Jul 22: 8Adani Energy Solutions' Q1 profit doubles to Rs 1,237 crore
8Jharkhand's discom posts a Rs 1,839 crore half-year loss
8JSW Energy lifts its Toshiba-turbine stake to 20.7% as its GE Power India merger clears the vote
8BHEL's Trichy unit carries a Rs 43,927 crore order book as it lifts capex and nuclear supply
8Servotech's Q1 revenue jumps 66% to Rs 208 crore on solar, chargers and storage
8Viviana Power Tech commissions a 400 kV wind-evacuation line and carries a Rs 1,340 crore book
8REC floats a Maharashtra transmission SPV for a 400 kV Solapur switching station
8Kirloskar Electric flags going concern even as it turns a small profit and raises Rs 40 crore
8NLC India raises Rs 150 crore of commercial paper as the July results run fills the diary
8Ratings Watch - ICRA assigns 'A' to Blupine's 50 MW Karnataka solar group; reaffirms AA+ for Adani Energy Solutions Details

COMMITTEES, PEOPLE & SYSTEM ADMINISTRATION

Jul 22: 8The North-East's control-system bill jumps Rs 167 crore as its grid loses visibility
8Three regions' weekly settlements paid generators Rs 100 crore-plus of must-run
8Three inter-state lines were charged in June, but 54 of 86 remain behind schedule
8PSPCL ties promotions to strike-regularisation as its establishment churns through 50-plus officers
8Rajasthan's RVPN reopens employee pay-fixation and amends its 1964 service regulations
8SJVN's state-nominee director ceases office as PSU board seats turn over Details

Methane blast kills at least 20 at NHPC's under-construction Teesta-VI tunnel in Sikkim

Jul 22: 8A sudden burst of methane deep inside the head-race tunnel of NHPC's 500 MW Teesta Stage-VI project at Samardung touched off an explosion and toxic fumes shortly after 1 pm on 20 July, trapping 25 workers and project officers. By the morning of 22 July at least 20 were confirmed dead and a handful still missing, as rescue teams battled the same gas that caused the blast. Details

IEX day-ahead sat at the Rs 10,000 ceiling in 54% of 21 July's blocks yet crashed to Rs 1,618 at noon

Jul 22: 8The day-ahead market averaged Rs 6,617.61 a MWh on 21 July but sat pinned at the Rs 10,000 ceiling through the overnight and evening blocks, then collapsed to Rs 1,617.91 in the solar-flooded early afternoon. None of it was scarcity - the grid met a 235,132 MW evening peak with zero shortage; the crunch is the shape of the day, not a shortage of power. Details

The grid paid Western generators Rs 80 crore in one week to stay on the site as monsoon load slumped

Jul 22: 8The Western load-despatch centre’s security-constrained unit-commitment account for 6–12 July shows Rs 80.17 crore paid to keep coal and gas units committed and run up, led by Rs 14.98 crore to NTPC’s Khargone. In the same week the Eastern pool paid a further Rs 21 crore of must-run, Farakka alone drawing Rs 15.6 crore - the cost of holding thermal ready while midday solar forces it down. Details

Half of India's inter-state transmission build is late - Rajasthan and Khavda solar links slip up to six years

Jul 22: 8The CEA’s June progress report shows 54 of 86 under-construction inter-state transmission lines awarded through competitive bidding running behind schedule, many of them the very lines meant to evacuate Rajasthan and Khavda solar. Sterlite’s Goa–Tamnar link has slipped almost six years; a cluster of renewable-zone corridors is 12 to 24 months late. Details

Adani Energy Solutions' Q1 profit doubles to Rs 1,237 crore on a Rs 71,779 crore transmission pipeline

Jul 22: 8Adani Energy Solutions reported a consolidated first-quarter net profit of Rs 1,236.56 crore, up 129%, on income of Rs 9,852 crore and EBITDA of Rs 3,178 crore. It is carrying a Rs 71,779 crore under-construction transmission pipeline and has agreed to buy the IntelliSmart smart-metering platform outright for Rs 3,050 crore. Details

The North-East grid is going blind as its control-system bill jumps Rs 167 crore on AI-driven hardware prices

Jul 22: 8The North-Eastern committee’s papers for its 23 July meeting show the region’s new SCADA and energy-management build re-costed to Rs 688.61 crore from Rs 521.67 crore, a Rs 167 crore jump the committee blames on server and memory prices inflated by AI data-centre demand. At the same time real-time visibility of the grid has collapsed - Nagaland is telemetering under 30% of its data to the regional despatch centre. Details

Twenty-seven thermal plants run coal-critical in mid-monsoon - Andhra's Damodaram Sanjeevaiah down to 2%

Jul 22: 8National coal stock at power plants held about 40.75 million tonnes, roughly 13 days’ cover, on 20 July - but 27 individual plants were running critical, one more than a week earlier. Andhra’s Damodaram Sanjeevaiah was at 2% of its normative stock and JSW’s two Torangallu units were out of coal altogether. Details

Jharkhand's discom posts a Rs 1,839 crore half-year loss as its accumulated deficit nears Rs 18,330 crore

Jul 22: 8Jharkhand Bijli Vitran Nigam’s unaudited results, filed ten months late under the distribution-reform scheme, show a Rs 746.70 crore loss for the September quarter and Rs 1,839.02 crore for the half-year. Its accumulated deficit is close to Rs 18,330 crore and its power-purchase bill alone exceeds its revenue from selling electricity. Details

India's under-construction coal fleet swells to 42,700 MW even as this year's additions collapse to 2,260 MW

Jul 22: 8The CEA’s June thermal status report shows 42,700 MW of coal capacity under construction, all supercritical, against a further 21,380 MW stalled or stressed. Yet only 2,260 MW of a 7,300 MW target has been commissioned this year - and most fleet growth now comes through insolvency buyers, not greenfield builds. Details

Contracting news for the day: Part-1

Jul 22: 81. PSTCL floats 90-day civil works tender for 160 MVA transformer at 220 kV Bathinda substation
PSTCL has published a notice inviting tender for civil works connected with a 160 MVA transformer at its 220 kV GNDTP Bathinda substation, with a compressed 90-day completion window and quoted rates valid for 120 days. Tender documents will be issued only to firms the corporation considers adequately experienced, though no qualification formula is disclosed. A striking drafting anomaly sits inside the notice: the document-issue deadline falls after the bid-submission deadline. Unless corrected, the timetable is internally unworkable and could undermine competitive participation.

 

82. UJVNL packages river diversion, tunnelling and powerhouse into single Rs 87.90 crore Tankul hydro contract
UJVN Limited has invited online bids for constructing the 12 MW Tankul small hydro project in Pithoragarh, combining trench weir, intake, river diversion, desilting tank, tunnel, surge shaft, powerhouse and hydro-mechanical works in one mandate. The submission deadline has moved by 25 days through two extensions alongside two corrigenda, signalling the package required correction before closure. Bidders must price geological uncertainty, river behaviour and remote Himalayan logistics into a compact contract value. The project's execution complexity far exceeds its modest installed capacity.

 

83. BSPGCL couples 150 MW solar with 75 MW/300 MWh battery in tariff-based bid with capacity-linked EMD
Bihar State Power Generation Company has issued an NIT to develop 150 MW of solar PV integrated with a four-hour battery system through tariff-based competitive bidding followed by e-reverse auction. The EMD scales at Rs 14.24 lakh per MW quoted, discouraging speculative capacity offers, while the original bid-security instrument must physically reach BSPGCL despite an otherwise digital process. Battery degradation, augmentation and charging rules — central to project economics — are left to the detailed documents. The outcome could set an early state benchmark for solar-plus-storage pricing.

 

84. HPSEBL seeks Rs 3.72 crore project management consultant under QCBS — then adds a reverse auction
HPSEBL has floated an RFP for a project management agency to support its reforms-linked distribution scheme, deploying 246 expert man-months across engineering review, field monitoring and funding-claim support, with the deadline extended by ten days. Selection follows a 70:30 quality-cost formula, yet the notice simultaneously announces an e-reverse auction — an unresolved structural clash. A Rs 70 crore annual turnover threshold towers over the modest assignment value, favouring large national consultancies. HPSEBL also retains the right to double expert deployment in every category, shifting staffing risk onto the consultant.

 

85. OCPL hands one consultant the entire blueprint for its 5 MTPA Manoharpur coal washery
Odisha Coal and Power Limited is appointing a single adviser to prepare the DPR, washability study, CAPEX-OPEX-IRR modelling and the complete EPC tender architecture for a proposed 5 MTPA coal washery, with the deadline extended by 18 days after the original schedule lapsed. The washability study must run through one of six named institutions, tying a core milestone to external laboratories. Joint ventures are barred, concentrating all credentials in one entity, while least cost selection meets a strict abnormally-low-bid clause that can exclude aggressive quoters from retenders. The 120-day programme leaves little slack for approval cycles.

 

86. GSECL's Rs 4.73 crore covered-conductor retrofit at Ukai TPS carries a 36-month owner-controlled execution horizon
GSECL has floated an open three-stage e-tender to replace 16 km of exposed 11 kV conductors at Ukai Thermal Power Station with medium-voltage covered conductors, including eight double-pole air-break switch structures and dismantling of old lines, as an indivisible supply-plus-works package. Supply must finish in six months, but the work order stays valid for 36 months — extendable by six more at unchanged prices. Thirty per cent of supply value remains locked until successful charging, tying contractor cashflow to shutdown availability. With no guaranteed work-release schedule, bidders are pricing a long-duration call-off obligation, not a fixed-schedule job.

 

87. MSEDCL extends commencement window but holds commercial line on Rs 130.38 crore STAR-II transformer buy
MSEDCL has issued Amendment No. 1 with pre-bid clarifications on its tender for 200 kVA STAR-II CRGO distribution transformers, extending the commencement period from two to three months while keeping the nine-month delivery schedule intact. Manufacturer requests for revised estimated cost, IEEMA price variation, relaxed experience thresholds and softer security terms were all rejected, while BEE certification was confirmed as not required for 22 kV units. The amendment signals selective operational flexibility without commercial concession. Certification-heavy entry barriers remain firmly in place for smaller suppliers.

 

88. POWERGRID engages exclusive land valuer for 219 km transmission corridor in Morbi under package-wise GeM bid
POWERGRID has invited a two-packet GeM bid to appoint a land valuer for transmission-line corridors in Morbi district under Package-7, covering roughly 219 km, with the consultant certifying survey-number-wise market rates for compensation and acquisition. The valuer must work exclusively for POWERGRID and is barred from representing any other project stakeholder — a stronger conflict-management measure than routine consultancy tenders carry. The district-wise package model spreads work across Gujarat while limiting how many packages one bidder can secure. The tender treats land valuation as project-critical infrastructure work rather than conventional advisory service.

 

89. NREDCAP offers 22-year DBFOT concession for Rs 324.70 crore Vijayawada waste-to-energy plant
NREDCAP, acting for Vijayawada Municipal Corporation and participating urban bodies, has issued an RFP for a private concessionaire to design, build, finance, operate and transfer a 15 MW municipal-waste-based power plant under a 22-year concession including two years of construction. The Rs 3.24 crore EMD and qualification framework point toward experienced infrastructure developers rather than general EPC contractors. Financing strategy and long-term operating assumptions will matter more than EPC pricing in determining competitiveness. The structure reflects a policy preference for private lifecycle ownership of complex municipal processing assets.

 

810. NTPC Ramagundam to double transformer capacity with 500 MVA units under integrated 30-month contract
NTPC has invited domestic bids to replace two 250 MVA auto transformers at Ramagundam with 500 MVA interconnecting units, bundling design, manufacture, transport, oil treatment, erection and commissioning into one accountability chain over 30 months. An unusual clause forces installation pricing into a 10–15% band of supply value, blocking payment-structure engineering. Loss penalties reach Rs 10 lakh per kW for no-load deviation — with no reward for overperformance — while the variable-price contract offers only narrow escalation relief. A Rs 1 crore bid security applies with no MSE exemption.

 

811. BHEL's 400 kV GIS package for Yamuna Nagar loads firm pricing, reverse auction and long-tail liabilities onto suppliers
BHEL is procuring a complete 400 kV gas-insulated switchgear installation for HPGCL's 800 MW ultra-supercritical expansion at Yamuna Nagar, with the deadline extended twice after a technical corrigendum rewrote testing, transport, packing and scope-boundary provisions. Prices stay firm across a 12-month supply cycle, while the 18-month warranty starts only after project trial operation — a milestone outside the supplier's control. Entire specification clauses were deleted without replacement, creating interpretation gaps, and packing must survive 24 months of outdoor monsoon exposure. Impact recorders must trace every shock from factory to site, with a reverse auction awaiting qualified vendors.

 

812. NTPC Talcher Kaniha's Rs 84.81 crore ash-backfilling contract pays only the lower of two measurements
NTPC has floated a GeM bid restricted to its enlisted ash-transport vendors for excavating, hauling and compacting ash from Talcher Kaniha into quarries and mine voids 50–100 km away, under a 12-month contract splittable 50:50 between two bidders. Payment follows the lower of dispatch-end or filling-site measurement, and every truck movement needs weighbridge, GPS, FASTag, toll and geotagged photo evidence uploaded daily — incomplete records mean withheld payment. A quantity mismatch between the scope figure and doubled BOQ entries demands careful reconciliation. Regulatory penalties on NTPC flow back entirely to the contractor, converting a transport job into a full land-reclamation obligation.

 

813. AEGCL's fixed-price 220 kV line for TATA semiconductor plant transfers all design-modification costs to the contractor
Assam Electricity Grid Corporation has published a turnkey tender for a 220 kV Sonapur-TSAT double-circuit line providing redundant power to the TATA semiconductor facility, spanning overhead line, underground cable, optical fibre and commissioning under single-point responsibility within 24 months. There is no advance payment and no escalation: AEGCL supplies the base design, but site-driven modifications — special towers, pile foundations, raised chimneys — must be executed at zero additional cost. The warranty runs five years from supply or four-and-a-half from commissioning, whichever is later, with liquidated damages at 1% per week up to 10%. Payments can take 60 days, subject to fund availability.

 

814. Powergrid caps land valuers at one package each across ten-district Gujarat valuation drive
Powergrid has issued a GeM bid for an IBBI-recognised land valuer covering 246 tower locations across 91.74 km spanning three transmission SPVs in Vadodara district, one of ten sequentially opened packages, with every assignment due within 15 days of intimation. A "one agency, one package" rule prevents any single firm from dominating, while packages with three or fewer bidders jump the price-opening queue. No escalation applies, quantities can swing 25% either way, and the bid summary denies arbitration even as attached conditions prescribe a full arbitration regime. Consistency across multiple independent valuers remains the unaddressed governance risk.

 

815. JREDA opens Jharkhand's 16-site hydro pipeline to solar, wind and thermal players through eligibility rewrite
JREDA has issued an EOI to identify developers for small hydro projects across 16 Jharkhand sites under the BOOT model, beginning with surveys and DPRs before full development, financing and long-term operation. Corrigendum-I broke the hydro-only entry barrier: any 5 MW DISCOM PPA — solar, wind or thermal — now qualifies, provided the bidder operates a plant in the supplying state, with the deadline extended by 14 days. A Rs 50 crore turnover floor screens for balance-sheet depth over technical pedigree. Concession terms, tariffs and free-power obligations are deferred entirely to the RfP stage, making second-stage evaluation the critical safeguard.

 

816. UJVNL's Sirkari Bhyol hydro tender swells 53% to Rs 243 crore through twenty corrigenda
UJVN Limited's EPC tender for the electromechanical works of the 3x40 MW Sirkari Bhyol Rupsiabagar project has been transformed through twenty corrigenda and seven addenda: the estimated value jumped 53% to Rs 243.05 crore, the EMD rose to Rs 4.87 crore, and every qualification threshold was rewritten upward. Technical access simultaneously widened through a fifteen-year experience window, more approved component makes and flexible efficiency testing, even as financial entry tightened. Himalayan logistics, construction power and site utilities stay contractor-facing despite repeated bidder requests for relief. Bidders must hold prices for 270 days on a package still being stabilised months after publication.

Details

Download tenders and news clips

Jul 22:  For reference purposes the website carries here the following tenders:
 8Tender for supply and installation of digital type loadcell based overload and slack protection me chanism for various hoists gantry cranes installed Details
 8Tender for work of supply of T and P (tools and plants) materials Details
 8Tender for work of providing and erection of additional poles Details
 8Tender for work of replacement of old PVC cable with new PVC armoured cable Details
 8Tender for R&M works including supply and installation of 11 kV indoor VCB panel Details
 8Tender for erection, dismantaling and maintenance of HT/LT and transformer Details
 8Tender for annual rate contract (ARC) for LED lights & related spares items Details
 8Tender for annual rate contract for various types of structural steel items. Details
 8Tender for NDCT overhauling works Details
 8Tender for procurement of CW pump mechanical seals Details
 8Tender for procurement of galvanized gratings and end bar Details
 8Tender for hot line stringing of 66 kV line Details
 8Tender for dismantling of existing fencing and installation of new main gate along Details
 8Tender for procurement of cable termination kit Details
 8Tender for material handling and management including receipt, unloading, verifying, shifting, stacking, preservation, handling and handing over of components of boiler with auxiliaries Details
 8Tender for modification of steam generator (boiler) of 210 MW for comprehensive work Details
 8Tender for replacement work of old main switch, fuse unit etc. Details
 8Tender for renovation of control room at 110 kV substation Details
 8Tender for shifting of electrical utilities in connection Details
 8Tender for supply of 3 nos digital insulation resistance tester Details
 8Tender for procurement of 180KW, 3.3kV HT motors Details
 8Tender for R and M of existing fire detection and protection system Details
 8Tender for replacement of existing 250MVA auto transformers with 500MVA transformer Details
 8Tender for housekeeping work of 2x150 MVA 220/ 132kV grid sub station Details
 8Tender for supply of wall soot blower and oil gun spares for boiler Details
 8Tender for supply, erection and commissioning of various accessories of conveyor belt Details
 8Tender for construction of yard work and misc. civil works at 33kV S/S Details
 8Tender for construction of control room, cable trench, water supply arrangement at 33 kV s/s Details
 8Tender for purchase of spares for 420kV, 3150A, TP, HCB isolators with earth switches Details
 8Tender for procurement of spares for BHEL make DVAR Details
 8Tender for supply, erection & commissioning of 11 kV lines with MVCC conductor & dismantling of existing Details
 8Tender for supply, erection, testing and commissioning of 220 V DC, 63 AH, KPH 63P, Ni-Cd type battery set Details
 8Tender for biennial rate contract for motor or heavy equipment lifting or shifting or placement and motor coupling fitting works Details
 8Tender for execution erection work for effecting the 33kV bulk NSC by laying UG 33 kV 3CX400 SQMM XLPE cable Details
 8Tender for execution of erection work by erection of 11KV RMU, laying of 11kV XLPE UG cable, laying of HDPE pipe Details
 8Tender for round the clock maintenance for routine breakdown and preventive maintenance of 4 x 9 MW and 2 x 4 MW TG sets with all auxiliaries 66 kV switchyard Details
 8Tender for electrical work for construction of 2X5 MVA 33/11 kV S/S Details
 8Tender for construction of 26 KM.33kV line Details
 8Tender for providing and fixing of insulated sheet for ST pole Details
 8Tender for work of replacement of old PVC cable with new PVC armoured cable Details
 8Tender for work of installation of one No. 5 MVA power transformer at 33/11 kV sub-station Details
 8Tender for providing and fixing of insulated sheet Details
 8Tender for providing and fixing of insulated sheet for ST pole Details
 8Tender for work of overhauling, servicing & repairing work of 400kV circuit breaker Details
 8Tender for work of bi-annual maintenance contract for the work of servicing, repairing of various size and capacities battery sets and chargers Details
 8Tender for supply of 5nos spare numerical distance protection relay Details
 8Tender for refilling, servicing & maintenace, supply of spares for fire extinguishers at various substations Details
 8Tender for work of feeder re-orientation at 110kV & 220kV substation Details
 8Tender for work of supply & installation of advance cable transit system by passive fire screen Details
 8Tender for work of fabrication and supply of 50 kL empty oil tank Details
 8Tender for AMC for battery sets maintenance work (220 volts & 48 volts) and charger Details
 8Tender for annual maintenance contract for repairs, overhauling of 33 kV VCB installed Details
 8Tender for work of providing & fixing of maintenance free earthing at 220 kV line Details
 8Tender for supply of pressure relay of converter transformer Details
 8Tender for work of supply and installation of bird diverters (BFD) on 132kV DC transmission line Details
 8Tender for conversion of existing indoor SF6 & VCB AIS switchgear panels pertaining Details
 8Tender for rate contract of excavation and laying of new power / control / telephone cables Details
 8Tender for supply and application of epoxy glass flake coating with UV resistance PU top coat on various external surfaces Details
 8Tender for supply of control panel spares of pump house Details
 8Tender for R&M work of erection, commissioning of new feeder bay HV & LV equipment’s, testing ,earthing,control wiring etc. of 220/66kV 160 MVA transformer Details
 8Tender for erection and maintenance of HT/LT & TC work Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8
India’s Coal Mine Closure Report and GIZ Agreement Explained Details
 
8Bharat Coking Coal shares drop over 7% after Q1 net loss, lower offtake Details
 
8India’s Coal Self-Reliance Push: Govt Takes Major Steps to Boost Production and Reduce Imports Details
 
8Coal Ministry to Sign MoUs for Sustainable Mine Closure, Jharia Rehabilitation and Skill Development Details
 
8SECL Plants 3.20 Lakh Saplings in a Day, Builds Bilaspur’s First Miyawaki Forest for Greener Future Details
 
8Pumped hydro storage of 16 GW capacity under construction: Power Ministry Details
 
8Core sector growth reaches five-month high in June, lifted by iron ore and power Details
 
8PM-KUSUM's Missing Link: Why India's Solar Pump Success Isn't Yet an Agricultural Energy Revolution Details
 
8Power discoms await revival as structural reform delays persist in India Details
 
8Major Boost to Island Energy Security as 50 MW LNG Power Project Moves Forward Details
 
8Why Storage Hydropower Must Become Nepal's Next National Priority Details
 
8India Reaches 548.85 GW Power Capacity As Renewables Account For 43.09%, And Solar Hits 162 GW Details
 
8Tata Power wins 324 MW SECI pumped hydro project Details
 
8India tunnel collapse at a hydropower project kills 10 as 17 remain missing Details
 
8Transformers & Rectifiers India Reports 8% Q1 FY27 Revenue Growth, Order Book Reaches Record INR 6,630 Crore Details
 
8MAHLE Unveils Range Extender and Magnet-Free Motor for Heavy Commercial Vehicles Details
 
8India’s clean energy boom: Why the City of London should be paying attention Details
 
8India’s Renewable Energy Generation Crosses 100 GW for the First Time Details
 
8Stocks to Watch: Adani Power, Eternal, and 6 Other Stocks Announcing Q1 Results Today Details
 
8India’s renewable energy capacity jumps nearly to 288.58 GW Details
 
8Kolkata Power Network Eyes Digital Meter Expansion Details
 
8EAC-PM Report Flags India's Power Grid Vulnerability Details
 
8NLC India Raises Rs 150 Crore Through Commercial Paper Issue to Boost Liquidity and Support Growth Plans Details
 
8India Allows 4 Chinese-Linked Firms to Bid on Power Projects Details
 
8India Signs Major Nuclear Technology MoU: NPCIL and ECIL to Develop Critical Systems Details
 
8ACME Solar signs PPA with SECI for 300MW ISTS-connected Wind-Solar Hybrid Renewable Energy Project Details
 
8REC Signs Agreement with RITES to Ensure Quality Checks of Power Transformers Under RDSS Details
 
8J&K Readies 1,624 MW Hydropower Units by December 2026 Details
 
You can also click on Newsclips for more Details

Hydro & Reservoir Ledger

Jul 21: 8Telangana’s Krishna-basin storage has collapsed about 92% year on year, Srisailam and Nagarjunasagar near-empty
8Odisha hydro ran about 528 MW on 19–20 July with several OHPC units forced out and reservoirs below last year Details

Eastern thermal earned about Rs 112 crore in June for running part-loaded - the same stations were also failing their frequency duty

Jul 21: 8Beneficiary states under-requisitioned below 85% of their entitlement, forcing nine Eastern-region thermal stations to run at part load, and the compensation bill for it reached about Rs 111.9 crore for the fiscal year to June. The stations that ran part-loaded also posted the region’s weakest frequency-response scores, so the pool is paying twice - once in compensation, once in lost grid support. Details

Day-ahead power hit the Rs 10 ceiling overnight and at dusk on 20 July - yet the grid met a ~239 GW peak nearly shortage-free

Jul 21: 8The day-ahead market averaged Rs 6,801 a MWh on 20 July but sat at the Rs 10,000 ceiling through the overnight hours and again in the evening, then collapsed to about Rs 1,815 in the solar-flooded middle of the day. None of this was scarcity - the grid met a roughly 239 GW peak with barely a megawatt-hour of shortage; the crunch is the shape of the day, not a shortage of power. Details

The North met a 93,981 MW summer peak nearly shortage-free - but a single wind trip cost Rajasthan 1,290 MW

Jul 21: 8The Northern Region’s peak demand climbed through the June quarter to 93,981 MW and was met with under half a percent of shortage, with Uttar Pradesh the only state left short. Yet the quarter also shows how thin the margins are: single elements swung a gigawatt at a time. Details

Jaiprakash Power’s Q1 profit jumps 69% to Rs 469 crore as NARCL files insolvency over a Rs 1,239 crore guarantee

Jul 21: 8Jaiprakash Power Ventures reported a standalone Q1 profit of Rs 468.95 crore, up 69% year on year, even after absorbing a Rs 193.63 crore exceptional loss. In the same disclosure it flagged that NARCL has filed a Section 7 insolvency petition against it over a Rs 1,239 crore corporate guarantee - the overhang that now prices the stock. Details

MERC lets Adani’s Mumbai discom adopt Rs 6.38 a unit for 750 MW of round-the-clock renewable power

Jul 21: 8The Maharashtra commission allowed Adani Electricity Mumbai’s distribution arm to adopt a Rs 6.38 a unit tariff for 750 MW of round-the-clock renewable power under a ten-year deal, undercutting MSEDCL’s own effective benchmark. It is a signal on where firm-renewable pricing is settling. Details

India’s pumped-storage build-out reaches 15,870 MW under construction as SECI awards another 1,344 MW

Jul 21: 8The power ministry told Parliament that 11 pumped-storage projects totalling 15,870 MW are under construction, with a further 24,010 MW in the pipeline. In the same week SECI’s first pumped-storage tender awarded 1,344 MW of a 1,500 MW offer, confirming the shift from policy to procurement. Details

Twenty-six thermal plants sit critical on coal in mid-monsoon - Andhra’s Damodaram Sanjeevaiah down to 2%

Jul 21: 8National coal stock at power plants held about 41 million tonnes, or roughly 21 days, on 19 July - but 26 individual plants were running critical, with Andhra’s Damodaram Sanjeevaiah at just 2% of its normative stock. The average hides a distribution problem, not comfort. Details

Punjab’s power employees and pensioners strike for two days, forcing PSPCL to draft engineers to man substations

Jul 21: 8PSPCL’s own management circulated an order on 20 July confirming that a joint front of power employees and pensioner bodies will hold a statewide protest and mass leave on 21–22 July, with pensioners threatening a “jail bharo” agitation. Chief engineers have been told to ensure every substation is manned through the stoppage. Details

Maharashtra’s new RE policy blocks MERC from ordering MSEDCL to buy Waterfront’s small-hydro - even after fixing its Rs 6.18 tariff

Jul 21: 8MERC determined a tariff of Rs 6.18 a unit for Waterfront’s 3 MW small-hydro project but refused to direct MSEDCL to sign a power-purchase agreement, because Maharashtra’s March 2026 renewable-energy policy dropped the procurement mandate. The regulator fixed the price and then found it could not compel the sale. Details

About 40 GW sat on outage on 20 July as North Chennai lost 800 MW and Rajpura 700 MW to boiler and ESP faults

Jul 21: 8Generation outages ran to about 40 GW across the northern, western and southern registers on 20 July, and the day added fresh forced trips - North Chennai’s 800 MW unit hand-tripped on an ESP problem and Rajpura’s 700 MW unit on a boiler-tube leak. This parked baseload is the other half of the day’s price story. Details

Power Markets Daily

Jul 21: 8Day-ahead power averaged Rs 6,801 a MWh on 20 July but sat at the Rs 10,000 ceiling overnight and at dusk
8Real-time power cleared just 3.34 MU at the Rs 10,000 ceiling; the green, intraday and ancillary segments did not clear
8Term and green contracts settled around Rs 7,500 a MWh as the high-price exchange (HPX) day-ahead did not clear on 20 July
8DVC floats an August reverse auction for two 100 MW thermal bands across the exchanges, e-auction 22 July Details

Grid Operations Daily

Jul 21: 8All-India peak of about 239,106 MW was met on 20 July with roughly 1 MU of shortage
8The grid ran high 28% of 20 July - 6.75 hours outside the IEGC band, peaking at 50.251 Hz
8Rajasthan and the NR–ER corridor breached their transfer limits about 20% and 17% of 20 July
8Maharashtra shed about 0.195 MU on 20 July when a 132 kV line overloaded and grid-security load-shedding operated
8The Northern grid met a 93,981 MW June-quarter peak nearly shortage-free Details

Outage & Maintenance Register

Jul 21: 8About 40 GW sat on outage on 20 July; North Chennai 800 MW and Rajpura 700 MW tripped
8Further 20 July trips took out KSTPS 500 MW, Meenakshi 350 MW, Paras, Neyveli, Ukai and Tuticorin units
8Yadadri’s 800 MW unit has been out on coal shortage since 9 July; ACBIL 135 MW out on coal since 12 June
8The 765 kV Ariyalur–North Chennai line was still out late on 20 July after a fault; a Gadarwara 765 kV line faulted
8Champa’s 400 kV bays were out on station flooding and Vindhyachal HVDC Pole-1 had tripped in the West
8The northern and western transmission registers ran to 538 and 422 elements on 20 July, storm-collapse lines still standing Details

Fuel & Coal Ledger

Jul 21: 8Twenty-six thermal plants ran coal-critical on 19 July; Damodaram Sanjeevaiah at 2%
8The Ministry of Coal advances a Rs 37,500 crore gasification scheme, applications closing 7 September
8Thermal plants held 42.8 MT of coal and 14 days’ cover as coal supplied 69.5% of Q1 power, the ministry told Parliament
8Delhi’s Pragati gas plant ramped spot RLNG offtake about six-fold into the summer, its bill reaching Rs 85.9 crore a fortnight Details

Daily Power Sector Tenders Excel update

Jul 21: 8Daily Excel covering new tenders and all published updates including corrigendum, amendment, addendum, clarification and status revisions, along with technical and financial bid opening, evaluation completion and final award actions including AOC and LOA issuance.
Click on Reports for more Details

CERC Docket

Jul 21: 8CERC cut NTPC’s decommissioned Talcher 460 MW annual charge to Rs 475 crore and disallowed most residual capex
8CERC shielded SJVN Green’s 860 MW connectivity from CTUIL revocation and barred encashment of its bank guarantees
8CERC reserved orders on THDC’s water-tax change-in-law claim for the Tehri and Koteshwar hydro stations
8NEEPCO sought a cut in its Tripura gas station’s availability norm to 70% as ONGC gas supply more than halved
8PSPCL and Pragati Power head to a 13 August hearing over a Rs 82.99 crore Pragati-III billing dispute
8CERC reserved a ruling on whether it can hear the TNPDCL–PTC 150 MW pilot-power dispute at Rs 3.26 a unit
8CERC admitted six NLDC and RLDC fee truing-up petitions for 2019-24 and issued notices
8Trading-licence moves: CERC reserved Infinite Voltx’s Category V grant and sought RPG Power Trading’s accounts
8CERC docket calendar - Kishtwar Transmission security interest admitted, UPPCL water-tax amendment allowed, ISTS-charge batch adjourned
8APTEL’s Court-I and Court-II carried 257 and 27 short matters and over 1,670 final appeals as on 17 July
8GERC cleared VMS TMT’s 11.88 MW solar connectivity but refused Iran-conflict force majeure; adjourned Gujarat discoms’ net-metering plea Details

State Regulatory Roundup

Jul 21: 8MERC let Adani’s Mumbai discom adopt Rs 6.38 a unit for 750 MW round-the-clock renewables
8MERC suspended MSEDCL’s power to seize an under-used consumer feeder and ordered Rs 45 lakh compensation
8MERC ordered MSEDCL to pay Vena Energy Rs 11.42 crore in late-payment surcharge and interest on wind dues
8MERC cleared a provisional tariff for Adani’s Rs 6,888 crore 1,000 MW HVDC link, trimming the claimed cost
8Maharashtra’s RE policy blocked MERC from ordering MSEDCL to buy Waterfront’s small-hydro
8MERC dismissed about 1,959 MW of NOPL solar change-in-law claims for non-appearance and closed a settled Talf Solar guarantee dispute
8Bihar’s regulator set FY27 biomass and bagasse tariffs and restored them retrospectively to 1 April
8CSERC let Shree Cement raise its Chhattisgarh contract demand to 51 MVA at a 5% energy surcharge
8Assam’s regulator holds a public hearing on the 8th amendment to its electricity supply code
8Tamil Nadu’s electricity ombudsman part-voided a Rs 2.73 lakh back-billing on a defective meter Details

Green Markets & RE Programme Watch

Jul 21: 8Renewables met about 38% of demand at midday on 20 July, solar peaking at 69.1 GW
8SECI awarded 1,344 MW of pumped storage as the national build-out reached 15,870 MW
8BNC Power won SECI’s 10 MW Odisha solar tender at Rs 2.60 a unit with zero viability-gap funding
8ACME Solar signed a 300 MW hybrid PPA at Rs 3.25 and commissioned 160.5 MWh of Rajasthan battery storage
8KPI Green commissioned 200 MW of Coal India’s 300 MW Khavda solar and won charging nod for a 100 MW Maharashtra plant
8MNRE sanctioned a Rs 436.93 crore renewable R&D programme with a Rs 200 crore perovskite pilot line
8SECI opened an EOI to aggregate bulk renewable off-takers and set a 3 August site visit for a 45.6 MW wind EPC Details

Corporate Wire

Jul 21: 8Jaiprakash Power’s Q1 profit rose 69% to Rs 469 crore as NARCL filed insolvency over a Rs 1,239 crore guarantee
8Transformers & Rectifiers’ order book hit a record Rs 6,630 crore as Q1 inflows surged 218%
8GE Power India’s shareholders and creditors met to clear its absorption into JSW Energy
8ICICI Direct rated BHEL a Buy at Rs 575 on a record Rs 2.6 lakh crore order book
8Nava lifted its FY26 dividend to a record Rs 8.50 as Zambia arrears fell to US$28 million
8Corporate diary - JK Cement Q1 profit slips 12% to Rs 291 crore; Premier Roadlines books Rs 182 crore of power orders
8Smaller filings - CLN Energy reprices a promoter issue to Rs 423; Pace Digitek’s Lineage ties up AI-data-centre power; L&T bags mega metals EPC
8Results and board diary - Waaree Renewable, Indosolar and RattanIndia Power report over 23–24 July Details

Committees, People & System Administration

Jul 21: 8Punjab’s power employees and pensioners strike on 21–22 July, forcing PSPCL to man substations
8The Eastern committee’s June settlement run put about Rs 112 crore of part-load compensation across nine stations
8The Eastern frequency scorecard ranked PVUNL (0.33) and JIPL (0.41) the region’s weakest responders in June
8PSPCL reshuffled 16 senior officers and about 25 substation engineers and sanctioned posts for a new 66 kV grid
8PSPCL’s CMD leads a team to POWERGEN India as the utility revises induction and training rosters
8Mahatransco named 28 apprentices for its 2026-27 intake at Nagpur Details

Contracting news for the day: Part-1

Jul 21: 81) APGENCO's Dr NTTPS meter tender carries three conflicting reference numbers and four different bid-closing times The portal cites M100030900/P41 while the NIT and enquiry use P211 and a longer CE/O&M reference. Submission deadlines shift across 12:00, 13:00, 14:00 and 15:00 hrs depending on the document read. Latest: price-bid opening has been fixed, following the enquiry letter's own submission and opening timing.

 

82) OPTCL's Rs 256.29 crore Pahala tender makes one EPC contractor own a new GIS, a 9.94-km line and two live-station bay extensions The turnkey scope stitches the new GIS to Balianta through one integrated commissioning obligation. EMD is Rs 97.23 lakh. Latest: bids have closed and techno-commercial opening has taken place, with the price-bid date still pending.

 

83) A second APGENCO filing recasts the same NTTPS meter package as a straightforward digital-metering upgrade Scope bundles Secure-make ABT meters, RS-485/Modbus communication, HMI software and full commissioning into one contract. Eligibility favours manufacturers/dealers with PSU or utility metering experience. Latest: presented under a single, unconflicted P211 reference.

 

84) TGGENCO's 42-lakh-tonne coal haulage tender keeps daily quantity unguaranteed while penalising monthly shortfalls Bidders must move ~15,000 tonnes/day with GPS-fitted, dual-end-weighed tippers. Only 30% of the rate is diesel-linked; 70% stays fixed. Latest: the tender has opened, with pre-qualification bid opening due ahead of the price-bid opening.

 

85) MSEDCL's Rs 215.89 crore transformer tender softens qualification but holds firm on price and delivery 33/11 kV experience now counts toward the rarer 33/22 kV and 22/11 kV variants, and their type-test reports can follow bid submission. The nine-month delivery and 66-month warranty stay unchanged. Latest: Amendment No. 1 has been issued, extending the bid deadline.

 

86) POWERGRID gates its 765kV Bikaner substation package behind a mandatory NDA before releasing bid documents The package supports the Rajasthan REZ Phase IV evacuation corridor. Bidders must clear an eligibility and confidentiality screen before seeing specifications or pricing. Latest: the Invitation for Bids has been published, with bid submission and opening still ahead.

 

87) NTPC extends bidding on its Farakka generator-transformer replacement without touching scope or terms The 250 MVA transformer package covers design through commissioning under one 30-month contract. Bid security is Rs 50 lakh with a mandatory Integrity Pact. Latest: an extension notice has revised the bid submission and opening schedule, with scope and terms unchanged.

 

88) AEGCL's Sonapur–TSAT line for TATA Semiconductor pushes site-driven design changes into the contractor's fixed price The Rs 1.57 crore-EMD, 24-month turnkey package spans towers, pile foundations, 220 kV cable and underground OFC. Warranty runs 60 months from supply or 54 from commissioning. Latest: the tender has been published, with bid submission, closing and technical opening still ahead.

 

89) NHPC's Sawalkot dam package jumps 5.6% in value after a capacity correction and 123 days of deadline extensions The estimate rose from Rs 5,129.03 crore to Rs 5,416.94 crore after fixing capacity from 1,856 MW to 1,800 MW. Turnover and working-capital thresholds rose in step. Latest: Corrigendum 10 has fixed the online submission date, with hard-copy submission and techno-commercial opening following shortly after.

 

810) NTPC's Pudimadaka green-urea plant links a Simhadri CO2 unit to five process blocks across two sites under one lump-sum price Carbon capture at Simhadri feeds hydrogen, ammonia and urea production 25 km away at Pudimadaka, all under one lump-sum contract. Bid security is Rs 20 crore, shareable among consortium partners. Latest: Date Corrigendum 02 has moved the submission/opening deadline forward again, following Commercial and Technical Amendments.

 

811) NHPC's Rs 5,541 crore Kamala Lot-1 bundles dam, diversion tunnels and hydro-mechanical works into one civil package The 1,720 MW project in Kamla district combines diversion tunnels, cofferdams, the dam and access roads/bridges. EMD is Rs 10 crore against a 2,372-day execution period. Latest: document download and bid submission remain open, with bid opening scheduled shortly after.

 

812) NTPC's 200,000-unit limestone GeM tender splits award among four suppliers with freight dwarfing the material cost Balajee Steel Udyog took 75,000 tonnes; three others split the remaining 25,000 tonnes. All contracts land at Rs 3,960/tonne, Rs 740 material plus Rs 3,220 freight. Latest: award has been finalised, with contracts running over a one-year supply period.

 

813) GUVNL's short-term power RFP shifts nearly all transmission and sourcing risk onto generators and traders The tender seeks 500–1,000 MW across monthly windows through the procurement period. Interstate bidders absorb a fixed 3.50% regional loss adjustment intrastate suppliers avoid. Latest: the RFP has been published, with bids due shortly before the IPO opening and e-reverse auction on DEEP.

Details

Download tenders and news clips

Jul 21:  For reference purposes the website carries here the following tenders:
 
8Tender for establishment of 765/ 400 kV transmission scheme Details
 
8Tender for supply of 245 kV RIP/RIS bushing for various substations Details
 
8Tender for supply of 420 kV draw rod/lead RIP/RIS bushing for various substation Details
 
8Tender for packing forwarding insurance, transportation supply delivery unloading on for destination of 400 kV bushings Details
 
8Tender for packing forwarding insurance, transportation supply delivery unloading on for destination of 245 kV and below bushings Details
 
8Tender for supply of ferric alum Details
 
8Tender for supply of 360kW HT motor Details
 
8Tender for work of complete overhauling of carious pumps installed for T-G set & BOP auxiliaries Details
 
8Tender for strengthening of exit lane of the existing bituminous coal Details
 
8Tender for construction of 33 kV bay Details
 
8Tender for work of transportation of erection and commissioning of emergency restoration system on 132 kV line Details
 
8Tender for incrasing capacity of (2X63 MVA to 3X63 MVA) T/F and related civil work Details
 
8Tender for supply and repairing of various duct of Ventilation system and overhauling of various air centrifugal fan Details
 
8Tender for work of removal & laying of 6.6/11kV (E), 1C X 1000Sq.mm, aluminum cables along Details
 
8Tender for supply, installation, commissioning and testing of vibration monitoring system for continuous vibration measurement Details
 
8Tender for supply of heating element baskets for air pre-heater of PH IV Details
 
8Tender for supply of heating element baskets for air pre-heater of PH III Details
 
8Tender for supply of seals fo rotary air pre heater Details
 
8Tender for supply of single pole str materials spare Details
 
8Tender for supply of 110KW 10 pole condenser vacuum pump motor Details
 
8Tender for ancillary work required for smooth operation of belt conveyors Details
 
8Tender for construction of foundations for various electrical equipments VCB, CTPT, cable trenches Details
 
8Tender for supply of equipment / material , design, erection, testing , commissioning for system improvement scheme for replacement of old/obsolete switchgear equipment at 33/11 kV sub-stations Details
 
8Tender for construction of 33/11 kV, 2x10MVA GIS sub-station Details
 
8Tender for turnkey construction of 220 kV double circuit transmission line Details
 
8Tender for in-house outsourcing of fabrication of sub-assemblies of HP heaters, LP heaters, condensers, lube oil piping works Details
 
8Tender for supply of BWSR spares Details
 
8Tender for annual maintenance contract for work of on-site N2 drying out for power transformers & ICT’s for various Details
 
8Tender for supply of assorted size of MS grill for repairing of platform of ash slurry line Details
 
8Tender for supply of liquor ammonia 25 % (AR grade) for boiler water treatment Details
 
8Tender for supply of capacitance type level switches for seal oil Details
 
8Tender for supply of IE4 class LT motors Details
 
8Tender for supply of canopies for DCS panels Details
 
8Tender for supply of C&S electric make ACB & panel spares Details
 
8Tender for supply of castable refractory for ash handling plant Details
 
8Tender for supply of battery water for 220V DC & 48V DC battery banks Details
 
8Tender for supply of PLC, VFD (variable frequency drive), HMI and installation Details
 
8Tender for supply of SMF batteries Details
 
8Tender for annual maintenance contract to carry out the routine repair & maintenance of power house equipments Details
 
8Tender for procurement of EPR grade cable 1.1 kV Details
 
8Tender for protection of power house Details
 
8Tender for supply of grinding rolls (roller liners) and bull ring segments Details
 
8Tender for annual maintenance contract for carrying out works in regular outage, emergency and attending breakdown of various 400kV, 220kV, 132kV & 66kV EHV lines Details
 
8Tender for construction of transformer fencing for various Details
 
8Tender for supply of coal nozzles for burner panel of boiler 250 MW Details
 
8Tender for supply of gland packing rings, gland rope and SS 304 spiral wound gaskets etc Details
 
8Tender for supply of spares for HP bypass valves and boiler safety valves for boiler Details
 
8Tender for requirement of spares of zirconia oxygen analysers installed Details
 
8Tender for purchase of spares for 3X1750 KVA DG sets Details
 
8Tender for supply of seals and spares for air pre heater Details
 
8Tender for supply of spares for LPBP stop And control valves Details
 
8Tender for procurement of 06 numbers of grinding ring and 216 number of balls of EL 76 pulveriser Details
 
8Tender for miscellaneous structural works Details
 
8Tender for procurement of different types of steel materials Details
 
8Tender for service contract for power extension and new point wiring Details
 
8Tender for execution of unit 3 COH during overhauling Details
 
8Tender for service contract for de-insulation and re-insulation job during overhauling and various maintenance work Details
 
8Tender for annual maintenance contract of telephone exchange, telephone set and line up Details
 
8Tender for supply of miscellaneous consumables items for electrical and generator maintenance Details
 
8Tender for supply of 11kV moving contact for 200Amps 11kV AB switch (double pole) Details
 
8Tender for work of annual maintenance contract for servicing/ maintenance of battery sets and chargers, taking capacity tests of battery sets and reconditioning of 220V/110V/48V,100/200/300/500/1000 A Details
 
8Tender for AMC for work of arresting oil leakages from the various joints of power transformers Details
 
8Tender for supply of 420kV, 3150A Male Female assembly of centre break isolator Details
 
8Tender for work of replacement of insulator or SRI work of attending the fault or broken conductor Details
 
8Tender for mechanical strengthening work of S/C 66kV line Details
 
8Tender for purchase of 400Amp SMC LTDB Details
 
8Tender for work of Re-tubing of tube nests of LP heater Details
 
8Tender for dismantling of conventional lighting system at boiler, ESP, ash plant Details
 
8Tender for biennial rate contract for works of online, preventive and breakdown maintenance of coal mills XRP-1003 and its associated auxiliaries Details
 
8Tender for work of removal of existing super heater header 5 (SHH5) and erection & commissioning of new SHH 5 along with its associated field joints for boiler Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8
India's Rs 37,500 Crore Coal Gasification Scheme Sees Strong Interest Details
 
8Coal gasification projects of over 22 MT capacity under implementation Details
 
8Solar Startups Attract Over $1 Bn As Clean Energy Investments Accelerate Details
 
8The Ultimate Guide to Solar Energy: Everything You Need to Know in 2026 and Beyond Details
 
8BHEL Invites Bids For Supply Monocrystalline 625 Wp Solar PV Modules For Hyderabad R&D Division Details
 
8Growth and Future of Solar Stocks in India Details
 
8RITES and MECON sign MoU to explore business avenues Details
 
8India has adequate coal stocks, thermal power plants equipped to meet daily demand: Govt Details
 
8AI, Data Centres To Accelerate India’s Power Cycle; Transmission Remains Top Bet: Vakil Of HDFC Securities Details
 
8India has adequate coal stocks to meet power demand, says government Details
 
8Adani Power Share Price Rises Nearly 2% Ahead of Q1 FY27 Results Details
 
8THDC India Commissions 11 MW Floating Solar Plant At Khurja STPP, Boosting NTPC’s Green Capacity Details
 
8India has sufficient coal stocks to meet thermal power demand, says power ministry Details
 
8How Wind Energy in India Is Powering Rural Electrification and Grid Stability Details
 
8Karnataka govt firm on implementing Sharavathi Pumped Storage Project: CM D K Shivakumar Details
 
8Bondada Engineering Secures NTPC REL Deal For 100 MWh Battery Storage Project Details
 
8Why Jaiprakash Power Ventures Shares Surged 8% Today — Here's What Drove The Rally Details
 
8From Standard Pipes to Project-Specific Solutions, Techno India Adapting to Forward Integration Details
 
8Punjab: Power Minister Tarunpreet Singh Sondh launches distribution of 10,500 safety tool kits to PSPCL employees Details
 
8Naveen Jindal Group in talks for proposed nuclear projects, in discussion with US, French companies Details
 
8Coal Stock at Thermal Power Plants Sufficient for 14 Days, Government Assures Uninterrupted Power Supply Details
 
8Thermal Power Plants hold 42.8 MT coal stock, enough for 14 days": MoS Power Shripad Naik Details
 
8India Holds 42.8 Million Tonnes of Coal for Power Stability Details
 
8Tata Power Bags 40-Year SECI Deal Worth Rs 351 Crore Annually for Pumped Hydro Details
 
8NTPC renewable Energy awards contract for 100MWh Details
 
8NPCIL and ECIL Enter MoU to Boost Indigenous Control Systems and Nuclear Technology Solutions Details
 
8India's core sector output rises to five-month high of 5 per cent in June Details
 
You can also click on Newsclips for more Details

The West runs a surplus while the North and South ration - July's squeeze is a delivery problem, not a generation shortfall

Jul 20: 8On 18–19 July the Northern Region shed load in Punjab and Haryana even as the Western Region exported close to 300 million units a day with no shortage and no renewable curtailment. The gap is not missing megawatts - it is congested corridors and benched gas standing between surplus in one region and unmet demand in another. Details

POWER MARKETS DAILY

Jul 20: 8IEX day-ahead cleared 1.30 million MWh in the week to 20 July at a Rs 6,666/MWh average
8Term-ahead buyers locked the Rs 10,000/MWh ceiling for forward daily blocks on 17 July
8APCPDCL and RUVITL float ~1,100 MW and ~1,000 MW thermal reverse auctions on all three exchanges
8IGSTPS-Jhajjar's Rs 45.69 crore tops NRPC's ~Rs 193-crore part-load bill for April–June
8NLDC benched the entire gas fleet at Rs 14–22/kWh while coal cleared at Rs 1.2–5.7/kWh
8Grid-India backed thermal down by up to 46,660 MWh a day to absorb midday solar
8ERPC's weekly deviation pool ran a Rs 60.37-crore balance
8All-India ISTS transmission loss set at 3.95% for the week to 26 July Details

GRID OPERATIONS DAILY

Jul 20: 8All-India frequency fell to 49.596 Hz on 19 July in a synchronous evening dip
8NR import corridor was in ATC violation 11.46% of 19 July as Rajasthan sat 19.1% congested
8NER–Tripura import corridor held in transfer-capacity violation ~three-quarters of the day
8Ancillary despatch ran heavily to down-regulation - up to 46,660 MWh backed down on 19 July
8Western Region exported ~282 MU north on 19 July as the grid's balancing sink and source
8High-voltage light-load regime held Amreli above 420 kV ~90% of 18 July
8NR and WR registers carried high-fault-current trips plus a decade-long tail of dead assets
8One relay-and-reclose event cascaded through five 400 kV bays at Fatehgarh-III / Serentica on 19 July
8Two Karnataka 400 kV corridors stay un-restored since May tower collapses
8Grid-India set the all-India ISTS transmission loss at 3.95% for 20–26 July
8NRPC rates Northern hydro the worst primary-frequency responders - Parbati-III scored 0.00
8ERPC re-cut a week's reactive-energy account off one meter swap - DARLIPALI draws Rs 3,37,902
8WRLDC swapped ~a dozen interface meters to check/standby readings in DSM week-14
8Karnataka's ageing thermal posted soft June returns - RTPS ran 58.2% PLF
8Thermal availability held 85.5% on 16 July as hydro ran 11% under its YTD programme
8Bihar alone curtailed load across 17–19 July despite zero ER-wide shortage Details

OUTAGE & MAINTENANCE REGISTER

Jul 20: 8India carried 53,415 MW under maintenance on 16 July - 22,936 MW of it forced thermal trips
8Western Region ran up to 18,336.5 MW out on 18 July, led by VSTPS-V and Adani Raipur trips
8Southern Region outage climbed 1,906 MW in two days to 11,820.88 MW on 19 July
8Northern Region carried 9,138 MW out on 19 July, 4,900 MW of it forced coal
8Eastern Region held ~5.1–5.9 GW out; Teesta-III's 1,200 MW forced into a 21st month
89,230.47 MW of thermal/nuclear went off-grid on 16 July on boiler and air-preheater faults
8NTPC water-wall tube leaks hit Gadarwara U1 (800 MW) and Barh U3 (660 MW)
8Long-parked units anchor the ~29,961 MW out beyond 15 days
8Telangana's Yadadri loses both first-stage 800 MW units, U1 and U2
8Jindal Simhapuri logged four trips of two 150 MW units in a single day - a repeat-tripping signal
8NPCIL's RAPS-A Unit-1 (100 MW) is formally set for decommissioning, out since 2004
8PVVNL runs a 100-plus feeder shutdown wave across Meerut–Muzaffarnagar ahead of the Kanwar Yatra
8Chronic multi-year transmission forced outages stay open - Raigarh–Raipur FSC since 2016
8Himachal hydro units force-out on high silt as monsoon flows spike
8KPCL's newest Raichur unit (250 MW Unit-8) sat out all June on planned outage
8OHPC carries multiple hydro units out - Burla and Chipilma forced
8KSEBL replaces Idukki Unit-6 upper guide bearing in-house in nine days, saving about Rs 35 lakh Details

FUEL & COAL LEDGER

Jul 20: 8Twenty-seven thermal plants sit at critical coal stock on 18 July
8WBPDCL bills a June fuel surcharge up to 60 paise/kWh, with Kolaghat the steepest pass-through
8NRPC bills IGSTPS-Jhajjar Rs 4,569.48 lakh of part-load compensation for Apr–Jun 2026
8Coal Ministry's Rs 37,500 crore surface coal-gasification scheme moves to procurement
8Every RLNG and liquid-fuel gas station stays out of merit order at 1,395–2,223 paise/kWh
8All-India coal stock at CIL/SCCL plants holds ~16 days, nine at five days or fewer
8Yadadri U4 (800 MW) stays shut on coal shortage - the South's sole such outage
8Imported-coal dependence concentrates at Adani Kawai, Nasik, Chandrapur and North Chennai-III
8Coal-supply failures force units down at ACBIL, Kasaipalli, Ghatampur, Raichur and Tanda
8A large gas-CCPP block backs down on costly or conserved fuel; Uran and Agartala run short Details

HYDRO & RESERVOIR LEDGER

Jul 20: 8Telangana reservoir live storage collapses from 300.7 to 43.8 TMC year-on-year
8National hydro generation runs ~11% below programme YTD, Eastern and Northern fleets worst
8Odisha's OHPC fleet generates just 590.44 MW / 14.17 MU, reservoirs below year-ago
8CERC re-rates NEEPCO's Kopili Stage-II from 25 to 23 MW, rules 2022 flood force majeure
8Northern Region reservoir energy falls to 1,116 MU from 1,361 MU year-on-year
8Western Region reservoirs run mixed - Koyna and Indira Sagar down, Sardar Sarovar up
8Southern Region reservoirs sit below last year across the board; Kerala at 28%
8Idukki Unit-6 fixed in-house in nine days, saving KSEBL about Rs 35 lakh Details

CERC DOCKET

Jul 20: 8NTPC claims Rs 3,063.91/tonne Talaipalli coal for Lara STPS, 27% above its own projection
8CERC trues up NEEPCO's Kopili-II tariff, sets 2024-29 AFC rising to Rs 2,527.01 lakh
8CERC opens objections on POWERGRID Vataman's bay for 250 MW Rajasthan BESS at Bhadla-III
8PGCIL withdraws its Rs 233.96 crore OT security-operations-centre O&M claim Details

STATE REGULATORY ROUNDUP

Jul 20: 8KSERC clears KSEBL's 300 MW peak-power bid method but forces a 12-month CTUIL average
8MERC freezes MSEDCL's 12 June supplementary bills to 15 open-access consumers pending APTEL
8MERC reserves orders in 11 matters - five Pune-corridor transmission licensees plus Carbonminus
8MERC adjourns Avaada's plea to extend supply-start dates on 2,300 MW of Maharashtra solar
8PSPCL reclassifies lawyers'-chamber connections from commercial to Domestic tariff
8PSPCL sanctions a new 66 kV Bathinda substation under RDSS at Rs 641.19 lakh
8MPERC opens consultation on the Sixth Amendment to the MP Electricity Supply Code
8GERC reserves maintainability on Trambovad farmers' SKY solar complaint against MGVCL
8TN Ombudsman orders TNPDCL to implement a Coimbatore hotel's 61 kW load within 30 days Details

GREEN MARKETS & RE PROGRAMME WATCH

Jul 20: 8Avaada's 2,300 MW of Maharashtra solar risks stranding as MSETCL evacuation slips to FY2027-28
8CERC moves to add a bay for Rajasthan BESS's 250 MW at saturated Bhadla-III
8All-India renewable penetration hit 38.05% on 17 July with zero curtailment
8Kerala lines up 250 MW / 1,000 MWh of BESS and 500 MW of solar before winter
8Green day-ahead cleared near-parity to grey as wind barely traded
8Gujarat's SKY farm-solar runs a third below promise, burdening farmers with loan recovery
8Southern renewables cleared without curtailment as pumped storage and BESS cycled against the peak
8Domestic solar-glass capacity is still a fraction of demand as the anti-dumping wall thickens
8ISA has collected no interest and given no award on Haryana's Kalpana Chawla Solar prize since 2022 Details

CORPORATE WIRE

Jul 20: 8Tata Power's 40-year SECI pumped-storage tolling award
8CBI searches Reliance Infrastructure's registered office; company reports no financial impact
8NTPC board to weigh Q1FY27 results and a Rs 12,000 crore NCD/bond programme on 24 July
8POWERGRID to raise its FY27 borrowing limit from Rs 30,000 crore to Rs 35,000 crore
8Adani Power tables a fundraise alongside Q1FY27 results on 22 July; quantum undisclosed
8Three large issuers cluster Q1FY27 results on 22 July - Adani Power, Adani Energy Solutions, JSW Energy
8PFC to seek enhanced domestic and international borrowing limit on 23 July
8TD Power Systems' FY26 income rises 44% to Rs 1,878 crore on record order inflow
8Bajel Projects' FY26 PAT jumps 74% to Rs 26.95 crore even as its order book slips
8Borosil Renewables swings to Rs 86.64 crore Q1FY27 profit on pricing, not volume
8POWERGRID wins TBCB mandate for two synchronous condensers at Fatehgarh-II
8REC floats two shell SPVs for Maharashtra intra-state TBCB transmission
8Coal India advances a 187.5 MW / 750 MWh BESS at Choutuppal; AHASOLAR wins the owner's-engineer role
8VA Tech WABAG secures a "Large" BWSSB wastewater DBO order with biogas captive power
8ACME Solar rebuts "13 containers" claim over Pokhran BESS fire; four PCS units hit
8Inox Green Energy Services to consider a fundraise on 22 July; quantum undisclosed
8BF Utilities fined by NSE and BSE for delayed consolidated FY26 results after subsidiaries missed filing
8International Solar Alliance swings to a USD 3.08 million surplus for FY2025 on trebled revenue (colour)

Ratings Watch

8Orient Electric's ESG rating improves to 74 on steady year-on-year gains Details

COMMITTEES, PEOPLE & SYSTEM ADMINISTRATION

Jul 20: 8NTPC and Coal India each gain a government-nominated independent director
8Alfa Transformers adds a discom veteran as Non-Executive Non-Independent Director
8Ministry of Coal builds the governance layer for its Rs 37,500 crore surface-gasification scheme
8ISA discloses a 2024 cyber-fraud that diverted USD 357.86 thousand; recovery partial
8SRPC 67th CCM minutes flagged unreadable - retrieval flag
8Rolled-over committee action items
8PSPCL reshuffles its cadres across Punjab - ministerial and 18 technical transfers, 29 clerks relieved
8PSPCL lists ~5 electrical officers born Aug-1968 for superannuation
8PSPCL deputes 6 officers to DoPT-sponsored MGSIPA training programmes
8PSPCL publishes provisional JE/Electrical recruitment merit list - ~5,700 candidates ranked
8PSPCL creates ~8 permanent posts for the new 66 kV Focal Point Mubarakpur substation
8NBPDCL constitutes a 5-member Energy Accounting Cell for DT metering under AMISP
8Ministry of Coal to engage 18 Young Professionals and 2 Legal Consultants on contract
8KSEBL awards a Good Service Entry to 20 staff for the in-house Idukki UGB repair Details

Nearly 30,000 MW has sat out of the grid for over a fortnight - flood, fire, tower collapse, GLOF and bankruptcy, some of it dead for years

Jul 20: 8CEA's registers show almost 30 GW out of service for more than fifteen days in mid-July, much of it stranded gas but a hard core of it long-dead thermal and hydro. Sikkim's Teesta-III has been out about 21 months since a glacial flood, two Karnataka 400 kV corridors since May tower collapses, and Tamil Nadu's Tuticorin units since a March-2025 control-room fire. Details

The West ran as a deviation conduit between East and South last week - settling a net Rs 51 crore, with Khavda solar the single biggest mover

Jul 20: 8The Western committee's deviation account for the week to 5 July shows the region paying the East a net Rs 263 crore and receiving a net Rs 267 crore from the South - passing imbalance through itself rather than causing it. The largest single line in the pool is no thermal station but a Khavda solar aggregator, whose forecast error now moves more money than any coal plant. Details

MNRE grants its sixth solar-cell reprieve in eight weeks and Delhi rewrites net-metering - a quiet admission that domestic cell supply still cannot carry distributed solar

Jul 20: 8A new MNRE order lets net-metering and open-access renewable projects commission without the domestic solar-cell (ALMM List-II) requirement until 31 December 2026, superseding a stack of earlier extensions. On the same days, Delhi's regulator collapsed net-metering into a two-stage online process with hard 25- and 10-day connection deadlines. Details

Tata Power lands a 40-year storage tolling contract from SECI - Rs 351 crore a year for a 324 MW pumped-storage plant, about Rs 14,000 crore over its life

Jul 20: 8SECI has issued Tata Power a Letter of Award for pumped-storage service from a 324 MW / 2,592 MWh plant on a 40-year annuity, at an annual fixed charge of Rs 351.3 crore. It is a long-dated, availability-based storage contract rather than a merchant arbitrage bet - and the payment only starts once SECI ties up its own downstream buyers. Details

CERC forgives NTPC a 22.5-month captive-mine delay as force majeure, then fences the money - Rs 4,340 crore recast, Rs 136 crore stripped, Rs 59 crore clawed from the mining contractor

Jul 20: 8The Commission held NTPC's 22.5-month slip in commissioning its Talaipalli captive coal mine to be beyond the company's control, fixing commercial operation at 1 October 2023 over discom objections. In the same order it capped the revised cost at Rs 4,340.50 crore, disallowed Rs 136.55 crore of claimed capital cost, and recorded that terminated contractor Thriveni had paid NTPC Rs 58.83 crore. Details

A monsoon flood knocks out the 765/400 kV Champa hub in Chhattisgarh - all three transformers trip and the operator logs the situation "out of control"

Jul 20: 8On 17 July heavy flooding tripped all three inter-connecting transformers at the Champa pooling station on Buchholz protection, taking down a top-tier 765 kV evacuation hub for Chhattisgarh's coal belt. The WRLDC outage log records an operator writing that the situation was "out of control now due to continuously raining." Details

The grid's designated shock-absorbers are its worst responders: NR's big hydro fleet scores near zero on governor response while NTPC thermal scores perfect

Jul 20: 8The Northern committee's June frequency-response league table puts Parbati-III at 0.00 and a row of NHPC and SJVN hydro stations just above it, while NTPC's coal units sit at a perfect 1.00. Because the score feeds tariff, the hydro fleet that is supposed to stabilise frequency is being penalised for failing to. Details

Southern coal stocks fall to single digits - Damodaram Sanjeevaiah at 2%, and Telangana's Yadadri backs an 800 MW unit off the grid for want of coal

Jul 20: 8Twenty-seven thermal plants sat on critical coal stock in mid-July, the tightest cluster in Andhra Pradesh, Telangana and Tamil Nadu, with APPDCL's 2,400 MW Damodaram Sanjeevaiah station down to 2% of its normative stock. The squeeze stopped being a warning and became lost megawatts when TGGENCO's Yadadri Unit 4 was shut for coal shortage. Details

Kerala's regulator adopts Rs 5.96/unit round-the-clock power and openly rebukes its own utility, ordering fixed day-ahead load-shedding as reservoirs fall to 28%

Jul 20: 8KSERC cleared KSEBL to buy 200 MW of round-the-clock power for a year at Rs 5.96 a unit, but recorded that the utility's Core Committee never costed the tariff impact and took two weeks to file after bidding closed. With reservoirs at 28% against a normal 60% and a peak deficit put at 500–1,000 MW, the Commission ordered load-shedding to be fixed a day ahead and held for a week. Details

Day-ahead and real-time power pinned the Rs 10,000/MWh ceiling through every peak block, 17–19 July

Jul 20: 8IEX's day-ahead and real-time markets cleared at the Rs 10,000 per MWh price cap in the morning and evening peaks on all three days, then crashed to Rs 1,300–1,900 in the solar midday. The Rs 20,000 high-price segment woke for a single night - a market pressed hard against its ceiling but rarely through it. Details

Contracting news for the day: Part-1

Jul 20: 81) Power Grid floats 1 GWh battery framework demanding firm prices without guaranteeing a single order Power Grid has invited first-stage bids for a 250 MW/1,000 MWh four-hour BESS long-term agreement. Capacity converts into work only when it wins external tariff tenders from SECI, states or DISCOMs. The partner must hold firm prices, sustain 95% availability and 87% round-trip efficiency at its own cost. Clause 9(e) guarantees no minimum quantity despite full readiness obligations.

82) POWERGRID picks its Sunni Dam–Luhri transmission contractor before knowing whether it will win the project The TL01 pre-bid tie-up covers the Nange–Koldam 400 kV double-circuit line. Award is conditional on POWERGRID winning RECPDCL's TBCB competition. The contractor must sign an exclusivity MoU and stay out of all rival bids. A mountain-specific 50 km qualification filter and 33-month completion clock frame the package.

83) UPRVUNL's pumped hydro tender absorbs six extensions without returning any developer risk The Rs 3,953 crore, minimum 640 MW project sits between the Rihand and Obra reservoirs. The developer must identify the layout itself, arrange land and clearances, and post a Rs 79.06 crore EMD. Commissioning must fit 54 months — 18 for the DPR and only 36 for construction. Every major execution and clearance risk stays with the developer.

84) Eleven corrigenda turn BHEL's Koradi lime-and-gypsum EPC into a different tender from the one first issued Six extensions have added 45 days to the original bidding window. Capacities are now fixed at 150/165 TPH for lime and 50/55 TPH for gypsum. Weighbridges, MCC buildings and pay loaders were pushed firmly into contractor scope. Escalation relief is capped at plus or minus 20% while intermediate LD stays.

85) WAPCOS caps its Atal Park consultancy at Rs 3.31 lakh while stretching the obligation across four-plus years The Cuttack assignment runs from concept and DPR through supervision and as-built documentation. The fee stays frozen through extensions of up to three additional years. Payment is back-to-back, released only after WAPCOS receives funds from Cuttack Development Authority. A 5% guarantee, 5% retention and exclusion of arbitration complete the burden.

86) BHEL's Koradi bottom-ash package extends contractor liability past commissioning and into plant operations The 970-day, no-deviation EPC withholds equipment payments where civil pricing falls below 50% of contract value. Latent-defect liability runs 24 months beyond the defect period. Conveyor belts damaged during operation must be replaced at contractor cost. Milestone slippage triggers 10% withholding from running-account bills.

87) WBSETCL's 55 km cable tender grants technical flexibility while refusing every commercial concession on copper risk The 33 kV XLPE procurement pairs a 120-day delivery clock with firm prices and a reverse auction. Order splitting can leave L1 with only 60% of the quantity. In-house NABL test reports and steel drums were accepted at pre-bid stage. The steel-drum reply collides with the wooden-drum specification without a formal amendment.

88) GPPC rewrites its Pipavav clarifier health study but parks half the fee behind a tender it does not control Amendment No. 1 opens eligibility from Gujarat to all of India and mandates NDT at 12 locations minimum. An impossible 50%-per-week penalty has been corrected to 5%, capped at 10%. Payment splits into four 25% tranches tied partly to a separate implementation tender. The amendment arrived months after the original submission schedule, making the chronology itself a live issue.

89) SECI pairs open-global access with a Rs 8.44 crore entry ticket for its 45.6 MW Ramagiri wind EPC The single package bundles design, supply, construction, commissioning and maintenance for an ISTS-connected project. A two-envelope evaluation will be followed by an e-reverse auction. The query window closes hours before the pre-bid meeting even begins. Maintenance period, turbine configuration and performance guarantees remain undisclosed.

810) MPPMCL's four-hour battery tender slips 57 days through three corrigenda and three addenda The 282.50 MW/1,130 MWh procurement follows a build-own-operate model with viability gap funding. EMD of Rs 4.80 lakh per MW means Rs 13.56 crore for the full capacity. A Rs 15 lakh processing fee raises entry costs before evaluation begins. Projects may sit anywhere in India, importing connectivity risk into every bid.

811) NTPC REL gives Nokhra battery bidders eleven more days and not one gram less risk Corrigendum No. 01 extends bid submission while the query deadline stays shut. Bidders must deliver 1,320 MWh of nameplate for 1,200 MWh of dispatch at the point of injection. Capacity must hold at 98% across 15 years with contractor-funded augmentation. A Rs 20 crore bid security guards the reverse-auction gateway.

812) NVVN puts Varanasi's green charcoal through 65 tests, one trip and one payment before it reaches the market The GeM tender covers charcoal, ash and emission testing down to dioxins, furans and mercury. All sampling must fit a single site visit at one consolidated charge. Full payment waits for report acceptance, with competition limited to 22 approved vendors. Bids sharing an IP address face summary rejection at either stage.

813) NHPC widens entry to its Rs 379.25 crore Jalaun solar evacuation package while keeping project-wide LD intact Corrigendum-1 broadens general experience to any large electrical infrastructure work, opening the gate beyond substation-and-line contractors. Three 33/400 kV pooling substations at Orai, Madhogarh and Pathrahi must be delivered within 24 months. Delay preventing beneficial use attracts LD on the total contract price, capped at 10% plus GST. Escrow payments, an interest-bearing advance against a 110% guarantee and 5% bill retention keep cashflow risk with the contractor.

Details

Contracting news for the day: Part-2

Jul 20: 81) Power Grid floats 1 GWh battery framework demanding firm prices without guaranteeing a single order Power Grid has invited first-stage bids for a 250 MW/1,000 MWh four-hour BESS long-term agreement. Capacity converts into work only when it wins external tariff tenders from SECI, states or DISCOMs. The partner must hold firm prices, sustain 95% availability and 87% round-trip efficiency at its own cost. Clause 9(e) guarantees no minimum quantity despite full readiness obligations.

82) POWERGRID picks its Sunni Dam–Luhri transmission contractor before knowing whether it will win the project The TL01 pre-bid tie-up covers the Nange–Koldam 400 kV double-circuit line. Award is conditional on POWERGRID winning RECPDCL's TBCB competition. The contractor must sign an exclusivity MoU and stay out of all rival bids. A mountain-specific 50 km qualification filter and 33-month clock frame the package.

83) UPRVUNL's pumped hydro tender absorbs six extensions without returning any developer risk The Rs 3,953 crore, minimum 640 MW project sits between the Rihand and Obra reservoirs. The developer must identify the layout itself, arrange land and clearances, and post a Rs 79.06 crore EMD. Commissioning must fit 54 months — 18 for the DPR and only 36 for construction. Every major execution and clearance risk stays with the developer.

84) Eleven corrigenda turn BHEL's Koradi lime-and-gypsum EPC into a different tender from the one first issued Six extensions have added 45 days to the original bidding window. Capacities are now fixed at 150/165 TPH for lime and 50/55 TPH for gypsum. Weighbridges, MCC buildings and pay loaders were pushed firmly into contractor scope. Escalation relief is capped at plus or minus 20% while intermediate LD stays.

85) WAPCOS caps its Atal Park consultancy at Rs 3.31 lakh while stretching the obligation across four-plus years The Cuttack assignment runs from concept and DPR through supervision and as-built documentation. The fee stays frozen through extensions of up to three additional years. Payment is back-to-back, released only after WAPCOS receives funds from Cuttack Development Authority. A 5% guarantee, 5% retention and exclusion of arbitration complete the burden.

86) BHEL's Koradi bottom-ash package extends contractor liability past commissioning and into plant operations The 970-day, no-deviation EPC withholds equipment payments where civil pricing falls below 50% of contract value. Latent-defect liability runs 24 months beyond the defect period. Conveyor belts damaged during operation must be replaced at contractor cost. Milestone slippage triggers 10% withholding from running-account bills.

87) WBSETCL's 55 km cable tender grants technical flexibility while refusing every commercial concession on copper risk The 33 kV XLPE procurement pairs a 120-day delivery clock with firm prices and a reverse auction. Order splitting can leave L1 with only 60% of the quantity. In-house NABL test reports and steel drums were accepted at pre-bid stage. The steel-drum reply collides with the wooden-drum specification without a formal amendment.

88) GPPC rewrites its Pipavav clarifier health study but parks half the fee behind a tender it does not control Amendment No. 1 opens eligibility from Gujarat to all of India and mandates NDT at 12 locations minimum. An impossible 50%-per-week penalty has been corrected to 5%, capped at 10%. Payment splits into four 25% tranches tied partly to a separate implementation tender. The amendment arrived months after the original bid schedule, making the chronology itself a live issue.

89) SECI pairs open-global access with a Rs 8.44 crore entry ticket for its 45.6 MW Ramagiri wind EPC The single package bundles design, supply, construction, commissioning and maintenance for an ISTS-connected project. A two-envelope evaluation will be followed by an e-reverse auction. The query window closes hours before the pre-bid meeting even begins. Maintenance period, turbine configuration and performance guarantees remain undisclosed.

810) MPPMCL's four-hour battery tender slips 57 days through three corrigenda and three addenda The 282.50 MW/1,130 MWh procurement follows a build-own-operate model with viability gap funding. EMD of Rs 4.80 lakh per MW means Rs 13.56 crore for the full capacity. A Rs 15 lakh processing fee raises entry costs before evaluation begins. Projects may sit anywhere in India, importing connectivity risk into every bid.

811) NTPC REL gives Nokhra battery bidders eleven more days and not one gram less risk Corrigendum No. 01 extends bid submission while the query deadline stays shut. Bidders must deliver 1,320 MWh of nameplate for 1,200 MWh of dispatch at the point of injection. Capacity must hold at 98% across 15 years with contractor-funded augmentation. A Rs 20 crore bid security guards the reverse-auction gateway.

812) NVVN puts Varanasi's green charcoal through 65 tests, one trip and one payment before it reaches the market The GeM tender covers charcoal, ash and emission testing down to dioxins, furans and mercury. All sampling must fit a single site visit at one consolidated charge. Full payment waits for report acceptance, with competition limited to 22 approved vendors. Bids sharing an IP address face summary rejection at either stage.

Details

Download tenders and news clips

Jul 20:  For reference purposes the website carries here the following tenders:
 8Tender for architectural, structural & MEP consultancy services Details
 8Tender for supply, installation, testing and commissioning with 5 year CMC of grid connected solar photovoltaic systems of various capacity Details
 8Tender for supply of equipments/ material, erection, testing and commissioning for the work augmentation by providing additional 1 x 25 MVA, 132- 110/33 kV T/F Details
 8Tender for remodeling and restructuring of existing 09 Nos. 400kV bays Details
 8Tender for civil works for construction of 132 kV bay at 220 kV S/s Details
 8Tender for civil works for construction of 132 kV bay Details
 8Tender for supply, installation, testing and commissioning of smoke an heat extraction system Details
 8Tender for supply, installation, testing and commissioning of complete set up of emergency alternate water drain arrangement from dewatering pit Details
 8Tender for supply of LT pilfer resistant metering cubicle Details
 8Tender for miscellaneous work regarding dismantling, fabrication and erection of hopper empty out /cleaning chutes Details
 8Tender for work of servicing of TG bearing/RTDs, seal liners TE/EE, servicing/overhauling of HP/IP CV, ESV, IV and misc. AOH related activities Details
 8Tender for erection of estimate for new 5 MVA substation Details
 8Tender for appointment of dealers for fly ash bricks Details
 8Tender for preventive and breakdown maintenance of exchangers, pressure filters, phosphate transferring system Details
 8Tender for ARC for HT/LT/TC erection and maintenance work Details
 8Tender for supply of various fasteners and consumables Details
 8Tender for work of collection of fly ash, bed ash Details
 8Tender for supply and retrofitment of 245kV circuit breakers Details
 8Tender for requirement of work order for transformer Details
 8Tender for provision of chain link fencing work inside the proposed 33/11kV P/S/S Details
 8Tender for construction of approach path at proposed 33/11kV P/S/S Details
 8Tender for construction of cable trench and drain at proposed Details
 8Tender for development of yard at proposed 33/11kV P/S/S Details
 8Tender for construction of proposed 33/11kV P/S/S Details
 8Tender for framework agreement for 1 year of silver plating of 5 micron on aluminium and copper conductor Details
 8Tender for epoxy mortar treatment for repair of chute spillway Details
 8Tender for erection laying of 11 kV HT cables on overhead line Details
 8Tender for release of new service connections of new HT line Details
 8Tender for replacement of existing 11 kV bare conductor by 11 kV AAAC AL-59, 70 Sq.mm Details
 8Tender for replacement of 11 kV ACSR conductor by AAAC feeder Details
 8Tender for construction of 33kV line and installation of 33/0.4kV, 1x1000KVA sub-station Details
 8Tender for supply of numerical transformer protection differential relays high end model Details
 8Tender for ARC for HT/LT/TC erection and maintenance work Details
 8Tender for ARC for HT/LT/TC erection and maintenance works Details
 8Tender for bulk procurement of MCBs Details
 8Tender for supply and commissioning of elect. eqpt for rain water harvesting system Details
 8Tender for supply, installation and commissioning of SCADA DASHBOARD for flow transmitters Details
 8Tender for procurement of transmission tower hardware fitting material for 400kV line Details
 8Tender for painting works of transformers, panels, bus ducts, motors, electrical structures, street light poles Details
 8Tender for ARC for HT/LT/TC erection and maintenance works Details
 8Tender for turnkey based contract for conversion of existing electrical line network in to underground cable Details
 8Tender for work of erection, commissioning of equipments, testing, control wiring etc. of 1 Nos. 66kV bus coupler bay Details
 8Tender for supply of 90/10 cupronickel condenser tubes Details
 8Tender for work for replacement of various pulleys and its bearing Details
 8Tender for supply and installation of energy saving BLDC ceiling fan Details
 8Tender for work of overhauling of ESP pass Details
 8Tender for supply of tarpaulin sheet for covering of coal Details
 8Tender for work of complete servicing/ overhauling/ defect attending of various hoists and cranes Details
 8Tender for supply of various consumable & routine maintenance items Details
 8Tender for supply, erection, testing, and commissioning of 220kV & 66kV equipment and materials Details
 8Tender for reconditioning of complete rotor assembly of ring granulators Details
 8Tender for procurement of sleeve type expansion joint (modified coupling device) for wet ash disposal pipe line Details
 8Tender for repair and maintenance of balance 56 Nos rollers of under sluice gate, spillway gate and HR gates Details
 8Tender for work of annual maintenance contract of 3MT capacity elevators of boiler Details
 8Tender for dismantling of 150 kWp rooftop solar plant Details
 8Tender for outsourcing of 2 no additional PTFs with 20 MVA PTF Details
 8Tender for outsourcing work of erection testing and commissioning of new 66 kV SS with 01 No 20 MVA power transformers along Details
 8Tender for installation of 11/0.4 kV 990 KVA compact sub station Details
 8Tender for installation of 11/0.4 kV 990 KVA compact sub station at 33/11 kV S/s Details
 8Tender for installation of 11/0.4 kV 990 KVA compact sub station Details
 8Tender for replacement of bare conductor by AB cable Details
 8Tender for replacement of bare conductor by AB cable in 11 kV feeder Details
 8Tender for procurement of grinding rolls and bull ring segment for XRP883 coal mill Details
 8Tender for procurement of 1200 MM conveyor belt Details
 8Tender for biennial maintenance contract for control and instrumentation system Details
 8Tender for procurement of spares for main turbine Details
 8Tender for service contract for insulation and sheet cladding work during overhauling Details
 8Tender for replacement of 210MW LMW turbo generator defective TG rotor Details
 8Tender for supply of equipments / material, erection, testing and commissioning for the work of augmentation by replacement of existing 1x25 MVA, 132/33kV, transformer Details
 8Tender for work of annual maintenance contract (AMC) for various 400kV lines Details
 8Tender for supply of spares for 400kV SF6 breaker Details
 8Tender for repair & complete overhauling work of 298.6 MVA converter transformer & 360 mH 500 kV smoothing reactor Details
 8Tender for work of repair & upgradation of crimping tool at various substation & line Details
 8Tender for work of supply, installation and commissioning of 100% hot redundancy based continuously available Details
 8Tender for providing and fixing of 400kV & 220kV isolators spare parts and servicing Details
 8Tender for work of cold line washing of disc insulator strings of various 132kV & 220 kV lines Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8Jindal Steel Deploys Indigenous Coal Gasification in Global First for Steelmaking Details
 
8As Solar and Wind Meet A Larger Share of India’s Grid Load , Incremental Additions Come At Ever Higher Cost To Grid Details
 
8Tata Power Gets SECI Approval For 324 MW Pumped Storage Plant Services Details
 
8APTEL Rules in Favour of Wind Developer in Dispute Over Unapproved PPA Details
 
8Battery PLI norms eased as India cuts subsidy rate Details
 
8Indian Government Extends ALMM 2 Deadline for Solar Projects Details
 
8GB Solar commissions 2 GW module plant in Gujarat Details
 
8Centre extends exemption for select RE projects from sourcing solar cells from ALMM-listed manufacturers Details
 
8India's solar push hits a manufacturing hurdle. Here's why the cell mandate was delayed Details
 
8Indian Railways Invites INR 4.02 Crore Tender For 1 MW Rooftop Solar PV Plant At BLW Workshop Details
 
8Power sector growth outlook remains strong on robust demand, thermal generation; higher costs, execution risks pose offsets: Report Details
 
8A problem of when, not how much Details
 
8SECI Invites EOI From Bulk Power Consumers For Long-Term Renewable Energy Procurement Across India Details
 
8India’s power discoms are healthier than before, but subsidy dependence remains a major challenge Details
 
8Hydel projects to add 14,000 Mw by 2032-33, CEA Chairman reckons Details
 
8Delhi launches ‘Smart Power Push’ with compact substation, 'Solarise East' campaign Details
 
8Prepare for surge in power demand: Dy CM Mallu Bhatti Details
 
8Weak monsoon halves TN hydel power output, forcing costly electricity purchases Details
 
8Laser Power & Infra wins Rs 4.15 crore HPSEBL order for HTLS conductors Details
 
8Gujarat’s Rs 6 trillion data centre bet may trigger 45 GW solar surge; Nuvama explains 22% cost cut Details
 
8Adani Enterprises and 7 Other Stocks in Which Mutual Funds Increased Their Stake in Q1 Details
 
8Erratic Monsoon Risks: Impact on Food Costs and Power Demand Details
 
8The power grid must get smarter before it gets bigger’: Vera Silva, Chief Strategy & Technology Officer, Electrification Systems, GE Vernova Details
 
8India Electricity Consumption Spikes 8% During April-June Quarter Details
 
8Stock with 111% Profit CAGR Is Now Betting Rs 1,000 Crore on India’s Defence Manufacturing Opportunity Details
 
8PTC India and Bandhan Bank See Technical Upside, Says Angel One Details
 
You can also click on Newsclips for more Details

Daily Power Sector Tenders Excel update

Jul 20: 8Daily Excel covering new tenders and all published updates including corrigendum, amendment, addendum, clarification and status revisions, along with technical and financial bid opening, evaluation completion and final award actions including AOC and LOA issuance.
Click on Reports for more Details

Contracting news for the day: Part-1

Jul 18: 8SECI floats 45.6 MW ISTS-connected wind project at Ramagiri, Andhra Pradesh, with 10-year O&M
SECI has invited bids for turnkey EPC of a 45.6 MW (+5%) wind power project at Ramagiri, Sri Sathya Sai district. It follows single-stage two-envelope bidding with e-reverse auction, a Rs 25,000 + GST processing fee and an Rs 8.44 crore EMD. The scope covers design through commissioning plus 10 years of comprehensive O&M. What's happening: SECI has split its 50 MW FDRE project into two separately awarded packages — this Wind package and a separate Solar+BESS one — but the wind contractor must still integrate both into a single functioning asset, keeping design, performance and lifecycle risk with the bidder.

 

8Powergrid invites bids for 16 units of 765 kV, 80 MVAR single-phase reactors under Lot-8
Powergrid has issued a tender for the 765 kV Reactor Package 7RT-34-BULK via the PRANIT portal. It is a lump-sum contract with a Rs 25,000 tender fee and EMD shown as Nil. Bid submission closes on 14 August 2026, with technical bid opening the same day; a pre-bid meeting is set for 28 July 2026. What's happening: Powergrid is aggregating sixteen reactors into one bulk package rather than ordering substation by substation, standardising specifications and securing manufacturing capacity in advance — keeping the field limited to proven high-voltage OEMs.

 

8Powergrid opens GeM tender for 765 kV current transformers across Eastern and Western Region-I
Powergrid has launched a GeM procurement for 765 kV current transformers, including 3000A, 4000A, extended-rating and six-core variants. Deliveries go to substations in Jharkhand, Bihar and Chhattisgarh over 365 days. It carries an Rs 8.71 lakh EMD and a 5% ePBG valid 26 months, reserved for Class-I local suppliers. Bids close 6 August 2026; the online pre-bid meeting is 23 July 2026. What's happening: Powergrid is pairing reverse-auction price discovery with Class-I local-supplier reservation for a specialised product, chasing lower prices without loosening technical entry barriers — which keeps competition among a small pool of qualified OEMs.

 

8Powergrid tenders 12 units of 765 kV, 80 MVAR reactors under 7RT-35-BULK with 60-month defect liability
Powergrid has issued a specification for 12 single-phase reactors under Lot-8, published 15 July 2026, with bids closing 13 August 2026. EMD is replaced by a bid-securing declaration, and an e-reverse auction applies. Reactors carry a 60-month defect liability, a further five-year latent-defect window and a Rs 8 lakh per kW loss LD. Six units must be commissioning-ready in 23 months and the remaining six in 26 months. What's happening: Powergrid is loading heavy lifetime-performance risk onto the contractor and deferring freight and insurance pricing until after it fixes destinations — so bidders win on ex-works price but negotiate logistics costs later, with little leverage.

 

8MPUVNL invites RESCO rooftop-solar bids across nine MP districts on a 25-year PPA model
MPUVNL has invited bids for grid-connected rooftop solar at government premises across nine districts, published 16 July 2026, with bids closing 17 August 2026. The developer finances, builds, owns and operates each system for 25 years under separate PPAs with each government DDO. EMD is Rs 1 lakh per MW, with performance security of Rs 1,750 per kW for each PPA, and the first-year tariff escalates 2% annually. What's happening: MPUVNL is capping each bidder's award at the lower of its EMD-backed and financial capacity, and fragmenting district awards into multiple DDO-level PPAs — turning the tender into a distributed 25-year operating platform rather than a simple EPC job.

 

8PFC appoints lender's legal counsel for Rs 254 crore Bikaner solar-plus-BESS financing
PFC has issued a GeM tender to appoint counsel for a ~Rs 254 crore loan to Juniper Nirjara Energy for a 42 MWp solar and 234.8 MWh BESS project, plus security changes to an existing 70 MWp solar loan. It is a two-packet limited tender among 12 empanelled category-A firms, with no EMD or ePBG, closing 31 July 2026, and the lump-sum fee is paid in five 20% milestones. What's happening: PFC needs the counsel to recast security so a new loan and an existing solar financing share collateral on a first pari-passu basis — buying execution certainty, with milestone payments hinging on registries and counterparties outside the firm's control while PFC keeps termination-at-will.

 

8TGGENCO floats two-year rate contract for grinding rolls and bull ring segments with conflicting qualification clauses
TGGENCO has invited two-part bids for grinding rolls and bull ring segments used in BHEL bowl mills across its 270–800 MW units, on a two-year rate-contract basis. Bids close 17 August 2026, with a Rs 1.15 crore EMD and a 10,000-hour operating guarantee with mid-life joint inspection. What's happening: The tender contradicts itself — five versus six years' experience, and Rs 30 crore versus Rs 7.20 crore solvency, across different sections — an unresolved drafting conflict that could decide who qualifies before price bids even open, while layered securities and firm pricing shift lifecycle risk onto the supplier.

Details

Download tenders and news clips

Jul 18:  For reference purposes the website carries here the following tenders:
 8Tender for development of railway siding for loading of pond ash Details
 8Tender for interconnection of 400kV line Details
 8Tender for supply, installation testing and commissioning of differential numeric relays at various Details
 8Tender for supply of TLSA for the transmission lines Details
 8Tender for work of 33 kV new substation Details
 8Tender for construction of 33 kV UG line Details
 8Tender for civil works for construction of 132 kV bays Details
 8Tender for selection of agency for providing application management services Details
 8Tender for procurement of spares of various rating motors HT motors Details
 8Tender for work of repairing of foundation bolts of rotary breakers Details
 8Tender for procurement of HS straight joint kit, HS outdoor and HS indoor termination kit for 11 kV 3 X 120 sqmm XLPE cable Details
 8Tender for procurement of 11 kV standalone structure materials complete set Details
 8Tender for R&M of AEP gear boxs Details
 8Tender for Package- 3 engineering procurement, supply, installation, testing & commissioning of electro- mechanical components for 640MW (8X80 MW) Details
 8Tender for work of bus strengthening from single panther conductor Details
 8Tender for procurement of non ferric alum commercial grade. Details
 8Tender for erection of 3.3kV overhead line Details
 8Tender for various pipeline related jobs (installation of pump, etc) along with associated electrical works Details
 8Tender for maintenance of 11kV, 3.3kV and 550V OH line Details
 8Tender for annual miscellaneous preparatory civil works for various Details
 8Tender for civil maintenance of ash dyke Details
 8Tender for maintenance of horticulture and landscape works Details
 8Tender for supply of R-22 refrigerant gas for AC plant system Details
 8Tender for supply of various types of clamp for 220 kV switchyard Details
 8Design, fabrication, supply, installation, testing, commissioning of ongrid solar ground mounted project with net meter and RMS capacity of 140 kW Details
 8Tender for repair of damaged platform, plinth surface, drain, railing Details
 8Tender for construction of 33kV underground line Details
 8Tender for supply of ferric alum Details
 8Tender for construction of new 33 /11 kV sub station Details
 8Tender for supply, erection, installation, testing, and commissioning of materials/equipment Details
 8Tender for supply of programmable multi function digital panel meters for switchyard and protection control panels Details
 8Tender for extension of drainage at 110kV substation Details
 8Tender for construction of 11kV new feeder from 110kV S/s Details
 8Tender for shifting of electrical utilities in connection Details
 8Tender for resurfacing of road inside substation, extension of road to 11kV yard Details
 8Tender for utility shifting of transformers and RMU Details
 8Tender for procurement of spare of mechanical seal of booster pump Details
 8Tender for procurement of carb clad/Tibo. sol coated rotary segregating valve assembly for buffer hopper Details
 8Tender for procurement of spares of DMCW (TG and SG) pumps Details
 8Tender for procurement of ABT compliant energy meters of 0.2s accuracy Details
 8Tender for procurement of spares for gas analyser Details
 8Tender for renewal and replacement of damaged water supply/sanitary paint electrical wiring Details
 8Tender for procurement of special steel sail hard/TISCRAL or equipment 6mm carbon steel for gas ducts. Details
 8Tender for supply and delivery of 61 Nos. guide vane seal Details
 8Tender for procurement of 4-inch PRV for unit 5 conveying line Details
 8Tender for biennial maintenance work of of water distribution line Details
 8Tender for biennial maintenance contract for electrical maintenance including illumination system Details
 8Tender for biennial maintenance contract for overall illumination maintenance jobs Details
 8Tender for procurement of electrical spare parts items Details
 8Tender for replacement of existing 11 kV ACSR conductor with 11 kV Dog conductor Details
 8Tender for ARC for HT/LT/TC erection and maintenance works Details
 8Tender for laying, erection, testing and commissioning of 132kV 1Cx800 sq.mm XLPE cable Details
 8Tender for Bi-annual contract for work of loading, unloading, stacking of any material Details
 8Tender for work of erection dismantling of 132kV/66kV/11kV equipment’s, structures, control wiring Details
 8Tender for ARC for HT/LT/TC erection and maintenance works Details
 8Tender for work biannual AMC of repairing / refurbishing, servicing & overhauling of 400KV & 220kV isolator along Details
 8Tender for annual battery maintenance work at various substations Details
 8Tender for annual maintenance contract for attending emergency / breakdown / planned maintenance works of 220kV & 132kV sub stations Details
 8Tender for work of replacement of old battery set by new battery set Details
 8Tender for various regular preventative maintenance / emergency and breakdown works of various 220kV & 100kV substations Details
 8Tender for supply of spares and repairing, servicing & overhauling VCBs at various sub stations Details
 8Tender for annual maintenance contract for the work of repairing, overhauling, servicing, maintenance & alignment of 220/132/33kV isolators Details
 8Tender for dismantling of existing damaged compound wall & reconstruction of compound wall at 132kV S/Stn Details
 8Tender for supply, installation, testing & commissioning of 2 TR split type variable speed inverter Details
 8Tender for work of establishment of 220/22kV GIS substation Details
 8Tender for establishment of 220/33kV substation along Details
 8Tender for work of LILO of 220kV line Details
 8Tender for supply of various types of contactors for LTMCC of 500 MW Details
 8Design, supply, installation, commission and maintenance of solar PV system Details
 8Tender for Bi-annual rate contract for erection of 66 kV line feeder bay / transformer bay for various sub-stations Details
 8Tender for purchase, erection, including foundation of conductor/cable measuring machine Details
 8Tender for work of replacement of insulator or SRI work of attending the fault or broken conductor and/or snapping from tower/gantry Details
 8Tender for work of overhauling, oil leakage attending and testing of 100MVA, 11/230 kV generating transformer Details
 8Tender for rate contract for repairing of failed / damaged / distribution transformers Details
 8Tender for supply, of LED flood lights 240 Watts Details
 8Tender for work of removal, supply and application of spray insulation of steam turbines Details
 8Tender for supply of mill discharge first piece after MPO for coal mill Details
 8Tender for supply of tubes, end plates & baffles and work Details
 8Tender for work of preventive maintenance, shutdown & emergency maintenance of IAC/SAC compressor, air washery fan/pump motor, ACW/FCW motor Details
 8Tender for work of dismantling replacement / repairing of PF pipe, orifice & PF bend of coal mills Details
 8Tender for work of replacement of various spares of drive system of wagon tippler Details
 8Tender for work of fabrication/ removal/ repairing /erection of metallic expansion bellows at various Details
 8Tender for supply of various spares for SWAS system of boiler Details
 8Tender for supply of various instruments for CHP Details
 8Tender for supply and replacement of NDCT components for 1x 800 MW Details
 8Tender for procurement of 6.6/0.415 kV feeder protection numerical relays Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8ECL CMD calls for balanced energy transition, says coal remains key to India's energy security Details
 
88 core industries index to become 9 as government adds iron ore Details
 
8West Bengal Energy Transition Shapes Coal Future Details
 
8India rebases its core sector index to 2022-23 on 20 July, and the same output will print a different growth number Details
 
8Iron Ore Joins India''s Core Sector Index, Total 9 Industries Details
 
8Index of Core Industries set to get an upgrade with revised base year and weights Details
 
8India Adds 30.6 GW Renewable Energy Capacity in H1 2026, Solar Leads Growth: Pralhad Joshi Details
 
8India's renewable energy capacity additions rose 25% in H1 2026 Details
 
8India’s renewable energy sector set for ‘transformational’ growth Details
 
8Adani Group breaks into India’s Top 10 most valuable brands; Adani Power leads energy sector Details
 
8Manju Gupta: Executive Director, Power Grid Corporation of India Limited Details
 
8Industry experts flag AI skills gap in clean energy sector Details
 
8Pinarayi Vijayan warns of protests if Kerala government sets up nuclear power plant Details
 
8Unlocking Efficiency: Building a unified power market through market coupling Details
 
8Advancing India’s sustainable industrial economy through clean energy Details
 
8FM Report: Power-Generation Risks Mount as Electricity Demand Soars Details
 
8Nuclear Ambitions: Building capacity for a low-carbon future Details
 
8Aryaman Vikram Birla targets 20 GW renewable capacity in medium term; plans to back growth with battery storage Details
 
8POWERGRID Invites Bids For 250 MW/1000 MWh Battery Energy Storage System Project Across India Details
 
8India a step closer to its first demonstration-scale geothermal power project Details
 
8India to Open Thorium Sector to Private Firms Details
 
8Assam govt plans Rs 77,353 crore power push Details
 
8Sanjay Ghodawat Group and Nordstar Estates Join Forces to Power India’s High-Growth Real Estate Markets Details
 
8Laser Power & Infra secures Rs 4.15 crore HPSEBL order for HTLS conductors Details
 
8Ratul Puri on Building Integrated Energy Solutions for India’s Rising Power Demand Details
 
8NTPC Appoints Dr. Som Nath Sachdeva as Non-Official Independent Director for Three-Year Term Details
 
8Laser Power & Infra Locks in 10% Upper Circuit Again After Heavy Institutional Buying on Listing Details
 
8Walchandnagar Industries, BHEL, L&T shares in focus as NTPC-NPCIL JV floats Rs 28,000 crore tender for Rajasthan Nuclear Power Project Details
 
You can also click on Newsclips for more Details

Power Markets Daily

Jul 17: 8Day-ahead and real-time prices at fresh highs
Day-ahead cleared Rs 7,284/MWh for 17 July (Rs 7,049 for the 16th; Rs 2,490 on 12 July); real-time averaged Rs 7,723/MWh on 16 July before easing to Rs 6,911; green day-ahead firmed to Rs 7,024. Night blocks repeatedly hit the Rs 10,000 ceiling. Cleared volumes were ordinary (day-ahead 148,764 MWh for the 17th); the move is on price, driven by an evening buy-side scramble, not by volume.

8Demand near an all-time high
Maximum demand met 270,203 MW on 16 July, against the 270.8 GW national record of 21 May; energy met 6,002 MU. A monsoon peak this close to a heatwave peak is the demand signal behind the price move.

8Term-ahead and intraday markets pinned to the ceiling, clearing only in the evening
IEX term-ahead and green term-ahead contracts traded thin and mostly at the Rs 10,000 ceiling, with genuine clearing only in round-the-clock products (term-ahead round-the-clock West cleared 2,640 MWh at about Rs 7,953). The intraday segment cleared nothing all day. Real-time cleared only from about 19:30, and the PXIL deviation market only between 20:30 and 23:00 - buyers paying the ceiling, then Rs 5,500 - confirming the scarcity is a post-solar evening event.

8High-price and ancillary day-ahead segments did not clear
The high-price day-ahead market drew a sell-only book of about 72,000 MWh with no matching demand and no clearing price for a second running day; the ancillary-services day-ahead segment saw no bids and no activity all week. The unused sell-side capacity is another marker of daytime surplus.

8GUVNL floats a 400 MW reverse auction across three exchanges
Hindustan Power Exchange circular HPX_RA_01056 (16 July) sets a single-side reverse auction for Gujarat Urja Vikas Nigam - three tranches of 400 MW covering 23–31 July, August and September, ceiling Rs 10,000/MWh, energy of any type - with the e-auction on 18 July; parallel auctions run on IEX and PXIL. A large discom buying blocks two to three months out is the mirror image of the evening-peak tightness.
Details

Grid Operations Daily

Jul 17: 8Frequency ran low, not high
On 16 July the frequency was inside the 49.9–50.05 Hz band 64.3 percent of the time, but it spent almost twice as long below the band (23.3 percent) as above it (12.4 percent), touching a low of 49.508 Hz at 06:18. After weeks of running high on surplus, a day that dips low points to tighter mornings and a stretched evening ramp rather than pure oversupply.

8The grid was net backing down, with costly gas left idle
Ancillary services backed generation down by a net 4,565 MWh on 16 July (31,543 down against 26,978 up), and NLDC's unit-commitment table shows eight RLNG-gas stations committed but scheduled at zero. The system was comfortable on energy through the day; see Story 1.

8A busbar-protection event at Vemagiri cost 1,400 MW for fourteen minutes
At 11:52 on 16 July a jumper cut on a 220 kV bus-coupler at Vemagiri (Andhra Pradesh) operated the busbar protection, tripping the Vemagiri transformers and then Guddigudem's on load transfer, for a load loss of about 1,400 MW; supply was restored by 12:06. A short, sharp reminder that single-point bus faults still take large blocks off instantly.

8National corridors clean, but Tripura's import path ran over its limit for nearly 20 hours
Nationally, inter-regional transfer and N-1 criteria showed zero violations on 16 July. Inside the North-East, though, the Tripura import corridor breached its available transfer capability for 19.7 hours on 15 July (82 percent of the day) and the Assam corridor for five - the chronic evacuation constraint behind the region's defence-scheme strain (see Story 4).

8A southern bus ran persistently over-voltage at Cuddapah
The 765 kV bus at Cuddapah spent 38 percent of 16 July above 800 kV, peaking at 813 kV - the day's largest voltage deviation, with smaller high-voltage excursions at Nizamabad, Maheshwaram and two Gujarat buses. Light evening loading on a high-voltage backbone with reactive support lagging; no low-voltage violations were recorded nationally.

8Weak primary frequency response from two North-East stations
NERLDC's June frequency-response scorecard rates Doyang hydro at 0.02 and Palatana gas at 0.21 on a scale to 1.0 - near-absent governor response - while Bongaigaon and Kopili scored a full 1.0. Poor primary response from large machines is what forces the ancillary market to do more of the second-by-second balancing.

8Eastern demand was chronically under-forecast
ERLDC's day-ahead load forecast for 16 July ran a mean error of 7.5 percent and under-called actual demand by up to about 3,900 MW through the midday blocks; the intraday forecast was tight at 1.4 percent. Day-ahead under-forecasting in a rising-demand month feeds straight into next-day exchange buying.

8A CT burst at Biharsharif cascaded to a 110 MW blackout when a breaker failed to open
On 26 June a current-transformer burst at Biharsharif faulted the bus, and the bus-coupler breaker's pole failed to open mechanically - so the fault spread to the second bus and cascaded to a 110 MW blackout, with the disturbance recorder found not time-synchronised. A single CT failure turning into a station blackout is exactly the latent mechanical defect a protection audit is meant to catch.

8Santaldih lost 225 MW when a bus-shift flashed over mid-operation
On 4 June a heavy flashover during a live shift of a unit from one bus to another at Santaldih operated the busbar differential and tripped the whole switchyard, losing 225 MW of generation and 92 MW of load. The committee's lesson is blunt: finish the feeder rearrangement before splitting a bus, not during it.

8Godda and Pakur lost load twice as healthy lines tripped with the faulted ones
Two events at Godda/Pakur (17 and 25 June, 168 and 216 MW of load lost) saw faults on the Madanpur lines simultaneously trip healthy parallel circuits; the Jharkhand utility must explain why an auto-reclose did not operate and segregate its special-protection outputs. Sympathetic tripping of sound lines is the signature of a protection-coordination gap.

8A Buxar transformer tripped on a setting that breaks the region's protection rule
On 11 June a Buxar transformer tripped on a standby-earth-fault element set to a fixed one-second delay rather than the eastern region's inverse-time philosophy - a settings mismatch the operator has asked the utility to correct. Small on its own, it is the kind of non-standard setting that turns an external fault into an unnecessary trip.

8Generation ran above programme on 15 July, but hydro is lagging
CEA's daily generation report puts all-India output at 5,020 MU on 15 July against a 4,485 MU programme. Year-to-date, eastern hydro is 32 percent below target and north-eastern 12 percent below, while northern nuclear runs 18 percent short - the shortfalls that a monsoon is supposed to be curing.

8Darbhanga went dark on 29 June though the fault cleared in under 100 milliseconds
At Darbhanga on 29 June a phase-to-earth fault cleared in under a tenth of a second, yet both 220 kV lines and both 400/220 kV transformers tripped together and the station went dark. The phasor records show the fault was cleared fast, so why healthy elements tripped with it is unexplained, and the two transmission utilities' reports are still awaited - the signature of a protection-logic fault rather than the fault itself.

8A north-eastern voltage problem is now spilling into Bhutan's grid
Chronic low voltage around Rangia in Assam - worse whenever a Bongaigaon–Rangia circuit is out - has Assam pulling so much power through a 132 kV tie to Motanga that it stresses the Bhutan system, whose operator has asked to open the tie from its end. The region's voltage weakness now crosses an international border, and the fix - a 400/220 kV substation at Rangia - is still pending.

8A Nagaland protection scheme keeps shedding load with no fault to answer for
Unequal loading on two parallel 132 kV lines at Dimapur keeps pushing one phase over the special-protection-scheme pickup, shedding load three times in late June and early July with no actual fault; the root cause is still not found. A defence scheme that fires on a loading imbalance is itself a reliability risk, not a safeguard.
Details
  • Jul 22: India's under-construction coal fleet swells to 42,700 MW even as this year's additions collapse to 2,260 MW:Details
  • Jul 22: MNRE extends the ALMM solar-cell exemption to 31 December 2026, sparing rooftop and open-access projects:Details
  • Jul 22: Download tenders and news clips:Details
  • Jul 21: Eastern thermal earned about Rs 112 crore in June for running part-loaded - the same stations were also failing their frequency duty:Details
  • Jul 21: Day-ahead power hit the Rs 10 ceiling overnight and at dusk on 20 July - yet the grid met a ~239 GW peak nearly shortage-free:Details
  • Jul 21: The North met a 93,981 MW summer peak nearly shortage-free - but a single wind trip cost Rajasthan 1,290 MW:Details