All content in this website is sourced legitimately

Power hit the Rs 10,000 ceiling overnight and at dusk on 22 July, then crashed to Rs 1,380 at noon - on a grid with zero shortage.  Now the North is paying to keep power on bars - Rs 46 crore last week to run Dadri, Anta and Jhajjar up through the solar trough.  A 765 kV trip stripped 1,320 MW off Uttar Pradesh's Jawaharpur late on 22 July as a protection review logs a spring of weather-hit losses.  Twenty-nine thermal plants run coal-critical in mid-monsoon - Andhra's Damodaram Sanjeevaiah down to a single day.  Adani Power's Q1 profit jumps 47% to Rs 4,867 crore and it clears a Rs 15,000 crore raise while swallowing the Jaiprakash insolvency estate.  JSW Energy's profit falls a third to Rs 533 crore even as it books its biggest-ever capacity quarter and absorbs GE Power India.   Shell is out of Indian renewables: Aditya Birla buys the Sprng platform for Rs 17,200 crore, nearly doubling its green fleet.  Adani Green's operating fleet crosses 20,000 MW as quarterly EBITDA hits a record Rs 4,122 crore.   The appellate tribunal stays Maharashtra's move to load legacy deviation charges onto thermal generators, siding with Adani and JSW.  Coal India wins its way into batteries - 80 MW of SECI's Odisha storage tender goes to the country's biggest coal miner.  Contracting news for the day.  Contracting news for the day.  Power Markets Daily.  Grid Operations Daily.  Outage & Maintenance Register.  Fuel & Coal Ledger.  Hydro & Reservoir Ledger.  CERC Docket & Adjudication.  State Regulatory Roundup.  Green Markets & RE Programme Watch.   Corporate Wire.  Committees, People & System Administration.  Daily Power Sector Tenders Excel update.  Download tenders and news clips.  .  MNRE extends the ALMM solar-cell exemption to 31 December 2026, sparing rooftop and open-access projects.  Daily Power Sector Tenders Excel update.  POWER MARKETS DAILY.  GRID OPERATIONS DAILY.  OUTAGE & MAINTENANCE REGISTER.  FUEL & COAL LEDGER.  HYDRO & RESERVOIR LEDGER.  CERC DOCKET.  STATE REGULATORY ROUNDUP.  GREEN MARKETS & RE PROGRAMME WATCH.  CORPORATE WIRE.  COMMITTEES, PEOPLE & SYSTEM ADMINISTRATION.  Methane blast kills at least 20 at NHPC's under-construction Teesta-VI tunnel in Sikkim.   IEX day-ahead sat at the Rs 10,000 ceiling in 54% of 21 July's blocks yet crashed to Rs 1,618 at noon.  The grid paid Western generators Rs 80 crore in one week to stay on the site as monsoon load slumped.  Half of India's inter-state transmission build is late - Rajasthan and Khavda solar links slip up to six years.  Adani Energy Solutions' Q1 profit doubles to Rs 1,237 crore on a Rs 71,779 crore transmission pipeline.  The North-East grid is going blind as its control-system bill jumps Rs 167 crore on AI-driven hardware prices.  Twenty-seven thermal plants run coal-critical in mid-monsoon - Andhra's Damodaram Sanjeevaiah down to 2%.  Jharkhand's discom posts a Rs 1,839 crore half-year loss as its accumulated deficit nears Rs 18,330 crore.  India's under-construction coal fleet swells to 42,700 MW even as this year's additions collapse to 2,260 MW.  Contracting news for the day: Part-1.  Download tenders and news clips.  Hydro & Reservoir Ledger.  Eastern thermal earned about Rs 112 crore in June for running part-loaded - the same stations were also failing their frequency duty.  Day-ahead power hit the Rs 10 ceiling overnight and at dusk on 20 July - yet the grid met a ~239 GW peak nearly shortage-free.  The North met a 93,981 MW summer peak nearly shortage-free - but a single wind trip cost Rajasthan 1,290 MW.  Jaiprakash Power’s Q1 profit jumps 69% to Rs 469 crore as NARCL files insolvency over a Rs 1,239 crore guarantee.  MERC lets Adani’s Mumbai discom adopt Rs 6.38 a unit for 750 MW of round-the-clock renewable power.   India’s pumped-storage build-out reaches 15,870 MW under construction as SECI awards another 1,344 MW.  Twenty-six thermal plants sit critical on coal in mid-monsoon - Andhra’s Damodaram Sanjeevaiah down to 2%.  Punjab’s power employees and pensioners strike for two days, forcing PSPCL to draft engineers to man substations.  Maharashtra’s new RE policy blocks MERC from ordering MSEDCL to buy Waterfront’s small-hydro - even after fixing its Rs 6.18 tariff.  About 40 GW sat on outage on 20 July as North Chennai lost 800 MW and Rajpura 700 MW to boiler and ESP faults.  Power Markets Daily.  Grid Operations Daily.  Outage & Maintenance Register.  Fuel & Coal Ledger.  Daily Power Sector Tenders Excel update.  CERC Docket.  State Regulatory Roundup.  Green Markets & RE Programme Watch.  Corporate Wire.  Committees, People & System Administration.  Contracting news for the day: Part-1.  Download tenders and news clips.  The West runs a surplus while the North and South ration - July's squeeze is a delivery problem, not a generation shortfall.  POWER MARKETS DAILY.  GRID OPERATIONS DAILY.  OUTAGE & MAINTENANCE REGISTER.  

Power hit the Rs 10,000 ceiling overnight and at dusk on 22 July, then crashed to Rs 1,380 at noon - on a grid with zero shortage

Jul 23: 8The IEX day-ahead market averaged Rs 5,249.71 a MWh on 22 July but sat pinned at the Rs 10,000 ceiling through the overnight and evening blocks and fell to Rs 1,379.70 in the solar-flooded early afternoon. None of it was scarcity - the grid met a 233,019 MW peak with essentially nil shortage; the crunch is the shape of the day, not a shortage of power. Details

Now the North is paying to keep power on bars - Rs 46 crore last week to run Dadri, Anta and Jhajjar up through the solar trough

Jul 23: 8The Northern load-despatch pool's security-constrained unit-commitment account for 6–12 July shows Rs 46.28 crore paid to keep coal and gas units committed and run up, led by Rs 18.62 crore to NTPC's Dadri gas station. It is the same bill the Western and Eastern pools ran the same week - the cost of holding thermal ready while midday solar forces it down has now gone nationwide. Details

A 765 kV trip stripped 1,320 MW off Uttar Pradesh's Jawaharpur late on 22 July as a protection review logs a spring of weather-hit losses

Jul 23: 8Both 660 MW units of UP's Jawaharpur thermal station tripped together at 22:20 on 22 July when the 765 kV line to Greater Noida went out on generator-transformer protection, and neither was revived by cutoff. It lands as the Western committee's protection papers catalogue more than forty grid disturbances from the spring - including a 1,704 MW loss at JSW's Mahanadi plant when a lightning strike collapsed a transmission tower. Details

Twenty-nine thermal plants run coal-critical in mid-monsoon - Andhra's Damodaram Sanjeevaiah down to a single day

Jul 23: 8National coal stock at power plants held about 40.4 million tonnes, roughly 13 days' cover, on 21 July - but 29 individual plants were running critical, two more than a week earlier. Andhra's Damodaram Sanjeevaiah was at 3% of its normative stock, about a day's cover, and Reliance's Sasan ultra-mega was at the same 3%. Details

Adani Power's Q1 profit jumps 47% to Rs 4,867 crore and it clears a Rs 15,000 crore raise while swallowing the Jaiprakash insolvency estate

Jul 23: 8Adani Power reported a consolidated first-quarter net profit of Rs 4,866.60 crore, up 47%, on income of Rs 19,322 crore and a plant load factor lifted to 77.9%. The board cleared a Rs 15,000 crore equity raise and doubled the borrowing ceiling to Rs 1 lakh crore, as the group folded in three plants from the Jaiprakash Associates bankruptcy and signed a 1,600 MW supply deal with Maharashtra. Details

JSW Energy's profit falls a third to Rs 533 crore even as it books its biggest-ever capacity quarter and absorbs GE Power India

Jul 23: 8JSW Energy's first-quarter net profit fell to Rs 533 crore from Rs 836 crore even though EBITDA edged up and capacity crossed 14,535 MW on a record organic addition. The drop is the cost of that growth - depreciation and finance charges on new plant, weak hydrology and a force-majeure at its Mahanadi coal station - as it also swallows GE Power India's boiler business and signs up another 300 MW of thermal. Details

Shell is out of Indian renewables: Aditya Birla buys the Sprng platform for Rs 17,200 crore, nearly doubling its green fleet

Jul 23: 8Aditya Birla Renewables has agreed to buy 100% of Solenergi Power - the holding company for Shell's Sprng Energy platform - for an enterprise value of about Rs 17,200 crore, taking on roughly 5 GW of solar and wind. The deal lifts the Aditya Birla green portfolio from 4.4 GW to 9.3 GW and marks a major oil-major's exit from the Indian renewable market. Details

Adani Green's operating fleet crosses 20,000 MW as quarterly EBITDA hits a record Rs 4,122 crore

Jul 23: 8Adani Green Energy reported a June-quarter operating capacity of 20,142 MW, up 27% on the year, with energy sales up 30% and EBITDA at a record Rs 4,122 crore on a 94% margin. Its battery build at Khavda nearly doubled in the quarter to 3,551 MWh. Details

The appellate tribunal stays Maharashtra's move to load legacy deviation charges onto thermal generators, siding with Adani and JSW

Jul 23: 8The Appellate Tribunal for Electricity has stayed a Maharashtra commission order that apportioned regional-pool and legacy deviation charges to thermal generators injecting into the grid, allowing interim relief to Adani Power's Dahanu station and JSW Energy. JSW alone had paid about Rs 3.8 crore under protest; the tribunal's order freezes the demands while the appeals are heard. Details

Coal India wins its way into batteries - 80 MW of SECI's Odisha storage tender goes to the country's biggest coal miner

Jul 23: 8In SECI's 125 MW / 500 MWh standalone battery tender for Odisha, backed by viability-gap funding, Coal India won two of the three clusters - 80 MW in all - at monthly capacity charges of about Rs 3.04–3.05 lakh a MW. A coal miner taking grid-scale storage is the sharp edge of how the majors are hedging the energy transition. Details

Contracting news for the day

Jul 23: 81) IntelliSmart takes Indore smart metering at 21.7% below MPPKVVCL's estimate Ten bidders entered, three fell at the technical gate and six were eliminated on price, leaving a single survivor. The 6.9% gap to Apraava suggests competitive pressure rather than distress bidding. What remains untested is whether a Rs 417.15 crore price absorbs a 3,650-day service obligation comfortably. Under DBFOOT, the winner carries financing, deployment and lifecycle risk long after the award headline fades.

 

82) NTPC Green's Khavda BESS tender kept moving after its own deadline had passed Six corrigenda and one addendum landed inside a single bidding cycle, with the last posted a day after the original closing date. That sequence tells bidders the package was still being calibrated while they were expected to fix prices. The notice never states MW rating, discharge duration, chemistry or augmentation responsibility. A reverse auction on 3,300 MWh of undefined configuration is where the real risk sits.

 

83) MPPGCL formalises a site visit so bidders cannot later claim they did not know The corrigendum changes no scope, no price basis and no qualification bar — it simply schedules an inspection. Its commercial value lies in what it removes: the post-award claim that site conditions were unforeseeable. For a turnkey EPC carrying five years of O&M, land and interface assumptions made blind become expensive. The promoter has quietly shifted diligence responsibility back onto the bidder.

 

84) UJVNL puts the entire Sirkari Bhyol electro-mechanical chain under one turnkey price Rs 158.53 crore covers design through commissioning for a 3x40 MW hydro package with no interface escape route. The structure rewards firms with manufacturing depth rather than assembly capability. Coordination risk, not equipment cost, is likely to decide who prices this realistically. The pre-bid stage will show whether the market treats the estimate as workable.

 

85) POWERGRID removes the performance guarantee but moves payment behind a Collector's order Deleting the CPG frees working capital for the Morbi valuation package — an unusual relaxation for a consultancy assignment. What replaces it is milestone payment tied to acceptance by authorities the contractor cannot control. The award cap has also loosened from one package to two, reshaping who can win what. Easier entry, harder cash conversion.

 

86) Two extensions on Tankul suggest the market needed more time than UJVNL assumed The bidding window has stretched by 25 days without any visible change to scope, capacity or the Rs 87.90 crore estimate. The package runs from river diversion through tunnel, surge shaft and powerhouse into hydro-mechanical works. Geological risk allocation across those fronts is not resolved in the public notice. Repeated extensions usually mean bidders are still pricing what they cannot see.

 

87) NTPC's Barauni ash package rules out reverse auction and self-performed design cannot be bought in A three-week extension eases bid preparation but changes nothing about a 630-day delivery obligation. Qualification demands an executed pneumatic system with in-house design — closing the route of borrowed engineering credentials. Rs 1 crore bid security and Rs 6.09 lakh daily delay damages narrow the field further. NTPC appears to want fewer bidders who can actually finish.

 

88) BHEL caps some liability at Lakhanpur while leaving the worst exposure at 100% Corrigendum VIII gives bidders numbers to model: 5% for delay, 5% for performance shortfall, 30% for make-good. Termination and risk-and-cost completion still reach the full contract price. Requests to soften the one-year force majeure and three-year hold thresholds were refused outright. Five deadline extensions later, the risk envelope is clearer but no lighter.

 

89) MSEDCL reaches Version 5 on a Rs 109.58 crore transformer buy before opening a single bid Successive revisions and an incorporated pre-bid reply document suggest the utility preferred argument before award rather than after. Firm pricing survives every revision, leaving cost risk with manufacturers. The extended window improves bid quality but delays a purchase of one of the network's most routinely consumed assets. Document stability, not competition, appears to be the priority here.

 

810) BHEL wants its Anantapur BOS partner locked in before the project even exists This is a pre-bid tie-up, not an award — capability is being secured ahead of the downstream contest. A Rs 3 crore EMD against an uncertain project outcome is a serious commitment to demand upfront. It filters out speculative participation while pushing bid-stage risk onto prospective partners. For 1,200 MW, BHEL is buying execution certainty before it needs it.

 

811) Ennore's FGD tender has spent 162 days in procurement without changing a single risk clause Five extensions and a cancelled-then-restored pre-bid meeting have stretched the calendar without relaxing EMD, LD, warranty or completion terms. Contractors gained preparation time; the 30 and 32-month clocks did not move. The 4%-1% security split makes the technology provider a secured party rather than an adviser. Market formation, not administration, appears to be what took so long.

 

812) POWERGRID makes survey counts indicative and tells Anand bidders not to expect more money Corrigendum C5 deletes the performance guarantee, then transfers parcel-density risk in the same breath. Bidders must quote a fixed total before receiving the Land Plan Schedule, survey details and KML files. Payment splits 80:20, with the tail dependent on committee acceptance and a Collector's order. Lower entry cost, higher pricing blindness.

 

813) Mahagenco asks one contractor to find the land, build the plant, evacuate the power and run it for a decade This is a development platform transfer disguised as a 300 MWac EPC procurement. The 25 MWac floor widens entry, but a 15 MWac reference plant and per-MW financial ratios quietly narrow it again. Consortium partners can share technical credentials; the lead member carries the full financial test alone. A reverse auction then compresses prices built on land and evacuation uncertainty.

 

814) Kulhal's pre-bid meeting was rescheduled to a date after its own bid deadline The original calendar collapsed once clarification moved past the closing date, forcing a third extension. The 29-day shift restores roughly the same clarification-to-submission interval the tender first intended. What bidders learned during that window matters more than the extension itself. Rs 110.57 crore of brownfield hydro renovation cannot be priced from drawings alone.

 

815) CTUIL reorders its contract hierarchy one day before bids close The corrigendum makes the uploaded RfP supreme over conflicting GeM terms and the service-level agreement, without extending the deadline. Bidders must reconcile a 286-page document against a portal summary in a single day. The consultancy itself carries authority over delay claims, force majeure, cost reasonableness and asset valuation. Personnel controls make the CVs submitted a binding commercial promise, not a bid-stage flourish.

 

816) A one-minute discrepancy sits inside NTPC REL's 600 MW Dhule bid schedule The schedule table says one cut-off; the portal banner says another sixty seconds later. Electronic systems reject late bids automatically, which makes ambiguity a procedural risk unrelated to price or capability. Corrigendum-1 arrived seven days before submission alongside a second addendum. Rs 20 crore in bid security filters the field before a reverse auction compresses whatever margin survives.

 

817) BHEL bundles two Korba West packages that share nothing except a single price Package-A and Package-B carry different boundaries and 42 and 58-month schedules, yet must be quoted as one lump sum. The price will be split 25:75 by prescription, not by the bidder's own cost structure. BHEL can then redistribute orders at will, with cross-default linking every instrument it issues. Administrative separation without contractual separation is the whole design.

 

818) POWERGRID tightens the one-package rule for Kheda while consolidating its own conditions The revised ATC pulls qualification, evaluation, payment and scope into a single controlling document. Restricting each agency to one award prioritises parallel execution across districts over economies of scale. A package-opening sequence is being used to manage bidder capacity before firms exhaust their entitlement. Fifteen days per assignment leaves no room for slow mobilisation.

 

819) Corrigendum C7 shows POWERGRID still adjusting its Gujarat valuation terms before award The amendment modifies the bidding process after original publication and must be read alongside the base documents. GeM provisions and POWERGRID's own conditions now operate together rather than in sequence. Land valuation has moved from incidental consultancy to a scheduling input for transmission construction. The final conditions matter more than the original release.

 

Details

Contracting news for the day

Jul 23: 81) IntelliSmart takes Indore smart metering at 21.7% below MPPKVVCL's estimate Ten bidders entered, three fell at the technical gate and six were eliminated on price, leaving a single survivor. The 6.9% gap to Apraava suggests competitive pressure rather than distress bidding. What remains untested is whether a Rs 417.15 crore price absorbs a 3,650-day service obligation comfortably. Under DBFOOT, the winner carries financing, deployment and lifecycle risk long after the award headline fades.

 

82) NTPC Green's Khavda BESS tender kept moving after its own deadline had passed Six corrigenda and one addendum landed inside a single bidding cycle, with the last posted a day after the original closing date. That sequence tells bidders the package was still being calibrated while they were expected to fix prices. The notice never states MW rating, discharge duration, chemistry or augmentation responsibility. A reverse auction on 3,300 MWh of undefined configuration is where the real risk sits.

 

83) MPPGCL formalises a site visit so bidders cannot later claim they did not know The corrigendum changes no scope, no price basis and no qualification bar — it simply schedules an inspection. Its commercial value lies in what it removes: the post-award claim that site conditions were unforeseeable. For a turnkey EPC carrying five years of O&M, land and interface assumptions made blind become expensive. The promoter has quietly shifted diligence responsibility back onto the bidder.

 

84) UJVNL puts the entire Sirkari Bhyol electro-mechanical chain under one turnkey price Rs 158.53 crore covers design through commissioning for a 3x40 MW hydro package with no interface escape route. The structure rewards firms with manufacturing depth rather than assembly capability. Coordination risk, not equipment cost, is likely to decide who prices this realistically. The pre-bid stage will show whether the market treats the estimate as workable.

 

85) POWERGRID removes the performance guarantee but moves payment behind a Collector's order Deleting the CPG frees working capital for the Morbi valuation package — an unusual relaxation for a consultancy assignment. What replaces it is milestone payment tied to acceptance by authorities the contractor cannot control. The award cap has also loosened from one package to two, reshaping who can win what. Easier entry, harder cash conversion.

 

86) Two extensions on Tankul suggest the market needed more time than UJVNL assumed The bidding window has stretched by 25 days without any visible change to scope, capacity or the Rs 87.90 crore estimate. The package runs from river diversion through tunnel, surge shaft and powerhouse into hydro-mechanical works. Geological risk allocation across those fronts is not resolved in the public notice. Repeated extensions usually mean bidders are still pricing what they cannot see.

 

87) NTPC's Barauni ash package rules out reverse auction and self-performed design cannot be bought in A three-week extension eases bid preparation but changes nothing about a 630-day delivery obligation. Qualification demands an executed pneumatic system with in-house design — closing the route of borrowed engineering credentials. Rs 1 crore bid security and Rs 6.09 lakh daily delay damages narrow the field further. NTPC appears to want fewer bidders who can actually finish.

 

88) BHEL caps some liability at Lakhanpur while leaving the worst exposure at 100% Corrigendum VIII gives bidders numbers to model: 5% for delay, 5% for performance shortfall, 30% for make-good. Termination and risk-and-cost completion still reach the full contract price. Requests to soften the one-year force majeure and three-year hold thresholds were refused outright. Five deadline extensions later, the risk envelope is clearer but no lighter.

 

89) MSEDCL reaches Version 5 on a Rs 109.58 crore transformer buy before opening a single bid Successive revisions and an incorporated pre-bid reply document suggest the utility preferred argument before award rather than after. Firm pricing survives every revision, leaving cost risk with manufacturers. The extended window improves bid quality but delays a purchase of one of the network's most routinely consumed assets. Document stability, not competition, appears to be the priority here.

 

810) BHEL wants its Anantapur BOS partner locked in before the project even exists This is a pre-bid tie-up, not an award — capability is being secured ahead of the downstream contest. A Rs 3 crore EMD against an uncertain project outcome is a serious commitment to demand upfront. It filters out speculative participation while pushing bid-stage risk onto prospective partners. For 1,200 MW, BHEL is buying execution certainty before it needs it.

 

811) Ennore's FGD tender has spent 162 days in procurement without changing a single risk clause Five extensions and a cancelled-then-restored pre-bid meeting have stretched the calendar without relaxing EMD, LD, warranty or completion terms. Contractors gained preparation time; the 30 and 32-month clocks did not move. The 4%-1% security split makes the technology provider a secured party rather than an adviser. Market formation, not administration, appears to be what took so long.

 

812) POWERGRID makes survey counts indicative and tells Anand bidders not to expect more money Corrigendum C5 deletes the performance guarantee, then transfers parcel-density risk in the same breath. Bidders must quote a fixed total before receiving the Land Plan Schedule, survey details and KML files. Payment splits 80:20, with the tail dependent on committee acceptance and a Collector's order. Lower entry cost, higher pricing blindness.

 

813) Mahagenco asks one contractor to find the land, build the plant, evacuate the power and run it for a decade This is a development platform transfer disguised as a 300 MWac EPC procurement. The 25 MWac floor widens entry, but a 15 MWac reference plant and per-MW financial ratios quietly narrow it again. Consortium partners can share technical credentials; the lead member carries the full financial test alone. A reverse auction then compresses prices built on land and evacuation uncertainty.

 

814) Kulhal's pre-bid meeting was rescheduled to a date after its own bid deadline The original calendar collapsed once clarification moved past the closing date, forcing a third extension. The 29-day shift restores roughly the same clarification-to-submission interval the tender first intended. What bidders learned during that window matters more than the extension itself. Rs 110.57 crore of brownfield hydro renovation cannot be priced from drawings alone.

 

815) CTUIL reorders its contract hierarchy one day before bids close The corrigendum makes the uploaded RfP supreme over conflicting GeM terms and the service-level agreement, without extending the deadline. Bidders must reconcile a 286-page document against a portal summary in a single day. The consultancy itself carries authority over delay claims, force majeure, cost reasonableness and asset valuation. Personnel controls make the CVs submitted a binding commercial promise, not a bid-stage flourish.

 

816) A one-minute discrepancy sits inside NTPC REL's 600 MW Dhule bid schedule The schedule table says one cut-off; the portal banner says another sixty seconds later. Electronic systems reject late bids automatically, which makes ambiguity a procedural risk unrelated to price or capability. Corrigendum-1 arrived seven days before submission alongside a second addendum. Rs 20 crore in bid security filters the field before a reverse auction compresses whatever margin survives.

 

817) BHEL bundles two Korba West packages that share nothing except a single price Package-A and Package-B carry different boundaries and 42 and 58-month schedules, yet must be quoted as one lump sum. The price will be split 25:75 by prescription, not by the bidder's own cost structure. BHEL can then redistribute orders at will, with cross-default linking every instrument it issues. Administrative separation without contractual separation is the whole design.

 

818) POWERGRID tightens the one-package rule for Kheda while consolidating its own conditions The revised ATC pulls qualification, evaluation, payment and scope into a single controlling document. Restricting each agency to one award prioritises parallel execution across districts over economies of scale. A package-opening sequence is being used to manage bidder capacity before firms exhaust their entitlement. Fifteen days per assignment leaves no room for slow mobilisation.

 

819) Corrigendum C7 shows POWERGRID still adjusting its Gujarat valuation terms before award The amendment modifies the bidding process after original publication and must be read alongside the base documents. GeM provisions and POWERGRID's own conditions now operate together rather than in sequence. Land valuation has moved from incidental consultancy to a scheduling input for transmission construction. The final conditions matter more than the original release.

 

Details

Power Markets Daily

Jul 23: 8IEX day-ahead averaged Rs 5,250 on 22 July but held the Rs 10,000 ceiling overnight and at dusk
8The green day-ahead cleared at Rs 6,685 - a premium of more than two times the conventional price
8HPX drew no buyers for a fourth day and PXIL cleared nothing for an eighth, so IEX carried the market
8Rajasthan's merit order runs from Rs 1.55 at Sasan to Rs 28.11 for liquid-fuel peaking
8Andhra's discom levies a Rs 0.40 a unit fuel surcharge for May in the August bills Details

Grid Operations Daily

Jul 23: 8India met a 233,019 MW maximum demand on 22 July at 11:19 - a solar-hour peak - with shortage near nil
8The grid ran high a sixth of 22 July and the operators backed generation down by nearly 56,000 MWh
8The North-East to Tripura corridor sat over its transfer limit for 63% of 21 July
8India imported 52 MU from Bhutan and wheeled 56 MU to Bangladesh on 22 July
8The West met a 63,684 MW evening peak with zero shortage as wind supplied 169 MU
8The South met a 55,049 MW peak shortage-free while carrying 10.7 GW of generation on outage Details

Outage & Maintenance Register

Jul 23: 8About 52 GW of capacity sat under maintenance on 21 July, 30 GW of it forced out
8A 765 kV trip took both Jawaharpur units - 1,320 MW - off the bars late on 22 July
8The South spent 22 July switching around a twin-circuit line snap and a Mysore bus-bar cascade
8Western forced losses took out Adani Raipur, Sasan and Shree Singaji - three units near 660 MW each
8NTPC carried about 5.6 GW of its own fleet out on boiler and condenser leaks
8About 32 GW has been out beyond a fortnight, including two 800 MW Yadadri units and Kudankulam-1 Details

Fuel & Coal Ledger

Jul 23: 8Twenty-nine thermal plants ran coal-critical on 21 July; Damodaram Sanjeevaiah down to a day
8The coal ministry counts 42 mines scientifically closed and sets a Rs 40,000 crore closure corpus
8Bharat Coking Coal swings to a Rs 68 crore loss as production falls 27%
8A Northern Coalfields e-auction carries a disputed Rs 300 a tonne Singrauli rehabilitation charge Details

Hydro & Reservoir Ledger

Jul 23: 8Telangana's Krishna reservoirs hold about 93% less energy than a year ago deep into the monsoon
8The East runs almost no hydro - Teesta-III still out, Odisha's reservoirs bare and a pumped-storage unit drawing power
8Big reservoirs are still filling - Bhakra sits 30 metres below its full level Details

CERC Docket & Adjudication

Jul 23: 8The appellate tribunal stays Maharashtra's legacy-deviation charge on thermal generators
8Himachal's regulator clears nine rooftop and ground-mounted solar tariffs at Rs 3.47 a unit
8Himachal grants interim connectivity to a 4.8 MW small-hydro project through a spare 33 kV bay Details

State Regulatory Roundup

Jul 23: 8Uttarakhand fixes UPCL's recoverable from a 214 MW gas station at Rs 19.83 crore and rejects the review
8UP defers a giant captive solar project's plea for full transmission and banking exemption
8Maharashtra allows interest on delayed late-payment surcharge to an 11 MW bagasse cogenerator
8Haryana clears a flexible-load scheme and a graded surcharge, and quashes a township reference-meter demand
8Haryana defers plant-wise deviation settlement for the Panipat thermal station by a year
8Chhattisgarh puts ArcelorMittal's beneficiation plant back in the steel tariff category after a suo-motu reclassification
8Kerala's board asks its regulator to approve per-kW distribution cost data averaging Rs 1,563 a kW
8Tamil Nadu's ombudsman orders a Rs 2,982 refund and Punjab adopts a supply-code amendment
8UP tightens SCADA compliance on its utilities and extends a transmission line's deadline to December Details

Green Markets & RE Programme Watch

Jul 23: 8Coal India wins 80 MW of SECI's 125 MW Odisha battery tender
8The solar-cell approved list adds nearly 1,700 MW of domestic capacity in its eighth revision
8Adani Green's operating fleet crosses 20,000 MW on record quarterly EBITDA
8India's installed wind capacity reaches 57,443 MW, fourth largest in the world
8Suzlon lands a 202 MW wind order as Waaree Renewable buys into transmission
8Borosil Renewables' quarterly EBITDA doubles as it plans a 60% capacity expansion
8National statistics put India's assessed renewable potential at 4.7 million MW Details

Corporate Wire

Jul 23: 8Adani Power's Q1 profit jumps 47% to Rs 4,867 crore with a Rs 15,000 crore raise
8JSW Energy's Q1 profit falls a third to Rs 533 crore
8Aditya Birla Renewables buys the Sprng platform from Shell for Rs 17,200 crore
8Bajel Projects wins a 500 kV Egyptian transmission order worth more than Rs 400 crore
8The Inox wind group lines up a Rs 600 crore raise, a Rs 3,500 crore captive order and an O&M demerger
8Orient Green's Q1 profit slips to Rs 24 crore as it winds up its European arm; Tata Power weighs a bond issue
8Ratings Watch - ICRA puts three Aditya Birla Renewables units on watch, upgrades Sunsure, and CARE withdraws Soleos Details

Committees, People & System Administration

Jul 23: 8The North's pool paid Rs 46 crore last week to keep thermal on bars
8The Western protection committee logs 40-plus spring disturbances, one a 1,704 MW loss at JSW Mahanadi
8The South's committee weighs an Adani 765 kV substation, a Rs 1.36 lakh crore HVDC plan and a Vallur battery award
8The East's disaster-management meeting orders an emergency restoration set and studies a Nepal-hydro black start
8Punjab's power strike stretches to four days as unions add pensioners and PSPCL orders no-work-no-pay
8Himachal advertises a regulatory Member (Law) vacancy as public-body staffing turns over Details

Daily Power Sector Tenders Excel update

Jul 23: 8Daily Excel covering new tenders and all published updates including corrigendum, amendment, addendum, clarification and status revisions, along with technical and financial bid opening, evaluation completion and final award actions including AOC and LOA issuance.
Click on Reports for more Details

Download tenders and news clips

Jul 23:  For reference purposes the website carries here the following tenders:
  
8Tender for Bi- annual rate contract for emergency power restoration work of 400/220/132/66kV lines Details
  
8Tender for Bi-ARC for original survey and check survey for various 400kV/220kV/132kV/66kV overhead line Details
  
8Tender for dismantling of existing fencing and installation of new main gate along Details
  
8Tender for supply, installation & commissioning of CSD Details
  
8Tender for drone based patrolling of transmission lines Details
  
8Tender for protection wall at tower Details
  
8Tender for supply of LED flood lights and street lights for replacement of faulty lights Details
  
8Tender for supply of 36 kV CT accuracy 0.2S accuracy classes along with terminal connectors and junction boxes Details
  
8Tender for inspection of TG bearings, in situ machining of LP rotor journal Details
  
8Tender for capability (performance) test of NDCT Details
  
8Tender for work for protection of water conductor Details
  
8Tender for replacement of conventional electrical switches Details
  
8Tender for EPC Package for internal coal handling plant Details
  
8Tender for annual maintenance of horticulture works Details
  
8Tender for standardization of transformer station Details
  
8Tender for repair of damaged UC fencing and allied civil works Details
  
8Tender for procurement of sulphuric acid commercial grade Details
  
8Tender for construction of 1 no. addl. 20 MVA 66/11 kV TF plinth along with allied civil works Details
  
8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects Details
  
8Design, supply, erection, testing and commissioning of new generator relay panels Details
  
8Tender for providing chain-link fencing Details
  
8Tender for supply of various type sleeves & fins for boiler Details
  
8Tender for supply & erection of MS grills at various Details
  
8Tender for day to day civil maintenance work Details
  
8Tender for repair and maintenance of external pipelines Details
  
8Tender for repair, renovation, and miscellaneous civil maintenance works Details
  
8Tender for procurement of spares for turbine supervisory system Details
  
8Tender for maintenance of station battery sets of power plant Details
  
8Tender for annual / running and breakdown maintenance of pipe lines Details
  
8Tender for annual repair and maintenance contract for electrical systems Details
  
8Tender for providing and fixing PUF panel operator cabin Details
  
8Tender for supply of electrical actuator Details
  
8Tender for supply of various types of pressure and temperature switches Details
  
8Tender for development of 2 Nos of bore wells for water supply Details
  
8Tender for annual maintenance of 04 (four) nos. of generating units Details
  
8Tender for repair of 02 KSB-manufactured 90 kW submersible pumps Details
  
8Tender for supply of material Details
  
8Tender for maintenance/operation of 33/11 kV sub-stations, associated HT/LT lines Details
  
8Tender for shifting and heightening of 11kV and LT lines including 11/0.4 kV DTRs Details
  
8Tender for biennial work contract for maintenance of ash handling plant Details
  
8Tender for renewal work with widening of existing Details
  
8Tender for work of attending hot-spots and oil DGA issues by modification of LV bushing internal connection Details
  
8Tender for empanelment of agencies for restoration of distribution infrastructure Details
  
8Tender for empanelment of contractors to award a contract for survey, installation, testing and commissioning of 33kV line Details
  
8Tender for work contract of day to day routine maintenance of 220kV and 400 kV switchyard, all HT and LT transformers, overhead line faults Details
  
8Tender for procurement of spares for caustic acid alum and polyelectrolyte dosind pumps installed Details
  
8Tender for const. of 33 kV S/S Details
  
8Tender for construction of power transformer and VCB foundation Details
  
8Tender for construction of store shed at 33 kV S/S Details
  
8Tender for construction of control room, water supply arrangement and yard levelling and gravelling work at 33 kV S/S Details
  
8Tender for roof leakage treatment, renovation Details
  
8Tender for purchase of 245kV 1250A motorized isolator Details
  
8Tender for purchase of 220V DC and 110V DC control and distribution board Details
  
8Tender for providing auxiliary earth mat at motorised isolator and earth switch mechanism point along Details
  
8Tender for construction of chemical earthing for towers along Details
  
8Tender for painting of HT and MS exposed steel structural tower member of 220 kV /132 kV LILO transmission line tower Details
  
8Tender for supply installation, connection and commissioning of 15 nos. bore type earth pit for improvement of earthing system of 50 MVA power with the work of pipe line Details
  
8Tender for complete overhauling of 132/33 kV 50MVA power transformer Details
  
8Tender for replacement of damaged cable hanger with providing perforated cable tray with cable tray support/fixture in 132 main and 132 kV side cable trenches Details
  
8Tender for repair and maintenance of grid control room at 400/220kV GSS Details
  
8Tender for work of aluminium and zinc chromat/phosphate based painting of rusted tower structure Details
  
8Tender for selection of cloud service provider for providing cloud infrastructure Details
  
8Tender for service contract for round the clock operation of 01 no. in motion weigh bridge Details
  
8Tender for Bi-annual maintenance contract of various equipments like dozers, DG sets, fire pump Details
  
8Tender for manufacture, testing, supply and delivery of 11 kV 200 A TPGO isolator with polymer post insulator. Details
  
8Tender for procurement of current transformers (400kV and 220kV C.T) Details
  
8Tender for supply of LT three phase channel cross arm Details
  
8Tender for supply of fixed contact for 11 kV AB switch Details
  
8Tender for supply of stay set complete Details
  
8Tender for supply of various sizes of MS bollt and nuts Details
  
8Tender for supply of HT /TI fitting and LT /TI fitting Details
  
8Tender for running works contract for effecting various works Details
  
8Tender for supply of HS type straight joint kit suitable for 33kV 1X630 sqmm XLPE UG cable Details
  
8Tender for supply of 11kV vertical type group operated AB switch with composite polymer insulators Details
  
8Tender for diversion of 220 kV transmission line Details
  
8Tender for maintenance/operation of 33/11 kV sub-stations Details
  
8Tender for maintenance/operation of 33/11 kV sub-stations, associated HT/LT lines Details
  
8Tender for supply and installation of pipe earthing Details
  
8Tender for supply and installation of pipe earthing in different capacity of DTRs Details
  
8Tender for electrical work for construction of 2X5 MVA 33/11 kV substation Details
  
8Tender for construction of 16.0 KM 33 kV line Details
  
8Tender for complete overhauling/maintenance work of 33 kV VCB’s panels Details
  
8Tender for complete overhauling/maintenance work of 33 kV VCB’s panels breakers complete unit) of different make installed Details
  
8Tender for complete overhauling/maintenance work of 33 kV VCB’s panels breakers Details
  
8Tender for regarding work shifting/displacement of 33 kV, 11 kV, LT lines Details
  
8Tender for work of providing and fixing of non-conductive turbo wind driven conical bird guards at various suspension tower Details
  
8Tender for AMC of optical fiber network and LAN for ERP and internet connectivity Details
  
8Tender for Bi-annual maintenance of NIFP system Details
  
8Tender for work of complete overhauling of 400kV breakers pole Details
  
8Tender for work of replacement of existing hanging/suspension type wave trap by new pedestal type wave trap along Details
  
8Tender for replacement work of 220kV GIS bays at 220 kV GIS substation Details
  
8Tender for work of servicing & overhauling along with providing & fixing of required spares of 245kV circuit breakers at various Details
  
8Tender for Bi-annual maintenance contract for work of repairs, servicing & alignment for 220kV, 132kV, 33kV isolators along Details
  
8Tender for work of providing and fixing of 33 kV current transformers at various sub-stations Details
  
8Tender for purchase of single phase SMC meter box Details
  
8Tender for purchase of LT shackle insulator Details
  
8Tender for supply and application of metal protective compound for various structure, pipes and duct Details
  
8Tender for supply of pre engineering shed for central store Details
  
8Tender for supply of ACB & panel spares Details
  
8Tender for supply of neutral grounding resistor Details
  
8Tender for supply and installation of an energy efficient lubricated rotary screw air compressor Details
  
8Tender for erection of new HT, LT line and transformer centers, replacement work, underground cabling work Details
  
8Tender for erection of 66kV Lilo line Details
  
8Tender for work of erection dismantling of 66kV/11KV equipment’s, structures, control wiring Details
  
8Tender for supply of fire system pumps Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8Jindal Steel Deploys Indigenous Coal Gasification in Global First for Steelmaking Details
 
8Coal Ministry unveils roadmap for sustainable mine closure Details
 
8India's renewable energy potential more than doubled in FY25: Mospi Details
 
8Coal ministry releases AAROH mine-closure report, signs EUR 10-million mine closure cooperation pact with GIZ Details
 
8India's steel ambitions face a coal reality check Details
 
8India's solar power boom faces regional imbalance, manufacturing glut Details
 
8The next farm revolution will hinge on energy economics, not just better seeds Details
 
8India’s Green Hydrogen Mission Gains Momentum Despite Capacity And Infrastructure Challenges Details
 
8India's Renewable Energy Capacity Nearly Quadruples To 288.58 GW Since 2014 Details
 
8Gautam Solar Earns EcoVadis Silver Medal, Ranks Among Top 15% Globally for Sustainability Details
 
8Power distribution, petroleum import going private Details
 
8Solar Cell Import Relief Stirs Concerns for Domestic Makers Details
 
8First Solar margin expansion draws analyst optimism despite solar sector downturn Details
 
8Delhi Launches Smart Substation, Rooftop Solar Drive To Strengthen Power Infra Details
 
8JSW Energy Q1 FY27 results: Net profit declines 36% to Rs 532 crore Details
 
8India's solar capacity to exceed coal by 200 GW by 2036: Pralhad Joshi Details
 
8How China and India are supercharging the battery storage market Details
 
8India’s geothermal energy dreams gather steam Details
 
8India’s Wind Power Capacity Rises to 57,443 MW, Ranks Fourth Globally Details
 
8Nuclear power capacity to reach 22 GW by FY32, says Jitendra Singh Details
 
8India's Solar Capacity Touches 162.15 GW As Renewable Push Gains Momentum Details
 
8MNRE adds Avaada, expands Fujiyama capacity under ALMM List-II Details
 
8Bajel Projects Concludes 500kV Transmission Line Agreement In Egypt Details
 
8Energy minister seeks proposals to privatise power distribution Details
 
8Adani Power Q1 PAT jumps 47% as higher power sales, tariff realisation boost earnings Details
 
8NLC India Raises INR 150 Crore Through Commercial Paper Issuance Details
 
8Adani Power shares down 2%: Q1 net profit rises 47%, power generation capacity hits 18,330 MW Details
 
8Telangana Withstands 7,000 MW ‘El Niño’ Power Shock, No Power Cuts Across State: Deputy CM Bhatti Vikramarka Details
 
You can also click on Newsclips for more Details

MNRE extends the ALMM solar-cell exemption to 31 December 2026, sparing rooftop and open-access projects

Jul 22: 8The renewable-energy ministry has pushed the deadline for mandatory use of listed domestic solar cells to 31 December 2026, from 31 May, for rooftop, net-metering and open-access projects. Utility-scale projects stay bound by the mandate, and everything must comply from 1 January 2027. Details

Daily Power Sector Tenders Excel update

Jul 22: 8Daily Excel covering new tenders and all published updates including corrigendum, amendment, addendum, clarification and status revisions, along with technical and financial bid opening, evaluation completion and final award actions including AOC and LOA issuance.
Click on Reports for more Details

POWER MARKETS DAILY

Jul 22: 8IEX day-ahead averaged Rs 6,617 on 21 July but held the Rs 10,000 ceiling in 54% of blocks
8Real-time power took the day's biggest volume - 192.70 MU - at a weekly-low Rs 4,143
8The green day-ahead cleared Rs 6,755 and term strips settled flat at Rs 6,350 - no green discount
8PXIL cleared nothing and HPX drew no buyers, so IEX carried the entire cleared market on 21 July
8DVC-style peak buying returns as GUVNL and UPPCL float HPX reverse auctions for evening blocks
8Rajasthan's merit order runs from Rs 0.99 at NLC Barsinghsar to Rs 27.87 for liquid-fuel peaking Details

GRID OPERATIONS DAILY

Jul 22: 8India met a 235,132 MW evening peak and a 237,218 MW day-max on 21 July with zero shortage
8The grid ran high a quarter of 21 July and the operators backed generation down by 51,305 MWh
8The North-East to Tripura corridor sat over its transfer limit for 51.9% of 21 July
8Gujarat alone curtailed 922 MW of solar and 353 MW of wind for grid security on 21 July
8The Northern grid switched out about 25 of its 765 kV bus reactors at dawn to hold voltage up
8India imported 51 MU from Bhutan and 22 MU from Nepal while wheeling power to Bangladesh Details

OUTAGE & MAINTENANCE REGISTER

Jul 22: 8About 43 GW of generation sat on outage on 21 July, the West carrying 18 GW of it
8Fresh 21 July trips took out Sasan 660 MW, Rihand-II 500 MW and a clutch of 200 MW units
8Yadadri's coal-starved 800 MW unit came back on 21 July; Ropar and Ghatampur stayed coal-hit
8North Chennai's 800 MW and Rajpura's 700 MW units stayed out on ESP and boiler faults
8Two Southern 400 kV corridors remain down two months after tower collapses in May
8Much of the 'outage' is economic reserve-shutdown - 2,700 MW of Western gas parked idle Details

FUEL & COAL LEDGER

Jul 22: 8Twenty-seven thermal plants ran coal-critical on 20 July; Damodaram Sanjeevaiah at 2%
8Coal ministry says 42 mines have been scientifically closed - a first since independence
8Fly-ash use hit 98.3% in 2024-25, but barely 1% of it moves by rail Details

HYDRO & RESERVOIR LEDGER

Jul 22: 8Telangana's Krishna reservoirs sit about 92% below last year deep into the monsoon
8Odisha's hydro fleet ran about 350 MW with several OHPC units forced out and reservoirs below last year
8Sikkim generated zero units on 21 July with the 1,200 MW Teesta-III still out since 2023 Details

CERC DOCKET

Jul 22: 8CERC proposes to grant PI Green Consulting a Category-V inter-state trading licence
8CERC clears POWERGRID's Mahan-Rewa transmission licence and rebukes Mahan Energen for non-compliance Details

STATE REGULATORY ROUNDUP

Jul 22: 8Uttarakhand's regulator clears a Kedarnath feeder after the fact and rebukes UPCL for jumping the gun
8Uttarakhand's ombudsman quashes a Rs 11 lakh back-bill and orders recovery from erring UPCL officers
8Bihar reserves one Section-142 order, lists two more and opens a supply code for sugar mills
8UP's regulator admits an Ayesha Steel removal-of-difficulty plea for a 20 August hearing
8Chhattisgarh's regulator takes up Jindal Steel's captive Raigarh ARR with a Rs 48 crore true-up gap
8Assam opens a public hearing on paying interest on consumers' security deposits
8Punjab's regulator advertises five deputation posts, including a secretary to the chairperson Details

GREEN MARKETS & RE PROGRAMME WATCH

Jul 22: 8MNRE extends the ALMM solar-cell exemption to 31 December 2026 for rooftop and open-access
8India's renewable capacity reaches 288.58 GW, four times its 2014 level, MNRE tells Parliament
8The power ministry halts two Tamil Nadu offshore-wind transmission projects
8India's battery-cell scheme has awarded 40 GWh but drawn zero incentive and Rs 5,180 crore of investment
8ACME Solar signs its 300 MW SECI hybrid PPA at Rs 3.25, lifting signed capacity to 6,870 MW
8Tripura's ADB-funded distribution plan pairs a 120 MW gas revamp with rooftop solar for weavers Details

CORPORATE WIRE

Jul 22: 8Adani Energy Solutions' Q1 profit doubles to Rs 1,237 crore
8Jharkhand's discom posts a Rs 1,839 crore half-year loss
8JSW Energy lifts its Toshiba-turbine stake to 20.7% as its GE Power India merger clears the vote
8BHEL's Trichy unit carries a Rs 43,927 crore order book as it lifts capex and nuclear supply
8Servotech's Q1 revenue jumps 66% to Rs 208 crore on solar, chargers and storage
8Viviana Power Tech commissions a 400 kV wind-evacuation line and carries a Rs 1,340 crore book
8REC floats a Maharashtra transmission SPV for a 400 kV Solapur switching station
8Kirloskar Electric flags going concern even as it turns a small profit and raises Rs 40 crore
8NLC India raises Rs 150 crore of commercial paper as the July results run fills the diary
8Ratings Watch - ICRA assigns 'A' to Blupine's 50 MW Karnataka solar group; reaffirms AA+ for Adani Energy Solutions Details

COMMITTEES, PEOPLE & SYSTEM ADMINISTRATION

Jul 22: 8The North-East's control-system bill jumps Rs 167 crore as its grid loses visibility
8Three regions' weekly settlements paid generators Rs 100 crore-plus of must-run
8Three inter-state lines were charged in June, but 54 of 86 remain behind schedule
8PSPCL ties promotions to strike-regularisation as its establishment churns through 50-plus officers
8Rajasthan's RVPN reopens employee pay-fixation and amends its 1964 service regulations
8SJVN's state-nominee director ceases office as PSU board seats turn over Details

Methane blast kills at least 20 at NHPC's under-construction Teesta-VI tunnel in Sikkim

Jul 22: 8A sudden burst of methane deep inside the head-race tunnel of NHPC's 500 MW Teesta Stage-VI project at Samardung touched off an explosion and toxic fumes shortly after 1 pm on 20 July, trapping 25 workers and project officers. By the morning of 22 July at least 20 were confirmed dead and a handful still missing, as rescue teams battled the same gas that caused the blast. Details

IEX day-ahead sat at the Rs 10,000 ceiling in 54% of 21 July's blocks yet crashed to Rs 1,618 at noon

Jul 22: 8The day-ahead market averaged Rs 6,617.61 a MWh on 21 July but sat pinned at the Rs 10,000 ceiling through the overnight and evening blocks, then collapsed to Rs 1,617.91 in the solar-flooded early afternoon. None of it was scarcity - the grid met a 235,132 MW evening peak with zero shortage; the crunch is the shape of the day, not a shortage of power. Details

The grid paid Western generators Rs 80 crore in one week to stay on the site as monsoon load slumped

Jul 22: 8The Western load-despatch centre’s security-constrained unit-commitment account for 6–12 July shows Rs 80.17 crore paid to keep coal and gas units committed and run up, led by Rs 14.98 crore to NTPC’s Khargone. In the same week the Eastern pool paid a further Rs 21 crore of must-run, Farakka alone drawing Rs 15.6 crore - the cost of holding thermal ready while midday solar forces it down. Details

Half of India's inter-state transmission build is late - Rajasthan and Khavda solar links slip up to six years

Jul 22: 8The CEA’s June progress report shows 54 of 86 under-construction inter-state transmission lines awarded through competitive bidding running behind schedule, many of them the very lines meant to evacuate Rajasthan and Khavda solar. Sterlite’s Goa–Tamnar link has slipped almost six years; a cluster of renewable-zone corridors is 12 to 24 months late. Details

Adani Energy Solutions' Q1 profit doubles to Rs 1,237 crore on a Rs 71,779 crore transmission pipeline

Jul 22: 8Adani Energy Solutions reported a consolidated first-quarter net profit of Rs 1,236.56 crore, up 129%, on income of Rs 9,852 crore and EBITDA of Rs 3,178 crore. It is carrying a Rs 71,779 crore under-construction transmission pipeline and has agreed to buy the IntelliSmart smart-metering platform outright for Rs 3,050 crore. Details

The North-East grid is going blind as its control-system bill jumps Rs 167 crore on AI-driven hardware prices

Jul 22: 8The North-Eastern committee’s papers for its 23 July meeting show the region’s new SCADA and energy-management build re-costed to Rs 688.61 crore from Rs 521.67 crore, a Rs 167 crore jump the committee blames on server and memory prices inflated by AI data-centre demand. At the same time real-time visibility of the grid has collapsed - Nagaland is telemetering under 30% of its data to the regional despatch centre. Details

Twenty-seven thermal plants run coal-critical in mid-monsoon - Andhra's Damodaram Sanjeevaiah down to 2%

Jul 22: 8National coal stock at power plants held about 40.75 million tonnes, roughly 13 days’ cover, on 20 July - but 27 individual plants were running critical, one more than a week earlier. Andhra’s Damodaram Sanjeevaiah was at 2% of its normative stock and JSW’s two Torangallu units were out of coal altogether. Details

Jharkhand's discom posts a Rs 1,839 crore half-year loss as its accumulated deficit nears Rs 18,330 crore

Jul 22: 8Jharkhand Bijli Vitran Nigam’s unaudited results, filed ten months late under the distribution-reform scheme, show a Rs 746.70 crore loss for the September quarter and Rs 1,839.02 crore for the half-year. Its accumulated deficit is close to Rs 18,330 crore and its power-purchase bill alone exceeds its revenue from selling electricity. Details

India's under-construction coal fleet swells to 42,700 MW even as this year's additions collapse to 2,260 MW

Jul 22: 8The CEA’s June thermal status report shows 42,700 MW of coal capacity under construction, all supercritical, against a further 21,380 MW stalled or stressed. Yet only 2,260 MW of a 7,300 MW target has been commissioned this year - and most fleet growth now comes through insolvency buyers, not greenfield builds. Details

Contracting news for the day: Part-1

Jul 22: 81. PSTCL floats 90-day civil works tender for 160 MVA transformer at 220 kV Bathinda substation
PSTCL has published a notice inviting tender for civil works connected with a 160 MVA transformer at its 220 kV GNDTP Bathinda substation, with a compressed 90-day completion window and quoted rates valid for 120 days. Tender documents will be issued only to firms the corporation considers adequately experienced, though no qualification formula is disclosed. A striking drafting anomaly sits inside the notice: the document-issue deadline falls after the bid-submission deadline. Unless corrected, the timetable is internally unworkable and could undermine competitive participation.

 

82. UJVNL packages river diversion, tunnelling and powerhouse into single Rs 87.90 crore Tankul hydro contract
UJVN Limited has invited online bids for constructing the 12 MW Tankul small hydro project in Pithoragarh, combining trench weir, intake, river diversion, desilting tank, tunnel, surge shaft, powerhouse and hydro-mechanical works in one mandate. The submission deadline has moved by 25 days through two extensions alongside two corrigenda, signalling the package required correction before closure. Bidders must price geological uncertainty, river behaviour and remote Himalayan logistics into a compact contract value. The project's execution complexity far exceeds its modest installed capacity.

 

83. BSPGCL couples 150 MW solar with 75 MW/300 MWh battery in tariff-based bid with capacity-linked EMD
Bihar State Power Generation Company has issued an NIT to develop 150 MW of solar PV integrated with a four-hour battery system through tariff-based competitive bidding followed by e-reverse auction. The EMD scales at Rs 14.24 lakh per MW quoted, discouraging speculative capacity offers, while the original bid-security instrument must physically reach BSPGCL despite an otherwise digital process. Battery degradation, augmentation and charging rules — central to project economics — are left to the detailed documents. The outcome could set an early state benchmark for solar-plus-storage pricing.

 

84. HPSEBL seeks Rs 3.72 crore project management consultant under QCBS — then adds a reverse auction
HPSEBL has floated an RFP for a project management agency to support its reforms-linked distribution scheme, deploying 246 expert man-months across engineering review, field monitoring and funding-claim support, with the deadline extended by ten days. Selection follows a 70:30 quality-cost formula, yet the notice simultaneously announces an e-reverse auction — an unresolved structural clash. A Rs 70 crore annual turnover threshold towers over the modest assignment value, favouring large national consultancies. HPSEBL also retains the right to double expert deployment in every category, shifting staffing risk onto the consultant.

 

85. OCPL hands one consultant the entire blueprint for its 5 MTPA Manoharpur coal washery
Odisha Coal and Power Limited is appointing a single adviser to prepare the DPR, washability study, CAPEX-OPEX-IRR modelling and the complete EPC tender architecture for a proposed 5 MTPA coal washery, with the deadline extended by 18 days after the original schedule lapsed. The washability study must run through one of six named institutions, tying a core milestone to external laboratories. Joint ventures are barred, concentrating all credentials in one entity, while least cost selection meets a strict abnormally-low-bid clause that can exclude aggressive quoters from retenders. The 120-day programme leaves little slack for approval cycles.

 

86. GSECL's Rs 4.73 crore covered-conductor retrofit at Ukai TPS carries a 36-month owner-controlled execution horizon
GSECL has floated an open three-stage e-tender to replace 16 km of exposed 11 kV conductors at Ukai Thermal Power Station with medium-voltage covered conductors, including eight double-pole air-break switch structures and dismantling of old lines, as an indivisible supply-plus-works package. Supply must finish in six months, but the work order stays valid for 36 months — extendable by six more at unchanged prices. Thirty per cent of supply value remains locked until successful charging, tying contractor cashflow to shutdown availability. With no guaranteed work-release schedule, bidders are pricing a long-duration call-off obligation, not a fixed-schedule job.

 

87. MSEDCL extends commencement window but holds commercial line on Rs 130.38 crore STAR-II transformer buy
MSEDCL has issued Amendment No. 1 with pre-bid clarifications on its tender for 200 kVA STAR-II CRGO distribution transformers, extending the commencement period from two to three months while keeping the nine-month delivery schedule intact. Manufacturer requests for revised estimated cost, IEEMA price variation, relaxed experience thresholds and softer security terms were all rejected, while BEE certification was confirmed as not required for 22 kV units. The amendment signals selective operational flexibility without commercial concession. Certification-heavy entry barriers remain firmly in place for smaller suppliers.

 

88. POWERGRID engages exclusive land valuer for 219 km transmission corridor in Morbi under package-wise GeM bid
POWERGRID has invited a two-packet GeM bid to appoint a land valuer for transmission-line corridors in Morbi district under Package-7, covering roughly 219 km, with the consultant certifying survey-number-wise market rates for compensation and acquisition. The valuer must work exclusively for POWERGRID and is barred from representing any other project stakeholder — a stronger conflict-management measure than routine consultancy tenders carry. The district-wise package model spreads work across Gujarat while limiting how many packages one bidder can secure. The tender treats land valuation as project-critical infrastructure work rather than conventional advisory service.

 

89. NREDCAP offers 22-year DBFOT concession for Rs 324.70 crore Vijayawada waste-to-energy plant
NREDCAP, acting for Vijayawada Municipal Corporation and participating urban bodies, has issued an RFP for a private concessionaire to design, build, finance, operate and transfer a 15 MW municipal-waste-based power plant under a 22-year concession including two years of construction. The Rs 3.24 crore EMD and qualification framework point toward experienced infrastructure developers rather than general EPC contractors. Financing strategy and long-term operating assumptions will matter more than EPC pricing in determining competitiveness. The structure reflects a policy preference for private lifecycle ownership of complex municipal processing assets.

 

810. NTPC Ramagundam to double transformer capacity with 500 MVA units under integrated 30-month contract
NTPC has invited domestic bids to replace two 250 MVA auto transformers at Ramagundam with 500 MVA interconnecting units, bundling design, manufacture, transport, oil treatment, erection and commissioning into one accountability chain over 30 months. An unusual clause forces installation pricing into a 10–15% band of supply value, blocking payment-structure engineering. Loss penalties reach Rs 10 lakh per kW for no-load deviation — with no reward for overperformance — while the variable-price contract offers only narrow escalation relief. A Rs 1 crore bid security applies with no MSE exemption.

 

811. BHEL's 400 kV GIS package for Yamuna Nagar loads firm pricing, reverse auction and long-tail liabilities onto suppliers
BHEL is procuring a complete 400 kV gas-insulated switchgear installation for HPGCL's 800 MW ultra-supercritical expansion at Yamuna Nagar, with the deadline extended twice after a technical corrigendum rewrote testing, transport, packing and scope-boundary provisions. Prices stay firm across a 12-month supply cycle, while the 18-month warranty starts only after project trial operation — a milestone outside the supplier's control. Entire specification clauses were deleted without replacement, creating interpretation gaps, and packing must survive 24 months of outdoor monsoon exposure. Impact recorders must trace every shock from factory to site, with a reverse auction awaiting qualified vendors.

 

812. NTPC Talcher Kaniha's Rs 84.81 crore ash-backfilling contract pays only the lower of two measurements
NTPC has floated a GeM bid restricted to its enlisted ash-transport vendors for excavating, hauling and compacting ash from Talcher Kaniha into quarries and mine voids 50–100 km away, under a 12-month contract splittable 50:50 between two bidders. Payment follows the lower of dispatch-end or filling-site measurement, and every truck movement needs weighbridge, GPS, FASTag, toll and geotagged photo evidence uploaded daily — incomplete records mean withheld payment. A quantity mismatch between the scope figure and doubled BOQ entries demands careful reconciliation. Regulatory penalties on NTPC flow back entirely to the contractor, converting a transport job into a full land-reclamation obligation.

 

813. AEGCL's fixed-price 220 kV line for TATA semiconductor plant transfers all design-modification costs to the contractor
Assam Electricity Grid Corporation has published a turnkey tender for a 220 kV Sonapur-TSAT double-circuit line providing redundant power to the TATA semiconductor facility, spanning overhead line, underground cable, optical fibre and commissioning under single-point responsibility within 24 months. There is no advance payment and no escalation: AEGCL supplies the base design, but site-driven modifications — special towers, pile foundations, raised chimneys — must be executed at zero additional cost. The warranty runs five years from supply or four-and-a-half from commissioning, whichever is later, with liquidated damages at 1% per week up to 10%. Payments can take 60 days, subject to fund availability.

 

814. Powergrid caps land valuers at one package each across ten-district Gujarat valuation drive
Powergrid has issued a GeM bid for an IBBI-recognised land valuer covering 246 tower locations across 91.74 km spanning three transmission SPVs in Vadodara district, one of ten sequentially opened packages, with every assignment due within 15 days of intimation. A "one agency, one package" rule prevents any single firm from dominating, while packages with three or fewer bidders jump the price-opening queue. No escalation applies, quantities can swing 25% either way, and the bid summary denies arbitration even as attached conditions prescribe a full arbitration regime. Consistency across multiple independent valuers remains the unaddressed governance risk.

 

815. JREDA opens Jharkhand's 16-site hydro pipeline to solar, wind and thermal players through eligibility rewrite
JREDA has issued an EOI to identify developers for small hydro projects across 16 Jharkhand sites under the BOOT model, beginning with surveys and DPRs before full development, financing and long-term operation. Corrigendum-I broke the hydro-only entry barrier: any 5 MW DISCOM PPA — solar, wind or thermal — now qualifies, provided the bidder operates a plant in the supplying state, with the deadline extended by 14 days. A Rs 50 crore turnover floor screens for balance-sheet depth over technical pedigree. Concession terms, tariffs and free-power obligations are deferred entirely to the RfP stage, making second-stage evaluation the critical safeguard.

 

816. UJVNL's Sirkari Bhyol hydro tender swells 53% to Rs 243 crore through twenty corrigenda
UJVN Limited's EPC tender for the electromechanical works of the 3x40 MW Sirkari Bhyol Rupsiabagar project has been transformed through twenty corrigenda and seven addenda: the estimated value jumped 53% to Rs 243.05 crore, the EMD rose to Rs 4.87 crore, and every qualification threshold was rewritten upward. Technical access simultaneously widened through a fifteen-year experience window, more approved component makes and flexible efficiency testing, even as financial entry tightened. Himalayan logistics, construction power and site utilities stay contractor-facing despite repeated bidder requests for relief. Bidders must hold prices for 270 days on a package still being stabilised months after publication.

Details

Download tenders and news clips

Jul 22:  For reference purposes the website carries here the following tenders:
 8Tender for supply and installation of digital type loadcell based overload and slack protection me chanism for various hoists gantry cranes installed Details
 8Tender for work of supply of T and P (tools and plants) materials Details
 8Tender for work of providing and erection of additional poles Details
 8Tender for work of replacement of old PVC cable with new PVC armoured cable Details
 8Tender for R&M works including supply and installation of 11 kV indoor VCB panel Details
 8Tender for erection, dismantaling and maintenance of HT/LT and transformer Details
 8Tender for annual rate contract (ARC) for LED lights & related spares items Details
 8Tender for annual rate contract for various types of structural steel items. Details
 8Tender for NDCT overhauling works Details
 8Tender for procurement of CW pump mechanical seals Details
 8Tender for procurement of galvanized gratings and end bar Details
 8Tender for hot line stringing of 66 kV line Details
 8Tender for dismantling of existing fencing and installation of new main gate along Details
 8Tender for procurement of cable termination kit Details
 8Tender for material handling and management including receipt, unloading, verifying, shifting, stacking, preservation, handling and handing over of components of boiler with auxiliaries Details
 8Tender for modification of steam generator (boiler) of 210 MW for comprehensive work Details
 8Tender for replacement work of old main switch, fuse unit etc. Details
 8Tender for renovation of control room at 110 kV substation Details
 8Tender for shifting of electrical utilities in connection Details
 8Tender for supply of 3 nos digital insulation resistance tester Details
 8Tender for procurement of 180KW, 3.3kV HT motors Details
 8Tender for R and M of existing fire detection and protection system Details
 8Tender for replacement of existing 250MVA auto transformers with 500MVA transformer Details
 8Tender for housekeeping work of 2x150 MVA 220/ 132kV grid sub station Details
 8Tender for supply of wall soot blower and oil gun spares for boiler Details
 8Tender for supply, erection and commissioning of various accessories of conveyor belt Details
 8Tender for construction of yard work and misc. civil works at 33kV S/S Details
 8Tender for construction of control room, cable trench, water supply arrangement at 33 kV s/s Details
 8Tender for purchase of spares for 420kV, 3150A, TP, HCB isolators with earth switches Details
 8Tender for procurement of spares for BHEL make DVAR Details
 8Tender for supply, erection & commissioning of 11 kV lines with MVCC conductor & dismantling of existing Details
 8Tender for supply, erection, testing and commissioning of 220 V DC, 63 AH, KPH 63P, Ni-Cd type battery set Details
 8Tender for biennial rate contract for motor or heavy equipment lifting or shifting or placement and motor coupling fitting works Details
 8Tender for execution erection work for effecting the 33kV bulk NSC by laying UG 33 kV 3CX400 SQMM XLPE cable Details
 8Tender for execution of erection work by erection of 11KV RMU, laying of 11kV XLPE UG cable, laying of HDPE pipe Details
 8Tender for round the clock maintenance for routine breakdown and preventive maintenance of 4 x 9 MW and 2 x 4 MW TG sets with all auxiliaries 66 kV switchyard Details
 8Tender for electrical work for construction of 2X5 MVA 33/11 kV S/S Details
 8Tender for construction of 26 KM.33kV line Details
 8Tender for providing and fixing of insulated sheet for ST pole Details
 8Tender for work of replacement of old PVC cable with new PVC armoured cable Details
 8Tender for work of installation of one No. 5 MVA power transformer at 33/11 kV sub-station Details
 8Tender for providing and fixing of insulated sheet Details
 8Tender for providing and fixing of insulated sheet for ST pole Details
 8Tender for work of overhauling, servicing & repairing work of 400kV circuit breaker Details
 8Tender for work of bi-annual maintenance contract for the work of servicing, repairing of various size and capacities battery sets and chargers Details
 8Tender for supply of 5nos spare numerical distance protection relay Details
 8Tender for refilling, servicing & maintenace, supply of spares for fire extinguishers at various substations Details
 8Tender for work of feeder re-orientation at 110kV & 220kV substation Details
 8Tender for work of supply & installation of advance cable transit system by passive fire screen Details
 8Tender for work of fabrication and supply of 50 kL empty oil tank Details
 8Tender for AMC for battery sets maintenance work (220 volts & 48 volts) and charger Details
 8Tender for annual maintenance contract for repairs, overhauling of 33 kV VCB installed Details
 8Tender for work of providing & fixing of maintenance free earthing at 220 kV line Details
 8Tender for supply of pressure relay of converter transformer Details
 8Tender for work of supply and installation of bird diverters (BFD) on 132kV DC transmission line Details
 8Tender for conversion of existing indoor SF6 & VCB AIS switchgear panels pertaining Details
 8Tender for rate contract of excavation and laying of new power / control / telephone cables Details
 8Tender for supply and application of epoxy glass flake coating with UV resistance PU top coat on various external surfaces Details
 8Tender for supply of control panel spares of pump house Details
 8Tender for R&M work of erection, commissioning of new feeder bay HV & LV equipment’s, testing ,earthing,control wiring etc. of 220/66kV 160 MVA transformer Details
 8Tender for erection and maintenance of HT/LT & TC work Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8
India’s Coal Mine Closure Report and GIZ Agreement Explained Details
 
8Bharat Coking Coal shares drop over 7% after Q1 net loss, lower offtake Details
 
8India’s Coal Self-Reliance Push: Govt Takes Major Steps to Boost Production and Reduce Imports Details
 
8Coal Ministry to Sign MoUs for Sustainable Mine Closure, Jharia Rehabilitation and Skill Development Details
 
8SECL Plants 3.20 Lakh Saplings in a Day, Builds Bilaspur’s First Miyawaki Forest for Greener Future Details
 
8Pumped hydro storage of 16 GW capacity under construction: Power Ministry Details
 
8Core sector growth reaches five-month high in June, lifted by iron ore and power Details
 
8PM-KUSUM's Missing Link: Why India's Solar Pump Success Isn't Yet an Agricultural Energy Revolution Details
 
8Power discoms await revival as structural reform delays persist in India Details
 
8Major Boost to Island Energy Security as 50 MW LNG Power Project Moves Forward Details
 
8Why Storage Hydropower Must Become Nepal's Next National Priority Details
 
8India Reaches 548.85 GW Power Capacity As Renewables Account For 43.09%, And Solar Hits 162 GW Details
 
8Tata Power wins 324 MW SECI pumped hydro project Details
 
8India tunnel collapse at a hydropower project kills 10 as 17 remain missing Details
 
8Transformers & Rectifiers India Reports 8% Q1 FY27 Revenue Growth, Order Book Reaches Record INR 6,630 Crore Details
 
8MAHLE Unveils Range Extender and Magnet-Free Motor for Heavy Commercial Vehicles Details
 
8India’s clean energy boom: Why the City of London should be paying attention Details
 
8India’s Renewable Energy Generation Crosses 100 GW for the First Time Details
 
8Stocks to Watch: Adani Power, Eternal, and 6 Other Stocks Announcing Q1 Results Today Details
 
8India’s renewable energy capacity jumps nearly to 288.58 GW Details
 
8Kolkata Power Network Eyes Digital Meter Expansion Details
 
8EAC-PM Report Flags India's Power Grid Vulnerability Details
 
8NLC India Raises Rs 150 Crore Through Commercial Paper Issue to Boost Liquidity and Support Growth Plans Details
 
8India Allows 4 Chinese-Linked Firms to Bid on Power Projects Details
 
8India Signs Major Nuclear Technology MoU: NPCIL and ECIL to Develop Critical Systems Details
 
8ACME Solar signs PPA with SECI for 300MW ISTS-connected Wind-Solar Hybrid Renewable Energy Project Details
 
8REC Signs Agreement with RITES to Ensure Quality Checks of Power Transformers Under RDSS Details
 
8J&K Readies 1,624 MW Hydropower Units by December 2026 Details
 
You can also click on Newsclips for more Details

Hydro & Reservoir Ledger

Jul 21: 8Telangana’s Krishna-basin storage has collapsed about 92% year on year, Srisailam and Nagarjunasagar near-empty
8Odisha hydro ran about 528 MW on 19–20 July with several OHPC units forced out and reservoirs below last year Details

Eastern thermal earned about Rs 112 crore in June for running part-loaded - the same stations were also failing their frequency duty

Jul 21: 8Beneficiary states under-requisitioned below 85% of their entitlement, forcing nine Eastern-region thermal stations to run at part load, and the compensation bill for it reached about Rs 111.9 crore for the fiscal year to June. The stations that ran part-loaded also posted the region’s weakest frequency-response scores, so the pool is paying twice - once in compensation, once in lost grid support. Details

Day-ahead power hit the Rs 10 ceiling overnight and at dusk on 20 July - yet the grid met a ~239 GW peak nearly shortage-free

Jul 21: 8The day-ahead market averaged Rs 6,801 a MWh on 20 July but sat at the Rs 10,000 ceiling through the overnight hours and again in the evening, then collapsed to about Rs 1,815 in the solar-flooded middle of the day. None of this was scarcity - the grid met a roughly 239 GW peak with barely a megawatt-hour of shortage; the crunch is the shape of the day, not a shortage of power. Details

The North met a 93,981 MW summer peak nearly shortage-free - but a single wind trip cost Rajasthan 1,290 MW

Jul 21: 8The Northern Region’s peak demand climbed through the June quarter to 93,981 MW and was met with under half a percent of shortage, with Uttar Pradesh the only state left short. Yet the quarter also shows how thin the margins are: single elements swung a gigawatt at a time. Details

Jaiprakash Power’s Q1 profit jumps 69% to Rs 469 crore as NARCL files insolvency over a Rs 1,239 crore guarantee

Jul 21: 8Jaiprakash Power Ventures reported a standalone Q1 profit of Rs 468.95 crore, up 69% year on year, even after absorbing a Rs 193.63 crore exceptional loss. In the same disclosure it flagged that NARCL has filed a Section 7 insolvency petition against it over a Rs 1,239 crore corporate guarantee - the overhang that now prices the stock. Details

MERC lets Adani’s Mumbai discom adopt Rs 6.38 a unit for 750 MW of round-the-clock renewable power

Jul 21: 8The Maharashtra commission allowed Adani Electricity Mumbai’s distribution arm to adopt a Rs 6.38 a unit tariff for 750 MW of round-the-clock renewable power under a ten-year deal, undercutting MSEDCL’s own effective benchmark. It is a signal on where firm-renewable pricing is settling. Details

India’s pumped-storage build-out reaches 15,870 MW under construction as SECI awards another 1,344 MW

Jul 21: 8The power ministry told Parliament that 11 pumped-storage projects totalling 15,870 MW are under construction, with a further 24,010 MW in the pipeline. In the same week SECI’s first pumped-storage tender awarded 1,344 MW of a 1,500 MW offer, confirming the shift from policy to procurement. Details

Twenty-six thermal plants sit critical on coal in mid-monsoon - Andhra’s Damodaram Sanjeevaiah down to 2%

Jul 21: 8National coal stock at power plants held about 41 million tonnes, or roughly 21 days, on 19 July - but 26 individual plants were running critical, with Andhra’s Damodaram Sanjeevaiah at just 2% of its normative stock. The average hides a distribution problem, not comfort. Details

Punjab’s power employees and pensioners strike for two days, forcing PSPCL to draft engineers to man substations

Jul 21: 8PSPCL’s own management circulated an order on 20 July confirming that a joint front of power employees and pensioner bodies will hold a statewide protest and mass leave on 21–22 July, with pensioners threatening a “jail bharo” agitation. Chief engineers have been told to ensure every substation is manned through the stoppage. Details

Maharashtra’s new RE policy blocks MERC from ordering MSEDCL to buy Waterfront’s small-hydro - even after fixing its Rs 6.18 tariff

Jul 21: 8MERC determined a tariff of Rs 6.18 a unit for Waterfront’s 3 MW small-hydro project but refused to direct MSEDCL to sign a power-purchase agreement, because Maharashtra’s March 2026 renewable-energy policy dropped the procurement mandate. The regulator fixed the price and then found it could not compel the sale. Details

About 40 GW sat on outage on 20 July as North Chennai lost 800 MW and Rajpura 700 MW to boiler and ESP faults

Jul 21: 8Generation outages ran to about 40 GW across the northern, western and southern registers on 20 July, and the day added fresh forced trips - North Chennai’s 800 MW unit hand-tripped on an ESP problem and Rajpura’s 700 MW unit on a boiler-tube leak. This parked baseload is the other half of the day’s price story. Details

Power Markets Daily

Jul 21: 8Day-ahead power averaged Rs 6,801 a MWh on 20 July but sat at the Rs 10,000 ceiling overnight and at dusk
8Real-time power cleared just 3.34 MU at the Rs 10,000 ceiling; the green, intraday and ancillary segments did not clear
8Term and green contracts settled around Rs 7,500 a MWh as the high-price exchange (HPX) day-ahead did not clear on 20 July
8DVC floats an August reverse auction for two 100 MW thermal bands across the exchanges, e-auction 22 July Details

Grid Operations Daily

Jul 21: 8All-India peak of about 239,106 MW was met on 20 July with roughly 1 MU of shortage
8The grid ran high 28% of 20 July - 6.75 hours outside the IEGC band, peaking at 50.251 Hz
8Rajasthan and the NR–ER corridor breached their transfer limits about 20% and 17% of 20 July
8Maharashtra shed about 0.195 MU on 20 July when a 132 kV line overloaded and grid-security load-shedding operated
8The Northern grid met a 93,981 MW June-quarter peak nearly shortage-free Details

Outage & Maintenance Register

Jul 21: 8About 40 GW sat on outage on 20 July; North Chennai 800 MW and Rajpura 700 MW tripped
8Further 20 July trips took out KSTPS 500 MW, Meenakshi 350 MW, Paras, Neyveli, Ukai and Tuticorin units
8Yadadri’s 800 MW unit has been out on coal shortage since 9 July; ACBIL 135 MW out on coal since 12 June
8The 765 kV Ariyalur–North Chennai line was still out late on 20 July after a fault; a Gadarwara 765 kV line faulted
8Champa’s 400 kV bays were out on station flooding and Vindhyachal HVDC Pole-1 had tripped in the West
8The northern and western transmission registers ran to 538 and 422 elements on 20 July, storm-collapse lines still standing Details

Fuel & Coal Ledger

Jul 21: 8Twenty-six thermal plants ran coal-critical on 19 July; Damodaram Sanjeevaiah at 2%
8The Ministry of Coal advances a Rs 37,500 crore gasification scheme, applications closing 7 September
8Thermal plants held 42.8 MT of coal and 14 days’ cover as coal supplied 69.5% of Q1 power, the ministry told Parliament
8Delhi’s Pragati gas plant ramped spot RLNG offtake about six-fold into the summer, its bill reaching Rs 85.9 crore a fortnight Details

Daily Power Sector Tenders Excel update

Jul 21: 8Daily Excel covering new tenders and all published updates including corrigendum, amendment, addendum, clarification and status revisions, along with technical and financial bid opening, evaluation completion and final award actions including AOC and LOA issuance.
Click on Reports for more Details

CERC Docket

Jul 21: 8CERC cut NTPC’s decommissioned Talcher 460 MW annual charge to Rs 475 crore and disallowed most residual capex
8CERC shielded SJVN Green’s 860 MW connectivity from CTUIL revocation and barred encashment of its bank guarantees
8CERC reserved orders on THDC’s water-tax change-in-law claim for the Tehri and Koteshwar hydro stations
8NEEPCO sought a cut in its Tripura gas station’s availability norm to 70% as ONGC gas supply more than halved
8PSPCL and Pragati Power head to a 13 August hearing over a Rs 82.99 crore Pragati-III billing dispute
8CERC reserved a ruling on whether it can hear the TNPDCL–PTC 150 MW pilot-power dispute at Rs 3.26 a unit
8CERC admitted six NLDC and RLDC fee truing-up petitions for 2019-24 and issued notices
8Trading-licence moves: CERC reserved Infinite Voltx’s Category V grant and sought RPG Power Trading’s accounts
8CERC docket calendar - Kishtwar Transmission security interest admitted, UPPCL water-tax amendment allowed, ISTS-charge batch adjourned
8APTEL’s Court-I and Court-II carried 257 and 27 short matters and over 1,670 final appeals as on 17 July
8GERC cleared VMS TMT’s 11.88 MW solar connectivity but refused Iran-conflict force majeure; adjourned Gujarat discoms’ net-metering plea Details

State Regulatory Roundup

Jul 21: 8MERC let Adani’s Mumbai discom adopt Rs 6.38 a unit for 750 MW round-the-clock renewables
8MERC suspended MSEDCL’s power to seize an under-used consumer feeder and ordered Rs 45 lakh compensation
8MERC ordered MSEDCL to pay Vena Energy Rs 11.42 crore in late-payment surcharge and interest on wind dues
8MERC cleared a provisional tariff for Adani’s Rs 6,888 crore 1,000 MW HVDC link, trimming the claimed cost
8Maharashtra’s RE policy blocked MERC from ordering MSEDCL to buy Waterfront’s small-hydro
8MERC dismissed about 1,959 MW of NOPL solar change-in-law claims for non-appearance and closed a settled Talf Solar guarantee dispute
8Bihar’s regulator set FY27 biomass and bagasse tariffs and restored them retrospectively to 1 April
8CSERC let Shree Cement raise its Chhattisgarh contract demand to 51 MVA at a 5% energy surcharge
8Assam’s regulator holds a public hearing on the 8th amendment to its electricity supply code
8Tamil Nadu’s electricity ombudsman part-voided a Rs 2.73 lakh back-billing on a defective meter Details

Green Markets & RE Programme Watch

Jul 21: 8Renewables met about 38% of demand at midday on 20 July, solar peaking at 69.1 GW
8SECI awarded 1,344 MW of pumped storage as the national build-out reached 15,870 MW
8BNC Power won SECI’s 10 MW Odisha solar tender at Rs 2.60 a unit with zero viability-gap funding
8ACME Solar signed a 300 MW hybrid PPA at Rs 3.25 and commissioned 160.5 MWh of Rajasthan battery storage
8KPI Green commissioned 200 MW of Coal India’s 300 MW Khavda solar and won charging nod for a 100 MW Maharashtra plant
8MNRE sanctioned a Rs 436.93 crore renewable R&D programme with a Rs 200 crore perovskite pilot line
8SECI opened an EOI to aggregate bulk renewable off-takers and set a 3 August site visit for a 45.6 MW wind EPC Details

Corporate Wire

Jul 21: 8Jaiprakash Power’s Q1 profit rose 69% to Rs 469 crore as NARCL filed insolvency over a Rs 1,239 crore guarantee
8Transformers & Rectifiers’ order book hit a record Rs 6,630 crore as Q1 inflows surged 218%
8GE Power India’s shareholders and creditors met to clear its absorption into JSW Energy
8ICICI Direct rated BHEL a Buy at Rs 575 on a record Rs 2.6 lakh crore order book
8Nava lifted its FY26 dividend to a record Rs 8.50 as Zambia arrears fell to US$28 million
8Corporate diary - JK Cement Q1 profit slips 12% to Rs 291 crore; Premier Roadlines books Rs 182 crore of power orders
8Smaller filings - CLN Energy reprices a promoter issue to Rs 423; Pace Digitek’s Lineage ties up AI-data-centre power; L&T bags mega metals EPC
8Results and board diary - Waaree Renewable, Indosolar and RattanIndia Power report over 23–24 July Details

Committees, People & System Administration

Jul 21: 8Punjab’s power employees and pensioners strike on 21–22 July, forcing PSPCL to man substations
8The Eastern committee’s June settlement run put about Rs 112 crore of part-load compensation across nine stations
8The Eastern frequency scorecard ranked PVUNL (0.33) and JIPL (0.41) the region’s weakest responders in June
8PSPCL reshuffled 16 senior officers and about 25 substation engineers and sanctioned posts for a new 66 kV grid
8PSPCL’s CMD leads a team to POWERGEN India as the utility revises induction and training rosters
8Mahatransco named 28 apprentices for its 2026-27 intake at Nagpur Details

Contracting news for the day: Part-1

Jul 21: 81) APGENCO's Dr NTTPS meter tender carries three conflicting reference numbers and four different bid-closing times The portal cites M100030900/P41 while the NIT and enquiry use P211 and a longer CE/O&M reference. Submission deadlines shift across 12:00, 13:00, 14:00 and 15:00 hrs depending on the document read. Latest: price-bid opening has been fixed, following the enquiry letter's own submission and opening timing.

 

82) OPTCL's Rs 256.29 crore Pahala tender makes one EPC contractor own a new GIS, a 9.94-km line and two live-station bay extensions The turnkey scope stitches the new GIS to Balianta through one integrated commissioning obligation. EMD is Rs 97.23 lakh. Latest: bids have closed and techno-commercial opening has taken place, with the price-bid date still pending.

 

83) A second APGENCO filing recasts the same NTTPS meter package as a straightforward digital-metering upgrade Scope bundles Secure-make ABT meters, RS-485/Modbus communication, HMI software and full commissioning into one contract. Eligibility favours manufacturers/dealers with PSU or utility metering experience. Latest: presented under a single, unconflicted P211 reference.

 

84) TGGENCO's 42-lakh-tonne coal haulage tender keeps daily quantity unguaranteed while penalising monthly shortfalls Bidders must move ~15,000 tonnes/day with GPS-fitted, dual-end-weighed tippers. Only 30% of the rate is diesel-linked; 70% stays fixed. Latest: the tender has opened, with pre-qualification bid opening due ahead of the price-bid opening.

 

85) MSEDCL's Rs 215.89 crore transformer tender softens qualification but holds firm on price and delivery 33/11 kV experience now counts toward the rarer 33/22 kV and 22/11 kV variants, and their type-test reports can follow bid submission. The nine-month delivery and 66-month warranty stay unchanged. Latest: Amendment No. 1 has been issued, extending the bid deadline.

 

86) POWERGRID gates its 765kV Bikaner substation package behind a mandatory NDA before releasing bid documents The package supports the Rajasthan REZ Phase IV evacuation corridor. Bidders must clear an eligibility and confidentiality screen before seeing specifications or pricing. Latest: the Invitation for Bids has been published, with bid submission and opening still ahead.

 

87) NTPC extends bidding on its Farakka generator-transformer replacement without touching scope or terms The 250 MVA transformer package covers design through commissioning under one 30-month contract. Bid security is Rs 50 lakh with a mandatory Integrity Pact. Latest: an extension notice has revised the bid submission and opening schedule, with scope and terms unchanged.

 

88) AEGCL's Sonapur–TSAT line for TATA Semiconductor pushes site-driven design changes into the contractor's fixed price The Rs 1.57 crore-EMD, 24-month turnkey package spans towers, pile foundations, 220 kV cable and underground OFC. Warranty runs 60 months from supply or 54 from commissioning. Latest: the tender has been published, with bid submission, closing and technical opening still ahead.

 

89) NHPC's Sawalkot dam package jumps 5.6% in value after a capacity correction and 123 days of deadline extensions The estimate rose from Rs 5,129.03 crore to Rs 5,416.94 crore after fixing capacity from 1,856 MW to 1,800 MW. Turnover and working-capital thresholds rose in step. Latest: Corrigendum 10 has fixed the online submission date, with hard-copy submission and techno-commercial opening following shortly after.

 

810) NTPC's Pudimadaka green-urea plant links a Simhadri CO2 unit to five process blocks across two sites under one lump-sum price Carbon capture at Simhadri feeds hydrogen, ammonia and urea production 25 km away at Pudimadaka, all under one lump-sum contract. Bid security is Rs 20 crore, shareable among consortium partners. Latest: Date Corrigendum 02 has moved the submission/opening deadline forward again, following Commercial and Technical Amendments.

 

811) NHPC's Rs 5,541 crore Kamala Lot-1 bundles dam, diversion tunnels and hydro-mechanical works into one civil package The 1,720 MW project in Kamla district combines diversion tunnels, cofferdams, the dam and access roads/bridges. EMD is Rs 10 crore against a 2,372-day execution period. Latest: document download and bid submission remain open, with bid opening scheduled shortly after.

 

812) NTPC's 200,000-unit limestone GeM tender splits award among four suppliers with freight dwarfing the material cost Balajee Steel Udyog took 75,000 tonnes; three others split the remaining 25,000 tonnes. All contracts land at Rs 3,960/tonne, Rs 740 material plus Rs 3,220 freight. Latest: award has been finalised, with contracts running over a one-year supply period.

 

813) GUVNL's short-term power RFP shifts nearly all transmission and sourcing risk onto generators and traders The tender seeks 500–1,000 MW across monthly windows through the procurement period. Interstate bidders absorb a fixed 3.50% regional loss adjustment intrastate suppliers avoid. Latest: the RFP has been published, with bids due shortly before the IPO opening and e-reverse auction on DEEP.

Details

Download tenders and news clips

Jul 21:  For reference purposes the website carries here the following tenders:
 
8Tender for establishment of 765/ 400 kV transmission scheme Details
 
8Tender for supply of 245 kV RIP/RIS bushing for various substations Details
 
8Tender for supply of 420 kV draw rod/lead RIP/RIS bushing for various substation Details
 
8Tender for packing forwarding insurance, transportation supply delivery unloading on for destination of 400 kV bushings Details
 
8Tender for packing forwarding insurance, transportation supply delivery unloading on for destination of 245 kV and below bushings Details
 
8Tender for supply of ferric alum Details
 
8Tender for supply of 360kW HT motor Details
 
8Tender for work of complete overhauling of carious pumps installed for T-G set & BOP auxiliaries Details
 
8Tender for strengthening of exit lane of the existing bituminous coal Details
 
8Tender for construction of 33 kV bay Details
 
8Tender for work of transportation of erection and commissioning of emergency restoration system on 132 kV line Details
 
8Tender for incrasing capacity of (2X63 MVA to 3X63 MVA) T/F and related civil work Details
 
8Tender for supply and repairing of various duct of Ventilation system and overhauling of various air centrifugal fan Details
 
8Tender for work of removal & laying of 6.6/11kV (E), 1C X 1000Sq.mm, aluminum cables along Details
 
8Tender for supply, installation, commissioning and testing of vibration monitoring system for continuous vibration measurement Details
 
8Tender for supply of heating element baskets for air pre-heater of PH IV Details
 
8Tender for supply of heating element baskets for air pre-heater of PH III Details
 
8Tender for supply of seals fo rotary air pre heater Details
 
8Tender for supply of single pole str materials spare Details
 
8Tender for supply of 110KW 10 pole condenser vacuum pump motor Details
 
8Tender for ancillary work required for smooth operation of belt conveyors Details
 
8Tender for construction of foundations for various electrical equipments VCB, CTPT, cable trenches Details
 
8Tender for supply of equipment / material , design, erection, testing , commissioning for system improvement scheme for replacement of old/obsolete switchgear equipment at 33/11 kV sub-stations Details
 
8Tender for construction of 33/11 kV, 2x10MVA GIS sub-station Details
 
8Tender for turnkey construction of 220 kV double circuit transmission line Details
 
8Tender for in-house outsourcing of fabrication of sub-assemblies of HP heaters, LP heaters, condensers, lube oil piping works Details
 
8Tender for supply of BWSR spares Details
 
8Tender for annual maintenance contract for work of on-site N2 drying out for power transformers & ICT’s for various Details
 
8Tender for supply of assorted size of MS grill for repairing of platform of ash slurry line Details
 
8Tender for supply of liquor ammonia 25 % (AR grade) for boiler water treatment Details
 
8Tender for supply of capacitance type level switches for seal oil Details
 
8Tender for supply of IE4 class LT motors Details
 
8Tender for supply of canopies for DCS panels Details
 
8Tender for supply of C&S electric make ACB & panel spares Details
 
8Tender for supply of castable refractory for ash handling plant Details
 
8Tender for supply of battery water for 220V DC & 48V DC battery banks Details
 
8Tender for supply of PLC, VFD (variable frequency drive), HMI and installation Details
 
8Tender for supply of SMF batteries Details
 
8Tender for annual maintenance contract to carry out the routine repair & maintenance of power house equipments Details
 
8Tender for procurement of EPR grade cable 1.1 kV Details
 
8Tender for protection of power house Details
 
8Tender for supply of grinding rolls (roller liners) and bull ring segments Details
 
8Tender for annual maintenance contract for carrying out works in regular outage, emergency and attending breakdown of various 400kV, 220kV, 132kV & 66kV EHV lines Details
 
8Tender for construction of transformer fencing for various Details
 
8Tender for supply of coal nozzles for burner panel of boiler 250 MW Details
 
8Tender for supply of gland packing rings, gland rope and SS 304 spiral wound gaskets etc Details
 
8Tender for supply of spares for HP bypass valves and boiler safety valves for boiler Details
 
8Tender for requirement of spares of zirconia oxygen analysers installed Details
 
8Tender for purchase of spares for 3X1750 KVA DG sets Details
 
8Tender for supply of seals and spares for air pre heater Details
 
8Tender for supply of spares for LPBP stop And control valves Details
 
8Tender for procurement of 06 numbers of grinding ring and 216 number of balls of EL 76 pulveriser Details
 
8Tender for miscellaneous structural works Details
 
8Tender for procurement of different types of steel materials Details
 
8Tender for service contract for power extension and new point wiring Details
 
8Tender for execution of unit 3 COH during overhauling Details
 
8Tender for service contract for de-insulation and re-insulation job during overhauling and various maintenance work Details
 
8Tender for annual maintenance contract of telephone exchange, telephone set and line up Details
 
8Tender for supply of miscellaneous consumables items for electrical and generator maintenance Details
 
8Tender for supply of 11kV moving contact for 200Amps 11kV AB switch (double pole) Details
 
8Tender for work of annual maintenance contract for servicing/ maintenance of battery sets and chargers, taking capacity tests of battery sets and reconditioning of 220V/110V/48V,100/200/300/500/1000 A Details
 
8Tender for AMC for work of arresting oil leakages from the various joints of power transformers Details
 
8Tender for supply of 420kV, 3150A Male Female assembly of centre break isolator Details
 
8Tender for work of replacement of insulator or SRI work of attending the fault or broken conductor Details
 
8Tender for mechanical strengthening work of S/C 66kV line Details
 
8Tender for purchase of 400Amp SMC LTDB Details
 
8Tender for work of Re-tubing of tube nests of LP heater Details
 
8Tender for dismantling of conventional lighting system at boiler, ESP, ash plant Details
 
8Tender for biennial rate contract for works of online, preventive and breakdown maintenance of coal mills XRP-1003 and its associated auxiliaries Details
 
8Tender for work of removal of existing super heater header 5 (SHH5) and erection & commissioning of new SHH 5 along with its associated field joints for boiler Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8
India's Rs 37,500 Crore Coal Gasification Scheme Sees Strong Interest Details
 
8Coal gasification projects of over 22 MT capacity under implementation Details
 
8Solar Startups Attract Over $1 Bn As Clean Energy Investments Accelerate Details
 
8The Ultimate Guide to Solar Energy: Everything You Need to Know in 2026 and Beyond Details
 
8BHEL Invites Bids For Supply Monocrystalline 625 Wp Solar PV Modules For Hyderabad R&D Division Details
 
8Growth and Future of Solar Stocks in India Details
 
8RITES and MECON sign MoU to explore business avenues Details
 
8India has adequate coal stocks, thermal power plants equipped to meet daily demand: Govt Details
 
8AI, Data Centres To Accelerate India’s Power Cycle; Transmission Remains Top Bet: Vakil Of HDFC Securities Details
 
8India has adequate coal stocks to meet power demand, says government Details
 
8Adani Power Share Price Rises Nearly 2% Ahead of Q1 FY27 Results Details
 
8THDC India Commissions 11 MW Floating Solar Plant At Khurja STPP, Boosting NTPC’s Green Capacity Details
 
8India has sufficient coal stocks to meet thermal power demand, says power ministry Details
 
8How Wind Energy in India Is Powering Rural Electrification and Grid Stability Details
 
8Karnataka govt firm on implementing Sharavathi Pumped Storage Project: CM D K Shivakumar Details
 
8Bondada Engineering Secures NTPC REL Deal For 100 MWh Battery Storage Project Details
 
8Why Jaiprakash Power Ventures Shares Surged 8% Today — Here's What Drove The Rally Details
 
8From Standard Pipes to Project-Specific Solutions, Techno India Adapting to Forward Integration Details
 
8Punjab: Power Minister Tarunpreet Singh Sondh launches distribution of 10,500 safety tool kits to PSPCL employees Details
 
8Naveen Jindal Group in talks for proposed nuclear projects, in discussion with US, French companies Details
 
8Coal Stock at Thermal Power Plants Sufficient for 14 Days, Government Assures Uninterrupted Power Supply Details
 
8Thermal Power Plants hold 42.8 MT coal stock, enough for 14 days": MoS Power Shripad Naik Details
 
8India Holds 42.8 Million Tonnes of Coal for Power Stability Details
 
8Tata Power Bags 40-Year SECI Deal Worth Rs 351 Crore Annually for Pumped Hydro Details
 
8NTPC renewable Energy awards contract for 100MWh Details
 
8NPCIL and ECIL Enter MoU to Boost Indigenous Control Systems and Nuclear Technology Solutions Details
 
8India's core sector output rises to five-month high of 5 per cent in June Details
 
You can also click on Newsclips for more Details

The West runs a surplus while the North and South ration - July's squeeze is a delivery problem, not a generation shortfall

Jul 20: 8On 18–19 July the Northern Region shed load in Punjab and Haryana even as the Western Region exported close to 300 million units a day with no shortage and no renewable curtailment. The gap is not missing megawatts - it is congested corridors and benched gas standing between surplus in one region and unmet demand in another. Details

POWER MARKETS DAILY

Jul 20: 8IEX day-ahead cleared 1.30 million MWh in the week to 20 July at a Rs 6,666/MWh average
8Term-ahead buyers locked the Rs 10,000/MWh ceiling for forward daily blocks on 17 July
8APCPDCL and RUVITL float ~1,100 MW and ~1,000 MW thermal reverse auctions on all three exchanges
8IGSTPS-Jhajjar's Rs 45.69 crore tops NRPC's ~Rs 193-crore part-load bill for April–June
8NLDC benched the entire gas fleet at Rs 14–22/kWh while coal cleared at Rs 1.2–5.7/kWh
8Grid-India backed thermal down by up to 46,660 MWh a day to absorb midday solar
8ERPC's weekly deviation pool ran a Rs 60.37-crore balance
8All-India ISTS transmission loss set at 3.95% for the week to 26 July Details

GRID OPERATIONS DAILY

Jul 20: 8All-India frequency fell to 49.596 Hz on 19 July in a synchronous evening dip
8NR import corridor was in ATC violation 11.46% of 19 July as Rajasthan sat 19.1% congested
8NER–Tripura import corridor held in transfer-capacity violation ~three-quarters of the day
8Ancillary despatch ran heavily to down-regulation - up to 46,660 MWh backed down on 19 July
8Western Region exported ~282 MU north on 19 July as the grid's balancing sink and source
8High-voltage light-load regime held Amreli above 420 kV ~90% of 18 July
8NR and WR registers carried high-fault-current trips plus a decade-long tail of dead assets
8One relay-and-reclose event cascaded through five 400 kV bays at Fatehgarh-III / Serentica on 19 July
8Two Karnataka 400 kV corridors stay un-restored since May tower collapses
8Grid-India set the all-India ISTS transmission loss at 3.95% for 20–26 July
8NRPC rates Northern hydro the worst primary-frequency responders - Parbati-III scored 0.00
8ERPC re-cut a week's reactive-energy account off one meter swap - DARLIPALI draws Rs 3,37,902
8WRLDC swapped ~a dozen interface meters to check/standby readings in DSM week-14
8Karnataka's ageing thermal posted soft June returns - RTPS ran 58.2% PLF
8Thermal availability held 85.5% on 16 July as hydro ran 11% under its YTD programme
8Bihar alone curtailed load across 17–19 July despite zero ER-wide shortage Details

OUTAGE & MAINTENANCE REGISTER

Jul 20: 8India carried 53,415 MW under maintenance on 16 July - 22,936 MW of it forced thermal trips
8Western Region ran up to 18,336.5 MW out on 18 July, led by VSTPS-V and Adani Raipur trips
8Southern Region outage climbed 1,906 MW in two days to 11,820.88 MW on 19 July
8Northern Region carried 9,138 MW out on 19 July, 4,900 MW of it forced coal
8Eastern Region held ~5.1–5.9 GW out; Teesta-III's 1,200 MW forced into a 21st month
89,230.47 MW of thermal/nuclear went off-grid on 16 July on boiler and air-preheater faults
8NTPC water-wall tube leaks hit Gadarwara U1 (800 MW) and Barh U3 (660 MW)
8Long-parked units anchor the ~29,961 MW out beyond 15 days
8Telangana's Yadadri loses both first-stage 800 MW units, U1 and U2
8Jindal Simhapuri logged four trips of two 150 MW units in a single day - a repeat-tripping signal
8NPCIL's RAPS-A Unit-1 (100 MW) is formally set for decommissioning, out since 2004
8PVVNL runs a 100-plus feeder shutdown wave across Meerut–Muzaffarnagar ahead of the Kanwar Yatra
8Chronic multi-year transmission forced outages stay open - Raigarh–Raipur FSC since 2016
8Himachal hydro units force-out on high silt as monsoon flows spike
8KPCL's newest Raichur unit (250 MW Unit-8) sat out all June on planned outage
8OHPC carries multiple hydro units out - Burla and Chipilma forced
8KSEBL replaces Idukki Unit-6 upper guide bearing in-house in nine days, saving about Rs 35 lakh Details

Power hit the Rs 10,000 ceiling overnight and at dusk on 22 July, then crashed to Rs 1,380 at noon - on a grid with zero shortage

Jul 23: 8The IEX day-ahead market averaged Rs 5,249.71 a MWh on 22 July but sat pinned at the Rs 10,000 ceiling through the overnight and evening blocks and fell to Rs 1,379.70 in the solar-flooded early afternoon. None of it was scarcity - the grid met a 233,019 MW peak with essentially nil shortage; the crunch is the shape of the day, not a shortage of power. Details

Now the North is paying to keep power on bars - Rs 46 crore last week to run Dadri, Anta and Jhajjar up through the solar trough

Jul 23: 8The Northern load-despatch pool's security-constrained unit-commitment account for 6–12 July shows Rs 46.28 crore paid to keep coal and gas units committed and run up, led by Rs 18.62 crore to NTPC's Dadri gas station. It is the same bill the Western and Eastern pools ran the same week - the cost of holding thermal ready while midday solar forces it down has now gone nationwide. Details

A 765 kV trip stripped 1,320 MW off Uttar Pradesh's Jawaharpur late on 22 July as a protection review logs a spring of weather-hit losses

Jul 23: 8Both 660 MW units of UP's Jawaharpur thermal station tripped together at 22:20 on 22 July when the 765 kV line to Greater Noida went out on generator-transformer protection, and neither was revived by cutoff. It lands as the Western committee's protection papers catalogue more than forty grid disturbances from the spring - including a 1,704 MW loss at JSW's Mahanadi plant when a lightning strike collapsed a transmission tower. Details

Twenty-nine thermal plants run coal-critical in mid-monsoon - Andhra's Damodaram Sanjeevaiah down to a single day

Jul 23: 8National coal stock at power plants held about 40.4 million tonnes, roughly 13 days' cover, on 21 July - but 29 individual plants were running critical, two more than a week earlier. Andhra's Damodaram Sanjeevaiah was at 3% of its normative stock, about a day's cover, and Reliance's Sasan ultra-mega was at the same 3%. Details

Adani Power's Q1 profit jumps 47% to Rs 4,867 crore and it clears a Rs 15,000 crore raise while swallowing the Jaiprakash insolvency estate

Jul 23: 8Adani Power reported a consolidated first-quarter net profit of Rs 4,866.60 crore, up 47%, on income of Rs 19,322 crore and a plant load factor lifted to 77.9%. The board cleared a Rs 15,000 crore equity raise and doubled the borrowing ceiling to Rs 1 lakh crore, as the group folded in three plants from the Jaiprakash Associates bankruptcy and signed a 1,600 MW supply deal with Maharashtra. Details

JSW Energy's profit falls a third to Rs 533 crore even as it books its biggest-ever capacity quarter and absorbs GE Power India

Jul 23: 8JSW Energy's first-quarter net profit fell to Rs 533 crore from Rs 836 crore even though EBITDA edged up and capacity crossed 14,535 MW on a record organic addition. The drop is the cost of that growth - depreciation and finance charges on new plant, weak hydrology and a force-majeure at its Mahanadi coal station - as it also swallows GE Power India's boiler business and signs up another 300 MW of thermal. Details

Shell is out of Indian renewables: Aditya Birla buys the Sprng platform for Rs 17,200 crore, nearly doubling its green fleet

Jul 23: 8Aditya Birla Renewables has agreed to buy 100% of Solenergi Power - the holding company for Shell's Sprng Energy platform - for an enterprise value of about Rs 17,200 crore, taking on roughly 5 GW of solar and wind. The deal lifts the Aditya Birla green portfolio from 4.4 GW to 9.3 GW and marks a major oil-major's exit from the Indian renewable market. Details

Adani Green's operating fleet crosses 20,000 MW as quarterly EBITDA hits a record Rs 4,122 crore

Jul 23: 8Adani Green Energy reported a June-quarter operating capacity of 20,142 MW, up 27% on the year, with energy sales up 30% and EBITDA at a record Rs 4,122 crore on a 94% margin. Its battery build at Khavda nearly doubled in the quarter to 3,551 MWh. Details

The appellate tribunal stays Maharashtra's move to load legacy deviation charges onto thermal generators, siding with Adani and JSW

Jul 23: 8The Appellate Tribunal for Electricity has stayed a Maharashtra commission order that apportioned regional-pool and legacy deviation charges to thermal generators injecting into the grid, allowing interim relief to Adani Power's Dahanu station and JSW Energy. JSW alone had paid about Rs 3.8 crore under protest; the tribunal's order freezes the demands while the appeals are heard. Details

Coal India wins its way into batteries - 80 MW of SECI's Odisha storage tender goes to the country's biggest coal miner

Jul 23: 8In SECI's 125 MW / 500 MWh standalone battery tender for Odisha, backed by viability-gap funding, Coal India won two of the three clusters - 80 MW in all - at monthly capacity charges of about Rs 3.04–3.05 lakh a MW. A coal miner taking grid-scale storage is the sharp edge of how the majors are hedging the energy transition. Details

Contracting news for the day

Jul 23: 81) IntelliSmart takes Indore smart metering at 21.7% below MPPKVVCL's estimate Ten bidders entered, three fell at the technical gate and six were eliminated on price, leaving a single survivor. The 6.9% gap to Apraava suggests competitive pressure rather than distress bidding. What remains untested is whether a Rs 417.15 crore price absorbs a 3,650-day service obligation comfortably. Under DBFOOT, the winner carries financing, deployment and lifecycle risk long after the award headline fades.

 

82) NTPC Green's Khavda BESS tender kept moving after its own deadline had passed Six corrigenda and one addendum landed inside a single bidding cycle, with the last posted a day after the original closing date. That sequence tells bidders the package was still being calibrated while they were expected to fix prices. The notice never states MW rating, discharge duration, chemistry or augmentation responsibility. A reverse auction on 3,300 MWh of undefined configuration is where the real risk sits.

 

83) MPPGCL formalises a site visit so bidders cannot later claim they did not know The corrigendum changes no scope, no price basis and no qualification bar — it simply schedules an inspection. Its commercial value lies in what it removes: the post-award claim that site conditions were unforeseeable. For a turnkey EPC carrying five years of O&M, land and interface assumptions made blind become expensive. The promoter has quietly shifted diligence responsibility back onto the bidder.

 

84) UJVNL puts the entire Sirkari Bhyol electro-mechanical chain under one turnkey price Rs 158.53 crore covers design through commissioning for a 3x40 MW hydro package with no interface escape route. The structure rewards firms with manufacturing depth rather than assembly capability. Coordination risk, not equipment cost, is likely to decide who prices this realistically. The pre-bid stage will show whether the market treats the estimate as workable.

 

85) POWERGRID removes the performance guarantee but moves payment behind a Collector's order Deleting the CPG frees working capital for the Morbi valuation package — an unusual relaxation for a consultancy assignment. What replaces it is milestone payment tied to acceptance by authorities the contractor cannot control. The award cap has also loosened from one package to two, reshaping who can win what. Easier entry, harder cash conversion.

 

86) Two extensions on Tankul suggest the market needed more time than UJVNL assumed The bidding window has stretched by 25 days without any visible change to scope, capacity or the Rs 87.90 crore estimate. The package runs from river diversion through tunnel, surge shaft and powerhouse into hydro-mechanical works. Geological risk allocation across those fronts is not resolved in the public notice. Repeated extensions usually mean bidders are still pricing what they cannot see.

 

87) NTPC's Barauni ash package rules out reverse auction and self-performed design cannot be bought in A three-week extension eases bid preparation but changes nothing about a 630-day delivery obligation. Qualification demands an executed pneumatic system with in-house design — closing the route of borrowed engineering credentials. Rs 1 crore bid security and Rs 6.09 lakh daily delay damages narrow the field further. NTPC appears to want fewer bidders who can actually finish.

 

88) BHEL caps some liability at Lakhanpur while leaving the worst exposure at 100% Corrigendum VIII gives bidders numbers to model: 5% for delay, 5% for performance shortfall, 30% for make-good. Termination and risk-and-cost completion still reach the full contract price. Requests to soften the one-year force majeure and three-year hold thresholds were refused outright. Five deadline extensions later, the risk envelope is clearer but no lighter.

 

89) MSEDCL reaches Version 5 on a Rs 109.58 crore transformer buy before opening a single bid Successive revisions and an incorporated pre-bid reply document suggest the utility preferred argument before award rather than after. Firm pricing survives every revision, leaving cost risk with manufacturers. The extended window improves bid quality but delays a purchase of one of the network's most routinely consumed assets. Document stability, not competition, appears to be the priority here.

 

810) BHEL wants its Anantapur BOS partner locked in before the project even exists This is a pre-bid tie-up, not an award — capability is being secured ahead of the downstream contest. A Rs 3 crore EMD against an uncertain project outcome is a serious commitment to demand upfront. It filters out speculative participation while pushing bid-stage risk onto prospective partners. For 1,200 MW, BHEL is buying execution certainty before it needs it.

 

811) Ennore's FGD tender has spent 162 days in procurement without changing a single risk clause Five extensions and a cancelled-then-restored pre-bid meeting have stretched the calendar without relaxing EMD, LD, warranty or completion terms. Contractors gained preparation time; the 30 and 32-month clocks did not move. The 4%-1% security split makes the technology provider a secured party rather than an adviser. Market formation, not administration, appears to be what took so long.

 

812) POWERGRID makes survey counts indicative and tells Anand bidders not to expect more money Corrigendum C5 deletes the performance guarantee, then transfers parcel-density risk in the same breath. Bidders must quote a fixed total before receiving the Land Plan Schedule, survey details and KML files. Payment splits 80:20, with the tail dependent on committee acceptance and a Collector's order. Lower entry cost, higher pricing blindness.

 

813) Mahagenco asks one contractor to find the land, build the plant, evacuate the power and run it for a decade This is a development platform transfer disguised as a 300 MWac EPC procurement. The 25 MWac floor widens entry, but a 15 MWac reference plant and per-MW financial ratios quietly narrow it again. Consortium partners can share technical credentials; the lead member carries the full financial test alone. A reverse auction then compresses prices built on land and evacuation uncertainty.

 

814) Kulhal's pre-bid meeting was rescheduled to a date after its own bid deadline The original calendar collapsed once clarification moved past the closing date, forcing a third extension. The 29-day shift restores roughly the same clarification-to-submission interval the tender first intended. What bidders learned during that window matters more than the extension itself. Rs 110.57 crore of brownfield hydro renovation cannot be priced from drawings alone.

 

815) CTUIL reorders its contract hierarchy one day before bids close The corrigendum makes the uploaded RfP supreme over conflicting GeM terms and the service-level agreement, without extending the deadline. Bidders must reconcile a 286-page document against a portal summary in a single day. The consultancy itself carries authority over delay claims, force majeure, cost reasonableness and asset valuation. Personnel controls make the CVs submitted a binding commercial promise, not a bid-stage flourish.

 

816) A one-minute discrepancy sits inside NTPC REL's 600 MW Dhule bid schedule The schedule table says one cut-off; the portal banner says another sixty seconds later. Electronic systems reject late bids automatically, which makes ambiguity a procedural risk unrelated to price or capability. Corrigendum-1 arrived seven days before submission alongside a second addendum. Rs 20 crore in bid security filters the field before a reverse auction compresses whatever margin survives.

 

817) BHEL bundles two Korba West packages that share nothing except a single price Package-A and Package-B carry different boundaries and 42 and 58-month schedules, yet must be quoted as one lump sum. The price will be split 25:75 by prescription, not by the bidder's own cost structure. BHEL can then redistribute orders at will, with cross-default linking every instrument it issues. Administrative separation without contractual separation is the whole design.

 

818) POWERGRID tightens the one-package rule for Kheda while consolidating its own conditions The revised ATC pulls qualification, evaluation, payment and scope into a single controlling document. Restricting each agency to one award prioritises parallel execution across districts over economies of scale. A package-opening sequence is being used to manage bidder capacity before firms exhaust their entitlement. Fifteen days per assignment leaves no room for slow mobilisation.

 

819) Corrigendum C7 shows POWERGRID still adjusting its Gujarat valuation terms before award The amendment modifies the bidding process after original publication and must be read alongside the base documents. GeM provisions and POWERGRID's own conditions now operate together rather than in sequence. Land valuation has moved from incidental consultancy to a scheduling input for transmission construction. The final conditions matter more than the original release.

 

Details

Contracting news for the day

Jul 23: 81) IntelliSmart takes Indore smart metering at 21.7% below MPPKVVCL's estimate Ten bidders entered, three fell at the technical gate and six were eliminated on price, leaving a single survivor. The 6.9% gap to Apraava suggests competitive pressure rather than distress bidding. What remains untested is whether a Rs 417.15 crore price absorbs a 3,650-day service obligation comfortably. Under DBFOOT, the winner carries financing, deployment and lifecycle risk long after the award headline fades.

 

82) NTPC Green's Khavda BESS tender kept moving after its own deadline had passed Six corrigenda and one addendum landed inside a single bidding cycle, with the last posted a day after the original closing date. That sequence tells bidders the package was still being calibrated while they were expected to fix prices. The notice never states MW rating, discharge duration, chemistry or augmentation responsibility. A reverse auction on 3,300 MWh of undefined configuration is where the real risk sits.

 

83) MPPGCL formalises a site visit so bidders cannot later claim they did not know The corrigendum changes no scope, no price basis and no qualification bar — it simply schedules an inspection. Its commercial value lies in what it removes: the post-award claim that site conditions were unforeseeable. For a turnkey EPC carrying five years of O&M, land and interface assumptions made blind become expensive. The promoter has quietly shifted diligence responsibility back onto the bidder.

 

84) UJVNL puts the entire Sirkari Bhyol electro-mechanical chain under one turnkey price Rs 158.53 crore covers design through commissioning for a 3x40 MW hydro package with no interface escape route. The structure rewards firms with manufacturing depth rather than assembly capability. Coordination risk, not equipment cost, is likely to decide who prices this realistically. The pre-bid stage will show whether the market treats the estimate as workable.

 

85) POWERGRID removes the performance guarantee but moves payment behind a Collector's order Deleting the CPG frees working capital for the Morbi valuation package — an unusual relaxation for a consultancy assignment. What replaces it is milestone payment tied to acceptance by authorities the contractor cannot control. The award cap has also loosened from one package to two, reshaping who can win what. Easier entry, harder cash conversion.

 

86) Two extensions on Tankul suggest the market needed more time than UJVNL assumed The bidding window has stretched by 25 days without any visible change to scope, capacity or the Rs 87.90 crore estimate. The package runs from river diversion through tunnel, surge shaft and powerhouse into hydro-mechanical works. Geological risk allocation across those fronts is not resolved in the public notice. Repeated extensions usually mean bidders are still pricing what they cannot see.

 

87) NTPC's Barauni ash package rules out reverse auction and self-performed design cannot be bought in A three-week extension eases bid preparation but changes nothing about a 630-day delivery obligation. Qualification demands an executed pneumatic system with in-house design — closing the route of borrowed engineering credentials. Rs 1 crore bid security and Rs 6.09 lakh daily delay damages narrow the field further. NTPC appears to want fewer bidders who can actually finish.

 

88) BHEL caps some liability at Lakhanpur while leaving the worst exposure at 100% Corrigendum VIII gives bidders numbers to model: 5% for delay, 5% for performance shortfall, 30% for make-good. Termination and risk-and-cost completion still reach the full contract price. Requests to soften the one-year force majeure and three-year hold thresholds were refused outright. Five deadline extensions later, the risk envelope is clearer but no lighter.

 

89) MSEDCL reaches Version 5 on a Rs 109.58 crore transformer buy before opening a single bid Successive revisions and an incorporated pre-bid reply document suggest the utility preferred argument before award rather than after. Firm pricing survives every revision, leaving cost risk with manufacturers. The extended window improves bid quality but delays a purchase of one of the network's most routinely consumed assets. Document stability, not competition, appears to be the priority here.

 

810) BHEL wants its Anantapur BOS partner locked in before the project even exists This is a pre-bid tie-up, not an award — capability is being secured ahead of the downstream contest. A Rs 3 crore EMD against an uncertain project outcome is a serious commitment to demand upfront. It filters out speculative participation while pushing bid-stage risk onto prospective partners. For 1,200 MW, BHEL is buying execution certainty before it needs it.

 

811) Ennore's FGD tender has spent 162 days in procurement without changing a single risk clause Five extensions and a cancelled-then-restored pre-bid meeting have stretched the calendar without relaxing EMD, LD, warranty or completion terms. Contractors gained preparation time; the 30 and 32-month clocks did not move. The 4%-1% security split makes the technology provider a secured party rather than an adviser. Market formation, not administration, appears to be what took so long.

 

812) POWERGRID makes survey counts indicative and tells Anand bidders not to expect more money Corrigendum C5 deletes the performance guarantee, then transfers parcel-density risk in the same breath. Bidders must quote a fixed total before receiving the Land Plan Schedule, survey details and KML files. Payment splits 80:20, with the tail dependent on committee acceptance and a Collector's order. Lower entry cost, higher pricing blindness.

 

813) Mahagenco asks one contractor to find the land, build the plant, evacuate the power and run it for a decade This is a development platform transfer disguised as a 300 MWac EPC procurement. The 25 MWac floor widens entry, but a 15 MWac reference plant and per-MW financial ratios quietly narrow it again. Consortium partners can share technical credentials; the lead member carries the full financial test alone. A reverse auction then compresses prices built on land and evacuation uncertainty.

 

814) Kulhal's pre-bid meeting was rescheduled to a date after its own bid deadline The original calendar collapsed once clarification moved past the closing date, forcing a third extension. The 29-day shift restores roughly the same clarification-to-submission interval the tender first intended. What bidders learned during that window matters more than the extension itself. Rs 110.57 crore of brownfield hydro renovation cannot be priced from drawings alone.

 

815) CTUIL reorders its contract hierarchy one day before bids close The corrigendum makes the uploaded RfP supreme over conflicting GeM terms and the service-level agreement, without extending the deadline. Bidders must reconcile a 286-page document against a portal summary in a single day. The consultancy itself carries authority over delay claims, force majeure, cost reasonableness and asset valuation. Personnel controls make the CVs submitted a binding commercial promise, not a bid-stage flourish.

 

816) A one-minute discrepancy sits inside NTPC REL's 600 MW Dhule bid schedule The schedule table says one cut-off; the portal banner says another sixty seconds later. Electronic systems reject late bids automatically, which makes ambiguity a procedural risk unrelated to price or capability. Corrigendum-1 arrived seven days before submission alongside a second addendum. Rs 20 crore in bid security filters the field before a reverse auction compresses whatever margin survives.

 

817) BHEL bundles two Korba West packages that share nothing except a single price Package-A and Package-B carry different boundaries and 42 and 58-month schedules, yet must be quoted as one lump sum. The price will be split 25:75 by prescription, not by the bidder's own cost structure. BHEL can then redistribute orders at will, with cross-default linking every instrument it issues. Administrative separation without contractual separation is the whole design.

 

818) POWERGRID tightens the one-package rule for Kheda while consolidating its own conditions The revised ATC pulls qualification, evaluation, payment and scope into a single controlling document. Restricting each agency to one award prioritises parallel execution across districts over economies of scale. A package-opening sequence is being used to manage bidder capacity before firms exhaust their entitlement. Fifteen days per assignment leaves no room for slow mobilisation.

 

819) Corrigendum C7 shows POWERGRID still adjusting its Gujarat valuation terms before award The amendment modifies the bidding process after original publication and must be read alongside the base documents. GeM provisions and POWERGRID's own conditions now operate together rather than in sequence. Land valuation has moved from incidental consultancy to a scheduling input for transmission construction. The final conditions matter more than the original release.

 

Details

Power Markets Daily

Jul 23: 8IEX day-ahead averaged Rs 5,250 on 22 July but held the Rs 10,000 ceiling overnight and at dusk
8The green day-ahead cleared at Rs 6,685 - a premium of more than two times the conventional price
8HPX drew no buyers for a fourth day and PXIL cleared nothing for an eighth, so IEX carried the market
8Rajasthan's merit order runs from Rs 1.55 at Sasan to Rs 28.11 for liquid-fuel peaking
8Andhra's discom levies a Rs 0.40 a unit fuel surcharge for May in the August bills Details

Grid Operations Daily

Jul 23: 8India met a 233,019 MW maximum demand on 22 July at 11:19 - a solar-hour peak - with shortage near nil
8The grid ran high a sixth of 22 July and the operators backed generation down by nearly 56,000 MWh
8The North-East to Tripura corridor sat over its transfer limit for 63% of 21 July
8India imported 52 MU from Bhutan and wheeled 56 MU to Bangladesh on 22 July
8The West met a 63,684 MW evening peak with zero shortage as wind supplied 169 MU
8The South met a 55,049 MW peak shortage-free while carrying 10.7 GW of generation on outage Details

Outage & Maintenance Register

Jul 23: 8About 52 GW of capacity sat under maintenance on 21 July, 30 GW of it forced out
8A 765 kV trip took both Jawaharpur units - 1,320 MW - off the bars late on 22 July
8The South spent 22 July switching around a twin-circuit line snap and a Mysore bus-bar cascade
8Western forced losses took out Adani Raipur, Sasan and Shree Singaji - three units near 660 MW each
8NTPC carried about 5.6 GW of its own fleet out on boiler and condenser leaks
8About 32 GW has been out beyond a fortnight, including two 800 MW Yadadri units and Kudankulam-1 Details

Fuel & Coal Ledger

Jul 23: 8Twenty-nine thermal plants ran coal-critical on 21 July; Damodaram Sanjeevaiah down to a day
8The coal ministry counts 42 mines scientifically closed and sets a Rs 40,000 crore closure corpus
8Bharat Coking Coal swings to a Rs 68 crore loss as production falls 27%
8A Northern Coalfields e-auction carries a disputed Rs 300 a tonne Singrauli rehabilitation charge Details

Hydro & Reservoir Ledger

Jul 23: 8Telangana's Krishna reservoirs hold about 93% less energy than a year ago deep into the monsoon
8The East runs almost no hydro - Teesta-III still out, Odisha's reservoirs bare and a pumped-storage unit drawing power
8Big reservoirs are still filling - Bhakra sits 30 metres below its full level Details

CERC Docket & Adjudication

Jul 23: 8The appellate tribunal stays Maharashtra's legacy-deviation charge on thermal generators
8Himachal's regulator clears nine rooftop and ground-mounted solar tariffs at Rs 3.47 a unit
8Himachal grants interim connectivity to a 4.8 MW small-hydro project through a spare 33 kV bay Details

State Regulatory Roundup

Jul 23: 8Uttarakhand fixes UPCL's recoverable from a 214 MW gas station at Rs 19.83 crore and rejects the review
8UP defers a giant captive solar project's plea for full transmission and banking exemption
8Maharashtra allows interest on delayed late-payment surcharge to an 11 MW bagasse cogenerator
8Haryana clears a flexible-load scheme and a graded surcharge, and quashes a township reference-meter demand
8Haryana defers plant-wise deviation settlement for the Panipat thermal station by a year
8Chhattisgarh puts ArcelorMittal's beneficiation plant back in the steel tariff category after a suo-motu reclassification
8Kerala's board asks its regulator to approve per-kW distribution cost data averaging Rs 1,563 a kW
8Tamil Nadu's ombudsman orders a Rs 2,982 refund and Punjab adopts a supply-code amendment
8UP tightens SCADA compliance on its utilities and extends a transmission line's deadline to December Details

Green Markets & RE Programme Watch

Jul 23: 8Coal India wins 80 MW of SECI's 125 MW Odisha battery tender
8The solar-cell approved list adds nearly 1,700 MW of domestic capacity in its eighth revision
8Adani Green's operating fleet crosses 20,000 MW on record quarterly EBITDA
8India's installed wind capacity reaches 57,443 MW, fourth largest in the world
8Suzlon lands a 202 MW wind order as Waaree Renewable buys into transmission
8Borosil Renewables' quarterly EBITDA doubles as it plans a 60% capacity expansion
8National statistics put India's assessed renewable potential at 4.7 million MW Details

Corporate Wire

Jul 23: 8Adani Power's Q1 profit jumps 47% to Rs 4,867 crore with a Rs 15,000 crore raise
8JSW Energy's Q1 profit falls a third to Rs 533 crore
8Aditya Birla Renewables buys the Sprng platform from Shell for Rs 17,200 crore
8Bajel Projects wins a 500 kV Egyptian transmission order worth more than Rs 400 crore
8The Inox wind group lines up a Rs 600 crore raise, a Rs 3,500 crore captive order and an O&M demerger
8Orient Green's Q1 profit slips to Rs 24 crore as it winds up its European arm; Tata Power weighs a bond issue
8Ratings Watch - ICRA puts three Aditya Birla Renewables units on watch, upgrades Sunsure, and CARE withdraws Soleos Details

Committees, People & System Administration

Jul 23: 8The North's pool paid Rs 46 crore last week to keep thermal on bars
8The Western protection committee logs 40-plus spring disturbances, one a 1,704 MW loss at JSW Mahanadi
8The South's committee weighs an Adani 765 kV substation, a Rs 1.36 lakh crore HVDC plan and a Vallur battery award
8The East's disaster-management meeting orders an emergency restoration set and studies a Nepal-hydro black start
8Punjab's power strike stretches to four days as unions add pensioners and PSPCL orders no-work-no-pay
8Himachal advertises a regulatory Member (Law) vacancy as public-body staffing turns over Details

Daily Power Sector Tenders Excel update

Jul 23: 8Daily Excel covering new tenders and all published updates including corrigendum, amendment, addendum, clarification and status revisions, along with technical and financial bid opening, evaluation completion and final award actions including AOC and LOA issuance.
Click on Reports for more Details

Download tenders and news clips

Jul 23:  For reference purposes the website carries here the following tenders:
  
8Tender for Bi- annual rate contract for emergency power restoration work of 400/220/132/66kV lines Details
  
8Tender for Bi-ARC for original survey and check survey for various 400kV/220kV/132kV/66kV overhead line Details
  
8Tender for dismantling of existing fencing and installation of new main gate along Details
  
8Tender for supply, installation & commissioning of CSD Details
  
8Tender for drone based patrolling of transmission lines Details
  
8Tender for protection wall at tower Details
  
8Tender for supply of LED flood lights and street lights for replacement of faulty lights Details
  
8Tender for supply of 36 kV CT accuracy 0.2S accuracy classes along with terminal connectors and junction boxes Details
  
8Tender for inspection of TG bearings, in situ machining of LP rotor journal Details
  
8Tender for capability (performance) test of NDCT Details
  
8Tender for work for protection of water conductor Details
  
8Tender for replacement of conventional electrical switches Details
  
8Tender for EPC Package for internal coal handling plant Details
  
8Tender for annual maintenance of horticulture works Details
  
8Tender for standardization of transformer station Details
  
8Tender for repair of damaged UC fencing and allied civil works Details
  
8Tender for procurement of sulphuric acid commercial grade Details
  
8Tender for construction of 1 no. addl. 20 MVA 66/11 kV TF plinth along with allied civil works Details
  
8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects Details
  
8Design, supply, erection, testing and commissioning of new generator relay panels Details
  
8Tender for providing chain-link fencing Details
  
8Tender for supply of various type sleeves & fins for boiler Details
  
8Tender for supply & erection of MS grills at various Details
  
8Tender for day to day civil maintenance work Details
  
8Tender for repair and maintenance of external pipelines Details
  
8Tender for repair, renovation, and miscellaneous civil maintenance works Details
  
8Tender for procurement of spares for turbine supervisory system Details
  
8Tender for maintenance of station battery sets of power plant Details
  
8Tender for annual / running and breakdown maintenance of pipe lines Details
  
8Tender for annual repair and maintenance contract for electrical systems Details
  
8Tender for providing and fixing PUF panel operator cabin Details
  
8Tender for supply of electrical actuator Details
  
8Tender for supply of various types of pressure and temperature switches Details
  
8Tender for development of 2 Nos of bore wells for water supply Details
  
8Tender for annual maintenance of 04 (four) nos. of generating units Details
  
8Tender for repair of 02 KSB-manufactured 90 kW submersible pumps Details
  
8Tender for supply of material Details
  
8Tender for maintenance/operation of 33/11 kV sub-stations, associated HT/LT lines Details
  
8Tender for shifting and heightening of 11kV and LT lines including 11/0.4 kV DTRs Details
  
8Tender for biennial work contract for maintenance of ash handling plant Details
  
8Tender for renewal work with widening of existing Details
  
8Tender for work of attending hot-spots and oil DGA issues by modification of LV bushing internal connection Details
  
8Tender for empanelment of agencies for restoration of distribution infrastructure Details
  
8Tender for empanelment of contractors to award a contract for survey, installation, testing and commissioning of 33kV line Details
  
8Tender for work contract of day to day routine maintenance of 220kV and 400 kV switchyard, all HT and LT transformers, overhead line faults Details
  
8Tender for procurement of spares for caustic acid alum and polyelectrolyte dosind pumps installed Details
  
8Tender for const. of 33 kV S/S Details
  
8Tender for construction of power transformer and VCB foundation Details
  
8Tender for construction of store shed at 33 kV S/S Details
  
8Tender for construction of control room, water supply arrangement and yard levelling and gravelling work at 33 kV S/S Details
  
8Tender for roof leakage treatment, renovation Details
  
8Tender for purchase of 245kV 1250A motorized isolator Details
  
8Tender for purchase of 220V DC and 110V DC control and distribution board Details
  
8Tender for providing auxiliary earth mat at motorised isolator and earth switch mechanism point along Details
  
8Tender for construction of chemical earthing for towers along Details
  
8Tender for painting of HT and MS exposed steel structural tower member of 220 kV /132 kV LILO transmission line tower Details
  
8Tender for supply installation, connection and commissioning of 15 nos. bore type earth pit for improvement of earthing system of 50 MVA power with the work of pipe line Details
  
8Tender for complete overhauling of 132/33 kV 50MVA power transformer Details
  
8Tender for replacement of damaged cable hanger with providing perforated cable tray with cable tray support/fixture in 132 main and 132 kV side cable trenches Details
  
8Tender for repair and maintenance of grid control room at 400/220kV GSS Details
  
8Tender for work of aluminium and zinc chromat/phosphate based painting of rusted tower structure Details
  
8Tender for selection of cloud service provider for providing cloud infrastructure Details
  
8Tender for service contract for round the clock operation of 01 no. in motion weigh bridge Details
  
8Tender for Bi-annual maintenance contract of various equipments like dozers, DG sets, fire pump Details
  
8Tender for manufacture, testing, supply and delivery of 11 kV 200 A TPGO isolator with polymer post insulator. Details
  
8Tender for procurement of current transformers (400kV and 220kV C.T) Details
  
8Tender for supply of LT three phase channel cross arm Details
  
8Tender for supply of fixed contact for 11 kV AB switch Details
  
8Tender for supply of stay set complete Details
  
8Tender for supply of various sizes of MS bollt and nuts Details
  
8Tender for supply of HT /TI fitting and LT /TI fitting Details
  
8Tender for running works contract for effecting various works Details
  
8Tender for supply of HS type straight joint kit suitable for 33kV 1X630 sqmm XLPE UG cable Details
  
8Tender for supply of 11kV vertical type group operated AB switch with composite polymer insulators Details
  
8Tender for diversion of 220 kV transmission line Details
  
8Tender for maintenance/operation of 33/11 kV sub-stations Details
  
8Tender for maintenance/operation of 33/11 kV sub-stations, associated HT/LT lines Details
  
8Tender for supply and installation of pipe earthing Details
  
8Tender for supply and installation of pipe earthing in different capacity of DTRs Details
  
8Tender for electrical work for construction of 2X5 MVA 33/11 kV substation Details
  
8Tender for construction of 16.0 KM 33 kV line Details
  
8Tender for complete overhauling/maintenance work of 33 kV VCB’s panels Details
  
8Tender for complete overhauling/maintenance work of 33 kV VCB’s panels breakers complete unit) of different make installed Details
  
8Tender for complete overhauling/maintenance work of 33 kV VCB’s panels breakers Details
  
8Tender for regarding work shifting/displacement of 33 kV, 11 kV, LT lines Details
  
8Tender for work of providing and fixing of non-conductive turbo wind driven conical bird guards at various suspension tower Details
  
8Tender for AMC of optical fiber network and LAN for ERP and internet connectivity Details
  
8Tender for Bi-annual maintenance of NIFP system Details
  
8Tender for work of complete overhauling of 400kV breakers pole Details
  
8Tender for work of replacement of existing hanging/suspension type wave trap by new pedestal type wave trap along Details
  
8Tender for replacement work of 220kV GIS bays at 220 kV GIS substation Details
  
8Tender for work of servicing & overhauling along with providing & fixing of required spares of 245kV circuit breakers at various Details
  
8Tender for Bi-annual maintenance contract for work of repairs, servicing & alignment for 220kV, 132kV, 33kV isolators along Details
  
8Tender for work of providing and fixing of 33 kV current transformers at various sub-stations Details
  
8Tender for purchase of single phase SMC meter box Details
  
8Tender for purchase of LT shackle insulator Details
  
8Tender for supply and application of metal protective compound for various structure, pipes and duct Details
  
8Tender for supply of pre engineering shed for central store Details
  
8Tender for supply of ACB & panel spares Details
  
8Tender for supply of neutral grounding resistor Details
  
8Tender for supply and installation of an energy efficient lubricated rotary screw air compressor Details
  
8Tender for erection of new HT, LT line and transformer centers, replacement work, underground cabling work Details
  
8Tender for erection of 66kV Lilo line Details
  
8Tender for work of erection dismantling of 66kV/11KV equipment’s, structures, control wiring Details
  
8Tender for supply of fire system pumps Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8Jindal Steel Deploys Indigenous Coal Gasification in Global First for Steelmaking Details
 
8Coal Ministry unveils roadmap for sustainable mine closure Details
 
8India's renewable energy potential more than doubled in FY25: Mospi Details
 
8Coal ministry releases AAROH mine-closure report, signs EUR 10-million mine closure cooperation pact with GIZ Details
 
8India's steel ambitions face a coal reality check Details
 
8India's solar power boom faces regional imbalance, manufacturing glut Details
 
8The next farm revolution will hinge on energy economics, not just better seeds Details
 
8India’s Green Hydrogen Mission Gains Momentum Despite Capacity And Infrastructure Challenges Details
 
8India's Renewable Energy Capacity Nearly Quadruples To 288.58 GW Since 2014 Details
 
8Gautam Solar Earns EcoVadis Silver Medal, Ranks Among Top 15% Globally for Sustainability Details
 
8Power distribution, petroleum import going private Details
 
8Solar Cell Import Relief Stirs Concerns for Domestic Makers Details
 
8First Solar margin expansion draws analyst optimism despite solar sector downturn Details
 
8Delhi Launches Smart Substation, Rooftop Solar Drive To Strengthen Power Infra Details
 
8JSW Energy Q1 FY27 results: Net profit declines 36% to Rs 532 crore Details
 
8India's solar capacity to exceed coal by 200 GW by 2036: Pralhad Joshi Details
 
8How China and India are supercharging the battery storage market Details
 
8India’s geothermal energy dreams gather steam Details
 
8India’s Wind Power Capacity Rises to 57,443 MW, Ranks Fourth Globally Details
 
8Nuclear power capacity to reach 22 GW by FY32, says Jitendra Singh Details
 
8India's Solar Capacity Touches 162.15 GW As Renewable Push Gains Momentum Details
 
8MNRE adds Avaada, expands Fujiyama capacity under ALMM List-II Details
 
8Bajel Projects Concludes 500kV Transmission Line Agreement In Egypt Details
 
8Energy minister seeks proposals to privatise power distribution Details
 
8Adani Power Q1 PAT jumps 47% as higher power sales, tariff realisation boost earnings Details
 
8NLC India Raises INR 150 Crore Through Commercial Paper Issuance Details
 
8Adani Power shares down 2%: Q1 net profit rises 47%, power generation capacity hits 18,330 MW Details
 
8Telangana Withstands 7,000 MW ‘El Niño’ Power Shock, No Power Cuts Across State: Deputy CM Bhatti Vikramarka Details
 
You can also click on Newsclips for more Details

Jan 01: Details

MNRE extends the ALMM solar-cell exemption to 31 December 2026, sparing rooftop and open-access projects

Jul 22: 8The renewable-energy ministry has pushed the deadline for mandatory use of listed domestic solar cells to 31 December 2026, from 31 May, for rooftop, net-metering and open-access projects. Utility-scale projects stay bound by the mandate, and everything must comply from 1 January 2027. Details

Daily Power Sector Tenders Excel update

Jul 22: 8Daily Excel covering new tenders and all published updates including corrigendum, amendment, addendum, clarification and status revisions, along with technical and financial bid opening, evaluation completion and final award actions including AOC and LOA issuance.
Click on Reports for more Details

POWER MARKETS DAILY

Jul 22: 8IEX day-ahead averaged Rs 6,617 on 21 July but held the Rs 10,000 ceiling in 54% of blocks
8Real-time power took the day's biggest volume - 192.70 MU - at a weekly-low Rs 4,143
8The green day-ahead cleared Rs 6,755 and term strips settled flat at Rs 6,350 - no green discount
8PXIL cleared nothing and HPX drew no buyers, so IEX carried the entire cleared market on 21 July
8DVC-style peak buying returns as GUVNL and UPPCL float HPX reverse auctions for evening blocks
8Rajasthan's merit order runs from Rs 0.99 at NLC Barsinghsar to Rs 27.87 for liquid-fuel peaking Details

GRID OPERATIONS DAILY

Jul 22: 8India met a 235,132 MW evening peak and a 237,218 MW day-max on 21 July with zero shortage
8The grid ran high a quarter of 21 July and the operators backed generation down by 51,305 MWh
8The North-East to Tripura corridor sat over its transfer limit for 51.9% of 21 July
8Gujarat alone curtailed 922 MW of solar and 353 MW of wind for grid security on 21 July
8The Northern grid switched out about 25 of its 765 kV bus reactors at dawn to hold voltage up
8India imported 51 MU from Bhutan and 22 MU from Nepal while wheeling power to Bangladesh Details

OUTAGE & MAINTENANCE REGISTER

Jul 22: 8About 43 GW of generation sat on outage on 21 July, the West carrying 18 GW of it
8Fresh 21 July trips took out Sasan 660 MW, Rihand-II 500 MW and a clutch of 200 MW units
8Yadadri's coal-starved 800 MW unit came back on 21 July; Ropar and Ghatampur stayed coal-hit
8North Chennai's 800 MW and Rajpura's 700 MW units stayed out on ESP and boiler faults
8Two Southern 400 kV corridors remain down two months after tower collapses in May
8Much of the 'outage' is economic reserve-shutdown - 2,700 MW of Western gas parked idle Details

FUEL & COAL LEDGER

Jul 22: 8Twenty-seven thermal plants ran coal-critical on 20 July; Damodaram Sanjeevaiah at 2%
8Coal ministry says 42 mines have been scientifically closed - a first since independence
8Fly-ash use hit 98.3% in 2024-25, but barely 1% of it moves by rail Details

HYDRO & RESERVOIR LEDGER

Jul 22: 8Telangana's Krishna reservoirs sit about 92% below last year deep into the monsoon
8Odisha's hydro fleet ran about 350 MW with several OHPC units forced out and reservoirs below last year
8Sikkim generated zero units on 21 July with the 1,200 MW Teesta-III still out since 2023 Details

CERC DOCKET

Jul 22: 8CERC proposes to grant PI Green Consulting a Category-V inter-state trading licence
8CERC clears POWERGRID's Mahan-Rewa transmission licence and rebukes Mahan Energen for non-compliance Details

STATE REGULATORY ROUNDUP

Jul 22: 8Uttarakhand's regulator clears a Kedarnath feeder after the fact and rebukes UPCL for jumping the gun
8Uttarakhand's ombudsman quashes a Rs 11 lakh back-bill and orders recovery from erring UPCL officers
8Bihar reserves one Section-142 order, lists two more and opens a supply code for sugar mills
8UP's regulator admits an Ayesha Steel removal-of-difficulty plea for a 20 August hearing
8Chhattisgarh's regulator takes up Jindal Steel's captive Raigarh ARR with a Rs 48 crore true-up gap
8Assam opens a public hearing on paying interest on consumers' security deposits
8Punjab's regulator advertises five deputation posts, including a secretary to the chairperson Details

GREEN MARKETS & RE PROGRAMME WATCH

Jul 22: 8MNRE extends the ALMM solar-cell exemption to 31 December 2026 for rooftop and open-access
8India's renewable capacity reaches 288.58 GW, four times its 2014 level, MNRE tells Parliament
8The power ministry halts two Tamil Nadu offshore-wind transmission projects
8India's battery-cell scheme has awarded 40 GWh but drawn zero incentive and Rs 5,180 crore of investment
8ACME Solar signs its 300 MW SECI hybrid PPA at Rs 3.25, lifting signed capacity to 6,870 MW
8Tripura's ADB-funded distribution plan pairs a 120 MW gas revamp with rooftop solar for weavers Details

CORPORATE WIRE

Jul 22: 8Adani Energy Solutions' Q1 profit doubles to Rs 1,237 crore
8Jharkhand's discom posts a Rs 1,839 crore half-year loss
8JSW Energy lifts its Toshiba-turbine stake to 20.7% as its GE Power India merger clears the vote
8BHEL's Trichy unit carries a Rs 43,927 crore order book as it lifts capex and nuclear supply
8Servotech's Q1 revenue jumps 66% to Rs 208 crore on solar, chargers and storage
8Viviana Power Tech commissions a 400 kV wind-evacuation line and carries a Rs 1,340 crore book
8REC floats a Maharashtra transmission SPV for a 400 kV Solapur switching station
8Kirloskar Electric flags going concern even as it turns a small profit and raises Rs 40 crore
8NLC India raises Rs 150 crore of commercial paper as the July results run fills the diary
8Ratings Watch - ICRA assigns 'A' to Blupine's 50 MW Karnataka solar group; reaffirms AA+ for Adani Energy Solutions Details

COMMITTEES, PEOPLE & SYSTEM ADMINISTRATION

Jul 22: 8The North-East's control-system bill jumps Rs 167 crore as its grid loses visibility
8Three regions' weekly settlements paid generators Rs 100 crore-plus of must-run
8Three inter-state lines were charged in June, but 54 of 86 remain behind schedule
8PSPCL ties promotions to strike-regularisation as its establishment churns through 50-plus officers
8Rajasthan's RVPN reopens employee pay-fixation and amends its 1964 service regulations
8SJVN's state-nominee director ceases office as PSU board seats turn over Details

Methane blast kills at least 20 at NHPC's under-construction Teesta-VI tunnel in Sikkim

Jul 22: 8A sudden burst of methane deep inside the head-race tunnel of NHPC's 500 MW Teesta Stage-VI project at Samardung touched off an explosion and toxic fumes shortly after 1 pm on 20 July, trapping 25 workers and project officers. By the morning of 22 July at least 20 were confirmed dead and a handful still missing, as rescue teams battled the same gas that caused the blast. Details

IEX day-ahead sat at the Rs 10,000 ceiling in 54% of 21 July's blocks yet crashed to Rs 1,618 at noon

Jul 22: 8The day-ahead market averaged Rs 6,617.61 a MWh on 21 July but sat pinned at the Rs 10,000 ceiling through the overnight and evening blocks, then collapsed to Rs 1,617.91 in the solar-flooded early afternoon. None of it was scarcity - the grid met a 235,132 MW evening peak with zero shortage; the crunch is the shape of the day, not a shortage of power. Details

The grid paid Western generators Rs 80 crore in one week to stay on the site as monsoon load slumped

Jul 22: 8The Western load-despatch centre’s security-constrained unit-commitment account for 6–12 July shows Rs 80.17 crore paid to keep coal and gas units committed and run up, led by Rs 14.98 crore to NTPC’s Khargone. In the same week the Eastern pool paid a further Rs 21 crore of must-run, Farakka alone drawing Rs 15.6 crore - the cost of holding thermal ready while midday solar forces it down. Details

Half of India's inter-state transmission build is late - Rajasthan and Khavda solar links slip up to six years

Jul 22: 8The CEA’s June progress report shows 54 of 86 under-construction inter-state transmission lines awarded through competitive bidding running behind schedule, many of them the very lines meant to evacuate Rajasthan and Khavda solar. Sterlite’s Goa–Tamnar link has slipped almost six years; a cluster of renewable-zone corridors is 12 to 24 months late. Details

Adani Energy Solutions' Q1 profit doubles to Rs 1,237 crore on a Rs 71,779 crore transmission pipeline

Jul 22: 8Adani Energy Solutions reported a consolidated first-quarter net profit of Rs 1,236.56 crore, up 129%, on income of Rs 9,852 crore and EBITDA of Rs 3,178 crore. It is carrying a Rs 71,779 crore under-construction transmission pipeline and has agreed to buy the IntelliSmart smart-metering platform outright for Rs 3,050 crore. Details

The North-East grid is going blind as its control-system bill jumps Rs 167 crore on AI-driven hardware prices

Jul 22: 8The North-Eastern committee’s papers for its 23 July meeting show the region’s new SCADA and energy-management build re-costed to Rs 688.61 crore from Rs 521.67 crore, a Rs 167 crore jump the committee blames on server and memory prices inflated by AI data-centre demand. At the same time real-time visibility of the grid has collapsed - Nagaland is telemetering under 30% of its data to the regional despatch centre. Details

Twenty-seven thermal plants run coal-critical in mid-monsoon - Andhra's Damodaram Sanjeevaiah down to 2%

Jul 22: 8National coal stock at power plants held about 40.75 million tonnes, roughly 13 days’ cover, on 20 July - but 27 individual plants were running critical, one more than a week earlier. Andhra’s Damodaram Sanjeevaiah was at 2% of its normative stock and JSW’s two Torangallu units were out of coal altogether. Details

Jharkhand's discom posts a Rs 1,839 crore half-year loss as its accumulated deficit nears Rs 18,330 crore

Jul 22: 8Jharkhand Bijli Vitran Nigam’s unaudited results, filed ten months late under the distribution-reform scheme, show a Rs 746.70 crore loss for the September quarter and Rs 1,839.02 crore for the half-year. Its accumulated deficit is close to Rs 18,330 crore and its power-purchase bill alone exceeds its revenue from selling electricity. Details

India's under-construction coal fleet swells to 42,700 MW even as this year's additions collapse to 2,260 MW

Jul 22: 8The CEA’s June thermal status report shows 42,700 MW of coal capacity under construction, all supercritical, against a further 21,380 MW stalled or stressed. Yet only 2,260 MW of a 7,300 MW target has been commissioned this year - and most fleet growth now comes through insolvency buyers, not greenfield builds. Details

Contracting news for the day: Part-1

Jul 22: 81. PSTCL floats 90-day civil works tender for 160 MVA transformer at 220 kV Bathinda substation
PSTCL has published a notice inviting tender for civil works connected with a 160 MVA transformer at its 220 kV GNDTP Bathinda substation, with a compressed 90-day completion window and quoted rates valid for 120 days. Tender documents will be issued only to firms the corporation considers adequately experienced, though no qualification formula is disclosed. A striking drafting anomaly sits inside the notice: the document-issue deadline falls after the bid-submission deadline. Unless corrected, the timetable is internally unworkable and could undermine competitive participation.

 

82. UJVNL packages river diversion, tunnelling and powerhouse into single Rs 87.90 crore Tankul hydro contract
UJVN Limited has invited online bids for constructing the 12 MW Tankul small hydro project in Pithoragarh, combining trench weir, intake, river diversion, desilting tank, tunnel, surge shaft, powerhouse and hydro-mechanical works in one mandate. The submission deadline has moved by 25 days through two extensions alongside two corrigenda, signalling the package required correction before closure. Bidders must price geological uncertainty, river behaviour and remote Himalayan logistics into a compact contract value. The project's execution complexity far exceeds its modest installed capacity.

 

83. BSPGCL couples 150 MW solar with 75 MW/300 MWh battery in tariff-based bid with capacity-linked EMD
Bihar State Power Generation Company has issued an NIT to develop 150 MW of solar PV integrated with a four-hour battery system through tariff-based competitive bidding followed by e-reverse auction. The EMD scales at Rs 14.24 lakh per MW quoted, discouraging speculative capacity offers, while the original bid-security instrument must physically reach BSPGCL despite an otherwise digital process. Battery degradation, augmentation and charging rules — central to project economics — are left to the detailed documents. The outcome could set an early state benchmark for solar-plus-storage pricing.

 

84. HPSEBL seeks Rs 3.72 crore project management consultant under QCBS — then adds a reverse auction
HPSEBL has floated an RFP for a project management agency to support its reforms-linked distribution scheme, deploying 246 expert man-months across engineering review, field monitoring and funding-claim support, with the deadline extended by ten days. Selection follows a 70:30 quality-cost formula, yet the notice simultaneously announces an e-reverse auction — an unresolved structural clash. A Rs 70 crore annual turnover threshold towers over the modest assignment value, favouring large national consultancies. HPSEBL also retains the right to double expert deployment in every category, shifting staffing risk onto the consultant.

 

85. OCPL hands one consultant the entire blueprint for its 5 MTPA Manoharpur coal washery
Odisha Coal and Power Limited is appointing a single adviser to prepare the DPR, washability study, CAPEX-OPEX-IRR modelling and the complete EPC tender architecture for a proposed 5 MTPA coal washery, with the deadline extended by 18 days after the original schedule lapsed. The washability study must run through one of six named institutions, tying a core milestone to external laboratories. Joint ventures are barred, concentrating all credentials in one entity, while least cost selection meets a strict abnormally-low-bid clause that can exclude aggressive quoters from retenders. The 120-day programme leaves little slack for approval cycles.

 

86. GSECL's Rs 4.73 crore covered-conductor retrofit at Ukai TPS carries a 36-month owner-controlled execution horizon
GSECL has floated an open three-stage e-tender to replace 16 km of exposed 11 kV conductors at Ukai Thermal Power Station with medium-voltage covered conductors, including eight double-pole air-break switch structures and dismantling of old lines, as an indivisible supply-plus-works package. Supply must finish in six months, but the work order stays valid for 36 months — extendable by six more at unchanged prices. Thirty per cent of supply value remains locked until successful charging, tying contractor cashflow to shutdown availability. With no guaranteed work-release schedule, bidders are pricing a long-duration call-off obligation, not a fixed-schedule job.

 

87. MSEDCL extends commencement window but holds commercial line on Rs 130.38 crore STAR-II transformer buy
MSEDCL has issued Amendment No. 1 with pre-bid clarifications on its tender for 200 kVA STAR-II CRGO distribution transformers, extending the commencement period from two to three months while keeping the nine-month delivery schedule intact. Manufacturer requests for revised estimated cost, IEEMA price variation, relaxed experience thresholds and softer security terms were all rejected, while BEE certification was confirmed as not required for 22 kV units. The amendment signals selective operational flexibility without commercial concession. Certification-heavy entry barriers remain firmly in place for smaller suppliers.

 

88. POWERGRID engages exclusive land valuer for 219 km transmission corridor in Morbi under package-wise GeM bid
POWERGRID has invited a two-packet GeM bid to appoint a land valuer for transmission-line corridors in Morbi district under Package-7, covering roughly 219 km, with the consultant certifying survey-number-wise market rates for compensation and acquisition. The valuer must work exclusively for POWERGRID and is barred from representing any other project stakeholder — a stronger conflict-management measure than routine consultancy tenders carry. The district-wise package model spreads work across Gujarat while limiting how many packages one bidder can secure. The tender treats land valuation as project-critical infrastructure work rather than conventional advisory service.

 

89. NREDCAP offers 22-year DBFOT concession for Rs 324.70 crore Vijayawada waste-to-energy plant
NREDCAP, acting for Vijayawada Municipal Corporation and participating urban bodies, has issued an RFP for a private concessionaire to design, build, finance, operate and transfer a 15 MW municipal-waste-based power plant under a 22-year concession including two years of construction. The Rs 3.24 crore EMD and qualification framework point toward experienced infrastructure developers rather than general EPC contractors. Financing strategy and long-term operating assumptions will matter more than EPC pricing in determining competitiveness. The structure reflects a policy preference for private lifecycle ownership of complex municipal processing assets.

 

810. NTPC Ramagundam to double transformer capacity with 500 MVA units under integrated 30-month contract
NTPC has invited domestic bids to replace two 250 MVA auto transformers at Ramagundam with 500 MVA interconnecting units, bundling design, manufacture, transport, oil treatment, erection and commissioning into one accountability chain over 30 months. An unusual clause forces installation pricing into a 10–15% band of supply value, blocking payment-structure engineering. Loss penalties reach Rs 10 lakh per kW for no-load deviation — with no reward for overperformance — while the variable-price contract offers only narrow escalation relief. A Rs 1 crore bid security applies with no MSE exemption.

 

811. BHEL's 400 kV GIS package for Yamuna Nagar loads firm pricing, reverse auction and long-tail liabilities onto suppliers
BHEL is procuring a complete 400 kV gas-insulated switchgear installation for HPGCL's 800 MW ultra-supercritical expansion at Yamuna Nagar, with the deadline extended twice after a technical corrigendum rewrote testing, transport, packing and scope-boundary provisions. Prices stay firm across a 12-month supply cycle, while the 18-month warranty starts only after project trial operation — a milestone outside the supplier's control. Entire specification clauses were deleted without replacement, creating interpretation gaps, and packing must survive 24 months of outdoor monsoon exposure. Impact recorders must trace every shock from factory to site, with a reverse auction awaiting qualified vendors.

 

812. NTPC Talcher Kaniha's Rs 84.81 crore ash-backfilling contract pays only the lower of two measurements
NTPC has floated a GeM bid restricted to its enlisted ash-transport vendors for excavating, hauling and compacting ash from Talcher Kaniha into quarries and mine voids 50–100 km away, under a 12-month contract splittable 50:50 between two bidders. Payment follows the lower of dispatch-end or filling-site measurement, and every truck movement needs weighbridge, GPS, FASTag, toll and geotagged photo evidence uploaded daily — incomplete records mean withheld payment. A quantity mismatch between the scope figure and doubled BOQ entries demands careful reconciliation. Regulatory penalties on NTPC flow back entirely to the contractor, converting a transport job into a full land-reclamation obligation.

 

813. AEGCL's fixed-price 220 kV line for TATA semiconductor plant transfers all design-modification costs to the contractor
Assam Electricity Grid Corporation has published a turnkey tender for a 220 kV Sonapur-TSAT double-circuit line providing redundant power to the TATA semiconductor facility, spanning overhead line, underground cable, optical fibre and commissioning under single-point responsibility within 24 months. There is no advance payment and no escalation: AEGCL supplies the base design, but site-driven modifications — special towers, pile foundations, raised chimneys — must be executed at zero additional cost. The warranty runs five years from supply or four-and-a-half from commissioning, whichever is later, with liquidated damages at 1% per week up to 10%. Payments can take 60 days, subject to fund availability.

 

814. Powergrid caps land valuers at one package each across ten-district Gujarat valuation drive
Powergrid has issued a GeM bid for an IBBI-recognised land valuer covering 246 tower locations across 91.74 km spanning three transmission SPVs in Vadodara district, one of ten sequentially opened packages, with every assignment due within 15 days of intimation. A "one agency, one package" rule prevents any single firm from dominating, while packages with three or fewer bidders jump the price-opening queue. No escalation applies, quantities can swing 25% either way, and the bid summary denies arbitration even as attached conditions prescribe a full arbitration regime. Consistency across multiple independent valuers remains the unaddressed governance risk.

 

815. JREDA opens Jharkhand's 16-site hydro pipeline to solar, wind and thermal players through eligibility rewrite
JREDA has issued an EOI to identify developers for small hydro projects across 16 Jharkhand sites under the BOOT model, beginning with surveys and DPRs before full development, financing and long-term operation. Corrigendum-I broke the hydro-only entry barrier: any 5 MW DISCOM PPA — solar, wind or thermal — now qualifies, provided the bidder operates a plant in the supplying state, with the deadline extended by 14 days. A Rs 50 crore turnover floor screens for balance-sheet depth over technical pedigree. Concession terms, tariffs and free-power obligations are deferred entirely to the RfP stage, making second-stage evaluation the critical safeguard.

 

816. UJVNL's Sirkari Bhyol hydro tender swells 53% to Rs 243 crore through twenty corrigenda
UJVN Limited's EPC tender for the electromechanical works of the 3x40 MW Sirkari Bhyol Rupsiabagar project has been transformed through twenty corrigenda and seven addenda: the estimated value jumped 53% to Rs 243.05 crore, the EMD rose to Rs 4.87 crore, and every qualification threshold was rewritten upward. Technical access simultaneously widened through a fifteen-year experience window, more approved component makes and flexible efficiency testing, even as financial entry tightened. Himalayan logistics, construction power and site utilities stay contractor-facing despite repeated bidder requests for relief. Bidders must hold prices for 270 days on a package still being stabilised months after publication.

Details

Download tenders and news clips

Jul 22:  For reference purposes the website carries here the following tenders:
 8Tender for supply and installation of digital type loadcell based overload and slack protection me chanism for various hoists gantry cranes installed Details
 8Tender for work of supply of T and P (tools and plants) materials Details
 8Tender for work of providing and erection of additional poles Details
 8Tender for work of replacement of old PVC cable with new PVC armoured cable Details
 8Tender for R&M works including supply and installation of 11 kV indoor VCB panel Details
 8Tender for erection, dismantaling and maintenance of HT/LT and transformer Details
 8Tender for annual rate contract (ARC) for LED lights & related spares items Details
 8Tender for annual rate contract for various types of structural steel items. Details
 8Tender for NDCT overhauling works Details
 8Tender for procurement of CW pump mechanical seals Details
 8Tender for procurement of galvanized gratings and end bar Details
 8Tender for hot line stringing of 66 kV line Details
 8Tender for dismantling of existing fencing and installation of new main gate along Details
 8Tender for procurement of cable termination kit Details
 8Tender for material handling and management including receipt, unloading, verifying, shifting, stacking, preservation, handling and handing over of components of boiler with auxiliaries Details
 8Tender for modification of steam generator (boiler) of 210 MW for comprehensive work Details
 8Tender for replacement work of old main switch, fuse unit etc. Details
 8Tender for renovation of control room at 110 kV substation Details
 8Tender for shifting of electrical utilities in connection Details
 8Tender for supply of 3 nos digital insulation resistance tester Details
 8Tender for procurement of 180KW, 3.3kV HT motors Details
 8Tender for R and M of existing fire detection and protection system Details
 8Tender for replacement of existing 250MVA auto transformers with 500MVA transformer Details
 8Tender for housekeeping work of 2x150 MVA 220/ 132kV grid sub station Details
 8Tender for supply of wall soot blower and oil gun spares for boiler Details
 8Tender for supply, erection and commissioning of various accessories of conveyor belt Details
 8Tender for construction of yard work and misc. civil works at 33kV S/S Details
 8Tender for construction of control room, cable trench, water supply arrangement at 33 kV s/s Details
 8Tender for purchase of spares for 420kV, 3150A, TP, HCB isolators with earth switches Details
 8Tender for procurement of spares for BHEL make DVAR Details
 8Tender for supply, erection & commissioning of 11 kV lines with MVCC conductor & dismantling of existing Details
 8Tender for supply, erection, testing and commissioning of 220 V DC, 63 AH, KPH 63P, Ni-Cd type battery set Details
 8Tender for biennial rate contract for motor or heavy equipment lifting or shifting or placement and motor coupling fitting works Details
 8Tender for execution erection work for effecting the 33kV bulk NSC by laying UG 33 kV 3CX400 SQMM XLPE cable Details
 8Tender for execution of erection work by erection of 11KV RMU, laying of 11kV XLPE UG cable, laying of HDPE pipe Details
 8Tender for round the clock maintenance for routine breakdown and preventive maintenance of 4 x 9 MW and 2 x 4 MW TG sets with all auxiliaries 66 kV switchyard Details
 8Tender for electrical work for construction of 2X5 MVA 33/11 kV S/S Details
 8Tender for construction of 26 KM.33kV line Details
 8Tender for providing and fixing of insulated sheet for ST pole Details
 8Tender for work of replacement of old PVC cable with new PVC armoured cable Details
 8Tender for work of installation of one No. 5 MVA power transformer at 33/11 kV sub-station Details
 8Tender for providing and fixing of insulated sheet Details
 8Tender for providing and fixing of insulated sheet for ST pole Details
 8Tender for work of overhauling, servicing & repairing work of 400kV circuit breaker Details
 8Tender for work of bi-annual maintenance contract for the work of servicing, repairing of various size and capacities battery sets and chargers Details
 8Tender for supply of 5nos spare numerical distance protection relay Details
 8Tender for refilling, servicing & maintenace, supply of spares for fire extinguishers at various substations Details
 8Tender for work of feeder re-orientation at 110kV & 220kV substation Details
 8Tender for work of supply & installation of advance cable transit system by passive fire screen Details
 8Tender for work of fabrication and supply of 50 kL empty oil tank Details
 8Tender for AMC for battery sets maintenance work (220 volts & 48 volts) and charger Details
 8Tender for annual maintenance contract for repairs, overhauling of 33 kV VCB installed Details
 8Tender for work of providing & fixing of maintenance free earthing at 220 kV line Details
 8Tender for supply of pressure relay of converter transformer Details
 8Tender for work of supply and installation of bird diverters (BFD) on 132kV DC transmission line Details
 8Tender for conversion of existing indoor SF6 & VCB AIS switchgear panels pertaining Details
 8Tender for rate contract of excavation and laying of new power / control / telephone cables Details
 8Tender for supply and application of epoxy glass flake coating with UV resistance PU top coat on various external surfaces Details
 8Tender for supply of control panel spares of pump house Details
 8Tender for R&M work of erection, commissioning of new feeder bay HV & LV equipment’s, testing ,earthing,control wiring etc. of 220/66kV 160 MVA transformer Details
 8Tender for erection and maintenance of HT/LT & TC work Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8
India’s Coal Mine Closure Report and GIZ Agreement Explained Details
 
8Bharat Coking Coal shares drop over 7% after Q1 net loss, lower offtake Details
 
8India’s Coal Self-Reliance Push: Govt Takes Major Steps to Boost Production and Reduce Imports Details
 
8Coal Ministry to Sign MoUs for Sustainable Mine Closure, Jharia Rehabilitation and Skill Development Details
 
8SECL Plants 3.20 Lakh Saplings in a Day, Builds Bilaspur’s First Miyawaki Forest for Greener Future Details
 
8Pumped hydro storage of 16 GW capacity under construction: Power Ministry Details
 
8Core sector growth reaches five-month high in June, lifted by iron ore and power Details
 
8PM-KUSUM's Missing Link: Why India's Solar Pump Success Isn't Yet an Agricultural Energy Revolution Details
 
8Power discoms await revival as structural reform delays persist in India Details
 
8Major Boost to Island Energy Security as 50 MW LNG Power Project Moves Forward Details
 
8Why Storage Hydropower Must Become Nepal's Next National Priority Details
 
8India Reaches 548.85 GW Power Capacity As Renewables Account For 43.09%, And Solar Hits 162 GW Details
 
8Tata Power wins 324 MW SECI pumped hydro project Details
 
8India tunnel collapse at a hydropower project kills 10 as 17 remain missing Details
 
8Transformers & Rectifiers India Reports 8% Q1 FY27 Revenue Growth, Order Book Reaches Record INR 6,630 Crore Details
 
8MAHLE Unveils Range Extender and Magnet-Free Motor for Heavy Commercial Vehicles Details
 
8India’s clean energy boom: Why the City of London should be paying attention Details
 
8India’s Renewable Energy Generation Crosses 100 GW for the First Time Details
 
8Stocks to Watch: Adani Power, Eternal, and 6 Other Stocks Announcing Q1 Results Today Details
 
8India’s renewable energy capacity jumps nearly to 288.58 GW Details
 
8Kolkata Power Network Eyes Digital Meter Expansion Details
 
8EAC-PM Report Flags India's Power Grid Vulnerability Details
 
8NLC India Raises Rs 150 Crore Through Commercial Paper Issue to Boost Liquidity and Support Growth Plans Details
 
8India Allows 4 Chinese-Linked Firms to Bid on Power Projects Details
 
8India Signs Major Nuclear Technology MoU: NPCIL and ECIL to Develop Critical Systems Details
 
8ACME Solar signs PPA with SECI for 300MW ISTS-connected Wind-Solar Hybrid Renewable Energy Project Details
 
8REC Signs Agreement with RITES to Ensure Quality Checks of Power Transformers Under RDSS Details
 
8J&K Readies 1,624 MW Hydropower Units by December 2026 Details
 
You can also click on Newsclips for more Details

Hydro & Reservoir Ledger

Jul 21: 8Telangana’s Krishna-basin storage has collapsed about 92% year on year, Srisailam and Nagarjunasagar near-empty
8Odisha hydro ran about 528 MW on 19–20 July with several OHPC units forced out and reservoirs below last year Details

Eastern thermal earned about Rs 112 crore in June for running part-loaded - the same stations were also failing their frequency duty

Jul 21: 8Beneficiary states under-requisitioned below 85% of their entitlement, forcing nine Eastern-region thermal stations to run at part load, and the compensation bill for it reached about Rs 111.9 crore for the fiscal year to June. The stations that ran part-loaded also posted the region’s weakest frequency-response scores, so the pool is paying twice - once in compensation, once in lost grid support. Details

Day-ahead power hit the Rs 10 ceiling overnight and at dusk on 20 July - yet the grid met a ~239 GW peak nearly shortage-free

Jul 21: 8The day-ahead market averaged Rs 6,801 a MWh on 20 July but sat at the Rs 10,000 ceiling through the overnight hours and again in the evening, then collapsed to about Rs 1,815 in the solar-flooded middle of the day. None of this was scarcity - the grid met a roughly 239 GW peak with barely a megawatt-hour of shortage; the crunch is the shape of the day, not a shortage of power. Details

The North met a 93,981 MW summer peak nearly shortage-free - but a single wind trip cost Rajasthan 1,290 MW

Jul 21: 8The Northern Region’s peak demand climbed through the June quarter to 93,981 MW and was met with under half a percent of shortage, with Uttar Pradesh the only state left short. Yet the quarter also shows how thin the margins are: single elements swung a gigawatt at a time. Details

Jaiprakash Power’s Q1 profit jumps 69% to Rs 469 crore as NARCL files insolvency over a Rs 1,239 crore guarantee

Jul 21: 8Jaiprakash Power Ventures reported a standalone Q1 profit of Rs 468.95 crore, up 69% year on year, even after absorbing a Rs 193.63 crore exceptional loss. In the same disclosure it flagged that NARCL has filed a Section 7 insolvency petition against it over a Rs 1,239 crore corporate guarantee - the overhang that now prices the stock. Details

MERC lets Adani’s Mumbai discom adopt Rs 6.38 a unit for 750 MW of round-the-clock renewable power

Jul 21: 8The Maharashtra commission allowed Adani Electricity Mumbai’s distribution arm to adopt a Rs 6.38 a unit tariff for 750 MW of round-the-clock renewable power under a ten-year deal, undercutting MSEDCL’s own effective benchmark. It is a signal on where firm-renewable pricing is settling. Details

India’s pumped-storage build-out reaches 15,870 MW under construction as SECI awards another 1,344 MW

Jul 21: 8The power ministry told Parliament that 11 pumped-storage projects totalling 15,870 MW are under construction, with a further 24,010 MW in the pipeline. In the same week SECI’s first pumped-storage tender awarded 1,344 MW of a 1,500 MW offer, confirming the shift from policy to procurement. Details

Twenty-six thermal plants sit critical on coal in mid-monsoon - Andhra’s Damodaram Sanjeevaiah down to 2%

Jul 21: 8National coal stock at power plants held about 41 million tonnes, or roughly 21 days, on 19 July - but 26 individual plants were running critical, with Andhra’s Damodaram Sanjeevaiah at just 2% of its normative stock. The average hides a distribution problem, not comfort. Details

Punjab’s power employees and pensioners strike for two days, forcing PSPCL to draft engineers to man substations

Jul 21: 8PSPCL’s own management circulated an order on 20 July confirming that a joint front of power employees and pensioner bodies will hold a statewide protest and mass leave on 21–22 July, with pensioners threatening a “jail bharo” agitation. Chief engineers have been told to ensure every substation is manned through the stoppage. Details

Maharashtra’s new RE policy blocks MERC from ordering MSEDCL to buy Waterfront’s small-hydro - even after fixing its Rs 6.18 tariff

Jul 21: 8MERC determined a tariff of Rs 6.18 a unit for Waterfront’s 3 MW small-hydro project but refused to direct MSEDCL to sign a power-purchase agreement, because Maharashtra’s March 2026 renewable-energy policy dropped the procurement mandate. The regulator fixed the price and then found it could not compel the sale. Details

About 40 GW sat on outage on 20 July as North Chennai lost 800 MW and Rajpura 700 MW to boiler and ESP faults

Jul 21: 8Generation outages ran to about 40 GW across the northern, western and southern registers on 20 July, and the day added fresh forced trips - North Chennai’s 800 MW unit hand-tripped on an ESP problem and Rajpura’s 700 MW unit on a boiler-tube leak. This parked baseload is the other half of the day’s price story. Details

Power Markets Daily

Jul 21: 8Day-ahead power averaged Rs 6,801 a MWh on 20 July but sat at the Rs 10,000 ceiling overnight and at dusk
8Real-time power cleared just 3.34 MU at the Rs 10,000 ceiling; the green, intraday and ancillary segments did not clear
8Term and green contracts settled around Rs 7,500 a MWh as the high-price exchange (HPX) day-ahead did not clear on 20 July
8DVC floats an August reverse auction for two 100 MW thermal bands across the exchanges, e-auction 22 July Details

Grid Operations Daily

Jul 21: 8All-India peak of about 239,106 MW was met on 20 July with roughly 1 MU of shortage
8The grid ran high 28% of 20 July - 6.75 hours outside the IEGC band, peaking at 50.251 Hz
8Rajasthan and the NR–ER corridor breached their transfer limits about 20% and 17% of 20 July
8Maharashtra shed about 0.195 MU on 20 July when a 132 kV line overloaded and grid-security load-shedding operated
8The Northern grid met a 93,981 MW June-quarter peak nearly shortage-free Details

Outage & Maintenance Register

Jul 21: 8About 40 GW sat on outage on 20 July; North Chennai 800 MW and Rajpura 700 MW tripped
8Further 20 July trips took out KSTPS 500 MW, Meenakshi 350 MW, Paras, Neyveli, Ukai and Tuticorin units
8Yadadri’s 800 MW unit has been out on coal shortage since 9 July; ACBIL 135 MW out on coal since 12 June
8The 765 kV Ariyalur–North Chennai line was still out late on 20 July after a fault; a Gadarwara 765 kV line faulted
8Champa’s 400 kV bays were out on station flooding and Vindhyachal HVDC Pole-1 had tripped in the West
8The northern and western transmission registers ran to 538 and 422 elements on 20 July, storm-collapse lines still standing Details

Fuel & Coal Ledger

Jul 21: 8Twenty-six thermal plants ran coal-critical on 19 July; Damodaram Sanjeevaiah at 2%
8The Ministry of Coal advances a Rs 37,500 crore gasification scheme, applications closing 7 September
8Thermal plants held 42.8 MT of coal and 14 days’ cover as coal supplied 69.5% of Q1 power, the ministry told Parliament
8Delhi’s Pragati gas plant ramped spot RLNG offtake about six-fold into the summer, its bill reaching Rs 85.9 crore a fortnight Details

Daily Power Sector Tenders Excel update

Jul 21: 8Daily Excel covering new tenders and all published updates including corrigendum, amendment, addendum, clarification and status revisions, along with technical and financial bid opening, evaluation completion and final award actions including AOC and LOA issuance.
Click on Reports for more Details

CERC Docket

Jul 21: 8CERC cut NTPC’s decommissioned Talcher 460 MW annual charge to Rs 475 crore and disallowed most residual capex
8CERC shielded SJVN Green’s 860 MW connectivity from CTUIL revocation and barred encashment of its bank guarantees
8CERC reserved orders on THDC’s water-tax change-in-law claim for the Tehri and Koteshwar hydro stations
8NEEPCO sought a cut in its Tripura gas station’s availability norm to 70% as ONGC gas supply more than halved
8PSPCL and Pragati Power head to a 13 August hearing over a Rs 82.99 crore Pragati-III billing dispute
8CERC reserved a ruling on whether it can hear the TNPDCL–PTC 150 MW pilot-power dispute at Rs 3.26 a unit
8CERC admitted six NLDC and RLDC fee truing-up petitions for 2019-24 and issued notices
8Trading-licence moves: CERC reserved Infinite Voltx’s Category V grant and sought RPG Power Trading’s accounts
8CERC docket calendar - Kishtwar Transmission security interest admitted, UPPCL water-tax amendment allowed, ISTS-charge batch adjourned
8APTEL’s Court-I and Court-II carried 257 and 27 short matters and over 1,670 final appeals as on 17 July
8GERC cleared VMS TMT’s 11.88 MW solar connectivity but refused Iran-conflict force majeure; adjourned Gujarat discoms’ net-metering plea Details

State Regulatory Roundup

Jul 21: 8MERC let Adani’s Mumbai discom adopt Rs 6.38 a unit for 750 MW round-the-clock renewables
8MERC suspended MSEDCL’s power to seize an under-used consumer feeder and ordered Rs 45 lakh compensation
8MERC ordered MSEDCL to pay Vena Energy Rs 11.42 crore in late-payment surcharge and interest on wind dues
8MERC cleared a provisional tariff for Adani’s Rs 6,888 crore 1,000 MW HVDC link, trimming the claimed cost
8Maharashtra’s RE policy blocked MERC from ordering MSEDCL to buy Waterfront’s small-hydro
8MERC dismissed about 1,959 MW of NOPL solar change-in-law claims for non-appearance and closed a settled Talf Solar guarantee dispute
8Bihar’s regulator set FY27 biomass and bagasse tariffs and restored them retrospectively to 1 April
8CSERC let Shree Cement raise its Chhattisgarh contract demand to 51 MVA at a 5% energy surcharge
8Assam’s regulator holds a public hearing on the 8th amendment to its electricity supply code
8Tamil Nadu’s electricity ombudsman part-voided a Rs 2.73 lakh back-billing on a defective meter Details

Green Markets & RE Programme Watch

Jul 21: 8Renewables met about 38% of demand at midday on 20 July, solar peaking at 69.1 GW
8SECI awarded 1,344 MW of pumped storage as the national build-out reached 15,870 MW
8BNC Power won SECI’s 10 MW Odisha solar tender at Rs 2.60 a unit with zero viability-gap funding
8ACME Solar signed a 300 MW hybrid PPA at Rs 3.25 and commissioned 160.5 MWh of Rajasthan battery storage
8KPI Green commissioned 200 MW of Coal India’s 300 MW Khavda solar and won charging nod for a 100 MW Maharashtra plant
8MNRE sanctioned a Rs 436.93 crore renewable R&D programme with a Rs 200 crore perovskite pilot line
8SECI opened an EOI to aggregate bulk renewable off-takers and set a 3 August site visit for a 45.6 MW wind EPC Details

Corporate Wire

Jul 21: 8Jaiprakash Power’s Q1 profit rose 69% to Rs 469 crore as NARCL filed insolvency over a Rs 1,239 crore guarantee
8Transformers & Rectifiers’ order book hit a record Rs 6,630 crore as Q1 inflows surged 218%
8GE Power India’s shareholders and creditors met to clear its absorption into JSW Energy
8ICICI Direct rated BHEL a Buy at Rs 575 on a record Rs 2.6 lakh crore order book
8Nava lifted its FY26 dividend to a record Rs 8.50 as Zambia arrears fell to US$28 million
8Corporate diary - JK Cement Q1 profit slips 12% to Rs 291 crore; Premier Roadlines books Rs 182 crore of power orders
8Smaller filings - CLN Energy reprices a promoter issue to Rs 423; Pace Digitek’s Lineage ties up AI-data-centre power; L&T bags mega metals EPC
8Results and board diary - Waaree Renewable, Indosolar and RattanIndia Power report over 23–24 July Details

Committees, People & System Administration

Jul 21: 8Punjab’s power employees and pensioners strike on 21–22 July, forcing PSPCL to man substations
8The Eastern committee’s June settlement run put about Rs 112 crore of part-load compensation across nine stations
8The Eastern frequency scorecard ranked PVUNL (0.33) and JIPL (0.41) the region’s weakest responders in June
8PSPCL reshuffled 16 senior officers and about 25 substation engineers and sanctioned posts for a new 66 kV grid
8PSPCL’s CMD leads a team to POWERGEN India as the utility revises induction and training rosters
8Mahatransco named 28 apprentices for its 2026-27 intake at Nagpur Details

Contracting news for the day: Part-1

Jul 21: 81) APGENCO's Dr NTTPS meter tender carries three conflicting reference numbers and four different bid-closing times The portal cites M100030900/P41 while the NIT and enquiry use P211 and a longer CE/O&M reference. Submission deadlines shift across 12:00, 13:00, 14:00 and 15:00 hrs depending on the document read. Latest: price-bid opening has been fixed, following the enquiry letter's own submission and opening timing.

 

82) OPTCL's Rs 256.29 crore Pahala tender makes one EPC contractor own a new GIS, a 9.94-km line and two live-station bay extensions The turnkey scope stitches the new GIS to Balianta through one integrated commissioning obligation. EMD is Rs 97.23 lakh. Latest: bids have closed and techno-commercial opening has taken place, with the price-bid date still pending.

 

83) A second APGENCO filing recasts the same NTTPS meter package as a straightforward digital-metering upgrade Scope bundles Secure-make ABT meters, RS-485/Modbus communication, HMI software and full commissioning into one contract. Eligibility favours manufacturers/dealers with PSU or utility metering experience. Latest: presented under a single, unconflicted P211 reference.

 

84) TGGENCO's 42-lakh-tonne coal haulage tender keeps daily quantity unguaranteed while penalising monthly shortfalls Bidders must move ~15,000 tonnes/day with GPS-fitted, dual-end-weighed tippers. Only 30% of the rate is diesel-linked; 70% stays fixed. Latest: the tender has opened, with pre-qualification bid opening due ahead of the price-bid opening.

 

85) MSEDCL's Rs 215.89 crore transformer tender softens qualification but holds firm on price and delivery 33/11 kV experience now counts toward the rarer 33/22 kV and 22/11 kV variants, and their type-test reports can follow bid submission. The nine-month delivery and 66-month warranty stay unchanged. Latest: Amendment No. 1 has been issued, extending the bid deadline.

 

86) POWERGRID gates its 765kV Bikaner substation package behind a mandatory NDA before releasing bid documents The package supports the Rajasthan REZ Phase IV evacuation corridor. Bidders must clear an eligibility and confidentiality screen before seeing specifications or pricing. Latest: the Invitation for Bids has been published, with bid submission and opening still ahead.

 

87) NTPC extends bidding on its Farakka generator-transformer replacement without touching scope or terms The 250 MVA transformer package covers design through commissioning under one 30-month contract. Bid security is Rs 50 lakh with a mandatory Integrity Pact. Latest: an extension notice has revised the bid submission and opening schedule, with scope and terms unchanged.

 

88) AEGCL's Sonapur–TSAT line for TATA Semiconductor pushes site-driven design changes into the contractor's fixed price The Rs 1.57 crore-EMD, 24-month turnkey package spans towers, pile foundations, 220 kV cable and underground OFC. Warranty runs 60 months from supply or 54 from commissioning. Latest: the tender has been published, with bid submission, closing and technical opening still ahead.

 

89) NHPC's Sawalkot dam package jumps 5.6% in value after a capacity correction and 123 days of deadline extensions The estimate rose from Rs 5,129.03 crore to Rs 5,416.94 crore after fixing capacity from 1,856 MW to 1,800 MW. Turnover and working-capital thresholds rose in step. Latest: Corrigendum 10 has fixed the online submission date, with hard-copy submission and techno-commercial opening following shortly after.

 

810) NTPC's Pudimadaka green-urea plant links a Simhadri CO2 unit to five process blocks across two sites under one lump-sum price Carbon capture at Simhadri feeds hydrogen, ammonia and urea production 25 km away at Pudimadaka, all under one lump-sum contract. Bid security is Rs 20 crore, shareable among consortium partners. Latest: Date Corrigendum 02 has moved the submission/opening deadline forward again, following Commercial and Technical Amendments.

 

811) NHPC's Rs 5,541 crore Kamala Lot-1 bundles dam, diversion tunnels and hydro-mechanical works into one civil package The 1,720 MW project in Kamla district combines diversion tunnels, cofferdams, the dam and access roads/bridges. EMD is Rs 10 crore against a 2,372-day execution period. Latest: document download and bid submission remain open, with bid opening scheduled shortly after.

 

812) NTPC's 200,000-unit limestone GeM tender splits award among four suppliers with freight dwarfing the material cost Balajee Steel Udyog took 75,000 tonnes; three others split the remaining 25,000 tonnes. All contracts land at Rs 3,960/tonne, Rs 740 material plus Rs 3,220 freight. Latest: award has been finalised, with contracts running over a one-year supply period.

 

813) GUVNL's short-term power RFP shifts nearly all transmission and sourcing risk onto generators and traders The tender seeks 500–1,000 MW across monthly windows through the procurement period. Interstate bidders absorb a fixed 3.50% regional loss adjustment intrastate suppliers avoid. Latest: the RFP has been published, with bids due shortly before the IPO opening and e-reverse auction on DEEP.

Details

Download tenders and news clips

Jul 21:  For reference purposes the website carries here the following tenders:
 
8Tender for establishment of 765/ 400 kV transmission scheme Details
 
8Tender for supply of 245 kV RIP/RIS bushing for various substations Details
 
8Tender for supply of 420 kV draw rod/lead RIP/RIS bushing for various substation Details
 
8Tender for packing forwarding insurance, transportation supply delivery unloading on for destination of 400 kV bushings Details
 
8Tender for packing forwarding insurance, transportation supply delivery unloading on for destination of 245 kV and below bushings Details
 
8Tender for supply of ferric alum Details
 
8Tender for supply of 360kW HT motor Details
 
8Tender for work of complete overhauling of carious pumps installed for T-G set & BOP auxiliaries Details
 
8Tender for strengthening of exit lane of the existing bituminous coal Details
 
8Tender for construction of 33 kV bay Details
 
8Tender for work of transportation of erection and commissioning of emergency restoration system on 132 kV line Details
 
8Tender for incrasing capacity of (2X63 MVA to 3X63 MVA) T/F and related civil work Details
 
8Tender for supply and repairing of various duct of Ventilation system and overhauling of various air centrifugal fan Details
 
8Tender for work of removal & laying of 6.6/11kV (E), 1C X 1000Sq.mm, aluminum cables along Details
 
8Tender for supply, installation, commissioning and testing of vibration monitoring system for continuous vibration measurement Details
 
8Tender for supply of heating element baskets for air pre-heater of PH IV Details
 
8Tender for supply of heating element baskets for air pre-heater of PH III Details
 
8Tender for supply of seals fo rotary air pre heater Details
 
8Tender for supply of single pole str materials spare Details
 
8Tender for supply of 110KW 10 pole condenser vacuum pump motor Details
 
8Tender for ancillary work required for smooth operation of belt conveyors Details
 
8Tender for construction of foundations for various electrical equipments VCB, CTPT, cable trenches Details
 
8Tender for supply of equipment / material , design, erection, testing , commissioning for system improvement scheme for replacement of old/obsolete switchgear equipment at 33/11 kV sub-stations Details
 
8Tender for construction of 33/11 kV, 2x10MVA GIS sub-station Details
 
8Tender for turnkey construction of 220 kV double circuit transmission line Details
 
8Tender for in-house outsourcing of fabrication of sub-assemblies of HP heaters, LP heaters, condensers, lube oil piping works Details
 
8Tender for supply of BWSR spares Details
 
8Tender for annual maintenance contract for work of on-site N2 drying out for power transformers & ICT’s for various Details
 
8Tender for supply of assorted size of MS grill for repairing of platform of ash slurry line Details
 
8Tender for supply of liquor ammonia 25 % (AR grade) for boiler water treatment Details
 
8Tender for supply of capacitance type level switches for seal oil Details
 
8Tender for supply of IE4 class LT motors Details
 
8Tender for supply of canopies for DCS panels Details
 
8Tender for supply of C&S electric make ACB & panel spares Details
 
8Tender for supply of castable refractory for ash handling plant Details
 
8Tender for supply of battery water for 220V DC & 48V DC battery banks Details
 
8Tender for supply of PLC, VFD (variable frequency drive), HMI and installation Details
 
8Tender for supply of SMF batteries Details
 
8Tender for annual maintenance contract to carry out the routine repair & maintenance of power house equipments Details
 
8Tender for procurement of EPR grade cable 1.1 kV Details
 
8Tender for protection of power house Details
 
8Tender for supply of grinding rolls (roller liners) and bull ring segments Details
 
8Tender for annual maintenance contract for carrying out works in regular outage, emergency and attending breakdown of various 400kV, 220kV, 132kV & 66kV EHV lines Details
 
8Tender for construction of transformer fencing for various Details
 
8Tender for supply of coal nozzles for burner panel of boiler 250 MW Details
 
8Tender for supply of gland packing rings, gland rope and SS 304 spiral wound gaskets etc Details
 
8Tender for supply of spares for HP bypass valves and boiler safety valves for boiler Details
 
8Tender for requirement of spares of zirconia oxygen analysers installed Details
 
8Tender for purchase of spares for 3X1750 KVA DG sets Details
 
8Tender for supply of seals and spares for air pre heater Details
 
8Tender for supply of spares for LPBP stop And control valves Details
 
8Tender for procurement of 06 numbers of grinding ring and 216 number of balls of EL 76 pulveriser Details
 
8Tender for miscellaneous structural works Details
 
8Tender for procurement of different types of steel materials Details
 
8Tender for service contract for power extension and new point wiring Details
 
8Tender for execution of unit 3 COH during overhauling Details
 
8Tender for service contract for de-insulation and re-insulation job during overhauling and various maintenance work Details
 
8Tender for annual maintenance contract of telephone exchange, telephone set and line up Details
 
8Tender for supply of miscellaneous consumables items for electrical and generator maintenance Details
 
8Tender for supply of 11kV moving contact for 200Amps 11kV AB switch (double pole) Details
 
8Tender for work of annual maintenance contract for servicing/ maintenance of battery sets and chargers, taking capacity tests of battery sets and reconditioning of 220V/110V/48V,100/200/300/500/1000 A Details
 
8Tender for AMC for work of arresting oil leakages from the various joints of power transformers Details
 
8Tender for supply of 420kV, 3150A Male Female assembly of centre break isolator Details
 
8Tender for work of replacement of insulator or SRI work of attending the fault or broken conductor Details
 
8Tender for mechanical strengthening work of S/C 66kV line Details
 
8Tender for purchase of 400Amp SMC LTDB Details
 
8Tender for work of Re-tubing of tube nests of LP heater Details
 
8Tender for dismantling of conventional lighting system at boiler, ESP, ash plant Details
 
8Tender for biennial rate contract for works of online, preventive and breakdown maintenance of coal mills XRP-1003 and its associated auxiliaries Details
 
8Tender for work of removal of existing super heater header 5 (SHH5) and erection & commissioning of new SHH 5 along with its associated field joints for boiler Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8
India's Rs 37,500 Crore Coal Gasification Scheme Sees Strong Interest Details
 
8Coal gasification projects of over 22 MT capacity under implementation Details
 
8Solar Startups Attract Over $1 Bn As Clean Energy Investments Accelerate Details
 
8The Ultimate Guide to Solar Energy: Everything You Need to Know in 2026 and Beyond Details
 
8BHEL Invites Bids For Supply Monocrystalline 625 Wp Solar PV Modules For Hyderabad R&D Division Details
 
8Growth and Future of Solar Stocks in India Details
 
8RITES and MECON sign MoU to explore business avenues Details
 
8India has adequate coal stocks, thermal power plants equipped to meet daily demand: Govt Details
 
8AI, Data Centres To Accelerate India’s Power Cycle; Transmission Remains Top Bet: Vakil Of HDFC Securities Details
 
8India has adequate coal stocks to meet power demand, says government Details
 
8Adani Power Share Price Rises Nearly 2% Ahead of Q1 FY27 Results Details
 
8THDC India Commissions 11 MW Floating Solar Plant At Khurja STPP, Boosting NTPC’s Green Capacity Details
 
8India has sufficient coal stocks to meet thermal power demand, says power ministry Details
 
8How Wind Energy in India Is Powering Rural Electrification and Grid Stability Details
 
8Karnataka govt firm on implementing Sharavathi Pumped Storage Project: CM D K Shivakumar Details
 
8Bondada Engineering Secures NTPC REL Deal For 100 MWh Battery Storage Project Details
 
8Why Jaiprakash Power Ventures Shares Surged 8% Today — Here's What Drove The Rally Details
 
8From Standard Pipes to Project-Specific Solutions, Techno India Adapting to Forward Integration Details
 
8Punjab: Power Minister Tarunpreet Singh Sondh launches distribution of 10,500 safety tool kits to PSPCL employees Details
 
8Naveen Jindal Group in talks for proposed nuclear projects, in discussion with US, French companies Details
 
8Coal Stock at Thermal Power Plants Sufficient for 14 Days, Government Assures Uninterrupted Power Supply Details
 
8Thermal Power Plants hold 42.8 MT coal stock, enough for 14 days": MoS Power Shripad Naik Details
 
8India Holds 42.8 Million Tonnes of Coal for Power Stability Details
 
8Tata Power Bags 40-Year SECI Deal Worth Rs 351 Crore Annually for Pumped Hydro Details
 
8NTPC renewable Energy awards contract for 100MWh Details
 
8NPCIL and ECIL Enter MoU to Boost Indigenous Control Systems and Nuclear Technology Solutions Details
 
8India's core sector output rises to five-month high of 5 per cent in June Details
 
You can also click on Newsclips for more Details

The West runs a surplus while the North and South ration - July's squeeze is a delivery problem, not a generation shortfall

Jul 20: 8On 18–19 July the Northern Region shed load in Punjab and Haryana even as the Western Region exported close to 300 million units a day with no shortage and no renewable curtailment. The gap is not missing megawatts - it is congested corridors and benched gas standing between surplus in one region and unmet demand in another. Details

POWER MARKETS DAILY

Jul 20: 8IEX day-ahead cleared 1.30 million MWh in the week to 20 July at a Rs 6,666/MWh average
8Term-ahead buyers locked the Rs 10,000/MWh ceiling for forward daily blocks on 17 July
8APCPDCL and RUVITL float ~1,100 MW and ~1,000 MW thermal reverse auctions on all three exchanges
8IGSTPS-Jhajjar's Rs 45.69 crore tops NRPC's ~Rs 193-crore part-load bill for April–June
8NLDC benched the entire gas fleet at Rs 14–22/kWh while coal cleared at Rs 1.2–5.7/kWh
8Grid-India backed thermal down by up to 46,660 MWh a day to absorb midday solar
8ERPC's weekly deviation pool ran a Rs 60.37-crore balance
8All-India ISTS transmission loss set at 3.95% for the week to 26 July Details

GRID OPERATIONS DAILY

Jul 20: 8All-India frequency fell to 49.596 Hz on 19 July in a synchronous evening dip
8NR import corridor was in ATC violation 11.46% of 19 July as Rajasthan sat 19.1% congested
8NER–Tripura import corridor held in transfer-capacity violation ~three-quarters of the day
8Ancillary despatch ran heavily to down-regulation - up to 46,660 MWh backed down on 19 July
8Western Region exported ~282 MU north on 19 July as the grid's balancing sink and source
8High-voltage light-load regime held Amreli above 420 kV ~90% of 18 July
8NR and WR registers carried high-fault-current trips plus a decade-long tail of dead assets
8One relay-and-reclose event cascaded through five 400 kV bays at Fatehgarh-III / Serentica on 19 July
8Two Karnataka 400 kV corridors stay un-restored since May tower collapses
8Grid-India set the all-India ISTS transmission loss at 3.95% for 20–26 July
8NRPC rates Northern hydro the worst primary-frequency responders - Parbati-III scored 0.00
8ERPC re-cut a week's reactive-energy account off one meter swap - DARLIPALI draws Rs 3,37,902
8WRLDC swapped ~a dozen interface meters to check/standby readings in DSM week-14
8Karnataka's ageing thermal posted soft June returns - RTPS ran 58.2% PLF
8Thermal availability held 85.5% on 16 July as hydro ran 11% under its YTD programme
8Bihar alone curtailed load across 17–19 July despite zero ER-wide shortage Details

OUTAGE & MAINTENANCE REGISTER

Jul 20: 8India carried 53,415 MW under maintenance on 16 July - 22,936 MW of it forced thermal trips
8Western Region ran up to 18,336.5 MW out on 18 July, led by VSTPS-V and Adani Raipur trips
8Southern Region outage climbed 1,906 MW in two days to 11,820.88 MW on 19 July
8Northern Region carried 9,138 MW out on 19 July, 4,900 MW of it forced coal
8Eastern Region held ~5.1–5.9 GW out; Teesta-III's 1,200 MW forced into a 21st month
89,230.47 MW of thermal/nuclear went off-grid on 16 July on boiler and air-preheater faults
8NTPC water-wall tube leaks hit Gadarwara U1 (800 MW) and Barh U3 (660 MW)
8Long-parked units anchor the ~29,961 MW out beyond 15 days
8Telangana's Yadadri loses both first-stage 800 MW units, U1 and U2
8Jindal Simhapuri logged four trips of two 150 MW units in a single day - a repeat-tripping signal
8NPCIL's RAPS-A Unit-1 (100 MW) is formally set for decommissioning, out since 2004
8PVVNL runs a 100-plus feeder shutdown wave across Meerut–Muzaffarnagar ahead of the Kanwar Yatra
8Chronic multi-year transmission forced outages stay open - Raigarh–Raipur FSC since 2016
8Himachal hydro units force-out on high silt as monsoon flows spike
8KPCL's newest Raichur unit (250 MW Unit-8) sat out all June on planned outage
8OHPC carries multiple hydro units out - Burla and Chipilma forced
8KSEBL replaces Idukki Unit-6 upper guide bearing in-house in nine days, saving about Rs 35 lakh Details
  • Jul 23: Corporate Wire:Details
  • Jul 23: Committees, People & System Administration:Details
  • Jul 23: Daily Power Sector Tenders Excel update:Details
  • Jul 23: Download tenders and news clips:Details
  • Jul 22: Contracting news for the day: Part-1:Details
  • Jul 22: Daily Power Sector Tenders Excel update:Details