All content in this website is sourced legitimately

Contracting news for the day.  Download tenders and news clips.  RDSS puts Rs 15,234 crore into grid digitalisation, but training and system use lag the hardware.  Delhi lifts the 10% fuel-cost cap for June bills, but the exception does not settle every discom claim.  Barh Stage I’s cost has risen above Rs 21,312 crore, but CERC still wants the escalation reconciled.  Coal plans 1,319 million tonnes of first-mile capacity, but output slipped before the logistics build-out.  Adani Jharkhand’s Bangladesh exports rose to 9,131 MU, but the power remains outside domestic allocation.  Andhra Pradesh has installed 30.82 lakh RDSS consumer meters, but network grants still trail project scale.   India targets 100 million tonnes of coal gasification, but only 8 million tonnes is operating.  Power-sector coal imports fell 71.5%, but domestic substitution is only part of the explanation.  India met a 270.8 GW peak, but the next 18.2 GW will test storage and local grids.  Tripura blocks most of TSECL’s past-gap recovery to avoid a tariff shock - the shortfall remains.  CEA’s unbuilt hydro list shows approvals stranded behind forest and environmental clearances - the paperwork has not become construction.  SJVN’s 1,200 MW firm-renewable and 600 MW wind tariffs await orders - the larger sale agreement is unsigned.  Chhattisgarh’s 500 MWh battery tender reaches tariff hearings with Rs 90 crore support - the contract remains unsigned.  Odisha sought Rs 6,284 crore of cyclone-resilient distribution work - but private ownership leaves its DISCOMs outside RDSS funding.  Uttar Pradesh sanctions Rs 40,738 crore for RDSS networks and meters - consumer complaints still lack a common remedy.  BRIEFS - VERIFIED DEVELOPMENTS WITH LIMITED DEPTH.  POLICY AND SYSTEM PLANNING - RELIEF, INVESTMENT AND CAPACITY CLAIMS MEET THEIR IMPLEMENTATION LIMITS.  REGULATION AND DISPUTES - PETITIONS SEEK MONEY OR RELIEF THAT ORDERS HAVE NOT YET AWARDED.  STORAGE AND HYDRO - ANNOUNCED CAPACITY STILL WAITS FOR AWARDS, CLEARANCES AND OPERATING EVIDENCE.  DISTRIBUTION AND CONSUMERS - DIGITAL INVESTMENT EXPANDS FASTER THAN PROOF OF SERVICE IMPROVEMENT.  COMPANIES AND FINANCE - GROWTH VISIBILITY MEETS HYDROLOGY, CREDIT AND ACCOUNTING RISK.  COAL AND TRANSITION - LOWER IMPORTS AND NEW LOGISTICS MEET OUTPUT, FUEL AND CONVERSION CONSTRAINTS.  MARKETS AND SETTLEMENT - ACCOUNT CORRECTIONS EXPOSE WHO CARRIES DEVIATION AND PAYMENT RISK.  GRID AND TRANSMISSION - EXPANSION PLANS CONFRONT AGEING ASSETS, OUTAGES AND UNFINISHED PROTECTION.  Contracting news for the day.  Download tenders and news clips.  India adds 55.3 GW of non-fossil capacity in FY26 while planning 315 GW of coal - energy security is producing two expansion tracks.  Tripura rejects most of TSECL’s Rs1,709 crore past-gap claim to avoid a tariff shock - but the unpaid gap still has to be worked down.  CEA’s unbuilt hydro list shows approvals stranded behind forest and environmental clearances - the paperwork has not become construction.  SJVN’s 1,200 MW firm-renewable and 600 MW wind tariff cases are reserved for order - but the 1,200 MW sale agreement is still unsigned.  Chhattisgarh’s 500 MWh battery tender reaches tariff-adoption hearings with Rs90 crore of support - but the storage contract is not final yet.  Odisha sought Rs6,284 crore of cyclone-resilient distribution work - but private ownership leaves its DISCOMs outside RDSS funding.  Madhya Pradesh cuts distribution losses but accumulated DISCOM losses rise to Rs71,394 crore - reform progress has not repaired the balance sheet.  India Energy Stack pilots are under way in five utility markets - but a national power-data architecture has not yet been proved.  Draft power policy would shift more fixed and fuel costs into regular electricity bills - while proposing a stabilisation fund to soften volatility.  Uttar Pradesh has Rs21,782 crore of RDSS network works and Rs18,956 crore of smart metering sanctioned - but consumer complaints are still handled state by state.  Four China-linked equipment makers can bid for Indian power projects for two years - but only under domestic-content conditions.  India has sanctioned 20.33 crore smart meters but installed 5.73 crore under RDSS - consumer safeguards now have to catch up with scale.  India proposes Rs20,000 crore for carbon capture - but the programme has no approved project-selection rules yet.  Rays Power Infra’s order book reaches Rs8,455 crore - but rapid growth is lifting leverage and supplier-finance dependence.  Amara Raja starts building a 10 GWh battery-storage factory - but first output is still tied to a FY27 construction timetable.  BRIEFS - VERIFIED DEVELOPMENTS WITH LIMITED DEPTH.  POLICY AND SYSTEM PLANNING - RELIEF, INVESTMENT AND CAPACITY CLAIMS MEET THEIR IMPLEMENTATION LIMITS.  REGULATION AND DISPUTES - PETITIONS SEEK MONEY OR RELIEF THAT ORDERS HAVE NOT YET AWARDED.  STORAGE AND HYDRO - ANNOUNCED CAPACITY STILL WAITS FOR AWARDS, CLEARANCES AND OPERATING EVIDENCE.  DISTRIBUTION AND CONSUMERS - DIGITAL INVESTMENT EXPANDS FASTER THAN PROOF OF SERVICE IMPROVEMENT.  COMPANIES AND FINANCE - GROWTH VISIBILITY MEETS HYDROLOGY, CREDIT AND ACCOUNTING RISK.  COAL AND TRANSITION - LOWER IMPORTS AND NEW LOGISTICS MEET OUTPUT, FUEL AND CONVERSION CONSTRAINTS.  MARKETS AND SETTLEMENT - ACCOUNT CORRECTIONS EXPOSE WHO CARRIES DEVIATION AND PAYMENT RISK.  GRID AND TRANSMISSION - EXPANSION PLANS CONFRONT AGEING ASSETS, OUTAGES AND UNFINISHED PROTECTION.  Contracting news for the day.  Download tenders and news clips.  Daily Power Sector Tenders Excel update.  More than 55,000 MW was outside the online fleet in CEA’s monitored snapshot - while generation still reached 98.2% of programme.  India has certified 78 green-steel units and advanced specialty-steel incentives - but neither measure yet proves how much cleaner steel is being produced.  BCCL put a new 2.0 MTPA washery into operation and monetised another - but profit collapsed nearly 90% as production and offtake weakened.  Coal India spent Rs. 19,607 crore and added 100 MW of solar - but coal output fell to 768.19 million tonnes, 168.81 million tonnes below its own target.  PFC’s loan book reached Rs. 5.80 lakh crore and net NPAs fell to 0.15% - but annual sanctions dropped Rs. 75,094 crore as fresh commitments slowed.   Inox Wind’s order book reached about 4.4 GW - but quarterly profit fell 34% as its shift toward equipment sales held income growth to 1%.  Premier Energies lifted profit 53% and opened 5.6 GW of module capacity - but the new factory must convert nameplate scale into sustained sales and margin.  Hitachi Energy’s orders and revenue surged - while Rs. 1,841.66 crore of QIP money still sat unused.  Amazon’s proposed Mumbai data-centre campus would demand 473 MW and install hundreds of backup generators - but it still lacks final environmental clearance.  CESC’s 3 GW solar-cell plan won environmental clearance only for Phase I - leaving the second phase and construction approvals outside the gate.  A Vemagiri bus fault cut about 1,150 MW of Andhra Pradesh load in 14 minutes - after overloaded transformers at another station also tripped.  Gujarat’s renewable evacuation network suffered repeated single-path failures, including 800 MW and 540 MW losses - making redundancy the month’s unresolved risk.  Two simultaneous line trips cut about 130 MW across six Assam load centres - after another 220 kV route was already shut.  A Champa–Kurukshetra HVDC failure cut about 2,680 MW of transfer and triggered Punjab’s defence scheme - but Punjab’s recorded demand drop was about 252 MW.  Thirty coal plants were critical even with 37 million tonnes on hand - because the fleet held only 60% of its normative stock.  Contracting news for the day.  Briefs - Signals to Watch.  Projects and Clearances - Investment Advanced, Permissions Lagged.  Corporate Growth and Finance - Scale Expanded, Execution Risk Remained.  Regulation and Access - Relief Was Sought, Decisions Stayed Conditional.  

Contracting news for the day

Aug 13: 8NPCIL's riser insulation package lists one set against four pipe sizes and 24 riser positions The bidder must fund detailed engineering, mock-ups, radiation qualification, five installation trials and site training before any payment falls due. ATC clause 13.0 ties 100% payment to final acceptance and completion of training, on a firm price held over 364 days. The GeM summary marks arbitration "No" while ATC clause 24.0 sets a three-arbitrator tribunal.

8NTPC Mining asks developers for indicative tariffs while holding the land lease rate back to the RFP The 50 MWp splits evenly across two mines, but one sits on an overburden dump and the other carries mandatory levelling plus a developer-scope 33 kV line on a shorter schedule. Penalties, payment security, deemed generation and curtailment treatment are all still open to market input. A later limited tender may be confined to those who respond now.

8WAPCOS's Rs 1 crore mandate says no pre-bid meeting will be held; GeM scheduled one with a Teams link The GeM field records 10:00 against a description reading 10:30-12:30, validity reads 90 days in one document and 120 in the other, and MSE relaxation is "No" in one and 50% in the other. Basic turnover eligibility starts at Rs 50 lakh while scored turnover starts at Rs 50 crore. Arbitration is expressly waived even though the 1996 Act appears in the same document's regulatory framework.

8AEGCL's Rs 6.72 lakh Narengi consultancy buys PLS CADD tower spotting and states no completion period Two lump-sum items cover bay feasibility and full route survey with profile drawings, with forest proposal and tree enumeration expressly carved out. Corridor width, accuracy tolerances, route alternatives and permitted iterations are undefined. The whole cycle from launch to close runs eight days.

8Tata Power's one-year final-checking agreement for a 765 kV line gives bidders 10 days and no quantities Tower counts, line length, inspection formats, acceptance authority, manpower and reporting protocol are all absent from the notice. So are EMD, PBG, payment cycle, LD and liability caps. For a year-long framework, minimum workload and call-off frequency are the terms that matter, and neither is stated.

8TGTRANSCO's Rs 60.71 crore package keeps negative escalation running after positive escalation stops Delay attributable to the contractor removes upward price protection while leaving downward adjustment enforceable, on top of milestone and post-completion penalties. Section 1.2 deems unlisted but necessary components into bidder supply, closing the variation route. A bid 20% below estimate draws additional security of 10% of the estimated cost by the document's own worked example.

8KPTCL's Rs 108.02 crore Ayyanahalli package deleted its 25% consortium floor after a pre-bid nobody attended The line qualification can now sit entirely with one partner, with a three-year electrical-works test replacing it for the other. The proceedings record nil bidder representatives; the queries that produced the change arrived by email. Underlying kilometre thresholds are unchanged.

8APGENCO reserves the right to amend its metering cubicle tender after its own submission window shuts Bids close at 14:00, technical opening is 15:00, and modifications are permitted up to 15:00. Validity reads 180 days in the NIT and 120 in the attached general conditions, while the covering enquiry gives a third set of times. Manufacturer-site QA inspection is marked "Not Required", moving conformity onto supplier certificates.

8NHPC's Sawalkot Lot-1 added Rs 287.91 crore, deleted a qualification route and moved its deadline eleven times The estimate reset from Rs 5,129.03 crore to Rs 5,416.94 crore carried turnover, working capital and bid capacity up with it, while the quantity-based dam alternative disappeared, leaving only an 80 m concrete dam. Project capacity was corrected from 1856 MW to 1800 MW without explanation. No reason is recorded against any of the 161 days of extensions.

8MPPGCL's 30 MWac solar tender moved its query-response date three times, ending seven days before bids close Responses now land after the deadline they were originally meant to precede, leaving one week to absorb them across engineering, vendor quotes, generation modelling and O&M pricing. Evaluation runs on Rs/kWh combining capex, discounted five-year O&M and accepted NEEGG. Omitted-but-necessary equipment is deemed included and prices stay firm.

8NHPC's Kamala amendment moved HM qualification into execution, then needed an errata to fix the clause it cited The same corrigendum cut muck disposal from four zones to two, removing both sites nearest the dam and leaving two shared 50/50 with the adjacent lot. Adverse climate moved from employer risk "Nil" to EOT, and earthquake gained express compensation. Grid power is tentative at two years out, with captive generation and compulsory later uptake both on the contractor.

8THDC's Kalai-II package moved 216 days and rewrote shotcrete from "no extra payment" to Rs 180 per kg Eight extensions ran alongside two substantive amendments and a notice refusing further queries — followed by another date revision. The 31.5-month clock now starts after a 30-day mobilisation period rather than on the seventh day from LOA. The road tunnel is carved out of the milestone-damage waiver every other milestone enjoys.

8AEGCL's Sonapur extension notice pushes bids to 2026 and schedules the opening for 2023 The same package records an NIT date in the pre-bid minutes that post-dates both the NIT and portal publication. A pre-bid meeting materialised where the portal fields read "NA", drawing nine firms. Prices stay fixed for 24 months and the request for conductor and cable escalation was refused.

8MPMKVVCL narrowed its type-test waiver to one rating and readmitted a disqualified bidder after opening The concession originally covered a new bidder lacking reports for any rating; it now covers only the 10 MVA unit. EMD is Rs 1 lakh against post-award security of 1% plus 9% on a 66-month instrument. A bidder rejected as a medium enterprise returned on the MSME notification preserving previous-category benefits for three years.

8NHPC's Salal award is 8.7% below estimate, or 1.5% above it, depending which estimate applies The benchmark rose 11.1% late in the cycle, taking experience, turnover, working capital and bid capacity up with it after an earlier corrigendum had widened technical eligibility. One of three bidders failed qualification, leaving a two-bid contest 3.4% apart. The NIT provides for reverse auction; the comparative statement shows only two values.

8WBSEDCL cut its retesting charge 90% and drew 188 bids in which L2 sits 44.0% above L1 EMD fell 30.0% and 16.7% across categories at pre-bid, while the charge per repeat inspection went from Rs 50,000 to Rs 5,000. Of 188 bids, 148 cleared technically, many only partially by capacity or transformer type. A bidder removed from the restricted-opening table after a corrigendum resurfaced in the price ranking at L22. Details

Download tenders and news clips

Aug 13:  For reference purposes the website carries here the following tenders:
 8Tender for work of annual/routine testing of various equipments installed at 400 kV GIS S/S Details
 8Tender for civil works for construction of 01 No. 63 MVA transformer plinth and related 132/33 kV bay Details
 8Tender for civil maintenance and upkeeping work at various volts transmission sub stations Details
 8Tender for diversion of submerged tower 400 kV line Details
 8Tender for supply of cross patrolling of transmission lines Details
 8Tender for supply of LT three phase channel cross arm and angle cross arm Details
 8Tender for procurement of transformer structure materials double pole Details
 8Tender for procurement LT GI pins Details
 8Tender for providing pile foundation for various tower Details
 8Tender for construction of control room foundations, cable trench Details
 8Tender for procurement of spares for SAM make sludge disposal pump model Details
 8Tender for construction work for new proposed 33/11 kV line Details
 8Tender for construction of new borewell at 132 kV GSS Details
 8Tender for construction of civil foundation and other misc civil works in yard for 20/25 MVA Tr At 132 kV GSS Details
 8Tender for construction of civil foundation and other misc civil works in yard Details
 8Tender for levelling and gravelling work of 132 kV switch yard at 132 kV GSS Details
 8Tender for procurement of 220V-600AH lead acid tubular type battery sets Details
 8Tender for procurement of non ferric alum Details
 8Tender for repairing/retrofitting/renovation of raw water pump house Details
 8Tender for supply of CPVC pipe & fittings Details
 8Tender for supply and application of epoxy glass flake coating with UV resistance PU top coat on various external surfaces Details
 8Tender for work of preventive maintenance of various 220 kV switchyard Details
 8Tender for supply of GI coated heavy duty MS grill Details
 8Tender for EPC package for ash handling system package Details
 8Tender for work of RCC revetment/protection wall work at various Details
 8Tender for procurement of furnace oil Details
 8Tender for construction of 132 kV sub-station Details
 8Tender for extension of control room construction of 02 No. 66kV bays Details
 8Tender for supply of wireless LCM kit for 220kV and 66kV class switchyard Details
 8Tender for supply of C&S electric make ACB & panel spares Details
 8Tender for procurement 22 kV, 200A AB switch Details
 8Tender for supply of LT three phase X arm channel Details
 8Tender for supply of T.C.fuse wire 12,14,16 SWG Details
 8Tender for supply of transformer structure materials Details
 8Tender for construction of new 11 kV, LT lines and 11/0.4 kV DTR Details
 8Tender for construction and shifting of existing 33kV/11kV/LT OH/UG lines Details
 8Tender for Re-construction of existing 33 kV UG line Details
 8Tender for construction of new 33 kV line from 33/11 kV DSS Details
 8Design, fabrication, supply, installation, testing, commissioning of on grid solar ground mounted project with net meter and remote monitoring system, capacity of 46 kW Details
 8Design, fabrication, supply, installation, testing, commissioning of on grid solar ground mounted project with net meter and remote monitoring system, capacity of 83 kW Details
 8Design, fabrication, supply, installation, testing, commissioning with RMS of total 156 kW grid connected solar PV power plant Details
 8Tender for supply and erection of 50TR capacity air cooled DX condensing unit for 400kV switchyard Details
 8Tender for supply, retrofit commissioning of 90 kW and above LT air contactor modules (DK21) with LT vacuum contactors Details
 8Tender for supply and replacement of LTG and HTG tubes Details
 8Tender for empanelment of contractors to award a rate contract award RCA for DTR renovation work of 63 KVA, 100 KVA, 200 KVA and 315 KVA substation Details
 8Tender for empanelment of contractors to award a rate contract award RCA for work for aug/conversion of LT line 3x95 Sqmm and 3 X 150sq.mm.XLPE cable Details
 8Tender for augmentation of 33 kV line on H-Beam using ACSR Dog conductor Details
 8Tender for empanelment of contractors to award a rate contract award RCA for work of aug conversion LT cable Details
 8Tender for work of aug of existing 11 kV line to ACSR Dog/Raccoon with 13Mtr H beam/PCC pole Details
 8Tender for procurement of lighting items for power houses Details
 8Tender for annual maintenance work of railway siding for power house Details
 8Tender for supply and running out of ballast for railway maintenance work Details
 8Tender for construction of new hydrogen shed for 1x210 MW unit Details
 8Tender for work contract of transportation of the ash from ash dyke II Details
 8Tender for construction of precast RCC cover and stone Details
 8Tender for procurement of spares of electromagnetic flow meter and SWAS spares installed Details
 8Tender for manufacture, testing, supply, delivery and operational training/ commissioning of three phase transformer turns ratio test sets Details
 8Tender for manufacturing, testing, supply and delivery of 50 Nos. 220V/100AH and 30 Nos.24V/100AH DC distribution boards and 80 Nos. 415V, 11 circuit, AC distribution boards Details
 8Tender for work related to construction and electrification of line and shifting of lines and poles Details
 8Tender for replacement of defective meters Details
 8Tender for maintenance and repair of 11 kV HT/LT line Details
 8Tender for replacement of defective meters Details
 8Tender for work of installation of one (01) No. 12.5 MVA power transformer Details
 8Tender for erection, testing & commissioning work of 66kV equipments, structures Details
 8Tender for erection, testing & commissioning work of 66kV equipments, structures, control wiring Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Karamsad Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Borsad Details
 8Tender for procurement of MS pipes 550 NB for replacement Details
 8Tender for thorough interior civil renovation and allied work Details
 8Tender for work of atactic polypropylene APP treatment to arrest leakages Details
 8Tender for supply loading at factory and transportation of LT distribution box Details
 8Tender for supply and delivery of different local materials Details
 8Tender for construction of 1 No 33 kV bay, 2 Nos. 11 kV feeder bay and providing transformer plinth Details
 8Tender for laying of 11kV 3x300sq.mm XLPE UG cable Details
 8Tender for laying of 11kV 3x300sq.mm XLPE UG cable for erection of new 11 kV feeder Details
 8Tender for supply of stay set complete Details
 8Tender for work of providing & fixing of 33kV numerical backup relay with non-directional three phase over current (3 O/C) & earth fault (E/F) protection Details
 8Tender for AMC for CTR make nitrogen injection fire protection system (NIFPS) for ICTs & transformer Details
 8Tender for annual maintenance contract (AMC) for the work of attending emergency breakdown works & planned maintenance works in various 220/132 kV EHV S/Stn Bhandara Details
 8Tender for annual maintenance contract (AMC) for the work of attending emergency breakdown works & planned maintenance works in various 220/132 kV EHV S/Stn Details
 8Tender for biennial maintenance contract of replacement of installed smoothing reactor by spare smoothing reactor Details
 8Tender for supply of pressure relay of converter transformer Details
 8Tender for annual maintenance contract (AMC) for the work of attending emergency breakdown work & planned maintenance works in various 220/132kV EHV S/S Details
 8Tender for refilling, servicing & maintenance, supply of spares for fire extinguishers at various substations Details
 8Tender for annual maintenance contract (AMC) for work of underground cables at various Details
 8Tender for attending emergency breakdown work & annual routine maintenance of 220/132/110kV various EHV lines Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Mehsana Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Patan Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Himatnagar Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Chhatral Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Dhansura Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Jamla Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Vijapur Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Agiyol Details
 8Tender for supply of pre engineering shed Details
 8Design, engineering, manufacture, supply, erection, testing & commissioning of 6.6 kV indoor metalClad draw-outtype VCB panels Details
 8Tender for supply, installation commissioning, & testing of soft starter with major/minor modification in existing panels for various motors Details
 8Tender for supply of assorted size of MS grill for repairing of platform of ash slurry line Details
 8Tender for supply of mill discharge first piece after MPO for coal mill Details
 8Tender for purchase of standard toolkit bag Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8Hinduja Renewables Bets On BESS, Pumped Storage To Make Renewables More Dispatchable Details
 
8Maharashtra Floats EOI for 170 MW Floating Solar & BESS Project Details
 
8NVVN Invites EOI for 263 MW Solar Open Access Power Details
 
8ACME Solar Refinances Rs 21.5 Billion Debt for 450 MW Portfolio Details
 
8MNRE Approves INR 258.83 Crore HRD Programme To Strengthen India’s Renewable Energy Workforce Details
 
8Rooftop solar installations soar in India Details
 
8CIL, ArcelorMittal sign MoU to explore syn-gas usage from a coal gasification plant at Paradip Details
 
8DNHDDPCL Invites Bids for 5 MW Rooftop Solar Program Details
 
8India’s small steelmakers could save money and cut emissions with switch to renewable power Details
 
8How India can get its BESS projects right Details
 
8India on e-wheels: There are hardly any electric cars on Srinagar’s roads; here is why Details
 
8H2 Innovation eyes collaboration with universities, government to develop green hydrogen in India Details
 
8Power Ministry Urges States: Accelerate Smart Meter Rollout Details
 
8Dr Jitendra shares in LS India’s Thorium driven indigenous Nuclear strategy Details
 
8Siemens Energy India to attend Motilal Oswal investor meet Details
 
8Gentari Explores Sale of India EV Charging Network With 3,000 Chargers Details
 
8Data Centre Power Boom: Why renewable developers are demanding a Rs 3,000 crore relief package Details
 
8Stocks to Watch: Solar Industries, LG, Tata Motors PV and 7 Other Stocks Announcing Q1 Results Today Details
 
8SJVN Commissions 75 MW Jamui Solar Power Project in Bihar, Expands Renewable Energy Portfolio Details
 
8India’s Solar Surge Highlights 50 GW Power Gap Challenge Details
 
8India's Planned Coal Mining Capacity Hits 638 MTPA Details
 
83 Best-Performing Mutual Funds With High Holdings in NTPC, Adani Power & Tata Power in 2026 Details
 
8Demand aggregation of renewable electricity can cut power costs for India’s secondary steel MSME clusters by 34 percent Details
 
8Bajel Projects Bags Rs 400 Crore Order From Power Grid for 765kV Transmission Line Details
 
8Power sector stocks today, August 12: TD Power Systems jumps 15.87%, Gujarat Industries up 7.40%, Diamond Power rises 4.36% Details
 
8India’s solar power cuts coal use in the day, but evening demand keeps fossil fuel running Details
 
8El Niño drives India's July power demand to a record high: Crisil report Details
 
8India nearly doubles proposed coal mine capacity as global pipeline expands: Report Details
 
8CEA Proposes New 2026 Grid Connectivity Technical Standards For Power Sector Entities Details
 
8How the Indian Railways moves closer to becoming net-zero carbon emitter by 2030 Details
 
You can also click on Newsclips for more Details

RDSS puts Rs 15,234 crore into grid digitalisation, but training and system use lag the hardware

Aug 12: 8SCADA, IT/OT and smart-distribution work now reaches 28 states and 45 utilities, alongside 19.79 crore sanctioned consumer meters.
Only Rs 23.36 crore of a Rs 100.9 crore training allocation had been used by July, leaving operational capability as the counterweight.
Details

Delhi lifts the 10% fuel-cost cap for June bills, but the exception does not settle every discom claim

Aug 12: 8BRPL, BYPL and TPDDL may recover total FPPAS of 17.94%, 17.43% and 18.50% respectively for June 2026.
The order is a one-month regulatory relaxation; it does not remove the normal ceiling or convert unallowed claims into approved revenue.
Details

Barh Stage I’s cost has risen above Rs 21,312 crore, but CERC still wants the escalation reconciled

Aug 12: 8The 1,980 MW station’s tariff case remains open while NTPC supplies package-level escalation and audited cost reconciliation.
Beneficiaries can face fixed-charge consequences only after the regulator decides which expenditure is prudent and attributable.
Details

Coal plans 1,319 million tonnes of first-mile capacity, but output slipped before the logistics build-out

Aug 12: 8The government plans 139 first-mile projects by FY30 and eight railway schemes, within a logistics plan covering 33 critical rail projects.
Domestic production and dispatch both fell provisionally in FY26, so planned handling capacity has not yet become higher delivered volume.
Details

Adani Jharkhand’s Bangladesh exports rose to 9,131 MU, but the power remains outside domestic allocation

Aug 12: 8The dedicated plant’s annual supply to Bangladesh increased from 155.55 MU in FY23 to 9,131 MU in FY26.
India also exported to Nepal, Bhutan and Myanmar, but APJL’s exclusive contract is distinct from domestic central-station allocation.
Details

Andhra Pradesh has installed 30.82 lakh RDSS consumer meters, but network grants still trail project scale

Aug 12: 8The state has Rs 10,391 crore of loss-reduction work and Rs 4,112.43 crore of smart metering sanctioned under RDSS.
Consumer-meter installation is substantial, while transformer meters, disaster-resilient works and grant release remain incomplete.
Details

India targets 100 million tonnes of coal gasification, but only 8 million tonnes is operating

Aug 12: 8The government counts 22.6 million tonnes a year as operating or under implementation and expects a new Rs 37,500 crore scheme to support about 75 million tonnes more.
Eight projects have been approved under the earlier Rs 8,500 crore scheme, but only Rs 235.52 crore had been disbursed and commissioning remains the decisive test.
Details

Power-sector coal imports fell 71.5%, but domestic substitution is only part of the explanation

Aug 12: 8Imports for blending at domestic coal-based plants fell from 23.9 million tonnes in FY24 to 6.8 million tonnes in FY26.
Coal India also held 122.46 million tonnes in March, yet imported-coal plants and technically necessary blending remain outside a simple substitution claim.
Details

India met a 270.8 GW peak, but the next 18.2 GW will test storage and local grids

Aug 12: 8National supply met the May 2026 peak in full, while the official FY27 forecast rises to 289 GW.
Thermal generation still supplied 68.3% to 72.7% from April to June, and the remaining gaps were attributed mainly to state-network constraints.
Details

Tripura blocks most of TSECL’s past-gap recovery to avoid a tariff shock - the shortfall remains

Aug 12: 8The regulator approved a Rs 479.24 crore revenue gap but allowed only Rs 117.77 crore against the FY27 tariff after calculating that full recovery would require a 42.82% average increase.
It paired partial recovery with smart-meter consent, billing-resolution and grievance directions, protecting consumers now while retaining future financial obligations.
Details

CEA’s unbuilt hydro list shows approvals stranded behind forest and environmental clearances - the paperwork has not become construction

Aug 12: 8Projects across conventional hydro and pumped storage remain untaken up even after appraisal, with some concurrences or environmental approvals already expired.
The clearance-pending category alone includes 14,649 MW in the CEA table, showing how a project pipeline can remain large without becoming executable capacity.
Details

SJVN’s 1,200 MW firm-renewable and 600 MW wind tariffs await orders - the larger sale agreement is unsigned

Aug 12: 8One case covers 1,200 MW of firm dispatchable renewable supply; the other covers 600 MW of inter-state wind projects selected through separate bidding.
For the firm and dispatchable procurement, HPSEB has sought state approval for the contracted power but had not executed its power-sale agreement at the hearing.
Details

Chhattisgarh’s 500 MWh battery tender reaches tariff hearings with Rs 90 crore support - the contract remains unsigned

Aug 12: 8The state distributor’s petition says the project must be commissioned within 18 months of the storage-purchase agreement and that land and connectivity will be provided.
Public comments are due before the September hearing, so the discovered tariff and contractual allocation still require regulatory adoption.
Details

Odisha sought Rs 6,284 crore of cyclone-resilient distribution work - but private ownership leaves its DISCOMs outside RDSS funding

Aug 12: 8The Centre says Odisha’s utilities are ineligible because RDSS financial assistance is limited to state-owned distributors and power departments.
It also says no formal Rs 10,000 crore special power-package proposal was submitted after Cyclone Yaas, separating the state’s actual RDSS request from the larger claimed package.
Details

Uttar Pradesh sanctions Rs 40,738 crore for RDSS networks and meters - consumer complaints still lack a common remedy

Aug 12: 8The Centre says funding is linked to physical and financial progress and vendor checks are built into standard bidding documents.
The monitoring chain reaches from state committees to PFC, REC and the Union power secretary, yet billing redress and meter mode remain with utilities and state regulators.
Details

BRIEFS - VERIFIED DEVELOPMENTS WITH LIMITED DEPTH

Aug 12: 8Uttar Pradesh moves its draft Grid Code hearing by one day - objections still close on the earlier timetable
8Gas stations flag a low-frequency threshold mismatch - compensation remains under regulatory review
8Secure meter-data software slows regional accounting - manual handling is still filling the processing gap
8Genus meter decryption produces conversion defects - corrected files are still awaited
8DSM defaults trigger letter-of-credit scrutiny - security compliance has not cured the pool’s unpaid balance
8Unreturned reconciliation statements are being deemed accepted - administrative closure does not create fresh cash
8NP Kunta’s STATCOM needs an SMPS upgrade - reliability work requires a planned equipment shutdown
8Hyderabad substation’s automation migration needs 400 kV outages - modernisation temporarily narrows network availability
8Talcher - Kolar HVDC Pole 1 seeks an eight-hour shutdown - refurbishment inspection still awaits outage clearance
8India’s demand forecast error moved across 7 - 9 August - three daily readings do not establish model performance
8Intraday auction reports expose bids, clearing and schedules block by block - the latest sheet is a market snapshot
8WCL still carries compassionate-appointment applications from earlier years - the source confirms backlog, not a clean total
8Odisha’s closed coal mines face an unfinished reclamation question - completion evidence is not established
8Fatehgarh - Bhadla lenders may take security over the transmission asset - a licence transfer still needs prior approval
8Tadas Wind challenges where DSM charges are computed - the interconnection point could change the bill
8SGPL presses a Haryana energy-charge claim - the hearing record does not award the money
8Osmanabad Solar seeks Rs 3.42 crore in DSM dues - the hearing was deferred before the merits were reached
8TPTCL’s withheld-dues dispute returns to jurisdiction - the Commission wants arguments before deciding the claim
8Teesta Low Dam IV’s tariff case reaches the order stage - additional capital claims remain under scrutiny
8MEL’s transmission-licence process draws a compliance warning - proposed approval is not yet unconditional
8Solarcraft seeks more time after bay-sharing delays - missing guidelines do not automatically extend connectivity
8Kreate’s banking claim against SPTPL meets a denial of monetary liability - updated claims still need adjudication
8UGVCL’s accident register records fatal network incidents - responsibility remains case-specific
8UGVCL tracks complaints received, resolved and pending - the extracted register does not yield a reliable aggregate
8UGVCL records transformer failures and restoration complaints - a verified failure-rate figure is missing
8UGVCL’s reliability register contains outage indices - the source slice cannot support a performance ranking
8Faulty-meter replacement remains in UGVCL’s operating records - the backlog needs a clean count
8UGVCL reports no standards-of-performance compensation in the selected table - nil claims require an audit trail
8UGVCL records unauthorised-use and theft enforcement - mixed source rows prevent a verified total
8Reserve-shutdown fuel-oil compensation needs a calculation rule - eligibility alone does not fix the quantity
8Faulty special-energy meters remain unreplaced after earlier meetings - delay keeps commercial disputes alive
8Radhanesda’s meter failure produced a Rs 17.83 lakh DSM revision claim - the account still needs correction
8RDSS funds workforce training for digital distribution - utilisation must match the technology rollout
8Grid-security readings were mostly compliant at Agra but weaker at Ajmer - one report cannot grade the corridor
8Western-region outages and line states changed on 10 August - the operating list is not an adequacy forecast
8The Centre retains 15% of central-station power as unallocated - states compete within the remaining allocation rules
8Chhattisgarh’s mining funds must favour high-priority services - allocation rules do not prove local delivery
8NLC’s TPS-I Expansion true-up accepts an 8.5% auxiliary-consumption norm - the wider tariff still rests on reconciled costs
8Vindhyachal Stage I seeks tariff and life-extension capital - the rules may prevent double recovery
8NLC TPS-II’s additional-capital claim contains a cash-basis mismatch - reconciliation must precede the order Details

POLICY AND SYSTEM PLANNING - RELIEF, INVESTMENT AND CAPACITY CLAIMS MEET THEIR IMPLEMENTATION LIMITS

Aug 12: 8NTPC wants station-transformer loads explicitly counted at Vindhyachal and Korba - only export apportionment would change under its proposal
8Legacy and current power-pool deficits are still holding back disbursement - collections received do not eliminate the unpaid tail
8Municipal bonds raise Rs 6,540.44 crore across 23 cities - green issuance does not prove project delivery
8NTPC Lara has settled rehabilitation claims for most affected families - jobs remain conditional on vacancies and suitability
8Ashoknagar’s petroleum lease has been extended twice - commercial oil and gas production still has not begun
8Electrical installations may use five-year inspection or self-certification cycles - digital reporting must keep the option auditable
8Public EV-charging use rises 39% in FY26 - four states dominate the national total
8Telangana’s station-wise generation moved through July - the monthly sheet reveals unit performance but not the cause of every change Details

REGULATION AND DISPUTES - PETITIONS SEEK MONEY OR RELIEF THAT ORDERS HAVE NOT YET AWARDED

Aug 12: 8Andaman solar and storage operators seek must-run compensation - deemed generation still needs a contractual basis
8ReNew seeks protection against a bank-guarantee call - the dispute has not erased the underlying obligation
8Sarda seeks tax and open-access reimbursement for 100 MW - contract allocation will decide who pays
8NTPC Renewable and SECI dispute a scheduled-completion extension - delay relief depends on the cause and notice record
8APPCPL’s banking claim meets SPTPL’s insolvency moratorium - recovery rights now collide with bankruptcy protection
8SEIL challenges coal-freight deductions - the dispute turns on whether transport was recoverable or already priced in
8Tamil Nadu’s Ombudsman protects the existing tariff for qualifying small extensions - separate construction can still trigger Tariff VI Details

STORAGE AND HYDRO - ANNOUNCED CAPACITY STILL WAITS FOR AWARDS, CLEARANCES AND OPERATING EVIDENCE

Aug 12: 8Assam is included in plans for 200 MWh of battery storage - but no state capacity has yet been allocated
8Nathpa Jhakri seeks recovery for hydrology shortfall - the case turns on evidence that water, not operation, caused the loss
8Kynshi and other hydro DPRs return for revision - redesign may improve viability but delays appraisal Details

DISTRIBUTION AND CONSUMERS - DIGITAL INVESTMENT EXPANDS FASTER THAN PROOF OF SERVICE IMPROVEMENT

Aug 12: 8India Energy Stack pilots begin in five utility markets - the national power-data architecture is still unproved
8RDSS pushes distribution utilities deeper into digital operations - installation counts still do not prove better service
8Private discoms report longer supply and lower losses than state utilities - but averages conceal company gaps Details

COMPANIES AND FINANCE - GROWTH VISIBILITY MEETS HYDROLOGY, CREDIT AND ACCOUNTING RISK

Aug 12: 8Amara Raja’s new-energy sales grow by more than 50% - but exports and factory execution pull in opposite directions
8Jagdambey Hydro retains fixed-tariff visibility - weak generation and one buyer still constrain the credit
8PFC and REC loans survive TANGEDCO’s restructuring - Rs 12,822 crore of annual interest shows the continuing burden Details

COAL AND TRANSITION - LOWER IMPORTS AND NEW LOGISTICS MEET OUTPUT, FUEL AND CONVERSION CONSTRAINTS

Aug 12: 8JP Nigrie seeks scheduling recognition after a coal-supply change - fuel availability must still support the declared output
8New Colliery Control rules replace the 2004 framework’s Rule 9 - compliance changes now depend on the substituted text
8India has auctioned 124 commercial coal blocks and attracted 44 first-time bidders - allocation totals still outrun producing mines
8FY26 coal output and dispatch fall - logistics additions have not prevented a weaker annual result Details

MARKETS AND SETTLEMENT - ACCOUNT CORRECTIONS EXPOSE WHO CARRIES DEVIATION AND PAYMENT RISK

Aug 12: 8Gujarat says schedule-allocation errors distorted weekly DSM accounts - corrected data could redistribute charges between entities
8Avaada’s PPA-and-merchant portfolio needs one DSM contract rate - the wrong method can shift deviation charges between sales routes
8Fuel-quality variation is being tested against partial-outage DSM treatment - one cause should not be labelled as another
8Western-region DSM defaults are delaying pool payments - unpaid participants shift the cash burden to compliant members
8Maharashtra’s legacy DSM deficit remains unpaid - old shortfalls are still reducing current disbursement capacity
8Rajasthan revises merit order after a central-station tariff change - cheaper dispatch depends on using the new cost ranking
8RGPPL’s Rs 18.64 crore legacy DSM amount is still awaiting settlement - recognition has not produced payment
8Renewable DSM calculations remain subject to interim High Court orders - final settlement still depends on the litigation
8June’s national SCED pool has paid generators under the monthly statement - heat-rate degradation compensation remains separate Details

GRID AND TRANSMISSION - EXPANSION PLANS CONFRONT AGEING ASSETS, OUTAGES AND UNFINISHED PROTECTION

Aug 12: 8Northern planners propose 23 optical terminals and an STM-64 data corridor - but allocation still starts a 12-month delivery clock
8Powergrid cuts planned VoIP control centres from 82 to 73 - while Ladakh and Chandigarh remain outside the approved scope
8Fibrehome support expires in October as replacement lags - RRVPNL wants Powergrid to take over delivery
8Repeated switching is stressing Maheshwaram’s 765 kV GIS - a flashover shows the wear is no longer theoretical
8Outage approvals delay tests on 53 ageing transmission lines - raising the failure risk they are meant to expose
8Grid-India escalates the Jeypore - Gazuwaka outage - east - south transfers remain dependent on alternative paths without a restoration date
8Kudankulam’s protection scheme delivered less load relief than intended - Nandikotkur stayed connected through a second line
8Kaiga’s Guttur circuits have been out since May - operators warn the remaining evacuation path could overload
8Odisha’s section of the Jagdishpur-Haldia gas pipeline is complete - Cuttack connectivity now depends on use, not construction
8Avaada’s connectivity-relaxation case is reserved for order - the requested network exception is not yet granted
8Gorbea Solar seeks compensation for delayed grid access - but generation loss remains a claim, not an awarded amount
8VEH Saur wants 33 MW more generation within existing connectivity - CERC first wants evidence that the projects are ready
8Kanjhawala’s 11 kV bus outage contributed to a one-hour consumer interruption - restoration is still an operating issue Details

Contracting news for the day

Aug 12: 8KSEB's Rs 65.87 lakh 110 kV upgrade deleted its 5 km experience threshold and took a bid 9.91% below estimate Terms and conditions XVIII required 110 kV work "for at least 5km length of line completed in last 7years"; corrigendum-3 removed the length and applied the change to all clauses stating experience. Three bidders were admitted — L1 Rs 59,34,453.02, L2 16.4% above, L3 26.5% above and rejected on rate. Special condition 18 sets defects liability at 60 months while clauses 1.9, 1.18 and the payment language repeat 36. 

8SECI's 45.6 MW Ramagiri wind package issued Corrigendum-1 nine minutes after queries closed and four hours before the pre-bid meeting Queries shut at 10:00 RTZ on 27 July, the corrigendum is timestamped 10:09, the pre-bid meeting sat at 14:30, and the amendment wording appears nowhere in the record. EMD is Rs 8.4368 crore for domestic and international bidders alike, against a Rs 25,000 processing fee. The tendering pattern reads "Single Stage Two Envelope followed by e-ReverseAuction" while the portal's evaluation-mechanism field reads "Not Applicable". PBG, bid validity, LD and maintenance duration sit outside the notice.

8RECPDCL's ERES-47 765 kV corridor turns a Rs 55.32 crore bid bond into a Rs 138.30 crore guarantee within ten days of LoI A 150% step-up lands on the winner the moment tariff competition ends. Qualification runs Rs 2,766 crore aggregate capex at Rs 553.20 crore per project and Rs 1,106.40 crore net worth. Clause 2.5.7 puts site, geology, transport and grid diligence on the bidder with no relief after deadline, while BSPTCL's Nawada–Guraru works and space at Jeerat stay outside TSP control. Assets, land, ROW and clearances transfer at zero cost 35 years after COD.

8RECPDCL's Solapur/Paranda GIS RFP moved its bid date 34 days and left the rest of Clause 2.7.2 behind Submission goes from 7 July to 10 August, stranding technical opening, qualification, initial offers, reverse auction, LoI and SPV transfer at their original July–August dates. CPG is Rs 30 crore, net worth Rs 250 crore, aggregate capex Rs 600 crore at Rs 120 crore per project. Three LILOs on HPC conductor and a Quad Moose link to Pune West carry a fallback obliging the TSP to buy adjacent land if utility space runs short. LD is 3.33% of monthly charges per day for 60 days then 5%, against a 24-month COD and 98% availability.

8OPTCL's Palaspanga–Barbil package states its estimate as Rs 3.15 crore in the narrative and Rs 315.27 crore in Table-A The smaller figure is exactly one-hundredth of the portal value and identical to the EMD. Table-A items 12–16 run a day behind the portal, while the IFB puts soft copies at 11 August, hard copies at 11 August 11:01 and EMD at 10 August 11:00. Lot-I and Lot-II are labelled separately but "shall be treated as a single contract" — two GIS upgrades plus 1.2 Rkm cable and 69.2 Rkm of 220 kV line. Both inside 24 months from LoA, with e-reverse auction reserved under ITB clause 29.

8NSPCL's Durgapur coal-mill R&M restored 24 mandatory pump assemblies eight days before closing, having cut them to three Amendment No. 2 made the reduction; Amendment No. 4, issued 10 August against an 18 August deadline, restored the original BOQ figure. Amendment No. 3 fixed instrumentation at one instrument for OLCS and two for CLCS and protection. Errata No. 01 corrected the tender ID to 2026_NSPCL_273894_1. The deadline moved 102 days across sixteen corrigenda while the technical baseline was still changing, with eight pulverisers to be replaced inside existing space without disturbing boiler performance.

8PSPCL's Ferozepur RDSS package went to the bidder that was 6.9% dearer before the auction and the only one that quoted in it The BOQ chart had SKS at Rs 84.95 crore against Nucon at Rs 90.84 crore; in the auction Nucon quoted Rs 84.87 crore and SKS was "Not Quoted". Final evaluation records Nucon Rs 83.80 crore at rank 1 and SKS Rs 84.95 crore at rank 2 — 1.4% apart, 31.0% and 32.8% above the Rs 63.97 crore published value. Corrigendum no. 3 reframes the tender from four packages to three and package 5 disappears unexplained. Financial opening was November 2024, final evaluation August 2026.

8RECPDCL's Barmer-II HVDC tender set a Rs 5,728 crore net-worth floor and five bidders cleared it Adani Energy Solutions, DRAIPL-CG Consortium, POWERGRID, Resonia and Terralight qualified; four are sole bidders, the fifth splits 26/74 between DRAIPL and Cube Grid Investments Pte. Ltd. The bid bond is Rs 286.40 crore and the CPG Rs 716 crore, due within ten days of LoI alongside full SPV acquisition. Scope covers two 6,000 MW ±800 kV LCC terminals, roughly 900 km of bipole and two synchronous condensers. Bipole-1 targets 48 months and Bipole-2 54, but the RFP requires simultaneous commissioning.

8BSUL's Rs 379.25 crore Jalaun evacuation package states EMD as Rs 3.80 crore in the NIT and Rs 38 lakh on the portal The tender ID shifts the same way, 913540_1 in the scanned NIT and Corrigendum-1 against 913570_1 across the CPPP record, clarification, Corrigendum-4 and opening report. Corrigendum-1 widened ITB 2.2.1 from "Sub-Station and/or Transmission line works" to "Sub-Station or any other electrical works" while holding the Rs 303.40/189.62/151.70 crore thresholds and the two 220 kV-plus bay test. SCC 3 keeps LD at 0.5% of total contract price per week where partial facilities cannot be beneficially used; SCC 3.1 and 4.0 read "Deleted" with substantive O&M text beneath, and the trial run reads "72 (Seventy-two) 24 (Twenty Four) hours continuously". Ten bidders were admitted on 10 August with the PGCIL Orai bay extension inside the contractor's scope.

8BHEL lets Talabira bidders borrow the ash-handling credentials they lack, then bills the prime bidder if a partner walks Vacuum conveying can substitute for pressure conveying where detailed engineering is vetted by an IIT or qualifying firm; missing water-impounded bottom-ash-hopper experience can be bridged by a design agency plus a performance-support undertaking; civil and structural gaps go to consortium partners. Clause 23.10 keeps the prime bidder accountable throughout. Clause 23.12 permits encashment of a departing partner's security, mandates replacement, and otherwise recovers the cost difference plus a 5% overhead factor. Clause 23.15 adds 1% consortium security, with reverse auction under clause 19.0 after technical qualification. Details

Download tenders and news clips

Aug 12:  For reference purposes the website carries here the following tenders:
 8Tender for work of supply, installation, testing and commissioning (SITC) of intelligent addressable hot redundancy based continuously available Details
 8Tender for supply of 36kV copper XLPE power cable Details
 8Tender for erection of new 132/33kV 40MVA T/F Details
 8Tender for construction of 2x40 MVA 132/33kV S/S Shahjahanpur Details
 8Tender for construction of 2x40 MVA 132/33kV S/S Details
 8Tender for construction of 2x63 MVA 132/33kV S/S Details
 8Tender for SITC of numerical line differential cum distance protection relay Details
 8Tender for work of PID testing of various tower various 132 kV, 220 kV & 400 kV lines Details
 8Tender for augmentation by replacement of existing 2x100MVA, 220/132kV ICTs by 2x200MVA, 220/132kV ICTs Details
 8Tender for AMC for repair/ service/ overhauling/problem attending of compressor of 245/145 kV circuit breaker at various Details
 8Tender for construction of LILO on 100kV line Details
 8Tender for repair maintenance of Two nos. 33kV, 10MVA transformer installed Details
 8Tender for providing fixing of negative sequence relay, over current earth fault relay Details
 8Tender for electrical works Details
 8Tender for supply and completion of HT straight through cable joints Details
 8Tender for re-organization and installation of 3.3kV overhead line and LT overhead line Details
 8Tender for replacement of 250KW, 6.6kV, HT motor of 20 no pump Details
 8Tender for dismantling, shifting of HT OH line Details
 8Tender for installation of Acs with accessories and installation of 30 nos. of streetlights Details
 8Tender for replacement of damaged GI sheets and various Details
 8Tender for making 02 Nos foundation and ramp for shifting of existing 100MT weigh bridges Details
 8Tender for replacement of old GI sheet on roof with profile sheet and misc. repair work Details
 8Tender for construction of control room foundations, cable trench Details
 8Tender for renovation of yard light works Details
 8Tender for repair of submersible pump for various 33kV S/S Details
 8Tender for renovation of control room and misc. civil works at 33kV S/S Details
 8Tender for renovation of sanitary, electric yard levelling gravelling work Details
 8Tender for suppy of P/F FRP fencing for RMU, transformer Details
 8Tender for construction of prestressed precast and brick masonry Details
 8Tender for work contract for work of lifting and disposal of used thermal insulation material Details
 8Tender for work contract for availing OEM supervisory services for complete overhauling along with commissioning of 6.6 kV, 360 KW glandless boiler Details
 8Tender for procurement of 250 NB and 300 NB sleeve type expansion joint for installation in pressure conveying line Details
 8Tender for construction of new 11 kV, LT lines and 11/0.4 kV DTR Details
 8Tender for miscellaneous civil work Details
 8Tender for replacement of flame proof (FLP) lighting distribution boards (LDBs) at various Details
 8Tender for construction of box culverts Details
 8Tender for rectification works for structural and civil defects in C-Row Details
 8Tender for job contract for removal of brick partition wall and extension of stage-1HT switchgear Details
 8Tender for civil works of construction of culvert and other necessary repair work Details
 8Tender for supply and retrofitting of 400 kV SF6 circuit breakers Details
 8Tender for work of erection, testing and commissioning of new FOAC cable in existing 66kV UG line network Details
 8Tender for work of erection-dismantling of 66kV/11kV equipment’s, structures, control wiring Details
 8Tender for work of complete servicing/ overhauling/ defect attending of various hoists and cranes Details
 8Tender for work of penthouse /APH centre section sealing for the unit Details
 8Tender for supply of liquor ammonia 25 % (AR grade) for boiler water treatment Details
 8Tender for EPC package for ash handling system Details
 8Tender for framework agreement for various industrial operations Details
 8Design, engineering, manufacture, supply, erection, testing & commissioning of 6.6 kV indoor metalclad draw-out type VCB panels Details
 8Tender for renovation of power house Details
 8Tender for shifting of electrical utilities in connection Details
 8Tender for interlinking of 11kV feeder Details
 8Tender for supply, erection & commissioning of 11 kV lines with MVCC conductor & dismantling of existing open conductor 11 kV lines Details
 8Tender for works contract for replacement of existing overhead bare conductor Details
 8Tender for works contract for replacement of existing overhead bare conductor ACSR 7 4.09 mm, AAAC 7 3.15 mm and AAAC 7 2.59 mm by XLPE coated covered conductor Details
 8Tender for turnkey construction of one no. of 33kV feeder bay and associated works at 220/132kV GSS Details
 8Tender for conversion of 11 kV feeder Details
 8Tender for refurbishment of coal burner nozzles and tips of 2x270 MW units Details
 8Design, manufacture, testing, supply and delivery of 162 nos. 66kV, 39 nos. 132kV and 63 nos. 220kV SF-6 circuit breakers Details
 8Tender for creation of new control room at 132kV S/stn Details
 8Tender for casting of machine pressed solid Details
 8Tender for work of annual rate contract for attending on site minor repairs / maintenance works / OLTC overhauling of EHV class power transformers / ICTs Details
 8Tender for laying of three single core 11kV XLPE 185 sq.mm. cable on elevated PSC structure Details
 8Tender for laying of three single core 11kV XLPE 185 sq.mm. cable Details
 8Tender for supply of BWSR spares Details
 8Tender for providing PVC coated chain link fencing Details
 8Tender for erection of 66 kV line Details
 8Tender for replacement of acid and alkali resistant tiles in DM plant Details
 8Tender for procurement of complete assembly of gear box model Details
 8Tender for procurement of M/s coupling and its spiders installed Details
 8Tender for rate contract for maintenance of AC machines Details
 8Tender for service contract for online leak sealing job as and when required Details
 8Tender for biennial contract of the job operation of gate valve for smoothly distributing Details
 8Tender for supply of vertically operated 11kV gang operated air breaker switch Details
 8Tender for works contract for carrying out HT LT DCW, improvement and capital extension works Details
 8Tender for works contract for stores handling works Details
 8Tender for procurement of MS bolt nut Details
 8Tender for provide services for installation of solar meter along Details
 8Tender for work of overhauling of 132KV/220 kV CB poles and mechanism of with required spares Details
 8Tender for work of two-year rate contract for the work of cold line washing of insulator strings of various Details
 8Tender for supply, installation & commissioning of neutral grounding reactor (NGR) for power transformer Details
 8Tender for work of providing & applying of high insulation resistance compound coating having Di-electric strength Details
 8Tender for annual maintenance contract for the work of attending emergency, break down and maintenance work of 220kV, 132kV lines Details
 8Tender for supply of equipments/ material, erection, testing and commissioning for the work augmentation by providing additional 1 x 50MVA, 132- 110/33 kV T/F along Details
 8Tender for supply of various CDS tubes and bend for drain & vent line Details
 8Tender for conductor replacement with hardware & SRI of 66kV tower line Details
 8Tender for loading & unloading of material and transformer Details
 8Tender for erection, maintenance and dismantling work of overhead HT/LT line Details
 8Tender for supply of spare for bosch make loudophone at switchyard Details
 8Tender for work of rubber lining of various equipments, pipes and fittings Details
 8Work of repairing of various pulleys of conveyor belts Details
 8Tender for biennial work contract for maintenance of ash handling plant Details
 8Tender for various maintenance works of wagon tippler Details
 8Tender for work of carry out corrosive test of various MS structure of coal handling plant Details
 8Tender for supply of control panel spares of pump house Details
 8Tender for work of misc pressure part related activity of boiler stage Details
 8Tender for work for dismantling, design & supply, installation and commissioning of GI duct and air filter assembly with supporting structure Details
 8Tender for rate contract for routine, preventive & breakdown maintenance of TPS lighting system, fans etc Details
 8Tender for work of replacement of various spares of drive system of wagon tippler Details
 8Tender for supply of various ratings LT motor Details
 8Tender for supply of various boiler tubes bends Details
 8Tender for carting of 11,500 Nos. of 8 meter PSC poles Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8How India seeks to translate its offshore wind potential into large-scale deployment Details
 8Coal India Weighs Buyout of Wealth Minerals' Chilean Lithium Unit Details
 8Five decades of research leads to solar PV’s emergence as the world’s dominant energy source Details
 8Look beyond solar, draw up roadmap for all renewable energy sectors: House panel to MNRE Details
 8Powering the Next Generation of Commercial Rooftops: Hoymiles MIT-5000-8T Takes Centre Stage in Hyderabad Solar Project Details
 8Beyond modules: Why cell manufacturing will shape India’s next solar growth story Details
 8ReNew Sells Solar Assets for Rs 4,859 Crore Details
 8Sodium-Ion Battery Prototypes Reach 200 Wh/kg Milestone Details
 8India Strengthens Energy Storage Framework With INR 5,400 Crore VGF And Transmission Incentives Details
 8India’s solar revolution lights the path to a Viksit Bharat Details
 8India's Delhi faces rising night-time power peaks: report Details
 8India awards 1 GW of round-the-clock renewables at competitive tariff Details
 8Electricity Demand Expected To Rise Up to 7.5% In FY27 Amid Higher Heat, Rainfall Deficit: Crisil Details
 8Huf India Commissions 1 MW Rooftop Solar Project in Pune Details
 8India’s Coal Imports For Power Blending Fall 71.5% In Two Years: Govt Details
 8India Accelerates Power Distribution Digitalization With Smart Meters And Grid Modernization Details
 8Global Renewable Energy Capacity Hits 5.2 TW Milestone Details
 8Lloyds Metals Secures 66 MW Renewable Power via Gentari Deal Details
 8UP to resume smart meter rollout after consumer awareness drive: State Power Minister Details
 8Cummins India Q1 FY27: Revenue rises 18%, data centers drive power gen growth Details
 8Shadows Over Green Energy Details
 8Porter Marks 10,000th Electric Truck Deployment in Delhi Details
 8Why India Had To Open Its Nuclear Power Sector Details
 8NLC India Renewables Bags SECI Letter of Award for 200 MW Wind Power Project in Karnataka Details
 8India's Draft National Electricity Policy 2026: Key proposals explained Details
 8HCC secures contract of around Rs 524 crore from State-run NHPC in Jammu and Kashmir Details
 8Jakson Infra Wins Rs 128 Crore Power Project in Karnataka Details
 8Hindustan Construction Company Wins Rs 524.17 Crore NHPC Order for Salal Hydro Project in J&K Details

 
You can also click on Newsclips for more Details

India adds 55.3 GW of non-fossil capacity in FY26 while planning 315 GW of coal - energy security is producing two expansion tracks

Aug 11: 8Solar contributed 44.6 GW and wind 6.1 GW to the year’s non-fossil additions, taking non-fossil sources above 54% of installed capacity.
The simultaneous build-outs leave transmission, storage, coal utilisation and peak adequacy to determine whether the two fleets complement each other or impose parallel system costs.
Details

Tripura rejects most of TSECL’s Rs1,709 crore past-gap claim to avoid a tariff shock - but the unpaid gap still has to be worked down

Aug 11: 8The regulator approved a Rs479.24 crore revenue gap but allowed only Rs117.77 crore against the FY27 tariff after calculating that full recovery would require a 42.82% average increase.
It paired partial recovery with smart-meter consent, billing-resolution and grievance directions, protecting consumers now while retaining future financial obligations.
Details

CEA’s unbuilt hydro list shows approvals stranded behind forest and environmental clearances - the paperwork has not become construction

Aug 11: 8Projects across conventional hydro and pumped storage remain untaken up even after appraisal, with some concurrences or environmental approvals already expired.
The clearance-pending category alone includes 14,649 MW in the CEA table, showing how a project pipeline can remain large without becoming executable capacity.
Details

SJVN’s 1,200 MW firm-renewable and 600 MW wind tariff cases are reserved for order - but the 1,200 MW sale agreement is still unsigned

Aug 11: 8One case covers 1,200 MW of firm dispatchable renewable supply; the other covers 600 MW of inter-state wind projects selected through separate bidding.
For the firm and dispatchable procurement, HPSEB has sought state approval for the contracted power but had not executed its power-sale agreement at the hearing.
Details

Chhattisgarh’s 500 MWh battery tender reaches tariff-adoption hearings with Rs90 crore of support - but the storage contract is not final yet

Aug 11: 8The state distributor’s petition says the project must be commissioned within 18 months of the storage-purchase agreement and that land and connectivity will be provided.
Public comments are due before the September hearing, so the discovered tariff and contractual allocation still require regulatory adoption.
Details

Odisha sought Rs6,284 crore of cyclone-resilient distribution work - but private ownership leaves its DISCOMs outside RDSS funding

Aug 11: 8The Centre says Odisha’s utilities are ineligible because RDSS financial assistance is limited to state-owned distributors and power departments.
It also says no formal Rs10,000 crore special power-package proposal was submitted after Cyclone Yaas, separating the state’s actual RDSS request from the larger claimed package.
Details

Madhya Pradesh cuts distribution losses but accumulated DISCOM losses rise to Rs71,394 crore - reform progress has not repaired the balance sheet

Aug 11: 8State-level AT&C losses fell from 41.72% in FY21 to 22.76% in FY25, and the reported cost-revenue gap moved to a small surplus.
Borrowings still stood at Rs49,239 crore, while large portions of sanctioned RDSS network and smart-meter work remained to be installed or completed.
Details

India Energy Stack pilots are under way in five utility markets - but a national power-data architecture has not yet been proved

Aug 11: 8Utilities in Delhi, Gujarat, Andhra Pradesh, Uttar Pradesh and Mumbai have been selected for proof-of-concept implementation.
The proposed stack is meant to connect power-sector systems through secure common protocols, with interoperability, governance and consumer protection still to be demonstrated in practice.
Details

Draft power policy would shift more fixed and fuel costs into regular electricity bills - while proposing a stabilisation fund to soften volatility

Aug 11: 8The Draft National Electricity Policy, 2026 calls for fixed charges to recover fixed costs and for monthly automatic fuel-and-power purchase adjustments.
It also seeks cost-reflective tariffs without new regulatory assets, placing distribution-company finances and household affordability in the same unresolved policy choice.
Details

Uttar Pradesh has Rs21,782 crore of RDSS network works and Rs18,956 crore of smart metering sanctioned - but consumer complaints are still handled state by state

Aug 11: 8The Centre says funding is linked to physical and financial progress and vendor checks are built into standard bidding documents.
The monitoring chain reaches from state committees to PFC, REC and the Union power secretary, yet billing redress and meter mode remain with utilities and state regulators.
Details

Four China-linked equipment makers can bid for Indian power projects for two years - but only under domestic-content conditions

Aug 11: 8The exemption covers TBEA Energy India, Nanjing Electric India, New Northeast Electric India and Taikai Electric India from 24 June 2026.
Government says wider competition can ease supply constraints and stabilise prices, while the conditional waiver keeps the domestic-manufacturing trade-off visible.
Details

India has sanctioned 20.33 crore smart meters but installed 5.73 crore under RDSS - consumer safeguards now have to catch up with scale

Aug 11: 8The sanctioned total covers consumers, feeders and distribution transformers; all schemes together account for 7.24 crore installed smart meters.
Government cites check meters, independent testing and third-party laboratory verification, but billing complaints remain the responsibility of state utilities and regulators.
Details

India proposes Rs20,000 crore for carbon capture - but the programme has no approved project-selection rules yet

Aug 11: 8The five-year proposal is intended to advance carbon-capture, utilisation and storage across power, steel, cement, refineries and chemicals.
The Ministry of Power says the programme is still being established, leaving cluster selection, audit standards and implementation rules to follow after approval.
Details

Rays Power Infra’s order book reaches Rs8,455 crore - but rapid growth is lifting leverage and supplier-finance dependence

Aug 11: 8The solar developer and contractor’s order book was 3.83 times FY26 operating income, giving it substantial revenue visibility after an 81% rise in annual income.
CareEdge nevertheless identifies project concentration, higher gearing, heavy use of supplier finance and timely equity for co-developed projects as the counterweights to that growth.
Details

Amara Raja starts building a 10 GWh battery-storage factory - but first output is still tied to a FY27 construction timetable

Aug 11: 8The Divitipally project is designed for grid-scale and commercial-and-industrial storage, with operations scheduled to begin in the third quarter of FY27.
The company has already commissioned a customer-qualification plant, but the larger manufacturing plan still depends on phased cell and storage-factory start-ups over FY27 and beyond.
Details

BRIEFS - VERIFIED DEVELOPMENTS WITH LIMITED DEPTH

Aug 11: 8Thermal coal-stock reports cover 6 - 9 August - four daily observations cannot establish a durable inventory trend
8India’s generation reports compare 7 and 8 August - the two-date fuel mix is an operating snapshot, not a transition trend
8Uttar Pradesh moves its draft Grid Code hearing by one day - objections still close on the earlier timetable
8Gas stations flag a low-frequency threshold mismatch - compensation remains under regulatory review
8Secure meter-data software slows regional accounting - manual handling is still filling the processing gap
8Genus meter decryption produces conversion defects - corrected files are still awaited
8DSM defaults trigger letter-of-credit scrutiny - security compliance has not cured the pool’s unpaid balance
8Unreturned reconciliation statements are being deemed accepted - administrative closure does not create fresh cash
8NP Kunta’s STATCOM needs an SMPS upgrade - reliability work requires a planned equipment shutdown
8Hyderabad substation’s automation migration needs 400 kV outages - modernisation temporarily narrows network availability
8Talcher - Kolar HVDC Pole 1 seeks an eight-hour shutdown - refurbishment inspection still awaits outage clearance
8India’s demand forecast error moved across 7 - 9 August - three daily readings do not establish model performance
8High-price day-ahead sellers offered 37,838.4 MWh - no purchase or cleared volume followed
8Intraday auction reports expose bids, clearing and schedules block by block - the latest sheet is a market snapshot
8WCL still carries compassionate-appointment applications from earlier years - the source confirms backlog, not a clean total
8Odisha’s closed coal mines face an unfinished reclamation question - completion evidence is not established
8Fatehgarh - Bhadla lenders may take security over the transmission asset - a licence transfer still needs prior approval
8Tadas Wind challenges where DSM charges are computed - the interconnection point could change the bill
8SGPL presses a Haryana energy-charge claim - the hearing record does not award the money
8Osmanabad Solar seeks Rs3.42 crore in DSM dues - the hearing was deferred before the merits were reached
8TPTCL’s withheld-dues dispute returns to jurisdiction - the Commission wants arguments before deciding the claim
8Teesta Low Dam IV’s tariff case reaches the order stage - additional capital claims remain under scrutiny
8MEL’s transmission-licence process draws a compliance warning - proposed approval is not yet unconditional
8Solarcraft seeks more time after bay-sharing delays - missing guidelines do not automatically extend connectivity
8Kreate’s banking claim against SPTPL meets a denial of monetary liability - updated claims still need adjudication
8UGVCL’s accident register records fatal network incidents - responsibility remains case-specific
8UGVCL tracks complaints received, resolved and pending - the extracted register does not yield a reliable aggregate
8UGVCL records transformer failures and restoration complaints - a verified failure-rate figure is missing
8UGVCL’s reliability register contains outage indices - the source slice cannot support a performance ranking
8Faulty-meter replacement remains in UGVCL’s operating records - the backlog needs a clean count
8UGVCL reports no standards-of-performance compensation in the selected table - nil claims require an audit trail
8UGVCL records unauthorised-use and theft enforcement - mixed source rows prevent a verified total
8Telangana’s reservoir sheet compares storage on 11 August - a single date cannot establish seasonal security
8Odisha’s hydro report links reservoir levels to available units - sparking and open gates constrain the snapshot
8Reserve-shutdown fuel-oil compensation needs a calculation rule - eligibility alone does not fix the quantity
8Faulty special-energy meters remain unreplaced after earlier meetings - delay keeps commercial disputes alive
8Radhanesda’s meter failure produced a Rs17.83 lakh DSM revision claim - the account still needs correction
8RDSS funds workforce training for digital distribution - utilisation must match the technology rollout
8SCUC reports show upward and downward schedules from 7 - 10 August - the short series is operational, not predictive
8Real-time market data run through 10 August - block prices and volumes need a longer benchmark
8Grid-security readings were mostly compliant at Agra but weaker at Ajmer - one report cannot grade the corridor
8Western-region outages and line states changed on 10 August - the operating list is not an adequacy forecast
8The Centre retains 15% of central-station power as unallocated - states compete within the remaining allocation rules
8Chhattisgarh’s mining funds must favour high-priority services - allocation rules do not prove local delivery
8NLC’s TPS-I Expansion true-up accepts an 8.5% auxiliary-consumption norm - the wider tariff still rests on reconciled costs
8Vindhyachal Stage I seeks tariff and life-extension capital - the rules may prevent double recovery
8NLC TPS-II’s additional-capital claim contains a cash-basis mismatch - reconciliation must precede the order Details

POLICY AND SYSTEM PLANNING - RELIEF, INVESTMENT AND CAPACITY CLAIMS MEET THEIR IMPLEMENTATION LIMITS

Aug 11: 8Delhi lets three discoms recover June fuel and power costs above the 10% billing ceiling - but only for one month and below their full claims
8NTPC wants station-transformer loads explicitly counted at Vindhyachal and Korba - only export apportionment would change under its proposal
8Legacy and current power-pool deficits are still holding back disbursement - collections received do not eliminate the unpaid tail
8Municipal bonds have raised Rs6,540.44 crore across 23 urban bodies - green issuance is growing but incentives do not prove project delivery
8NTPC Lara has settled rehabilitation claims for most affected families - jobs remain conditional on vacancies and suitability
8Ashoknagar’s petroleum lease has been extended twice - commercial oil and gas production still has not begun
8India met a 270.8 GW peak in May against a 289 GW FY27 forecast - national adequacy still leaves local network constraints
8Electrical installations may use inspection or self-certification cycles of up to five years - digital reporting must make the option auditable
8Public EV-charging electricity use rose from 107.41 MU to 149.58 MU between April 2025 and March 2026 - four states dominate the annual total
8Telangana’s station-wise generation moved through July - the monthly sheet reveals unit performance but not the cause of every change Details

REGULATION AND DISPUTES - PETITIONS SEEK MONEY OR RELIEF THAT ORDERS HAVE NOT YET AWARDED

Aug 11: 8Andaman solar and storage operators seek must-run compensation - deemed generation still needs a contractual basis
8ReNew seeks protection against a bank-guarantee call - the dispute has not erased the underlying obligation
8Barh Stage I capital costs require another reconciliation - escalation cannot enter tariff without an accepted basis
8Sarda seeks tax and open-access reimbursement for 100 MW - contract allocation will decide who pays
8Sikkim Urja, PTC and NDMC trade reciprocal dues - set-off cannot replace proof of each underlying bill
8NTPC Renewable and SECI dispute a scheduled-completion extension - delay relief depends on the cause and notice record
8APPCPL’s banking claim meets SPTPL’s insolvency moratorium - recovery rights now collide with bankruptcy protection
8SEIL disputes coal-transport deductions under its power-supply arrangement - the case must decide whether freight was recoverable or already embedded in another charge
8Tamil Nadu’s Ombudsman protects the existing tariff for qualifying small extensions - separate construction can still trigger Tariff VI
8Adani’s Jharkhand plant supplies Bangladesh exclusively - cross-border trade adds power without entering India’s domestic allocation Details

STORAGE AND HYDRO - ANNOUNCED CAPACITY STILL WAITS FOR AWARDS, CLEARANCES AND OPERATING EVIDENCE

Aug 11: 8Assam is included in plans for 200 MWh of battery storage - but no state capacity has yet been allocated
8Nathpa Jhakri seeks recovery for hydrology shortfall - the case turns on evidence that water, not operation, caused the loss
8Kynshi and other hydro DPRs go back for revision - redesign delays appraisal but may be necessary for a viable project
8Draft power policy backs storage and flexible grids - integration measures remain plans until capacity and networks are commissioned Details

DISTRIBUTION AND CONSUMERS - DIGITAL INVESTMENT EXPANDS FASTER THAN PROOF OF SERVICE IMPROVEMENT

Aug 11: 8PSPCL proposes an online settlement for 37.2 lakh consumers owing about Rs6,201 crore - agricultural accounts are excluded and PSERC approval is pending
8RDSS pushes distribution utilities deeper into digital operations - installation counts still do not prove better service
8Private discoms average 23.87 hours of daily supply and 10.05% AT&C losses versus state utilities’ 23.22 hours and 15.40% - group averages still hide company-level variation
8Andhra Pradesh advances RDSS cabling and smart meters - large awards still leave an installation gap
8RDSS adds SCADA, IT/OT integration and smart-distribution-city projects - cybersecurity becomes part of reliability Details

COMPANIES AND FINANCE - GROWTH VISIBILITY MEETS HYDROLOGY, CREDIT AND ACCOUNTING RISK

Aug 11: 8Amara Raja’s new-energy sales grow by more than 50% - but exports and factory execution pull in opposite directions
8Jagdambey Hydro retains fixed-tariff visibility - weak generation and one buyer still constrain the credit
8PFC and REC loans survive TANGEDCO’s restructuring - Rs12,822 crore of annual interest shows the continuing burden
8Quality Power’s income rises 32% and its order book reaches Rs19,455 million - reported profit still carries a hyperinflation adjustment Details

COAL AND TRANSITION - LOWER IMPORTS AND NEW LOGISTICS MEET OUTPUT, FUEL AND CONVERSION CONSTRAINTS

Aug 11: 8JP Nigrie seeks scheduling recognition after a coal-supply change - fuel availability must still support the declared output
8New Colliery Control rules replace the 2004 framework’s Rule 9 - compliance changes now depend on the substituted text
8Power-sector coal imports fall 71.5% to 6.8 million tonnes in two years - the source does not isolate how much domestic coal replaced them
8India has auctioned 124 commercial coal blocks and attracted 44 first-time bidders - allocation totals still outrun producing mines
8Coal-gasification incentives support a 100 million-tonne ambition - projects still need buyers, feedstock and working economics
8FY26 coal output and dispatch fall - logistics additions have not prevented a weaker annual result
8Coal India plans 139 first-mile projects with 1,319 million-tonne capacity by FY30 - eight rail schemes still have to turn that capacity into dispatch Details

MARKETS AND SETTLEMENT - ACCOUNT CORRECTIONS EXPOSE WHO CARRIES DEVIATION AND PAYMENT RISK

Aug 11: 8Gujarat says schedule-allocation errors distorted weekly DSM accounts - corrected data could redistribute charges between entities
8Avaada’s PPA-and-merchant portfolio needs one DSM contract rate - the wrong method can shift deviation charges between sales routes
8Fuel-quality variation is being tested against partial-outage DSM treatment - one cause should not be labelled as another
8Western-region DSM defaults are delaying pool payments - unpaid participants shift the cash burden to compliant members
8Maharashtra’s legacy DSM deficit remains unpaid - old shortfalls are still reducing current disbursement capacity
8Rajasthan revises merit order after a central-station tariff change - cheaper dispatch depends on using the new cost ranking
8RGPPL’s Rs18.64 crore legacy DSM amount is still awaiting settlement - recognition has not produced payment
8Renewable DSM calculations remain subject to interim High Court orders - final settlement still depends on the litigation
8June’s national SCED pool has paid generators under the monthly statement - heat-rate degradation compensation remains separate Details

GRID AND TRANSMISSION - EXPANSION PLANS CONFRONT AGEING ASSETS, OUTAGES AND UNFINISHED PROTECTION

Aug 11: 8Northern planners propose 23 optical terminals and an STM-64 data corridor - but allocation still starts a 12-month delivery clock
8Powergrid cuts planned VoIP control centres from 82 to 73 - while Ladakh and Chandigarh remain outside the approved scope
8Fibrehome support expires in October as replacement lags - RRVPNL wants Powergrid to take over delivery
8Repeated switching is stressing Maheshwaram’s 765 kV GIS - a flashover shows the wear is no longer theoretical
8Testing on 53 ageing transmission lines is being slowed by outage approvals - the delay raises the failure risk the tests are meant to reduce
8Grid-India escalates the Jeypore - Gazuwaka outage - east - south transfers remain dependent on alternative paths without a restoration date
8Kudankulam’s protection scheme delivered less load relief than intended - Nandikotkur stayed connected through a second line
8Kaiga’s Guttur circuits have been out since May - operators warn the remaining evacuation path could overload
8Odisha’s section of the Jagdishpur-Haldia gas pipeline is complete - Cuttack connectivity now depends on use, not construction
8Avaada’s connectivity-relaxation case is reserved for order - the requested network exception is not yet granted
8Gorbea Solar seeks compensation for delayed grid access - but generation loss remains a claim, not an awarded amount
8VEH Saur wants 33 MW more generation within existing connectivity - CERC first wants evidence that the projects are ready
8Kanjhawala’s 11 kV bus outage contributed to a one-hour consumer interruption - restoration is still an operating issue
8India plans to raise inter-regional transfer capacity from 120 GW to 168 GW by 2032 - renewable growth still needs the lines to arrive Details

Contracting news for the day

Aug 11: 8Mahagenco's Rs 93.55 crore Koradi pipe tender asks a manufacturer for 100% turnover and a contractor for 30% Annexure A sets average annual turnover equal to the entire Rs 63.37 crore supply estimate; Annexure B sets its test at 30% of Rs 30.18 crore, or Rs 9.054 crore. The two rounded annexure values total Rs 93.55 crore against the NIT's Rs 93.552027 crore. Annexure B says the bidder or a consortium member should qualify both the works and supply conditions, while later provisions require only one member to meet the works QR — leaving unstated whether credentials can be split between two partners. Holding-company support runs five years from the last month of bidding or to the end of the defect-liability period.

8BHEL's Jharsuguda ash-handling EPC excludes civil and structural works, then makes the contractor responsible for them anyway TCC clause 3.14 keeps any additional item required for package completeness — mechanical, electrical, C&I, civil and structural — inside bidder scope unless specifically excluded. NIT clause 35.0 issues one LOA and then splits billing into supply, installation and five-year O&M, reserves BHEL's right to redistribute that split later, and makes a breach under one order a breach under the others. O&M starts at 5% of contract price and escalates 3% a year, aggregating roughly 26.5% over five years. Auxiliary power is capped at 3,173 kW with LD of Rs 14 lakh per additional kW. Bid issue to submission: eleven days.

8DVC's Rs 90.20 crore Chandrapura diversion names three different conductors for one package The high-level scope cites AAAC Panther 37/3.15 mm and AAAC Dog 19/2.89 mm; the detailed supply section calls for AAAC Zebra 61/3.31 mm plus underground cable, and the tender text does not map either set to a particular line. Corrigendum-I moved download, submission and opening each by seven days and states all other terms remain unaltered. Bid validity is 180 days while bid security must run 225. Price variation under SCC clause 8 stops rising past scheduled dates unless preserved in an extension letter; downward movement still accrues to the owner.

8OPGC's Rs 21.83 lakh protection audit carries two turnover thresholds, two experience windows and a handwritten voltage GeM shows minimum average annual turnover of Rs 7 lakh; the committee-approved QR clause 2.2.1 sets Rs 6.55 lakh. GeM states five years of past experience while QR clause 2.1.1 admits similar works completed in the preceding seven. The 40%/50%/80% ladder should read Rs 8.732, 10.915 and 17.464 lakh; the QR prints Rs 8.73, 10.90 and 17.50 lakh — 40.0%, 49.9% and 80.2%. The QR scan carries a handwritten "220KV" beside the printed 400 kV similar-work description. Payment is set at 30 days, expressly superseding the 10 days in GeM GTC clause 12.

8OPTCL's Rs 147.97 crore Balasore cable tender can't agree with itself on how many stages it has The IFB describes a "single stage two part system"; the portal field reads "Stage: Two Stages". Document availability differs the same way — the notice runs 06.06.2026 to 06.07.2026, the portal 11-06-2026 to 08-07-2026, with closing at 14:00 and techno-commercial opening at 15:00 on 8 July. The notice rounds the estimate to Rs 147.97 crore while the portal records Rs 1,47,97,02,728 and fixes EMD at Rs 1,47,97,027. No corrigendum in the package reconciles either. Cost-opening date is to be defined later.

8NTPC's Ramagundam transformer tender gives three different answers on price escalation The technical specification applies IEEMA escalation to the transformer price alone and keeps freight, insurance, spares, tests and erection firm; BDS marks price-adjustment data "Not Applicable"; Appendix-2 sets out a wider adjustment framework across equipment, erection, structural and civil components without a ceiling. The contract runs 30 months. BDS clause 13 confines installation pricing to 10–15% of the supply portion and retains amounts quoted outside that band without interest rather than rejecting the bid. BDS clause 31 carves 5% of the service portion out against quarterly safety certification. The NIT calls it single-stage two-envelope; the portal operates three covers.

8JPDCL's Rs 538.15 lakh "DPR" is a 33 kV line build, and its extension left bid opening six days before bid closing The SBD reduces scope to "As per BOQ", and the BOQ carries 420 11-metre poles, 40 13-metre poles, 42,000 kg of channel iron, 72 km of ACSR, 920 stay sets and 15 lattice-structure jobs. Extension Notice-1 moved the last date for bidding from 10 August to 17 August "due to low response" but left technical opening at 11 August and hard-copy EMD submission at 10 August. The performance-security clause is numbered 2 yet directs bidders to "clause 3.2", and the unbalanced-bid provision refers back to "clause 3.1". Clause 20.2 places jurisdiction by reference to Ramban in a Udhampur-Chenani package.

8HPSEBL's Rs 3.72 crore distribution-reform consultancy is gated on transmission turnover, then run through both QCBS and a reverse auction Eligibility requires Rs 70 crore average annual turnover in power-transmission consultancy at 66 kV and above for an assignment framed under a distribution-sector scheme; joint ventures are barred. ITC 25.1 sets 70:30 QCBS while the NIT adds an e-reverse auction with a 0.5% decrement, and no provision states how the auction price enters the financial score. The NIT and portal require Rs 7.44 lakh EMD; the RFP requires a bid-securing declaration in lieu of it. Validity is 180 days on the portal and 120 in Data Sheet ITC 12.1; one ITC provision bars subcontracting while ITC 12.8 permits it. Three corrigenda, 31 days, no substantive change.

8MPPMCL's 625 MW storage tender still shows its opening event six days before the bids come in The header applies 10 August for receipt of bids while the NIT table retains 4 August as the tender opening event and 30 July for document procurement. Corrigendum-1 issued 24 July and the record separately notes "Addendum #2 Issued", neither reproduced at NIT level. Bid security is Rs 2.20 lakh/MW rather than a flat sum, alongside a Rs 15 lakh processing fee plus GST and a Rs 30,000 ETS charge. Chemistry, cycle life, degradation, augmentation, availability and PBG terms sit outside the notice.

8NSPCL's Durgapur mill tender cut mandatory spare pump assemblies from 24 to three, then put them back to 24 Amendment no. 2 made the reduction; Amendment no. 4 restored the original figure, stating "As per the Original BOQ". The same amendment chain rewrote completion LD from a flat Rs 6,89,750 per day to 0.5% per week on the contract price attributable to uncommissioned mills, capped at 5%; deleted unburnt-carbon loss as a sizing criterion; disallowed YGP correction of wear life; and cut the wear-life demonstration population from three pulverisers to two. The shutdown-extension LD provision still reads "INR xxxxxx". Eleven closing-date revisions moved the deadline 102 days from 8 May to 18 August.

8NTPC's Rihand generator-transformer tender marks price adjustment applicable and the price-adjustment appendix "NOT APPLICABLE" BDS identifies Attachment 8P as applicable; Appendix-2 is headed "PRICE ADJUSTMENT (NOT APPLICABLE)" and then sets out uncapped escalation formulas for equipment, erection and other components. BDS item 13.0 states "Civil work Price Component: Not Applicable" and immediately requires that component to fall between 70% and 75% of the supply portion, against a BOQ built around supply, erection, freight, spares and tests. Installation pricing outside the 10–15% band draws interest-free retention. Contract period 36 months; LD 0.5% weekly capped at 5%.

8DVVNL's Rs 79.32 crore AB cable tender shows 5% performance security on the portal and 10% in the terms that override it GeM prescribes a 5% ePBG for 48 months; the ATC declares itself overriding and sets a 10% contract performance guarantee, with clause 36 rendering it as "Ten Percent (10%) plus GST@18% of the total Contract price". Guarantee duration is written three ways — 90 days after contract completion, 180 days after warranty expiry, and again 90 days beyond successful warranty completion. Corrigenda C5 and C6 carry identical substantive terms and differ only in identifier, yet C6 states it supersedes all existing buyer-added conditions. The portal permits splitting among 30 bidders while the ATC requires each bidder to offer at least 25% of quantity; the award went five ways at one rate, Rs 474.10 per metre.

8KSEB's transformer tender has two probable contract amounts, Rs 10.46 crore apart, and L1 and L2 separated by Rs 2.67 lakh The notice and portal record a PAC of Rs 72.16 crore; the 3 August pre-qualification minutes cite Rs 61.70 crore, with no reconciliation. Against the first figure L1 at Rs 84.65 crore is 17.3% high; against the second, 37.2%. L2 stood at Rs 84.68 crore — a 0.03% spread — while L5 came in 31.6% above L1. Clause 18.7.4 had specified a finishing coat as both "dark admiral gray conforming to No. 632" and "No. 541 (Light Brown)" until the corrigendum removed the second. Three of the five qualified bidders were admitted on undertakings to produce compliant type-test reports before supply.

8PSPCL's Faridkot RDSS package records an auction price of Rs 111.60 crore and an award value of Rs 111.71 crore The difference, about Rs 11.17 lakh, is almost exactly the single 0.1% decrement that produced the auction result; the comparative BOQ summary and award-facing record remain at the pre-auction figure. Only two bidders reached financial evaluation and only one entered a revised figure, the other recorded "Not Quoted". L1 finished 24.8% above the Rs 89.46 crore estimate, L2 42.0% above. SCC fixes performance security at 3% while the advance-payment condition refers to 10% of contract price, and the payment clause reads "sixty-five (60) days". Individual BOQ items may move ±50%.

8PFCCL's Fatehgarh-II synchronous condenser tender opened bids 76 days after the date the RFP set Clause 2.7.1 fixed 17 April 2026; the qualification notice records actual opening on 2 July and qualified bidders declared on 10 July. Exactly four bidders qualified against a rule advancing the higher of the top 50% of ranked initial offers or four — so the shortlist and the auction field are the same set. Qualification tests infrastructure capex of Rs 1,140 crore aggregate and Rs 456 crore net worth, not synchronous-condenser operating history, while performance is measured at the PCC with total losses below 2%, 97% availability and 1,200 MVA short-circuit contribution. Assets transfer at zero cost 35 years after COD.

8RECPDCL amended its Rs 55.32 crore-bond ERES-47 bid deadline the day before it fell due, and left COD where it was Amendment-IV, dated 10.08.2026, moved submission from 11 to 18 August, qualified-bidder announcement to 27 August, initial-offer opening to 31 August, the reverse auction to 1 September and SPV transfer from 10 to 21 September — an 11-day shift at the far end. Scheduled COD stays 31.03.2029, so the post-award runway shortens by the same amount. Technical qualification requires Rs 2,766 crore aggregate capex with Rs 553.20 crore per project and Rs 1,106.40 crore net worth. Execution depends on BSPTCL's matching Nawada–Guraru works and space at Jeerat from another entity.

8A 400 kV GIS switching-station RFP has now moved its bid date 48 days without touching a 24-month COD Amendment-III shifts submission from 10 to 24 August, 14 days, against an original RFP date of 7 July; qualification announcement, initial-offer opening and reverse auction all move to 1, 2 and 3 September, and document signing to 21 September. Initial offers and the auction remain one day apart. The bid bond is Rs 12 crore and the performance guarantee Rs 30 crore, with net worth of Rs 250 crore and Rs 600 crore aggregate capex required. LILO conductor, OPGW and earth wire must match existing-line parameters, and bay-extension work may add roads, drainage, trenches and levelling identified only at site inspection. The amendment states the revised timetable and no reason for it. Details

Download tenders and news clips

Aug 11:  For reference purposes the website carries here the following tenders:
 
8Tender for supply of 33 kV, 3CX300 Sq mm HT power cable Details
 
8Tender for supply of M.S forged pins for 33kV pin insulators Details
 
8Tender for supply of electro-pneumatic and resistance to current convertors Details
 
8Tender for requirement of emergency oil pump (EOP) with DC motor for 210/195MW units Details
 
8Tender for carting of 11,500 Nos. of 8 meter PSC poles Details
 
8Tender for supply of 36 kV copper XLPE power cable Details
 
8Tender for erection of new 132/33kV/ 40MVA T/F Details
 
8Tender for rate contract for supply of 33 kV vaccum interrupter Details
 
8Tender for procurement of 02 Nos. 6.6 kV 988 KW ,992 RPM,ID fan motor Details
 
8Tender for procurement of mechanical spare parts of stacker reclaimer Details
 
8Tender for procurement of LT motor above 100KW Details
 
8Tender for supply and installation of 780KWp solar PV modules Details
 
8Tender for annual maintenance contract (AMC) of firewalls installed Details
 
8Tender for AMC to desilting, earthwork, painting and sectioning Details
 
8Tender for certain improvement works Details
 
8Tender for work of shifting of 132KV D/C line Details
 
8Tender for civil works of 400/220kV yard Details
 
8Tender for framework agreement for various industrial operations to be carried out Details
 
8Tender for procurement of complete cartridge assembly for boiler feed pump Details
 
8Tender for construction of soild waste management yard Details
 
8Tender for work of chemical washing of disc insulator strings of various 132kV & 220 kV lines Details
 
8Tender for supply of 66kV isolators at switchyard Details
 
8Tender for supply of various types of clamp for 220 kV switchyard Details
 
8Tender for rate contract for dismantling, lifting, shifting, overhauling & reinstallation of LT motors Details
 
8Tender for supply, erection, testing & commissioning of 66kV D/C line on M/C tower with ACSR panther conductor Details
 
8Tender for construction of control room foundations, cable trench Details
 
8Design, engineering, supply, erection including civil works, testing and commissioning of 11kV single circuit line Details
 
8Tender for miscellaneous civil maintenance works Details
 
8Tender for dismantling of existing transformers and the design, engineering, erection, civil works, testing, and commissioning of 31.5 MVA, 132/34.5 kV power transformers Details
 
8Tender for construction and renovation of sub-station Details
 
8Tender for upgradation/ renovation of lane and drain Details
 
8Tender for diversion of forest land for hydro electric project 81MW including Details
 
8Tender for supply of consumable items for maintenance at power house Details
 
8Tender for supply of material and related work for undergrounding of LT line Details
 
8Tender for renovation, reconductoring and restrengthening of 33 kV feeder Details
 
8Tender for procurement of GI earth pipe B class medium Details
 
8Tender for constructing additional circuit 11kV OH with covered conductor Details
 
8Tender for supply of 1.1 kV XLPE insulated 1Cx150, 1Cx120 and 1Cx95 sq.mm aluminium unarmoured cables Details
 
8Tender for construction of 8 km 110kV double circuit LILO line Details
 
8Tender for upgradation of 66kV substation Details
 
8Tender for constructing 11 kV OH line Details
 
8Tender for rate contract for repair and maintenance works pertaining to 400 kV D/CC transmission line Details
 
8Tender for fixing of rate contract for unforeseen restoration of civil works like protection walls, crate revetment, masonry drains etc pertaining to 400 KV D/C transmission line Details
 
8Tender for providing of services of PLCC and RTU automation engineers for checking/ repairing / rectification of PLCC and telemetry panels installed Details
 
8Tender for work of proximate and ultimate analysis of coal Details
 
8Tender for left over work of design engineering supply erection testing and commissioning of LILO of 220 kV D/C transmission line Details
 
8Tender for miscellaneous civil works Details
 
8Tender for supply of single-phase secondary set with variable frequency and voltage testing kits Details
 
8Tender for strengthening of tower foundation of tower no.63 of 220kV line Details
 
8Tender for supply, design, manufacture, testing, charging and delivery of 220 VDC and 200AH battery bank along with all accessories Details
 
8Tender for annual overhauling of unit 2 and 3, repair of various underwater parts Details
 
8Tender for biennial maintenance of sewer line works, repairing of pits etc. Details
 
8Tender for procurement of different steel items Details
 
8Tender for procurement of fasteners for overhauling job of coal mill, APH ducts, coal burner nozzle Details
 
8Tender for procurement of coal burner spares Details
 
8Tender for laying of 02 Nos. 3X400 Sq.mm. cable for making LILO arrangement Details
 
8Tender for procurement LT shackle hardware (metal parts) Details
 
8Tender for supply of 11kV polymer disc insulators Details
 
8Tender for work of erection of 66kV equipment, structures, control wiring, yard lighting Details
 
8Tender for ARC for laying of HT U/G cable Details
 
8Tender for supply, installation, testing & commissioning of conversion of 66kV line Details
 
8Tender for balanced work of supply, erection, testing and commissioning of additional 1 x 25MVA, 132/33 kV T/F along Details
 
8Tender for work of ash lifting of ESP Details
 
8Tender for supply, erection and commissioning of new street light poles with cable laying Details
 
8Tender for supply of 90/10 cupronickel condenser tubes Details
 
8Tender for job contract for works of attending daily/routine defects, preventive maintenance, shutdown & emergency maintenance of electrical auxiliaries Details
 
8Tender for supply, installation, testing & commissioning of conversion of 66kV line Details
 
8Tender for ARC for laying of HT U/G cable Details
 
8Tender for rate contract of excavation and laying of new power / control / telephone cables Details
 
8Tender for providing RCC chamber with protection wall Details
 
8Tender for work of supply and application of anti-corrosive paint/coating on external surface of various steel structures, pipelines Details
 
8Tender for work of complete o/h of MS & HRH strainers, HP&IP stop and control valves, TG bearings, H2 seal body, generator Details
 
8Tender for supply of I to P converters for 3 x 210 MW unit Details
 
8Tender for ARC for laying of HT U/G cable Details
 
8Tender for work of complete cleaning of boiler Details
 
8Tender for ARC for laying of HT U/G cable Details
 
8Tender for work of U/G 11kV 185/240/300 mm2 XLPE cable laying, fault finding and provide & fixing outdoor, indoor cable box & straight joint kit for work Details
 
8Tender for ARC for laying of HT U/G cable (SI scheme) work Details
 
8Tender for ARC for laying of HT U/G cable Details
 
8Tender for supply of various spares for SWAS system of boiler Details
 
8Tender for ARC for laying of HT U/G cable Details
 
8Tender for ARC for supply erection and commissioning of of GI cable tray Details
 
8Tender for supply of refrigerant gas mafron R-22 and R-134a in cylinders for air conditioning plants Details
 
8Tender for supply and replacement of NDCT components for 1x 800 MW unit Details
 
8Tender for annual maintenance contract AMC for ring main units Details
 
8Tender for providing and fixing of first 20 pole earthing Details
 
8Tender for providing and fixing of first 20 pole earthing of 11kV feeders Details
 
8Tender for supply and application of HVOF (high velocity oxy flame) thermal spray coating in various Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8
1,132 solar plants installed under MSSY across Uttarakhand Details
 
8Number of rooftop solar power plants in western MP crosses 82,000 mark, capacity reaches 500 MW Details
 
8Dilip Buildcon Agrees to Sell Stake in Under-Construction Power Transmission & Solar Projects to Alpha Alternatives Details
 
8Jupiter Wagons wins two BESS project from WBSEDCL Details
 
8Fuel shortage cuts power generation, increases load-shedding Details
 
8South West Pinnacle Exploration secures Letter of Award from CMPDI for coal exploration in Jharkhand Details
 
8Govt Asset Sales Hit 73% of FY27 Goal With Rs 58,154 Crore Realized Details
 
8GE Vernova Expands Wind Footprint in India With 163.4 MW Order Details
 
8Mayr introduces smart wind safety solutions at WindEnergy 2026 Details
 
8India's peak power demand rises 12% in April-June, evening supply gap widens to 3,045 MW: Govt Details
 
8India's Power Sector Revolution: 19.79 Crore Consumers to Get Smart Meters Details
 
8India Solar Power Generation Surges 45.9% in Q2 2026 Details
 
8Nuclear Ambitions: Building capacity for a low-carbon future Details
 
8Aluminium Conductors: Powering India’s Next Generation of Sustainable Energy Details
 
8NPCIL seeks financial autonomy as India accelerates nuclear power push Details
 
8Basudev Hansdah, CEO, Maithon Power Limited Details
 
8Tamil Nadu allocates Rs 15,828 crore for energy sector in 2026-27 budget Details
 
8RPSG Group’s Purvah Green to acquire 1.4 GWp operating solar portfolio for INR 4,859 crore from ReNew Details
 
8Against target of 500 GW by 2030, India registers 300 GW of non- fossil fuel electricity generation as on July 31, 2026 Details
 
8Parliamentary Panel Flags Underutilisation of Govt Funds for India’s Renewable Sector Details
 
8India Records Rs 26.75 Lakh Crore Investment Announcements In FY27 So Far Details
 
8MRF, TD Power and 6 Other Stocks Announcing Q1 Results Today to Look Out For Details
 
8India's Power Demand Hits 270.8 GW Record, Exposing Grid Bottlenecks Details
 
8India's Power Grid Braces for El Niño Supply Gap Through October Details
 
8India Needs 10-Fold Bus Fleet Expansion by 2047: Sector Outlook Details
 
8Sri Lankan MP Elayathamby Sreenath offers prayers at Sri Venkateswara Swamy Temple in Andhra Pradesh Details
 
8CESC Limited: Acquires 1.4 GWp Renewable Portfolio for Rs 4,859 Crore Details
 
You can also click on Newsclips for more Details

Daily Power Sector Tenders Excel update

Aug 11: 8Daily Excel covering new tenders and all published updates including corrigendum, amendment, addendum, clarification and status revisions, along with technical and financial bid opening, evaluation completion and final award actions including AOC and LOA issuance.
Click on Reports for more Details

More than 55,000 MW was outside the online fleet in CEA’s monitored snapshot - while generation still reached 98.2% of programme

Aug 10: 8CEA counted 55,674 MW unavailable across planned, forced and other outage categories while monitored stations still produced 98.2% of programme. The near-target output shows that the remaining fleet carried the day, but the outage burden narrowed the buffer against another large failure. Details

India has certified 78 green-steel units and advanced specialty-steel incentives - but neither measure yet proves how much cleaner steel is being produced

Aug 10: 8India has certified 78 green-steel units and advanced production-linked incentives for specialty steel, creating formal routes for cleaner and higher-value output. The policy architecture is moving, but the disclosed record still does not quantify how much certified low-emission steel has actually been produced or sold. Details

BCCL put a new 2.0 MTPA washery into operation and monetised another - but profit collapsed nearly 90% as production and offtake weakened

Aug 10: 8BCCL started commercial operation of the 2.0 MTPA Bhojudih washery and monetised the 2.0 MTPA Dugda washery through a long-term operating agreement. Those projects could lift domestic washed-coking-coal supply, but profit after tax fell from Rs. 1,240.19 crore to Rs. 128.28 crore as production, offtake and costs moved against the company. Details

Coal India spent Rs. 19,607 crore and added 100 MW of solar - but coal output fell to 768.19 million tonnes, 168.81 million tonnes below its own target

Aug 10: 8Coal India spent Rs. 19,607 crore and commissioned the 100 MW Patan solar project while expanding into critical minerals and a proposed 1,600 MW thermal venture. The diversification advanced, but coal production slipped to 768.19 million tonnes and missed the company’s 937 million-tonne target by 168.81 million tonnes. Details

PFC’s loan book reached Rs. 5.80 lakh crore and net NPAs fell to 0.15% - but annual sanctions dropped Rs. 75,094 crore as fresh commitments slowed

Aug 10: 8PFC ended 2025–26 with Rs. 5.80 lakh crore of loan assets, Rs. 20,051 crore of standalone profit and a net NPA ratio of 0.15%. Asset quality strengthened, but sanctions fell to Rs. 2.86 lakh crore from Rs. 3.61 lakh crore, making the pace and quality of new commitments the next growth test. Details

Inox Wind’s order book reached about 4.4 GW - but quarterly profit fell 34% as its shift toward equipment sales held income growth to 1%

Aug 10: 8Inox Wind reported an order book of about 4.4 GW in July, including a 500 MW firm group order and a 200 MW NLC award. The pipeline is large, but first-quarter profit fell 34% and management’s equipment-sales pivot has yet to show the promised improvement in later quarters. Details

Premier Energies lifted profit 53% and opened 5.6 GW of module capacity - but the new factory must convert nameplate scale into sustained sales and margin

Aug 10: 8Premier Energies raised quarterly profit by 53% and opened 5.6 GW of module capacity, expanding the manufacturing base behind its order pipeline. The new factory changes the company’s scale immediately, but earnings quality depends on utilisation, cell supply, pricing and sustained conversion of capacity into sales. Details

Hitachi Energy’s orders and revenue surged - while Rs. 1,841.66 crore of QIP money still sat unused

Aug 10: 8Hitachi Energy India reported sharp growth in orders and revenue while retaining Rs. 1,841.66 crore of QIP proceeds as unutilised at quarter end. The balance sheet can fund expansion, but the investment case now depends on converting record demand and idle capital into delivered capacity, cash and margins. Details

Amazon’s proposed Mumbai data-centre campus would demand 473 MW and install hundreds of backup generators - but it still lacks final environmental clearance

Aug 10: 8Amazon Data Services’ proposed Mumbai campus would require 473 MW of power and a large diesel-backup fleet across a multi-building development. The scale makes it a major new load, but the committee recommendation is not final clearance, grid sanction or proof of a contracted cleaner supply. Details

CESC’s 3 GW solar-cell plan won environmental clearance only for Phase I - leaving the second phase and construction approvals outside the gate

Aug 10: 8CESC Green Power’s 3 GW solar-cell proposal has environmental clearance for its first phase at Jewar, not for the entire factory. The approval moves a major manufacturing investment forward, but Phase II, construction permissions and operating execution still sit outside the cleared gate. Details

A Vemagiri bus fault cut about 1,150 MW of Andhra Pradesh load in 14 minutes - after overloaded transformers at another station also tripped

Aug 10: 8A Vemagiri bus fault removed about 1,150 MW of Andhra Pradesh demand for 14 minutes while overloaded transformers at another station also tripped. Supply returned quickly, but the scale of the loss shows how a local fault and stressed parallel equipment can combine into a statewide reliability event. Details

Gujarat’s renewable evacuation network suffered repeated single-path failures, including 800 MW and 540 MW losses - making redundancy the month’s unresolved risk

Aug 10: 8Gujarat’s renewable network recorded repeated single-path events, including losses of about 800 MW and 540 MW, across the month’s grid-event register. Individual protection operations may have worked, but the recurrence shows that several generation pockets still depended on evacuation arrangements that did not survive one credible failure. Details

Two simultaneous line trips cut about 130 MW across six Assam load centres - after another 220 kV route was already shut

Aug 10: 8During an approved shutdown of the BTPS–Rangia-I line, all six affected load centres were being supplied through the Sonabil–Depota and Sonabil–Ghoramari paths. Both lines tripped at 15:04, cutting about 130 MW until the network was restored, and turning a planned outage into a direct redundancy failure. Details

A Champa–Kurukshetra HVDC failure cut about 2,680 MW of transfer and triggered Punjab’s defence scheme - but Punjab’s recorded demand drop was about 252 MW

Aug 10: 8A measuring-card failure blocked two poles carrying about 2,680 MW and triggered Punjab’s feeder defence scheme, while the state’s recorded demand changed by about 252 MW. Protection limited the disturbance, but the gap between transfer loss and demand response shows why the event cannot be described as 2,680 MW of consumer load shedding. Details

Thirty coal plants were critical even with 37 million tonnes on hand - because the fleet held only 60% of its normative stock

Aug 10: 8Thirty plants were at critical stock even though total coal holdings reached 37 million tonnes, because the monitored fleet held only 60% of its normative requirement. The national pile therefore concealed plant-level exposure where location and delivery, not aggregate tonnes, determined security. Details

Contracting news for the day

Aug 10: 8Arunachal's Pathar Camp award carries two prices for the same bid, 19.0% apart Financial-opening proceedings record Techno Power at Rs 98.75 crore and Shyam Steel at Rs 119.57 crore; the BOQ comparative chart records Rs 82.98 crore and Rs 100.48 crore — the same 19.0% gap for both bidders. The award settles on the lower BOQ figure. Three of five bidders never reached price opening, falling on unsigned pages, missing OEM authorisations and EHV-licence gaps, leaving a 21.1% spread between the only two survivors. The portal and committee proceedings also cite two different NIT numbers for one tender ID.

8AVVNL's 110 MW rooftop tender now allocates a multi-lot winner's cheapest circle first, not its biggest Corrigendum No. 2 replaces descending lot quantity with ascending quoted price per unit as the allocation sequence — so a bidder that is L1 across several circles can have its highest-priced win displaced once the 20,000-consumer cap is reached. Turnover is tested at 30% of the total value quoted, making a five-lot bid a balance-sheet decision. Nineteen of the 25 technically admitted bids arrived only after the original deadline.

8Ukwa mine tender sets quantity variation at ±20% in one document and 25% in another The technical specification says "+/- 20%"; the GeM option clause permits 25% at issue and a further 25% post-award — a five-point gap across a four-year contract committing nine LHDs, 36 face drills and nine shotcrete machines. The GeM summary also reads "Arbitration Clause: No" while clause 48 sets out a sole-arbitrator regime with Nagpur jurisdiction. Corrigendum C5 declares itself to supersede all prior buyer-added terms.

8PVVNL's conductor tender qualified one bidder "as trial" while simultaneously coding it rejected The evaluation record shows "Rejected-Technical" alongside the remark "Techno Commercially qualified as trial" for the same participant — a status distinct from the seven bidders marked qualified as regular. What trial standing entitles that bidder to, whether its price bid opens, and how trial converts to regular are nowhere defined. Seven of nine reached the 6 August price opening on regular terms.

8JdVVNL's 110 MW rooftop tender makes MNRE guidelines override its own specification Clarification No. 1 states that where the tender's material specification conflicts with MNRE requirements, MNRE prevails — a compliance baseline that can move during a ten-year O&M term. The same package flips lot allocation from quantity-first to lowest-unit-price-first, swaps meter standard IS 14697 for IS 13779, and holds half the 10% performance security to year five and the balance to year ten.

8JVVNL's 18-lot rooftop tender lets a bidder's own price ladder decide which circles it loses Corrigendum No. 1 allocates successful lots in ascending order of quoted unit price, with a lottery in the Chief Engineer's chamber where price and lot quantity tie. Turnover is now tested against the lots actually quoted rather than the full Rs 627.50 crore estimate. The e-procurement record and the specification also carried different original technical-opening times — 3:00 pm against 5:00 pm — before the seven-day extension overrode both.

8NTPC's Rs 200 crore Kaniha ash contract ended with five identical contracts at 10.58% of base value All five awardees hold contracts of Rs 21.156 crore — a 0.0% spread across L1, L2 and L3 — because ranked bidders were invited to match the L1 price. The panel includes L1 through L4 and, unexplained, L9; L5 to L8 do not appear. Clause C's formula for calculating each bidder's cumulative cap against a five-member panel doesn't reconcile with the identical full-value contracts actually issued. Corrigendum C2 fixed a penalty clause that cross-referenced a nonexistent "Clause 16."

8UPNEDA's 40,000-light tender can extinguish a quarterly AMC payment if district verification doesn't happen in time The amended Clause 8.18 requires live RMS data to be verified by the district project officer each quarter and uploaded to RESIMS; failure causes that quarter's payment to lapse with no later claim — against a 15% retention released at 3% a year over five years. Corrigendum-1 separately disabled equalisation charging, which the original spec had mandated every 30±2 days on an LFP battery. Sixteen of 22 bidders cleared technical evaluation.

8BHEL's Bandhabal ASU tender doubled the power baseline used to load bids, from 400 kW to 800 kW The same amendment nets turbine-generated electricity against consumption before applying NPV loading over a 25-year life — so integration, not gross demand, decides evaluated L1. Qualification was cut in the opposite direction: the reference threshold fell from 1,000 TPD oxygen to 500 TPD, the window widened from 10 to 15 years, and required operating history halved to one year. Five closing-date extensions. A bidder's warning that simultaneous LOX and LIN vaporisation would breach the 10 TPH steam cap drew a request for figures, not a ruling.

8NHPC raised the generator performance coefficients on its Rs 641.11 crore Uri-I tender by 20.6% Both the bid-equalisation rate and the shortfall deduction moved from Rs 21.642 lakh to Rs 26.099 lakh and Rs 86.565 lakh to Rs 104.396 lakh — turbine figures rose 5.0%. Corrigendum No. 4 also replaced the cooling-water and HVAC chapters outright, rebased escalation indices from 2011-12 to 2022-23, added partial acceptance, and introduced a contractor-change route that pays nothing for rejected proposals. Deadlines have moved 32 days.

8JVVNL's 25,000-transformer tender withdrew the bid-security relaxation its own registered vendors previously enjoyed Appendix-A removes the Nigam-registration concession and resets performance security at 5%, with additional security where a bid falls more than 15% under estimate. L1 gets only 20% of the volume under the allocation ladder; 50% can go to firms outside the top four. Prior execution acts as a gate — a supplier under 50% delivered on an earlier order may find its bid unopened. Schedule-X prints a June 1 submission deadline for a tender published in August and closing 1 September.

8GETCO's Rs 94.87 crore HTLS tender pays more to bidders who refuse its advance Amended Clause 86.0 splits payment by financing choice: 90% progressive supply payment without the advance, less with it, and 80% versus 70% on erection RA bills — the advance carrying SBI MCLR interest against a 110% BG. Conductor losses are capitalised at Rs 1,60,000 per kW before reverse bidding starts, so the lowest percentage isn't automatically L1. RoW compensation moved to GETCO; RoW fieldwork stayed with the contractor. Security validity is written as "25 Months (60 Months + 01 Month)."

8CSPDCL's Atal Nagar batch bars Class III contractors from its Rs 1.37 lakh package while admitting them to the Rs 1.76 lakh one Only the 33KV isolator replacement at Mungi substation carries the tighter classification — the gate is voltage and operational risk, not value. All five packages share one deadline, one completion figure recorded simply as "30" with no unit stated, and a stated opening time identical to the closing time.

8TANTRANSCO's Rs 271.79 crore GEC-II substation limits escalation to transformers and reactors, and only on 90% of their cost Everything else — civil works, erection, freight, insurance, switchgear installation — stays firm across 24 months that expressly include rainy seasons, with the transformer adjustment itself capped at ±30%. Delay damages start softer than usual at 0.10% weekly, but can be calculated on the entire contract price where partial works can't be beneficially used. Unresolved level-3 ESHS non-conformity cuts interim certificates 33.3%, then 66.6%, then 100%. Guarantee obligations appear as 36 months in the payment documents, 60 months in the technical requirements and five years for ICTs in the Particular Conditions.

8APEPDCL called a hybrid pre-bid meeting for its Rs 143.32 crore SCADA tender one day before queries close Corrigendum-1 fixes the meeting for 18 August; the RFP keeps 19 August at 17:00 as the query cut-off, leaving roughly a working day to convert answers into formal clarifications on OEM responsibilities, field interfaces and FMS economics. The portal describes the meeting as offline while the corrigendum provides hybrid attendance. The BOQ separately requires five-year FMS charges to be at least 20% of SCADA project cost, with the annual figure identical across all five years.

8UPPTCL's conductor tender demands 10% performance security in the SBD and 5% on GeM — and says the SBD wins ITB 41.2 requires a CPBG of 10% of contract price including GST; the GeM page shows a 5% ePBG for 30 months, while BDS ITB 30 expressly gives the SBD precedence over GeM. The turnover threshold diverges the same way: Rs 224.82 crore in the BDS against Rs 56.20 crore on the portal. Positive IEEMA variation stops once supply runs past schedule even with an extension granted; negative variation continues.

8TPCODL halved its own GCC delay penalty on a Rs 44 crore substation conversion, then extended the liability tail to a decade Tender clause 7.1.7 sets LD at 0.5% weekly on unfinished work capped at 5%; the GCC position is 1% weekly on executed value capped at 10%. In exchange, the CPBG stays alive across a 78-month architecture and a five-year latent-defect warranty starts only after the 60-month guarantee ends. Clause 2.2 states there is no guarantee on quantity of job, with release orders issued only after substation-wise joint survey. Turnover requirement: Rs 100 crore against a Rs 44 crore estimate.

8OPTCL's Rs 102.39 crore Narendrapur cable tender can't agree with itself on how many stages it has The IFB describes a "single stage two part system"; the portal field reads "Stage: Two Stages" — a distinction that changes submission and evaluation mechanics for a bidder committing Rs 1.02 crore of EMD. The document-availability window also differs: the IFB closes it 6 July, the portal 8 July at 12:00, with tender closing at 14:00 the same day. The package bundles 132 kV underground cable with bay extensions at two live substations.

8JVVNL's 37-substation RDSS tender states nine months for completion in one part and 12 in another Part 1 gives one month for survey plus eight for execution; SCC GCC 8.1 and 8.2 give three months for commencement inside a 12-month total — and the contract hierarchy puts Part 3 above Part 1. The second 30% supply payment is conditioned on commissioning "a minimum one cluster," defined by electrification of rural households, inside a package that procures 33/11 kV substations. The technical specification also refers to supervision at substations "in state of Uttar Pradesh."

8RVPN's Dholpur line tender lists a bid amount of Rs 1.00 against a Rs 94.48 crore turnover requirement The portal field is economically meaningless beside a Rs 31.49 crore liquidity threshold and a 50 km single-order 400 kV execution test. Subsidiary, associate and subcontractor credentials don't count, and JV bidding is marked not applicable. OPGW installation runs predominantly live-line, with tower structural analysis and any resulting strengthening at no additional cost to the employer, plus a 99.9% availability target requiring a seven-person certified gang, a jeep and a Tata 407.

8NTPC REL extended its 540 MW Anantapur wind tender a day after the original deadline had passed Corrigendum-2 carries a 5 August timestamp; the original bid receipt closed 4 August, and the applicable deadline now reads 17 August. A WTG manufacturer may use only one qualifying route and, under the association route, back only one bidder — multiple participation can void all affected bids. Land acquisition, ROW, the external EHV line to the ISTS substation and ten years of comprehensive O&M all sit inside contractor scope. A 540 MW quote requires Rs 714.04 crore of average annual turnover.

8MPPMCL's 625 MW storage tender now closes six days after the opening date printed in its own schedule The portal header applies 10 August for bid receipt while the NIT table still shows the tender opening event on 4 August and document procurement closing 30 July — an 11-day extension layered over legacy dates never rewritten. Corrigendum-1 and Addendum #2 have both issued. Bid security runs Rs 2.20 lakh/MW across a BOO structure with VGF support and a reverse auction at the end.

8SJVN's 265 MW Haryana storage tender shows an addendum issued and no corrigenda at the same time Addendum #1 is flagged on the tender page while the portal separately records "No Corrigenda Issued," and the clauses it supplements aren't identified anywhere at NIT level. EMD scales with capacity at Rs 2.40 lakh per MWh rather than sitting as a fixed sum, and the Rs 15 lakh processing fee plus GST applies to each project. Degradation, augmentation, availability guarantees and PBG terms all sit outside the published notice. Details

Briefs - Signals to Watch

Aug 10: 8India’s grid frequency left the prescribed band for 21.1% of the day even as the daily average stayed near 50 Hz
8Eastern grid operators cut day-ahead demand error from 7.53% to 1.04% intraday - but only after the operating day began
8Every interstate schedule will carry a 3.62% transmission-loss adjustment this week - but the national factor says nothing about any single project’s efficiency
8Odisha’s hydro stations reported 18.6646 MU, but duplicated rows prevent the table from proving a larger fleet total
8PXIL’s real-time market touched the Rs. 10,000/MWh ceiling - then recorded no trades across the next five reports
8Grid-India’s next security-constrained schedule starts with low-cost generators - but the dispatch plan becomes real only if those units run in the assigned blocks
8Late SCED payments in the eastern region will now attract daily interest - turning settlement delay into a rising cost for every entity shown as payable
8Two states capped reverse-auction bids at Rs. 10,000/MWh - while Rajasthan’s notices left bidders without a ceiling
8POWERGRID’s proposed Mandsaur licence change has entered formal hearing - but the company cannot use the revised terms unless CERC approves them
8Hexa Climate has finished arguing for connectivity relief over land documents - but the project remains exposed until CERC delivers its reserved order
8Gadag Power’s 190 MW solar project has reached the order stage - but its deadline extension and transmission-charge waiver remain undecided
8ReNew’s 73 MW Solapur project keeps interim protection - while final connectivity relief waits
8A new party and affidavit have widened the Tumkur-II transmission case - but they deliver neither the licence nor the tariff the project ultimately needs
8Lakadia-B seeks to push its transmission deadline to November - but force majeure still needs regulatory acceptance
8Solar developers say inverters should qualify for GST-change compensation - but CERC has not decided whether the equipment fits the claimed tax category
8NTPC REL commissioned six more inverters and moved the project forward - but tariff, tax and deadline claims still determine what the delay will cost
8India has opened accreditation for carbon-market verifiers - but no agency can validate credits until BEE completes the approval process
8PSPCL has taken smart-meter reconnection out of local hands - but its order gives no timeline or count for consumers waiting to be restored
8Punjab’s discom wants another settlement window for defaulting consumers - but the regulator is asking why the existing recovery mechanism was not used first
8Haryana ordered utilities to answer renewable-supply claims on a deadline - but kept deviation-settlement relief outside the interim order
8KEC’s CRISIL ESG score rose by five points - but the filing shows no change yet in borrowing cost, orders or operating performance
8Refex’s promoters plan to move 30.94% of the company within their own group - changing the holding structure without bringing in an outside buyer
8Sarda Metals gained Four Star Export House status - but investors still lack any disclosed export, revenue or incentive benefit
8Nuvoco and Nu Vista lost their current appraisal path because mandatory mapping files were missing - forcing both limestone proposals back before any merits decision
8Svaryu Energy asked to surrender its Category V interstate trading licence
8NLC asked CERC to determine the 2024–29 input price for Barsingsar lignite
8AK Renewables wants financial-close and commissioning deadlines aligned with delayed connectivity Details

Projects and Clearances - Investment Advanced, Permissions Lagged

Aug 10: 8Coal-gasification bidders won flexibility on products and technology - but every project must clear the approval gate before an award can be issued
8Amanthin’s Mumbai data-centre expansion seeks 200 MVA and 123 large generators - but its Rs. 6,670 crore plan remains a conditional recommendation
8Mevasa’s bauxite proposal gained an EAC recommendation - but road strength, dump stability and wildlife safeguards remain conditions on the mine
8Jhamarkotra’s phosphate expansion could not clear appraisal - because two foundational land and survey records remain unresolved
8Star Cement can study a 12 MTPA limestone mine - but the ToR does not permit mining
8Hindalco and Ambuja lead a 13-project industrial agenda worth watching - but every proposal still awaits the committee’s merits decision
8SECI is searching for dependable CO? supplies for green urea and methanol - but the exercise offers no tender, buyer or financial commitment
8TERI says solar heat can produce steam for about Rs. 1.20 a kilogram and pay back quickly - but industry still lacks the mission needed to overcome upfront risk
8Anant Raj’s Sonipat IT park would require 26 MW and 36 MVA of diesel backup - but its proposed solar capacity equals only 3% of sanctioned load
8Radiance’s Gurugram cyber park cut its planned load to 8.947 MW - but still pairs the project with large diesel backup and only 269 kWp of solar Details

Corporate Growth and Finance - Scale Expanded, Execution Risk Remained

Aug 10: 8Vikram Solar shipped more modules and lifted revenue 38% - but EBITDA nearly halved as margin fell to 8%
8Northern Coalfields selected only 545 people for 906 apprentice places - leaving 361 training positions unfilled
8Quality Power’s Rs. 19,455 million order book backs strong Q1 profit - but two capacity projects are still in installation and trial stages
8Reliance’s two Jamnagar battery units represent Rs. 3,162 crore of investment - but no ACC incentive had been claimed
8India counted 52,718 EV charging stations - but the government cannot say how many are fast chargers
8GK Energy crossed Rs. 15,325 million of annual turnover - but its Rs. 541 crore order book still has to convert into commissioned systems
8Batteries generated almost two-thirds of HBL Engineering’s quarterly segment revenue - concentrating growth in one business while electronics supplied the balance
8Bajel won a 765 kV interstate line worth at least Rs. 400 crore - but disclosed only a band and a 33-month delivery clock
8Refex can halve a solar loan exposure under a proposed settlement - but payment and legal withdrawals are still conditions
8L&T won ONGC work on subsea pipelines and four offshore platforms - but the Rs. 5,000–10,000 crore value band hides the exact contract economics
8GR Infraprojects led a Rs. 91.60 crore Varanasi logistics-park bid - but a 45-year concession starts with contract and finance risk
8Bajel plans to nearly double tower capacity even as quarterly revenue fell - betting Rs. 170 crore that margins can recover
8Inox Green’s profit rose 86% and a 4.5 GW wind-service acquisition cleared the tribunal - but the portfolio is not fully owned or consolidated yet
8Ola Electric cut operating losses but reversed a Rs. 57 crore provision without ministry approval - keeping the audit qualification alive
8Panasonic restarted dispatches after its Pithampur fire - but the damage is still unpriced and a battery-waste obligation remains unprovided
8NLC’s group generation rose 25% - but profit before tax increased only 9.76%
8IMP Powers multiplied quarterly revenue but still lost money - while auditors say old receivables and assets may be overstated
8Urja Global’s auditors flagged Rs. 34 crore of unreversed tax credits - alongside Rs. 42 crore of ageing receivables
8Anboto Solar says its supply deadline slipped because the ISTS substation was not ready - but status quo protects the project only until CERC decides the delay claim
8Power Mech proposed up to one million employee options at 10%–25% of market price - but shareholders and regulators still have to approve the plan
8Urja Global’s board opened a route to raise up to $500 million - but shareholders have not approved it and no instrument or price has been fixed Details

Regulation and Access - Relief Was Sought, Decisions Stayed Conditional

Aug 10: 8Load despatch centres seek 85% provisional fee billing - but CERC has not authorised the cash flow
8BALCO faces a Rs. 48 crore damages claim from TANGEDCO - but liability is frozen behind a pending review
8Korba Power seeks Rs. 36.88 crore for ash transport and surcharge - but none of it has been awarded
8GETCO listed 800 possible renewable connections - but warned that planned substations may never arrive
8Government support erased Andaman’s approved revenue gaps on paper - after the regulator found Rs. 1,613 crore across two years
8Haryana discoms want to postpone monthly fuel adjustments and recover them with interest - but the regulator demanded the full backlog first
8Two renewable projects want their connectivity clocks moved because the Koppal-II network may not be ready until 2027 - but neither extension has been granted
8Two discoms say Kreate Energy failed to return banked power and want its trading licence revoked - but an appellate status-quo order has frozen the regulatory hearing
8PSPCL approved a 15% wage rise across PESCO worker categories - but the new rate raises the utility’s outsourced labour bill before efficiency gains are known
8PSPCL can now cancel energy bills and optionally reverse late-payment interest - but larger corrections require progressively higher approval
8Goa–Tamnar wants its transmission deadline extended and force-majeure costs compensated - but the regulator has not accepted either claim
8Osmanabad Solar wants four months of 2022 power bills paid - but CERC has not ruled on who must correct the scheduling record
8IL&FS Tamil Nadu says Section 11 benchmark energy charges remain unpaid - but CERC has only opened the merits hearing
8KSK and southern discoms remain locked over 2013 capacity and transmission charges - but the 13-year-old disputes still have no merits ruling
8NHPC wants consumers to fund a 1997 pay-anomaly correction ordered in 2024 - but CERC has not admitted the cost to tariff
8DNH and Daman & Diu seek legacy gas, capacity and imbalance charges for 2006–12 - but the reopened dispute has no liability finding
8SEIL seeks fixed charges for 150 MW it says was available - but Andhra counterparties have not been ordered to pay
8SEIL wants June–July 2022 invoice deductions repaid with surcharge - but CERC has not decided that Telangana’s withholding was wrongful
8Adani Solar says long-term transmission charges are not its liability - but CERC has not allocated the cost Details

Contracting news for the day

Aug 13: 8NPCIL's riser insulation package lists one set against four pipe sizes and 24 riser positions The bidder must fund detailed engineering, mock-ups, radiation qualification, five installation trials and site training before any payment falls due. ATC clause 13.0 ties 100% payment to final acceptance and completion of training, on a firm price held over 364 days. The GeM summary marks arbitration "No" while ATC clause 24.0 sets a three-arbitrator tribunal.

8NTPC Mining asks developers for indicative tariffs while holding the land lease rate back to the RFP The 50 MWp splits evenly across two mines, but one sits on an overburden dump and the other carries mandatory levelling plus a developer-scope 33 kV line on a shorter schedule. Penalties, payment security, deemed generation and curtailment treatment are all still open to market input. A later limited tender may be confined to those who respond now.

8WAPCOS's Rs 1 crore mandate says no pre-bid meeting will be held; GeM scheduled one with a Teams link The GeM field records 10:00 against a description reading 10:30-12:30, validity reads 90 days in one document and 120 in the other, and MSE relaxation is "No" in one and 50% in the other. Basic turnover eligibility starts at Rs 50 lakh while scored turnover starts at Rs 50 crore. Arbitration is expressly waived even though the 1996 Act appears in the same document's regulatory framework.

8AEGCL's Rs 6.72 lakh Narengi consultancy buys PLS CADD tower spotting and states no completion period Two lump-sum items cover bay feasibility and full route survey with profile drawings, with forest proposal and tree enumeration expressly carved out. Corridor width, accuracy tolerances, route alternatives and permitted iterations are undefined. The whole cycle from launch to close runs eight days.

8Tata Power's one-year final-checking agreement for a 765 kV line gives bidders 10 days and no quantities Tower counts, line length, inspection formats, acceptance authority, manpower and reporting protocol are all absent from the notice. So are EMD, PBG, payment cycle, LD and liability caps. For a year-long framework, minimum workload and call-off frequency are the terms that matter, and neither is stated.

8TGTRANSCO's Rs 60.71 crore package keeps negative escalation running after positive escalation stops Delay attributable to the contractor removes upward price protection while leaving downward adjustment enforceable, on top of milestone and post-completion penalties. Section 1.2 deems unlisted but necessary components into bidder supply, closing the variation route. A bid 20% below estimate draws additional security of 10% of the estimated cost by the document's own worked example.

8KPTCL's Rs 108.02 crore Ayyanahalli package deleted its 25% consortium floor after a pre-bid nobody attended The line qualification can now sit entirely with one partner, with a three-year electrical-works test replacing it for the other. The proceedings record nil bidder representatives; the queries that produced the change arrived by email. Underlying kilometre thresholds are unchanged.

8APGENCO reserves the right to amend its metering cubicle tender after its own submission window shuts Bids close at 14:00, technical opening is 15:00, and modifications are permitted up to 15:00. Validity reads 180 days in the NIT and 120 in the attached general conditions, while the covering enquiry gives a third set of times. Manufacturer-site QA inspection is marked "Not Required", moving conformity onto supplier certificates.

8NHPC's Sawalkot Lot-1 added Rs 287.91 crore, deleted a qualification route and moved its deadline eleven times The estimate reset from Rs 5,129.03 crore to Rs 5,416.94 crore carried turnover, working capital and bid capacity up with it, while the quantity-based dam alternative disappeared, leaving only an 80 m concrete dam. Project capacity was corrected from 1856 MW to 1800 MW without explanation. No reason is recorded against any of the 161 days of extensions.

8MPPGCL's 30 MWac solar tender moved its query-response date three times, ending seven days before bids close Responses now land after the deadline they were originally meant to precede, leaving one week to absorb them across engineering, vendor quotes, generation modelling and O&M pricing. Evaluation runs on Rs/kWh combining capex, discounted five-year O&M and accepted NEEGG. Omitted-but-necessary equipment is deemed included and prices stay firm.

8NHPC's Kamala amendment moved HM qualification into execution, then needed an errata to fix the clause it cited The same corrigendum cut muck disposal from four zones to two, removing both sites nearest the dam and leaving two shared 50/50 with the adjacent lot. Adverse climate moved from employer risk "Nil" to EOT, and earthquake gained express compensation. Grid power is tentative at two years out, with captive generation and compulsory later uptake both on the contractor.

8THDC's Kalai-II package moved 216 days and rewrote shotcrete from "no extra payment" to Rs 180 per kg Eight extensions ran alongside two substantive amendments and a notice refusing further queries — followed by another date revision. The 31.5-month clock now starts after a 30-day mobilisation period rather than on the seventh day from LOA. The road tunnel is carved out of the milestone-damage waiver every other milestone enjoys.

8AEGCL's Sonapur extension notice pushes bids to 2026 and schedules the opening for 2023 The same package records an NIT date in the pre-bid minutes that post-dates both the NIT and portal publication. A pre-bid meeting materialised where the portal fields read "NA", drawing nine firms. Prices stay fixed for 24 months and the request for conductor and cable escalation was refused.

8MPMKVVCL narrowed its type-test waiver to one rating and readmitted a disqualified bidder after opening The concession originally covered a new bidder lacking reports for any rating; it now covers only the 10 MVA unit. EMD is Rs 1 lakh against post-award security of 1% plus 9% on a 66-month instrument. A bidder rejected as a medium enterprise returned on the MSME notification preserving previous-category benefits for three years.

8NHPC's Salal award is 8.7% below estimate, or 1.5% above it, depending which estimate applies The benchmark rose 11.1% late in the cycle, taking experience, turnover, working capital and bid capacity up with it after an earlier corrigendum had widened technical eligibility. One of three bidders failed qualification, leaving a two-bid contest 3.4% apart. The NIT provides for reverse auction; the comparative statement shows only two values.

8WBSEDCL cut its retesting charge 90% and drew 188 bids in which L2 sits 44.0% above L1 EMD fell 30.0% and 16.7% across categories at pre-bid, while the charge per repeat inspection went from Rs 50,000 to Rs 5,000. Of 188 bids, 148 cleared technically, many only partially by capacity or transformer type. A bidder removed from the restricted-opening table after a corrigendum resurfaced in the price ranking at L22. Details

Download tenders and news clips

Aug 13:  For reference purposes the website carries here the following tenders:
 8Tender for work of annual/routine testing of various equipments installed at 400 kV GIS S/S Details
 8Tender for civil works for construction of 01 No. 63 MVA transformer plinth and related 132/33 kV bay Details
 8Tender for civil maintenance and upkeeping work at various volts transmission sub stations Details
 8Tender for diversion of submerged tower 400 kV line Details
 8Tender for supply of cross patrolling of transmission lines Details
 8Tender for supply of LT three phase channel cross arm and angle cross arm Details
 8Tender for procurement of transformer structure materials double pole Details
 8Tender for procurement LT GI pins Details
 8Tender for providing pile foundation for various tower Details
 8Tender for construction of control room foundations, cable trench Details
 8Tender for procurement of spares for SAM make sludge disposal pump model Details
 8Tender for construction work for new proposed 33/11 kV line Details
 8Tender for construction of new borewell at 132 kV GSS Details
 8Tender for construction of civil foundation and other misc civil works in yard for 20/25 MVA Tr At 132 kV GSS Details
 8Tender for construction of civil foundation and other misc civil works in yard Details
 8Tender for levelling and gravelling work of 132 kV switch yard at 132 kV GSS Details
 8Tender for procurement of 220V-600AH lead acid tubular type battery sets Details
 8Tender for procurement of non ferric alum Details
 8Tender for repairing/retrofitting/renovation of raw water pump house Details
 8Tender for supply of CPVC pipe & fittings Details
 8Tender for supply and application of epoxy glass flake coating with UV resistance PU top coat on various external surfaces Details
 8Tender for work of preventive maintenance of various 220 kV switchyard Details
 8Tender for supply of GI coated heavy duty MS grill Details
 8Tender for EPC package for ash handling system package Details
 8Tender for work of RCC revetment/protection wall work at various Details
 8Tender for procurement of furnace oil Details
 8Tender for construction of 132 kV sub-station Details
 8Tender for extension of control room construction of 02 No. 66kV bays Details
 8Tender for supply of wireless LCM kit for 220kV and 66kV class switchyard Details
 8Tender for supply of C&S electric make ACB & panel spares Details
 8Tender for procurement 22 kV, 200A AB switch Details
 8Tender for supply of LT three phase X arm channel Details
 8Tender for supply of T.C.fuse wire 12,14,16 SWG Details
 8Tender for supply of transformer structure materials Details
 8Tender for construction of new 11 kV, LT lines and 11/0.4 kV DTR Details
 8Tender for construction and shifting of existing 33kV/11kV/LT OH/UG lines Details
 8Tender for Re-construction of existing 33 kV UG line Details
 8Tender for construction of new 33 kV line from 33/11 kV DSS Details
 8Design, fabrication, supply, installation, testing, commissioning of on grid solar ground mounted project with net meter and remote monitoring system, capacity of 46 kW Details
 8Design, fabrication, supply, installation, testing, commissioning of on grid solar ground mounted project with net meter and remote monitoring system, capacity of 83 kW Details
 8Design, fabrication, supply, installation, testing, commissioning with RMS of total 156 kW grid connected solar PV power plant Details
 8Tender for supply and erection of 50TR capacity air cooled DX condensing unit for 400kV switchyard Details
 8Tender for supply, retrofit commissioning of 90 kW and above LT air contactor modules (DK21) with LT vacuum contactors Details
 8Tender for supply and replacement of LTG and HTG tubes Details
 8Tender for empanelment of contractors to award a rate contract award RCA for DTR renovation work of 63 KVA, 100 KVA, 200 KVA and 315 KVA substation Details
 8Tender for empanelment of contractors to award a rate contract award RCA for work for aug/conversion of LT line 3x95 Sqmm and 3 X 150sq.mm.XLPE cable Details
 8Tender for augmentation of 33 kV line on H-Beam using ACSR Dog conductor Details
 8Tender for empanelment of contractors to award a rate contract award RCA for work of aug conversion LT cable Details
 8Tender for work of aug of existing 11 kV line to ACSR Dog/Raccoon with 13Mtr H beam/PCC pole Details
 8Tender for procurement of lighting items for power houses Details
 8Tender for annual maintenance work of railway siding for power house Details
 8Tender for supply and running out of ballast for railway maintenance work Details
 8Tender for construction of new hydrogen shed for 1x210 MW unit Details
 8Tender for work contract of transportation of the ash from ash dyke II Details
 8Tender for construction of precast RCC cover and stone Details
 8Tender for procurement of spares of electromagnetic flow meter and SWAS spares installed Details
 8Tender for manufacture, testing, supply, delivery and operational training/ commissioning of three phase transformer turns ratio test sets Details
 8Tender for manufacturing, testing, supply and delivery of 50 Nos. 220V/100AH and 30 Nos.24V/100AH DC distribution boards and 80 Nos. 415V, 11 circuit, AC distribution boards Details
 8Tender for work related to construction and electrification of line and shifting of lines and poles Details
 8Tender for replacement of defective meters Details
 8Tender for maintenance and repair of 11 kV HT/LT line Details
 8Tender for replacement of defective meters Details
 8Tender for work of installation of one (01) No. 12.5 MVA power transformer Details
 8Tender for erection, testing & commissioning work of 66kV equipments, structures Details
 8Tender for erection, testing & commissioning work of 66kV equipments, structures, control wiring Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Karamsad Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Borsad Details
 8Tender for procurement of MS pipes 550 NB for replacement Details
 8Tender for thorough interior civil renovation and allied work Details
 8Tender for work of atactic polypropylene APP treatment to arrest leakages Details
 8Tender for supply loading at factory and transportation of LT distribution box Details
 8Tender for supply and delivery of different local materials Details
 8Tender for construction of 1 No 33 kV bay, 2 Nos. 11 kV feeder bay and providing transformer plinth Details
 8Tender for laying of 11kV 3x300sq.mm XLPE UG cable Details
 8Tender for laying of 11kV 3x300sq.mm XLPE UG cable for erection of new 11 kV feeder Details
 8Tender for supply of stay set complete Details
 8Tender for work of providing & fixing of 33kV numerical backup relay with non-directional three phase over current (3 O/C) & earth fault (E/F) protection Details
 8Tender for AMC for CTR make nitrogen injection fire protection system (NIFPS) for ICTs & transformer Details
 8Tender for annual maintenance contract (AMC) for the work of attending emergency breakdown works & planned maintenance works in various 220/132 kV EHV S/Stn Bhandara Details
 8Tender for annual maintenance contract (AMC) for the work of attending emergency breakdown works & planned maintenance works in various 220/132 kV EHV S/Stn Details
 8Tender for biennial maintenance contract of replacement of installed smoothing reactor by spare smoothing reactor Details
 8Tender for supply of pressure relay of converter transformer Details
 8Tender for annual maintenance contract (AMC) for the work of attending emergency breakdown work & planned maintenance works in various 220/132kV EHV S/S Details
 8Tender for refilling, servicing & maintenance, supply of spares for fire extinguishers at various substations Details
 8Tender for annual maintenance contract (AMC) for work of underground cables at various Details
 8Tender for attending emergency breakdown work & annual routine maintenance of 220/132/110kV various EHV lines Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Mehsana Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Patan Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Himatnagar Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Chhatral Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Dhansura Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Jamla Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Vijapur Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Agiyol Details
 8Tender for supply of pre engineering shed Details
 8Design, engineering, manufacture, supply, erection, testing & commissioning of 6.6 kV indoor metalClad draw-outtype VCB panels Details
 8Tender for supply, installation commissioning, & testing of soft starter with major/minor modification in existing panels for various motors Details
 8Tender for supply of assorted size of MS grill for repairing of platform of ash slurry line Details
 8Tender for supply of mill discharge first piece after MPO for coal mill Details
 8Tender for purchase of standard toolkit bag Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8Hinduja Renewables Bets On BESS, Pumped Storage To Make Renewables More Dispatchable Details
 
8Maharashtra Floats EOI for 170 MW Floating Solar & BESS Project Details
 
8NVVN Invites EOI for 263 MW Solar Open Access Power Details
 
8ACME Solar Refinances Rs 21.5 Billion Debt for 450 MW Portfolio Details
 
8MNRE Approves INR 258.83 Crore HRD Programme To Strengthen India’s Renewable Energy Workforce Details
 
8Rooftop solar installations soar in India Details
 
8CIL, ArcelorMittal sign MoU to explore syn-gas usage from a coal gasification plant at Paradip Details
 
8DNHDDPCL Invites Bids for 5 MW Rooftop Solar Program Details
 
8India’s small steelmakers could save money and cut emissions with switch to renewable power Details
 
8How India can get its BESS projects right Details
 
8India on e-wheels: There are hardly any electric cars on Srinagar’s roads; here is why Details
 
8H2 Innovation eyes collaboration with universities, government to develop green hydrogen in India Details
 
8Power Ministry Urges States: Accelerate Smart Meter Rollout Details
 
8Dr Jitendra shares in LS India’s Thorium driven indigenous Nuclear strategy Details
 
8Siemens Energy India to attend Motilal Oswal investor meet Details
 
8Gentari Explores Sale of India EV Charging Network With 3,000 Chargers Details
 
8Data Centre Power Boom: Why renewable developers are demanding a Rs 3,000 crore relief package Details
 
8Stocks to Watch: Solar Industries, LG, Tata Motors PV and 7 Other Stocks Announcing Q1 Results Today Details
 
8SJVN Commissions 75 MW Jamui Solar Power Project in Bihar, Expands Renewable Energy Portfolio Details
 
8India’s Solar Surge Highlights 50 GW Power Gap Challenge Details
 
8India's Planned Coal Mining Capacity Hits 638 MTPA Details
 
83 Best-Performing Mutual Funds With High Holdings in NTPC, Adani Power & Tata Power in 2026 Details
 
8Demand aggregation of renewable electricity can cut power costs for India’s secondary steel MSME clusters by 34 percent Details
 
8Bajel Projects Bags Rs 400 Crore Order From Power Grid for 765kV Transmission Line Details
 
8Power sector stocks today, August 12: TD Power Systems jumps 15.87%, Gujarat Industries up 7.40%, Diamond Power rises 4.36% Details
 
8India’s solar power cuts coal use in the day, but evening demand keeps fossil fuel running Details
 
8El Niño drives India's July power demand to a record high: Crisil report Details
 
8India nearly doubles proposed coal mine capacity as global pipeline expands: Report Details
 
8CEA Proposes New 2026 Grid Connectivity Technical Standards For Power Sector Entities Details
 
8How the Indian Railways moves closer to becoming net-zero carbon emitter by 2030 Details
 
You can also click on Newsclips for more Details

RDSS puts Rs 15,234 crore into grid digitalisation, but training and system use lag the hardware

Aug 12: 8SCADA, IT/OT and smart-distribution work now reaches 28 states and 45 utilities, alongside 19.79 crore sanctioned consumer meters.
Only Rs 23.36 crore of a Rs 100.9 crore training allocation had been used by July, leaving operational capability as the counterweight.
Details

Delhi lifts the 10% fuel-cost cap for June bills, but the exception does not settle every discom claim

Aug 12: 8BRPL, BYPL and TPDDL may recover total FPPAS of 17.94%, 17.43% and 18.50% respectively for June 2026.
The order is a one-month regulatory relaxation; it does not remove the normal ceiling or convert unallowed claims into approved revenue.
Details

Barh Stage I’s cost has risen above Rs 21,312 crore, but CERC still wants the escalation reconciled

Aug 12: 8The 1,980 MW station’s tariff case remains open while NTPC supplies package-level escalation and audited cost reconciliation.
Beneficiaries can face fixed-charge consequences only after the regulator decides which expenditure is prudent and attributable.
Details

Coal plans 1,319 million tonnes of first-mile capacity, but output slipped before the logistics build-out

Aug 12: 8The government plans 139 first-mile projects by FY30 and eight railway schemes, within a logistics plan covering 33 critical rail projects.
Domestic production and dispatch both fell provisionally in FY26, so planned handling capacity has not yet become higher delivered volume.
Details

Adani Jharkhand’s Bangladesh exports rose to 9,131 MU, but the power remains outside domestic allocation

Aug 12: 8The dedicated plant’s annual supply to Bangladesh increased from 155.55 MU in FY23 to 9,131 MU in FY26.
India also exported to Nepal, Bhutan and Myanmar, but APJL’s exclusive contract is distinct from domestic central-station allocation.
Details

Andhra Pradesh has installed 30.82 lakh RDSS consumer meters, but network grants still trail project scale

Aug 12: 8The state has Rs 10,391 crore of loss-reduction work and Rs 4,112.43 crore of smart metering sanctioned under RDSS.
Consumer-meter installation is substantial, while transformer meters, disaster-resilient works and grant release remain incomplete.
Details

India targets 100 million tonnes of coal gasification, but only 8 million tonnes is operating

Aug 12: 8The government counts 22.6 million tonnes a year as operating or under implementation and expects a new Rs 37,500 crore scheme to support about 75 million tonnes more.
Eight projects have been approved under the earlier Rs 8,500 crore scheme, but only Rs 235.52 crore had been disbursed and commissioning remains the decisive test.
Details

Power-sector coal imports fell 71.5%, but domestic substitution is only part of the explanation

Aug 12: 8Imports for blending at domestic coal-based plants fell from 23.9 million tonnes in FY24 to 6.8 million tonnes in FY26.
Coal India also held 122.46 million tonnes in March, yet imported-coal plants and technically necessary blending remain outside a simple substitution claim.
Details

India met a 270.8 GW peak, but the next 18.2 GW will test storage and local grids

Aug 12: 8National supply met the May 2026 peak in full, while the official FY27 forecast rises to 289 GW.
Thermal generation still supplied 68.3% to 72.7% from April to June, and the remaining gaps were attributed mainly to state-network constraints.
Details

Tripura blocks most of TSECL’s past-gap recovery to avoid a tariff shock - the shortfall remains

Aug 12: 8The regulator approved a Rs 479.24 crore revenue gap but allowed only Rs 117.77 crore against the FY27 tariff after calculating that full recovery would require a 42.82% average increase.
It paired partial recovery with smart-meter consent, billing-resolution and grievance directions, protecting consumers now while retaining future financial obligations.
Details

CEA’s unbuilt hydro list shows approvals stranded behind forest and environmental clearances - the paperwork has not become construction

Aug 12: 8Projects across conventional hydro and pumped storage remain untaken up even after appraisal, with some concurrences or environmental approvals already expired.
The clearance-pending category alone includes 14,649 MW in the CEA table, showing how a project pipeline can remain large without becoming executable capacity.
Details

SJVN’s 1,200 MW firm-renewable and 600 MW wind tariffs await orders - the larger sale agreement is unsigned

Aug 12: 8One case covers 1,200 MW of firm dispatchable renewable supply; the other covers 600 MW of inter-state wind projects selected through separate bidding.
For the firm and dispatchable procurement, HPSEB has sought state approval for the contracted power but had not executed its power-sale agreement at the hearing.
Details

Chhattisgarh’s 500 MWh battery tender reaches tariff hearings with Rs 90 crore support - the contract remains unsigned

Aug 12: 8The state distributor’s petition says the project must be commissioned within 18 months of the storage-purchase agreement and that land and connectivity will be provided.
Public comments are due before the September hearing, so the discovered tariff and contractual allocation still require regulatory adoption.
Details

Odisha sought Rs 6,284 crore of cyclone-resilient distribution work - but private ownership leaves its DISCOMs outside RDSS funding

Aug 12: 8The Centre says Odisha’s utilities are ineligible because RDSS financial assistance is limited to state-owned distributors and power departments.
It also says no formal Rs 10,000 crore special power-package proposal was submitted after Cyclone Yaas, separating the state’s actual RDSS request from the larger claimed package.
Details

Uttar Pradesh sanctions Rs 40,738 crore for RDSS networks and meters - consumer complaints still lack a common remedy

Aug 12: 8The Centre says funding is linked to physical and financial progress and vendor checks are built into standard bidding documents.
The monitoring chain reaches from state committees to PFC, REC and the Union power secretary, yet billing redress and meter mode remain with utilities and state regulators.
Details

BRIEFS - VERIFIED DEVELOPMENTS WITH LIMITED DEPTH

Aug 12: 8Uttar Pradesh moves its draft Grid Code hearing by one day - objections still close on the earlier timetable
8Gas stations flag a low-frequency threshold mismatch - compensation remains under regulatory review
8Secure meter-data software slows regional accounting - manual handling is still filling the processing gap
8Genus meter decryption produces conversion defects - corrected files are still awaited
8DSM defaults trigger letter-of-credit scrutiny - security compliance has not cured the pool’s unpaid balance
8Unreturned reconciliation statements are being deemed accepted - administrative closure does not create fresh cash
8NP Kunta’s STATCOM needs an SMPS upgrade - reliability work requires a planned equipment shutdown
8Hyderabad substation’s automation migration needs 400 kV outages - modernisation temporarily narrows network availability
8Talcher - Kolar HVDC Pole 1 seeks an eight-hour shutdown - refurbishment inspection still awaits outage clearance
8India’s demand forecast error moved across 7 - 9 August - three daily readings do not establish model performance
8Intraday auction reports expose bids, clearing and schedules block by block - the latest sheet is a market snapshot
8WCL still carries compassionate-appointment applications from earlier years - the source confirms backlog, not a clean total
8Odisha’s closed coal mines face an unfinished reclamation question - completion evidence is not established
8Fatehgarh - Bhadla lenders may take security over the transmission asset - a licence transfer still needs prior approval
8Tadas Wind challenges where DSM charges are computed - the interconnection point could change the bill
8SGPL presses a Haryana energy-charge claim - the hearing record does not award the money
8Osmanabad Solar seeks Rs 3.42 crore in DSM dues - the hearing was deferred before the merits were reached
8TPTCL’s withheld-dues dispute returns to jurisdiction - the Commission wants arguments before deciding the claim
8Teesta Low Dam IV’s tariff case reaches the order stage - additional capital claims remain under scrutiny
8MEL’s transmission-licence process draws a compliance warning - proposed approval is not yet unconditional
8Solarcraft seeks more time after bay-sharing delays - missing guidelines do not automatically extend connectivity
8Kreate’s banking claim against SPTPL meets a denial of monetary liability - updated claims still need adjudication
8UGVCL’s accident register records fatal network incidents - responsibility remains case-specific
8UGVCL tracks complaints received, resolved and pending - the extracted register does not yield a reliable aggregate
8UGVCL records transformer failures and restoration complaints - a verified failure-rate figure is missing
8UGVCL’s reliability register contains outage indices - the source slice cannot support a performance ranking
8Faulty-meter replacement remains in UGVCL’s operating records - the backlog needs a clean count
8UGVCL reports no standards-of-performance compensation in the selected table - nil claims require an audit trail
8UGVCL records unauthorised-use and theft enforcement - mixed source rows prevent a verified total
8Reserve-shutdown fuel-oil compensation needs a calculation rule - eligibility alone does not fix the quantity
8Faulty special-energy meters remain unreplaced after earlier meetings - delay keeps commercial disputes alive
8Radhanesda’s meter failure produced a Rs 17.83 lakh DSM revision claim - the account still needs correction
8RDSS funds workforce training for digital distribution - utilisation must match the technology rollout
8Grid-security readings were mostly compliant at Agra but weaker at Ajmer - one report cannot grade the corridor
8Western-region outages and line states changed on 10 August - the operating list is not an adequacy forecast
8The Centre retains 15% of central-station power as unallocated - states compete within the remaining allocation rules
8Chhattisgarh’s mining funds must favour high-priority services - allocation rules do not prove local delivery
8NLC’s TPS-I Expansion true-up accepts an 8.5% auxiliary-consumption norm - the wider tariff still rests on reconciled costs
8Vindhyachal Stage I seeks tariff and life-extension capital - the rules may prevent double recovery
8NLC TPS-II’s additional-capital claim contains a cash-basis mismatch - reconciliation must precede the order Details

POLICY AND SYSTEM PLANNING - RELIEF, INVESTMENT AND CAPACITY CLAIMS MEET THEIR IMPLEMENTATION LIMITS

Aug 12: 8NTPC wants station-transformer loads explicitly counted at Vindhyachal and Korba - only export apportionment would change under its proposal
8Legacy and current power-pool deficits are still holding back disbursement - collections received do not eliminate the unpaid tail
8Municipal bonds raise Rs 6,540.44 crore across 23 cities - green issuance does not prove project delivery
8NTPC Lara has settled rehabilitation claims for most affected families - jobs remain conditional on vacancies and suitability
8Ashoknagar’s petroleum lease has been extended twice - commercial oil and gas production still has not begun
8Electrical installations may use five-year inspection or self-certification cycles - digital reporting must keep the option auditable
8Public EV-charging use rises 39% in FY26 - four states dominate the national total
8Telangana’s station-wise generation moved through July - the monthly sheet reveals unit performance but not the cause of every change Details

REGULATION AND DISPUTES - PETITIONS SEEK MONEY OR RELIEF THAT ORDERS HAVE NOT YET AWARDED

Aug 12: 8Andaman solar and storage operators seek must-run compensation - deemed generation still needs a contractual basis
8ReNew seeks protection against a bank-guarantee call - the dispute has not erased the underlying obligation
8Sarda seeks tax and open-access reimbursement for 100 MW - contract allocation will decide who pays
8NTPC Renewable and SECI dispute a scheduled-completion extension - delay relief depends on the cause and notice record
8APPCPL’s banking claim meets SPTPL’s insolvency moratorium - recovery rights now collide with bankruptcy protection
8SEIL challenges coal-freight deductions - the dispute turns on whether transport was recoverable or already priced in
8Tamil Nadu’s Ombudsman protects the existing tariff for qualifying small extensions - separate construction can still trigger Tariff VI Details

STORAGE AND HYDRO - ANNOUNCED CAPACITY STILL WAITS FOR AWARDS, CLEARANCES AND OPERATING EVIDENCE

Aug 12: 8Assam is included in plans for 200 MWh of battery storage - but no state capacity has yet been allocated
8Nathpa Jhakri seeks recovery for hydrology shortfall - the case turns on evidence that water, not operation, caused the loss
8Kynshi and other hydro DPRs return for revision - redesign may improve viability but delays appraisal Details

DISTRIBUTION AND CONSUMERS - DIGITAL INVESTMENT EXPANDS FASTER THAN PROOF OF SERVICE IMPROVEMENT

Aug 12: 8India Energy Stack pilots begin in five utility markets - the national power-data architecture is still unproved
8RDSS pushes distribution utilities deeper into digital operations - installation counts still do not prove better service
8Private discoms report longer supply and lower losses than state utilities - but averages conceal company gaps Details

COMPANIES AND FINANCE - GROWTH VISIBILITY MEETS HYDROLOGY, CREDIT AND ACCOUNTING RISK

Aug 12: 8Amara Raja’s new-energy sales grow by more than 50% - but exports and factory execution pull in opposite directions
8Jagdambey Hydro retains fixed-tariff visibility - weak generation and one buyer still constrain the credit
8PFC and REC loans survive TANGEDCO’s restructuring - Rs 12,822 crore of annual interest shows the continuing burden Details

COAL AND TRANSITION - LOWER IMPORTS AND NEW LOGISTICS MEET OUTPUT, FUEL AND CONVERSION CONSTRAINTS

Aug 12: 8JP Nigrie seeks scheduling recognition after a coal-supply change - fuel availability must still support the declared output
8New Colliery Control rules replace the 2004 framework’s Rule 9 - compliance changes now depend on the substituted text
8India has auctioned 124 commercial coal blocks and attracted 44 first-time bidders - allocation totals still outrun producing mines
8FY26 coal output and dispatch fall - logistics additions have not prevented a weaker annual result Details

MARKETS AND SETTLEMENT - ACCOUNT CORRECTIONS EXPOSE WHO CARRIES DEVIATION AND PAYMENT RISK

Aug 12: 8Gujarat says schedule-allocation errors distorted weekly DSM accounts - corrected data could redistribute charges between entities
8Avaada’s PPA-and-merchant portfolio needs one DSM contract rate - the wrong method can shift deviation charges between sales routes
8Fuel-quality variation is being tested against partial-outage DSM treatment - one cause should not be labelled as another
8Western-region DSM defaults are delaying pool payments - unpaid participants shift the cash burden to compliant members
8Maharashtra’s legacy DSM deficit remains unpaid - old shortfalls are still reducing current disbursement capacity
8Rajasthan revises merit order after a central-station tariff change - cheaper dispatch depends on using the new cost ranking
8RGPPL’s Rs 18.64 crore legacy DSM amount is still awaiting settlement - recognition has not produced payment
8Renewable DSM calculations remain subject to interim High Court orders - final settlement still depends on the litigation
8June’s national SCED pool has paid generators under the monthly statement - heat-rate degradation compensation remains separate Details

GRID AND TRANSMISSION - EXPANSION PLANS CONFRONT AGEING ASSETS, OUTAGES AND UNFINISHED PROTECTION

Aug 12: 8Northern planners propose 23 optical terminals and an STM-64 data corridor - but allocation still starts a 12-month delivery clock
8Powergrid cuts planned VoIP control centres from 82 to 73 - while Ladakh and Chandigarh remain outside the approved scope
8Fibrehome support expires in October as replacement lags - RRVPNL wants Powergrid to take over delivery
8Repeated switching is stressing Maheshwaram’s 765 kV GIS - a flashover shows the wear is no longer theoretical
8Outage approvals delay tests on 53 ageing transmission lines - raising the failure risk they are meant to expose
8Grid-India escalates the Jeypore - Gazuwaka outage - east - south transfers remain dependent on alternative paths without a restoration date
8Kudankulam’s protection scheme delivered less load relief than intended - Nandikotkur stayed connected through a second line
8Kaiga’s Guttur circuits have been out since May - operators warn the remaining evacuation path could overload
8Odisha’s section of the Jagdishpur-Haldia gas pipeline is complete - Cuttack connectivity now depends on use, not construction
8Avaada’s connectivity-relaxation case is reserved for order - the requested network exception is not yet granted
8Gorbea Solar seeks compensation for delayed grid access - but generation loss remains a claim, not an awarded amount
8VEH Saur wants 33 MW more generation within existing connectivity - CERC first wants evidence that the projects are ready
8Kanjhawala’s 11 kV bus outage contributed to a one-hour consumer interruption - restoration is still an operating issue Details

Contracting news for the day

Aug 12: 8KSEB's Rs 65.87 lakh 110 kV upgrade deleted its 5 km experience threshold and took a bid 9.91% below estimate Terms and conditions XVIII required 110 kV work "for at least 5km length of line completed in last 7years"; corrigendum-3 removed the length and applied the change to all clauses stating experience. Three bidders were admitted — L1 Rs 59,34,453.02, L2 16.4% above, L3 26.5% above and rejected on rate. Special condition 18 sets defects liability at 60 months while clauses 1.9, 1.18 and the payment language repeat 36. 

8SECI's 45.6 MW Ramagiri wind package issued Corrigendum-1 nine minutes after queries closed and four hours before the pre-bid meeting Queries shut at 10:00 RTZ on 27 July, the corrigendum is timestamped 10:09, the pre-bid meeting sat at 14:30, and the amendment wording appears nowhere in the record. EMD is Rs 8.4368 crore for domestic and international bidders alike, against a Rs 25,000 processing fee. The tendering pattern reads "Single Stage Two Envelope followed by e-ReverseAuction" while the portal's evaluation-mechanism field reads "Not Applicable". PBG, bid validity, LD and maintenance duration sit outside the notice.

8RECPDCL's ERES-47 765 kV corridor turns a Rs 55.32 crore bid bond into a Rs 138.30 crore guarantee within ten days of LoI A 150% step-up lands on the winner the moment tariff competition ends. Qualification runs Rs 2,766 crore aggregate capex at Rs 553.20 crore per project and Rs 1,106.40 crore net worth. Clause 2.5.7 puts site, geology, transport and grid diligence on the bidder with no relief after deadline, while BSPTCL's Nawada–Guraru works and space at Jeerat stay outside TSP control. Assets, land, ROW and clearances transfer at zero cost 35 years after COD.

8RECPDCL's Solapur/Paranda GIS RFP moved its bid date 34 days and left the rest of Clause 2.7.2 behind Submission goes from 7 July to 10 August, stranding technical opening, qualification, initial offers, reverse auction, LoI and SPV transfer at their original July–August dates. CPG is Rs 30 crore, net worth Rs 250 crore, aggregate capex Rs 600 crore at Rs 120 crore per project. Three LILOs on HPC conductor and a Quad Moose link to Pune West carry a fallback obliging the TSP to buy adjacent land if utility space runs short. LD is 3.33% of monthly charges per day for 60 days then 5%, against a 24-month COD and 98% availability.

8OPTCL's Palaspanga–Barbil package states its estimate as Rs 3.15 crore in the narrative and Rs 315.27 crore in Table-A The smaller figure is exactly one-hundredth of the portal value and identical to the EMD. Table-A items 12–16 run a day behind the portal, while the IFB puts soft copies at 11 August, hard copies at 11 August 11:01 and EMD at 10 August 11:00. Lot-I and Lot-II are labelled separately but "shall be treated as a single contract" — two GIS upgrades plus 1.2 Rkm cable and 69.2 Rkm of 220 kV line. Both inside 24 months from LoA, with e-reverse auction reserved under ITB clause 29.

8NSPCL's Durgapur coal-mill R&M restored 24 mandatory pump assemblies eight days before closing, having cut them to three Amendment No. 2 made the reduction; Amendment No. 4, issued 10 August against an 18 August deadline, restored the original BOQ figure. Amendment No. 3 fixed instrumentation at one instrument for OLCS and two for CLCS and protection. Errata No. 01 corrected the tender ID to 2026_NSPCL_273894_1. The deadline moved 102 days across sixteen corrigenda while the technical baseline was still changing, with eight pulverisers to be replaced inside existing space without disturbing boiler performance.

8PSPCL's Ferozepur RDSS package went to the bidder that was 6.9% dearer before the auction and the only one that quoted in it The BOQ chart had SKS at Rs 84.95 crore against Nucon at Rs 90.84 crore; in the auction Nucon quoted Rs 84.87 crore and SKS was "Not Quoted". Final evaluation records Nucon Rs 83.80 crore at rank 1 and SKS Rs 84.95 crore at rank 2 — 1.4% apart, 31.0% and 32.8% above the Rs 63.97 crore published value. Corrigendum no. 3 reframes the tender from four packages to three and package 5 disappears unexplained. Financial opening was November 2024, final evaluation August 2026.

8RECPDCL's Barmer-II HVDC tender set a Rs 5,728 crore net-worth floor and five bidders cleared it Adani Energy Solutions, DRAIPL-CG Consortium, POWERGRID, Resonia and Terralight qualified; four are sole bidders, the fifth splits 26/74 between DRAIPL and Cube Grid Investments Pte. Ltd. The bid bond is Rs 286.40 crore and the CPG Rs 716 crore, due within ten days of LoI alongside full SPV acquisition. Scope covers two 6,000 MW ±800 kV LCC terminals, roughly 900 km of bipole and two synchronous condensers. Bipole-1 targets 48 months and Bipole-2 54, but the RFP requires simultaneous commissioning.

8BSUL's Rs 379.25 crore Jalaun evacuation package states EMD as Rs 3.80 crore in the NIT and Rs 38 lakh on the portal The tender ID shifts the same way, 913540_1 in the scanned NIT and Corrigendum-1 against 913570_1 across the CPPP record, clarification, Corrigendum-4 and opening report. Corrigendum-1 widened ITB 2.2.1 from "Sub-Station and/or Transmission line works" to "Sub-Station or any other electrical works" while holding the Rs 303.40/189.62/151.70 crore thresholds and the two 220 kV-plus bay test. SCC 3 keeps LD at 0.5% of total contract price per week where partial facilities cannot be beneficially used; SCC 3.1 and 4.0 read "Deleted" with substantive O&M text beneath, and the trial run reads "72 (Seventy-two) 24 (Twenty Four) hours continuously". Ten bidders were admitted on 10 August with the PGCIL Orai bay extension inside the contractor's scope.

8BHEL lets Talabira bidders borrow the ash-handling credentials they lack, then bills the prime bidder if a partner walks Vacuum conveying can substitute for pressure conveying where detailed engineering is vetted by an IIT or qualifying firm; missing water-impounded bottom-ash-hopper experience can be bridged by a design agency plus a performance-support undertaking; civil and structural gaps go to consortium partners. Clause 23.10 keeps the prime bidder accountable throughout. Clause 23.12 permits encashment of a departing partner's security, mandates replacement, and otherwise recovers the cost difference plus a 5% overhead factor. Clause 23.15 adds 1% consortium security, with reverse auction under clause 19.0 after technical qualification. Details

Download tenders and news clips

Aug 12:  For reference purposes the website carries here the following tenders:
 8Tender for work of supply, installation, testing and commissioning (SITC) of intelligent addressable hot redundancy based continuously available Details
 8Tender for supply of 36kV copper XLPE power cable Details
 8Tender for erection of new 132/33kV 40MVA T/F Details
 8Tender for construction of 2x40 MVA 132/33kV S/S Shahjahanpur Details
 8Tender for construction of 2x40 MVA 132/33kV S/S Details
 8Tender for construction of 2x63 MVA 132/33kV S/S Details
 8Tender for SITC of numerical line differential cum distance protection relay Details
 8Tender for work of PID testing of various tower various 132 kV, 220 kV & 400 kV lines Details
 8Tender for augmentation by replacement of existing 2x100MVA, 220/132kV ICTs by 2x200MVA, 220/132kV ICTs Details
 8Tender for AMC for repair/ service/ overhauling/problem attending of compressor of 245/145 kV circuit breaker at various Details
 8Tender for construction of LILO on 100kV line Details
 8Tender for repair maintenance of Two nos. 33kV, 10MVA transformer installed Details
 8Tender for providing fixing of negative sequence relay, over current earth fault relay Details
 8Tender for electrical works Details
 8Tender for supply and completion of HT straight through cable joints Details
 8Tender for re-organization and installation of 3.3kV overhead line and LT overhead line Details
 8Tender for replacement of 250KW, 6.6kV, HT motor of 20 no pump Details
 8Tender for dismantling, shifting of HT OH line Details
 8Tender for installation of Acs with accessories and installation of 30 nos. of streetlights Details
 8Tender for replacement of damaged GI sheets and various Details
 8Tender for making 02 Nos foundation and ramp for shifting of existing 100MT weigh bridges Details
 8Tender for replacement of old GI sheet on roof with profile sheet and misc. repair work Details
 8Tender for construction of control room foundations, cable trench Details
 8Tender for renovation of yard light works Details
 8Tender for repair of submersible pump for various 33kV S/S Details
 8Tender for renovation of control room and misc. civil works at 33kV S/S Details
 8Tender for renovation of sanitary, electric yard levelling gravelling work Details
 8Tender for suppy of P/F FRP fencing for RMU, transformer Details
 8Tender for construction of prestressed precast and brick masonry Details
 8Tender for work contract for work of lifting and disposal of used thermal insulation material Details
 8Tender for work contract for availing OEM supervisory services for complete overhauling along with commissioning of 6.6 kV, 360 KW glandless boiler Details
 8Tender for procurement of 250 NB and 300 NB sleeve type expansion joint for installation in pressure conveying line Details
 8Tender for construction of new 11 kV, LT lines and 11/0.4 kV DTR Details
 8Tender for miscellaneous civil work Details
 8Tender for replacement of flame proof (FLP) lighting distribution boards (LDBs) at various Details
 8Tender for construction of box culverts Details
 8Tender for rectification works for structural and civil defects in C-Row Details
 8Tender for job contract for removal of brick partition wall and extension of stage-1HT switchgear Details
 8Tender for civil works of construction of culvert and other necessary repair work Details
 8Tender for supply and retrofitting of 400 kV SF6 circuit breakers Details
 8Tender for work of erection, testing and commissioning of new FOAC cable in existing 66kV UG line network Details
 8Tender for work of erection-dismantling of 66kV/11kV equipment’s, structures, control wiring Details
 8Tender for work of complete servicing/ overhauling/ defect attending of various hoists and cranes Details
 8Tender for work of penthouse /APH centre section sealing for the unit Details
 8Tender for supply of liquor ammonia 25 % (AR grade) for boiler water treatment Details
 8Tender for EPC package for ash handling system Details
 8Tender for framework agreement for various industrial operations Details
 8Design, engineering, manufacture, supply, erection, testing & commissioning of 6.6 kV indoor metalclad draw-out type VCB panels Details
 8Tender for renovation of power house Details
 8Tender for shifting of electrical utilities in connection Details
 8Tender for interlinking of 11kV feeder Details
 8Tender for supply, erection & commissioning of 11 kV lines with MVCC conductor & dismantling of existing open conductor 11 kV lines Details
 8Tender for works contract for replacement of existing overhead bare conductor Details
 8Tender for works contract for replacement of existing overhead bare conductor ACSR 7 4.09 mm, AAAC 7 3.15 mm and AAAC 7 2.59 mm by XLPE coated covered conductor Details
 8Tender for turnkey construction of one no. of 33kV feeder bay and associated works at 220/132kV GSS Details
 8Tender for conversion of 11 kV feeder Details
 8Tender for refurbishment of coal burner nozzles and tips of 2x270 MW units Details
 8Design, manufacture, testing, supply and delivery of 162 nos. 66kV, 39 nos. 132kV and 63 nos. 220kV SF-6 circuit breakers Details
 8Tender for creation of new control room at 132kV S/stn Details
 8Tender for casting of machine pressed solid Details
 8Tender for work of annual rate contract for attending on site minor repairs / maintenance works / OLTC overhauling of EHV class power transformers / ICTs Details
 8Tender for laying of three single core 11kV XLPE 185 sq.mm. cable on elevated PSC structure Details
 8Tender for laying of three single core 11kV XLPE 185 sq.mm. cable Details
 8Tender for supply of BWSR spares Details
 8Tender for providing PVC coated chain link fencing Details
 8Tender for erection of 66 kV line Details
 8Tender for replacement of acid and alkali resistant tiles in DM plant Details
 8Tender for procurement of complete assembly of gear box model Details
 8Tender for procurement of M/s coupling and its spiders installed Details
 8Tender for rate contract for maintenance of AC machines Details
 8Tender for service contract for online leak sealing job as and when required Details
 8Tender for biennial contract of the job operation of gate valve for smoothly distributing Details
 8Tender for supply of vertically operated 11kV gang operated air breaker switch Details
 8Tender for works contract for carrying out HT LT DCW, improvement and capital extension works Details
 8Tender for works contract for stores handling works Details
 8Tender for procurement of MS bolt nut Details
 8Tender for provide services for installation of solar meter along Details
 8Tender for work of overhauling of 132KV/220 kV CB poles and mechanism of with required spares Details
 8Tender for work of two-year rate contract for the work of cold line washing of insulator strings of various Details
 8Tender for supply, installation & commissioning of neutral grounding reactor (NGR) for power transformer Details
 8Tender for work of providing & applying of high insulation resistance compound coating having Di-electric strength Details
 8Tender for annual maintenance contract for the work of attending emergency, break down and maintenance work of 220kV, 132kV lines Details
 8Tender for supply of equipments/ material, erection, testing and commissioning for the work augmentation by providing additional 1 x 50MVA, 132- 110/33 kV T/F along Details
 8Tender for supply of various CDS tubes and bend for drain & vent line Details
 8Tender for conductor replacement with hardware & SRI of 66kV tower line Details
 8Tender for loading & unloading of material and transformer Details
 8Tender for erection, maintenance and dismantling work of overhead HT/LT line Details
 8Tender for supply of spare for bosch make loudophone at switchyard Details
 8Tender for work of rubber lining of various equipments, pipes and fittings Details
 8Work of repairing of various pulleys of conveyor belts Details
 8Tender for biennial work contract for maintenance of ash handling plant Details
 8Tender for various maintenance works of wagon tippler Details
 8Tender for work of carry out corrosive test of various MS structure of coal handling plant Details
 8Tender for supply of control panel spares of pump house Details
 8Tender for work of misc pressure part related activity of boiler stage Details
 8Tender for work for dismantling, design & supply, installation and commissioning of GI duct and air filter assembly with supporting structure Details
 8Tender for rate contract for routine, preventive & breakdown maintenance of TPS lighting system, fans etc Details
 8Tender for work of replacement of various spares of drive system of wagon tippler Details
 8Tender for supply of various ratings LT motor Details
 8Tender for supply of various boiler tubes bends Details
 8Tender for carting of 11,500 Nos. of 8 meter PSC poles Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8How India seeks to translate its offshore wind potential into large-scale deployment Details
 8Coal India Weighs Buyout of Wealth Minerals' Chilean Lithium Unit Details
 8Five decades of research leads to solar PV’s emergence as the world’s dominant energy source Details
 8Look beyond solar, draw up roadmap for all renewable energy sectors: House panel to MNRE Details
 8Powering the Next Generation of Commercial Rooftops: Hoymiles MIT-5000-8T Takes Centre Stage in Hyderabad Solar Project Details
 8Beyond modules: Why cell manufacturing will shape India’s next solar growth story Details
 8ReNew Sells Solar Assets for Rs 4,859 Crore Details
 8Sodium-Ion Battery Prototypes Reach 200 Wh/kg Milestone Details
 8India Strengthens Energy Storage Framework With INR 5,400 Crore VGF And Transmission Incentives Details
 8India’s solar revolution lights the path to a Viksit Bharat Details
 8India's Delhi faces rising night-time power peaks: report Details
 8India awards 1 GW of round-the-clock renewables at competitive tariff Details
 8Electricity Demand Expected To Rise Up to 7.5% In FY27 Amid Higher Heat, Rainfall Deficit: Crisil Details
 8Huf India Commissions 1 MW Rooftop Solar Project in Pune Details
 8India’s Coal Imports For Power Blending Fall 71.5% In Two Years: Govt Details
 8India Accelerates Power Distribution Digitalization With Smart Meters And Grid Modernization Details
 8Global Renewable Energy Capacity Hits 5.2 TW Milestone Details
 8Lloyds Metals Secures 66 MW Renewable Power via Gentari Deal Details
 8UP to resume smart meter rollout after consumer awareness drive: State Power Minister Details
 8Cummins India Q1 FY27: Revenue rises 18%, data centers drive power gen growth Details
 8Shadows Over Green Energy Details
 8Porter Marks 10,000th Electric Truck Deployment in Delhi Details
 8Why India Had To Open Its Nuclear Power Sector Details
 8NLC India Renewables Bags SECI Letter of Award for 200 MW Wind Power Project in Karnataka Details
 8India's Draft National Electricity Policy 2026: Key proposals explained Details
 8HCC secures contract of around Rs 524 crore from State-run NHPC in Jammu and Kashmir Details
 8Jakson Infra Wins Rs 128 Crore Power Project in Karnataka Details
 8Hindustan Construction Company Wins Rs 524.17 Crore NHPC Order for Salal Hydro Project in J&K Details

 
You can also click on Newsclips for more Details

India adds 55.3 GW of non-fossil capacity in FY26 while planning 315 GW of coal - energy security is producing two expansion tracks

Aug 11: 8Solar contributed 44.6 GW and wind 6.1 GW to the year’s non-fossil additions, taking non-fossil sources above 54% of installed capacity.
The simultaneous build-outs leave transmission, storage, coal utilisation and peak adequacy to determine whether the two fleets complement each other or impose parallel system costs.
Details

Tripura rejects most of TSECL’s Rs1,709 crore past-gap claim to avoid a tariff shock - but the unpaid gap still has to be worked down

Aug 11: 8The regulator approved a Rs479.24 crore revenue gap but allowed only Rs117.77 crore against the FY27 tariff after calculating that full recovery would require a 42.82% average increase.
It paired partial recovery with smart-meter consent, billing-resolution and grievance directions, protecting consumers now while retaining future financial obligations.
Details

CEA’s unbuilt hydro list shows approvals stranded behind forest and environmental clearances - the paperwork has not become construction

Aug 11: 8Projects across conventional hydro and pumped storage remain untaken up even after appraisal, with some concurrences or environmental approvals already expired.
The clearance-pending category alone includes 14,649 MW in the CEA table, showing how a project pipeline can remain large without becoming executable capacity.
Details

SJVN’s 1,200 MW firm-renewable and 600 MW wind tariff cases are reserved for order - but the 1,200 MW sale agreement is still unsigned

Aug 11: 8One case covers 1,200 MW of firm dispatchable renewable supply; the other covers 600 MW of inter-state wind projects selected through separate bidding.
For the firm and dispatchable procurement, HPSEB has sought state approval for the contracted power but had not executed its power-sale agreement at the hearing.
Details

Chhattisgarh’s 500 MWh battery tender reaches tariff-adoption hearings with Rs90 crore of support - but the storage contract is not final yet

Aug 11: 8The state distributor’s petition says the project must be commissioned within 18 months of the storage-purchase agreement and that land and connectivity will be provided.
Public comments are due before the September hearing, so the discovered tariff and contractual allocation still require regulatory adoption.
Details

Odisha sought Rs6,284 crore of cyclone-resilient distribution work - but private ownership leaves its DISCOMs outside RDSS funding

Aug 11: 8The Centre says Odisha’s utilities are ineligible because RDSS financial assistance is limited to state-owned distributors and power departments.
It also says no formal Rs10,000 crore special power-package proposal was submitted after Cyclone Yaas, separating the state’s actual RDSS request from the larger claimed package.
Details

Madhya Pradesh cuts distribution losses but accumulated DISCOM losses rise to Rs71,394 crore - reform progress has not repaired the balance sheet

Aug 11: 8State-level AT&C losses fell from 41.72% in FY21 to 22.76% in FY25, and the reported cost-revenue gap moved to a small surplus.
Borrowings still stood at Rs49,239 crore, while large portions of sanctioned RDSS network and smart-meter work remained to be installed or completed.
Details

India Energy Stack pilots are under way in five utility markets - but a national power-data architecture has not yet been proved

Aug 11: 8Utilities in Delhi, Gujarat, Andhra Pradesh, Uttar Pradesh and Mumbai have been selected for proof-of-concept implementation.
The proposed stack is meant to connect power-sector systems through secure common protocols, with interoperability, governance and consumer protection still to be demonstrated in practice.
Details

Draft power policy would shift more fixed and fuel costs into regular electricity bills - while proposing a stabilisation fund to soften volatility

Aug 11: 8The Draft National Electricity Policy, 2026 calls for fixed charges to recover fixed costs and for monthly automatic fuel-and-power purchase adjustments.
It also seeks cost-reflective tariffs without new regulatory assets, placing distribution-company finances and household affordability in the same unresolved policy choice.
Details

Uttar Pradesh has Rs21,782 crore of RDSS network works and Rs18,956 crore of smart metering sanctioned - but consumer complaints are still handled state by state

Aug 11: 8The Centre says funding is linked to physical and financial progress and vendor checks are built into standard bidding documents.
The monitoring chain reaches from state committees to PFC, REC and the Union power secretary, yet billing redress and meter mode remain with utilities and state regulators.
Details

Four China-linked equipment makers can bid for Indian power projects for two years - but only under domestic-content conditions

Aug 11: 8The exemption covers TBEA Energy India, Nanjing Electric India, New Northeast Electric India and Taikai Electric India from 24 June 2026.
Government says wider competition can ease supply constraints and stabilise prices, while the conditional waiver keeps the domestic-manufacturing trade-off visible.
Details

India has sanctioned 20.33 crore smart meters but installed 5.73 crore under RDSS - consumer safeguards now have to catch up with scale

Aug 11: 8The sanctioned total covers consumers, feeders and distribution transformers; all schemes together account for 7.24 crore installed smart meters.
Government cites check meters, independent testing and third-party laboratory verification, but billing complaints remain the responsibility of state utilities and regulators.
Details

India proposes Rs20,000 crore for carbon capture - but the programme has no approved project-selection rules yet

Aug 11: 8The five-year proposal is intended to advance carbon-capture, utilisation and storage across power, steel, cement, refineries and chemicals.
The Ministry of Power says the programme is still being established, leaving cluster selection, audit standards and implementation rules to follow after approval.
Details

Rays Power Infra’s order book reaches Rs8,455 crore - but rapid growth is lifting leverage and supplier-finance dependence

Aug 11: 8The solar developer and contractor’s order book was 3.83 times FY26 operating income, giving it substantial revenue visibility after an 81% rise in annual income.
CareEdge nevertheless identifies project concentration, higher gearing, heavy use of supplier finance and timely equity for co-developed projects as the counterweights to that growth.
Details

Amara Raja starts building a 10 GWh battery-storage factory - but first output is still tied to a FY27 construction timetable

Aug 11: 8The Divitipally project is designed for grid-scale and commercial-and-industrial storage, with operations scheduled to begin in the third quarter of FY27.
The company has already commissioned a customer-qualification plant, but the larger manufacturing plan still depends on phased cell and storage-factory start-ups over FY27 and beyond.
Details

BRIEFS - VERIFIED DEVELOPMENTS WITH LIMITED DEPTH

Aug 11: 8Thermal coal-stock reports cover 6 - 9 August - four daily observations cannot establish a durable inventory trend
8India’s generation reports compare 7 and 8 August - the two-date fuel mix is an operating snapshot, not a transition trend
8Uttar Pradesh moves its draft Grid Code hearing by one day - objections still close on the earlier timetable
8Gas stations flag a low-frequency threshold mismatch - compensation remains under regulatory review
8Secure meter-data software slows regional accounting - manual handling is still filling the processing gap
8Genus meter decryption produces conversion defects - corrected files are still awaited
8DSM defaults trigger letter-of-credit scrutiny - security compliance has not cured the pool’s unpaid balance
8Unreturned reconciliation statements are being deemed accepted - administrative closure does not create fresh cash
8NP Kunta’s STATCOM needs an SMPS upgrade - reliability work requires a planned equipment shutdown
8Hyderabad substation’s automation migration needs 400 kV outages - modernisation temporarily narrows network availability
8Talcher - Kolar HVDC Pole 1 seeks an eight-hour shutdown - refurbishment inspection still awaits outage clearance
8India’s demand forecast error moved across 7 - 9 August - three daily readings do not establish model performance
8High-price day-ahead sellers offered 37,838.4 MWh - no purchase or cleared volume followed
8Intraday auction reports expose bids, clearing and schedules block by block - the latest sheet is a market snapshot
8WCL still carries compassionate-appointment applications from earlier years - the source confirms backlog, not a clean total
8Odisha’s closed coal mines face an unfinished reclamation question - completion evidence is not established
8Fatehgarh - Bhadla lenders may take security over the transmission asset - a licence transfer still needs prior approval
8Tadas Wind challenges where DSM charges are computed - the interconnection point could change the bill
8SGPL presses a Haryana energy-charge claim - the hearing record does not award the money
8Osmanabad Solar seeks Rs3.42 crore in DSM dues - the hearing was deferred before the merits were reached
8TPTCL’s withheld-dues dispute returns to jurisdiction - the Commission wants arguments before deciding the claim
8Teesta Low Dam IV’s tariff case reaches the order stage - additional capital claims remain under scrutiny
8MEL’s transmission-licence process draws a compliance warning - proposed approval is not yet unconditional
8Solarcraft seeks more time after bay-sharing delays - missing guidelines do not automatically extend connectivity
8Kreate’s banking claim against SPTPL meets a denial of monetary liability - updated claims still need adjudication
8UGVCL’s accident register records fatal network incidents - responsibility remains case-specific
8UGVCL tracks complaints received, resolved and pending - the extracted register does not yield a reliable aggregate
8UGVCL records transformer failures and restoration complaints - a verified failure-rate figure is missing
8UGVCL’s reliability register contains outage indices - the source slice cannot support a performance ranking
8Faulty-meter replacement remains in UGVCL’s operating records - the backlog needs a clean count
8UGVCL reports no standards-of-performance compensation in the selected table - nil claims require an audit trail
8UGVCL records unauthorised-use and theft enforcement - mixed source rows prevent a verified total
8Telangana’s reservoir sheet compares storage on 11 August - a single date cannot establish seasonal security
8Odisha’s hydro report links reservoir levels to available units - sparking and open gates constrain the snapshot
8Reserve-shutdown fuel-oil compensation needs a calculation rule - eligibility alone does not fix the quantity
8Faulty special-energy meters remain unreplaced after earlier meetings - delay keeps commercial disputes alive
8Radhanesda’s meter failure produced a Rs17.83 lakh DSM revision claim - the account still needs correction
8RDSS funds workforce training for digital distribution - utilisation must match the technology rollout
8SCUC reports show upward and downward schedules from 7 - 10 August - the short series is operational, not predictive
8Real-time market data run through 10 August - block prices and volumes need a longer benchmark
8Grid-security readings were mostly compliant at Agra but weaker at Ajmer - one report cannot grade the corridor
8Western-region outages and line states changed on 10 August - the operating list is not an adequacy forecast
8The Centre retains 15% of central-station power as unallocated - states compete within the remaining allocation rules
8Chhattisgarh’s mining funds must favour high-priority services - allocation rules do not prove local delivery
8NLC’s TPS-I Expansion true-up accepts an 8.5% auxiliary-consumption norm - the wider tariff still rests on reconciled costs
8Vindhyachal Stage I seeks tariff and life-extension capital - the rules may prevent double recovery
8NLC TPS-II’s additional-capital claim contains a cash-basis mismatch - reconciliation must precede the order Details

POLICY AND SYSTEM PLANNING - RELIEF, INVESTMENT AND CAPACITY CLAIMS MEET THEIR IMPLEMENTATION LIMITS

Aug 11: 8Delhi lets three discoms recover June fuel and power costs above the 10% billing ceiling - but only for one month and below their full claims
8NTPC wants station-transformer loads explicitly counted at Vindhyachal and Korba - only export apportionment would change under its proposal
8Legacy and current power-pool deficits are still holding back disbursement - collections received do not eliminate the unpaid tail
8Municipal bonds have raised Rs6,540.44 crore across 23 urban bodies - green issuance is growing but incentives do not prove project delivery
8NTPC Lara has settled rehabilitation claims for most affected families - jobs remain conditional on vacancies and suitability
8Ashoknagar’s petroleum lease has been extended twice - commercial oil and gas production still has not begun
8India met a 270.8 GW peak in May against a 289 GW FY27 forecast - national adequacy still leaves local network constraints
8Electrical installations may use inspection or self-certification cycles of up to five years - digital reporting must make the option auditable
8Public EV-charging electricity use rose from 107.41 MU to 149.58 MU between April 2025 and March 2026 - four states dominate the annual total
8Telangana’s station-wise generation moved through July - the monthly sheet reveals unit performance but not the cause of every change Details

REGULATION AND DISPUTES - PETITIONS SEEK MONEY OR RELIEF THAT ORDERS HAVE NOT YET AWARDED

Aug 11: 8Andaman solar and storage operators seek must-run compensation - deemed generation still needs a contractual basis
8ReNew seeks protection against a bank-guarantee call - the dispute has not erased the underlying obligation
8Barh Stage I capital costs require another reconciliation - escalation cannot enter tariff without an accepted basis
8Sarda seeks tax and open-access reimbursement for 100 MW - contract allocation will decide who pays
8Sikkim Urja, PTC and NDMC trade reciprocal dues - set-off cannot replace proof of each underlying bill
8NTPC Renewable and SECI dispute a scheduled-completion extension - delay relief depends on the cause and notice record
8APPCPL’s banking claim meets SPTPL’s insolvency moratorium - recovery rights now collide with bankruptcy protection
8SEIL disputes coal-transport deductions under its power-supply arrangement - the case must decide whether freight was recoverable or already embedded in another charge
8Tamil Nadu’s Ombudsman protects the existing tariff for qualifying small extensions - separate construction can still trigger Tariff VI
8Adani’s Jharkhand plant supplies Bangladesh exclusively - cross-border trade adds power without entering India’s domestic allocation Details

STORAGE AND HYDRO - ANNOUNCED CAPACITY STILL WAITS FOR AWARDS, CLEARANCES AND OPERATING EVIDENCE

Aug 11: 8Assam is included in plans for 200 MWh of battery storage - but no state capacity has yet been allocated
8Nathpa Jhakri seeks recovery for hydrology shortfall - the case turns on evidence that water, not operation, caused the loss
8Kynshi and other hydro DPRs go back for revision - redesign delays appraisal but may be necessary for a viable project
8Draft power policy backs storage and flexible grids - integration measures remain plans until capacity and networks are commissioned Details

DISTRIBUTION AND CONSUMERS - DIGITAL INVESTMENT EXPANDS FASTER THAN PROOF OF SERVICE IMPROVEMENT

Aug 11: 8PSPCL proposes an online settlement for 37.2 lakh consumers owing about Rs6,201 crore - agricultural accounts are excluded and PSERC approval is pending
8RDSS pushes distribution utilities deeper into digital operations - installation counts still do not prove better service
8Private discoms average 23.87 hours of daily supply and 10.05% AT&C losses versus state utilities’ 23.22 hours and 15.40% - group averages still hide company-level variation
8Andhra Pradesh advances RDSS cabling and smart meters - large awards still leave an installation gap
8RDSS adds SCADA, IT/OT integration and smart-distribution-city projects - cybersecurity becomes part of reliability Details

COMPANIES AND FINANCE - GROWTH VISIBILITY MEETS HYDROLOGY, CREDIT AND ACCOUNTING RISK

Aug 11: 8Amara Raja’s new-energy sales grow by more than 50% - but exports and factory execution pull in opposite directions
8Jagdambey Hydro retains fixed-tariff visibility - weak generation and one buyer still constrain the credit
8PFC and REC loans survive TANGEDCO’s restructuring - Rs12,822 crore of annual interest shows the continuing burden
8Quality Power’s income rises 32% and its order book reaches Rs19,455 million - reported profit still carries a hyperinflation adjustment Details

COAL AND TRANSITION - LOWER IMPORTS AND NEW LOGISTICS MEET OUTPUT, FUEL AND CONVERSION CONSTRAINTS

Aug 11: 8JP Nigrie seeks scheduling recognition after a coal-supply change - fuel availability must still support the declared output
8New Colliery Control rules replace the 2004 framework’s Rule 9 - compliance changes now depend on the substituted text
8Power-sector coal imports fall 71.5% to 6.8 million tonnes in two years - the source does not isolate how much domestic coal replaced them
8India has auctioned 124 commercial coal blocks and attracted 44 first-time bidders - allocation totals still outrun producing mines
8Coal-gasification incentives support a 100 million-tonne ambition - projects still need buyers, feedstock and working economics
8FY26 coal output and dispatch fall - logistics additions have not prevented a weaker annual result
8Coal India plans 139 first-mile projects with 1,319 million-tonne capacity by FY30 - eight rail schemes still have to turn that capacity into dispatch Details

MARKETS AND SETTLEMENT - ACCOUNT CORRECTIONS EXPOSE WHO CARRIES DEVIATION AND PAYMENT RISK

Aug 11: 8Gujarat says schedule-allocation errors distorted weekly DSM accounts - corrected data could redistribute charges between entities
8Avaada’s PPA-and-merchant portfolio needs one DSM contract rate - the wrong method can shift deviation charges between sales routes
8Fuel-quality variation is being tested against partial-outage DSM treatment - one cause should not be labelled as another
8Western-region DSM defaults are delaying pool payments - unpaid participants shift the cash burden to compliant members
8Maharashtra’s legacy DSM deficit remains unpaid - old shortfalls are still reducing current disbursement capacity
8Rajasthan revises merit order after a central-station tariff change - cheaper dispatch depends on using the new cost ranking
8RGPPL’s Rs18.64 crore legacy DSM amount is still awaiting settlement - recognition has not produced payment
8Renewable DSM calculations remain subject to interim High Court orders - final settlement still depends on the litigation
8June’s national SCED pool has paid generators under the monthly statement - heat-rate degradation compensation remains separate Details

GRID AND TRANSMISSION - EXPANSION PLANS CONFRONT AGEING ASSETS, OUTAGES AND UNFINISHED PROTECTION

Aug 11: 8Northern planners propose 23 optical terminals and an STM-64 data corridor - but allocation still starts a 12-month delivery clock
8Powergrid cuts planned VoIP control centres from 82 to 73 - while Ladakh and Chandigarh remain outside the approved scope
8Fibrehome support expires in October as replacement lags - RRVPNL wants Powergrid to take over delivery
8Repeated switching is stressing Maheshwaram’s 765 kV GIS - a flashover shows the wear is no longer theoretical
8Testing on 53 ageing transmission lines is being slowed by outage approvals - the delay raises the failure risk the tests are meant to reduce
8Grid-India escalates the Jeypore - Gazuwaka outage - east - south transfers remain dependent on alternative paths without a restoration date
8Kudankulam’s protection scheme delivered less load relief than intended - Nandikotkur stayed connected through a second line
8Kaiga’s Guttur circuits have been out since May - operators warn the remaining evacuation path could overload
8Odisha’s section of the Jagdishpur-Haldia gas pipeline is complete - Cuttack connectivity now depends on use, not construction
8Avaada’s connectivity-relaxation case is reserved for order - the requested network exception is not yet granted
8Gorbea Solar seeks compensation for delayed grid access - but generation loss remains a claim, not an awarded amount
8VEH Saur wants 33 MW more generation within existing connectivity - CERC first wants evidence that the projects are ready
8Kanjhawala’s 11 kV bus outage contributed to a one-hour consumer interruption - restoration is still an operating issue
8India plans to raise inter-regional transfer capacity from 120 GW to 168 GW by 2032 - renewable growth still needs the lines to arrive Details

Contracting news for the day

Aug 11: 8Mahagenco's Rs 93.55 crore Koradi pipe tender asks a manufacturer for 100% turnover and a contractor for 30% Annexure A sets average annual turnover equal to the entire Rs 63.37 crore supply estimate; Annexure B sets its test at 30% of Rs 30.18 crore, or Rs 9.054 crore. The two rounded annexure values total Rs 93.55 crore against the NIT's Rs 93.552027 crore. Annexure B says the bidder or a consortium member should qualify both the works and supply conditions, while later provisions require only one member to meet the works QR — leaving unstated whether credentials can be split between two partners. Holding-company support runs five years from the last month of bidding or to the end of the defect-liability period.

8BHEL's Jharsuguda ash-handling EPC excludes civil and structural works, then makes the contractor responsible for them anyway TCC clause 3.14 keeps any additional item required for package completeness — mechanical, electrical, C&I, civil and structural — inside bidder scope unless specifically excluded. NIT clause 35.0 issues one LOA and then splits billing into supply, installation and five-year O&M, reserves BHEL's right to redistribute that split later, and makes a breach under one order a breach under the others. O&M starts at 5% of contract price and escalates 3% a year, aggregating roughly 26.5% over five years. Auxiliary power is capped at 3,173 kW with LD of Rs 14 lakh per additional kW. Bid issue to submission: eleven days.

8DVC's Rs 90.20 crore Chandrapura diversion names three different conductors for one package The high-level scope cites AAAC Panther 37/3.15 mm and AAAC Dog 19/2.89 mm; the detailed supply section calls for AAAC Zebra 61/3.31 mm plus underground cable, and the tender text does not map either set to a particular line. Corrigendum-I moved download, submission and opening each by seven days and states all other terms remain unaltered. Bid validity is 180 days while bid security must run 225. Price variation under SCC clause 8 stops rising past scheduled dates unless preserved in an extension letter; downward movement still accrues to the owner.

8OPGC's Rs 21.83 lakh protection audit carries two turnover thresholds, two experience windows and a handwritten voltage GeM shows minimum average annual turnover of Rs 7 lakh; the committee-approved QR clause 2.2.1 sets Rs 6.55 lakh. GeM states five years of past experience while QR clause 2.1.1 admits similar works completed in the preceding seven. The 40%/50%/80% ladder should read Rs 8.732, 10.915 and 17.464 lakh; the QR prints Rs 8.73, 10.90 and 17.50 lakh — 40.0%, 49.9% and 80.2%. The QR scan carries a handwritten "220KV" beside the printed 400 kV similar-work description. Payment is set at 30 days, expressly superseding the 10 days in GeM GTC clause 12.

8OPTCL's Rs 147.97 crore Balasore cable tender can't agree with itself on how many stages it has The IFB describes a "single stage two part system"; the portal field reads "Stage: Two Stages". Document availability differs the same way — the notice runs 06.06.2026 to 06.07.2026, the portal 11-06-2026 to 08-07-2026, with closing at 14:00 and techno-commercial opening at 15:00 on 8 July. The notice rounds the estimate to Rs 147.97 crore while the portal records Rs 1,47,97,02,728 and fixes EMD at Rs 1,47,97,027. No corrigendum in the package reconciles either. Cost-opening date is to be defined later.

8NTPC's Ramagundam transformer tender gives three different answers on price escalation The technical specification applies IEEMA escalation to the transformer price alone and keeps freight, insurance, spares, tests and erection firm; BDS marks price-adjustment data "Not Applicable"; Appendix-2 sets out a wider adjustment framework across equipment, erection, structural and civil components without a ceiling. The contract runs 30 months. BDS clause 13 confines installation pricing to 10–15% of the supply portion and retains amounts quoted outside that band without interest rather than rejecting the bid. BDS clause 31 carves 5% of the service portion out against quarterly safety certification. The NIT calls it single-stage two-envelope; the portal operates three covers.

8JPDCL's Rs 538.15 lakh "DPR" is a 33 kV line build, and its extension left bid opening six days before bid closing The SBD reduces scope to "As per BOQ", and the BOQ carries 420 11-metre poles, 40 13-metre poles, 42,000 kg of channel iron, 72 km of ACSR, 920 stay sets and 15 lattice-structure jobs. Extension Notice-1 moved the last date for bidding from 10 August to 17 August "due to low response" but left technical opening at 11 August and hard-copy EMD submission at 10 August. The performance-security clause is numbered 2 yet directs bidders to "clause 3.2", and the unbalanced-bid provision refers back to "clause 3.1". Clause 20.2 places jurisdiction by reference to Ramban in a Udhampur-Chenani package.

8HPSEBL's Rs 3.72 crore distribution-reform consultancy is gated on transmission turnover, then run through both QCBS and a reverse auction Eligibility requires Rs 70 crore average annual turnover in power-transmission consultancy at 66 kV and above for an assignment framed under a distribution-sector scheme; joint ventures are barred. ITC 25.1 sets 70:30 QCBS while the NIT adds an e-reverse auction with a 0.5% decrement, and no provision states how the auction price enters the financial score. The NIT and portal require Rs 7.44 lakh EMD; the RFP requires a bid-securing declaration in lieu of it. Validity is 180 days on the portal and 120 in Data Sheet ITC 12.1; one ITC provision bars subcontracting while ITC 12.8 permits it. Three corrigenda, 31 days, no substantive change.

8MPPMCL's 625 MW storage tender still shows its opening event six days before the bids come in The header applies 10 August for receipt of bids while the NIT table retains 4 August as the tender opening event and 30 July for document procurement. Corrigendum-1 issued 24 July and the record separately notes "Addendum #2 Issued", neither reproduced at NIT level. Bid security is Rs 2.20 lakh/MW rather than a flat sum, alongside a Rs 15 lakh processing fee plus GST and a Rs 30,000 ETS charge. Chemistry, cycle life, degradation, augmentation, availability and PBG terms sit outside the notice.

8NSPCL's Durgapur mill tender cut mandatory spare pump assemblies from 24 to three, then put them back to 24 Amendment no. 2 made the reduction; Amendment no. 4 restored the original figure, stating "As per the Original BOQ". The same amendment chain rewrote completion LD from a flat Rs 6,89,750 per day to 0.5% per week on the contract price attributable to uncommissioned mills, capped at 5%; deleted unburnt-carbon loss as a sizing criterion; disallowed YGP correction of wear life; and cut the wear-life demonstration population from three pulverisers to two. The shutdown-extension LD provision still reads "INR xxxxxx". Eleven closing-date revisions moved the deadline 102 days from 8 May to 18 August.

8NTPC's Rihand generator-transformer tender marks price adjustment applicable and the price-adjustment appendix "NOT APPLICABLE" BDS identifies Attachment 8P as applicable; Appendix-2 is headed "PRICE ADJUSTMENT (NOT APPLICABLE)" and then sets out uncapped escalation formulas for equipment, erection and other components. BDS item 13.0 states "Civil work Price Component: Not Applicable" and immediately requires that component to fall between 70% and 75% of the supply portion, against a BOQ built around supply, erection, freight, spares and tests. Installation pricing outside the 10–15% band draws interest-free retention. Contract period 36 months; LD 0.5% weekly capped at 5%.

8DVVNL's Rs 79.32 crore AB cable tender shows 5% performance security on the portal and 10% in the terms that override it GeM prescribes a 5% ePBG for 48 months; the ATC declares itself overriding and sets a 10% contract performance guarantee, with clause 36 rendering it as "Ten Percent (10%) plus GST@18% of the total Contract price". Guarantee duration is written three ways — 90 days after contract completion, 180 days after warranty expiry, and again 90 days beyond successful warranty completion. Corrigenda C5 and C6 carry identical substantive terms and differ only in identifier, yet C6 states it supersedes all existing buyer-added conditions. The portal permits splitting among 30 bidders while the ATC requires each bidder to offer at least 25% of quantity; the award went five ways at one rate, Rs 474.10 per metre.

8KSEB's transformer tender has two probable contract amounts, Rs 10.46 crore apart, and L1 and L2 separated by Rs 2.67 lakh The notice and portal record a PAC of Rs 72.16 crore; the 3 August pre-qualification minutes cite Rs 61.70 crore, with no reconciliation. Against the first figure L1 at Rs 84.65 crore is 17.3% high; against the second, 37.2%. L2 stood at Rs 84.68 crore — a 0.03% spread — while L5 came in 31.6% above L1. Clause 18.7.4 had specified a finishing coat as both "dark admiral gray conforming to No. 632" and "No. 541 (Light Brown)" until the corrigendum removed the second. Three of the five qualified bidders were admitted on undertakings to produce compliant type-test reports before supply.

8PSPCL's Faridkot RDSS package records an auction price of Rs 111.60 crore and an award value of Rs 111.71 crore The difference, about Rs 11.17 lakh, is almost exactly the single 0.1% decrement that produced the auction result; the comparative BOQ summary and award-facing record remain at the pre-auction figure. Only two bidders reached financial evaluation and only one entered a revised figure, the other recorded "Not Quoted". L1 finished 24.8% above the Rs 89.46 crore estimate, L2 42.0% above. SCC fixes performance security at 3% while the advance-payment condition refers to 10% of contract price, and the payment clause reads "sixty-five (60) days". Individual BOQ items may move ±50%.

8PFCCL's Fatehgarh-II synchronous condenser tender opened bids 76 days after the date the RFP set Clause 2.7.1 fixed 17 April 2026; the qualification notice records actual opening on 2 July and qualified bidders declared on 10 July. Exactly four bidders qualified against a rule advancing the higher of the top 50% of ranked initial offers or four — so the shortlist and the auction field are the same set. Qualification tests infrastructure capex of Rs 1,140 crore aggregate and Rs 456 crore net worth, not synchronous-condenser operating history, while performance is measured at the PCC with total losses below 2%, 97% availability and 1,200 MVA short-circuit contribution. Assets transfer at zero cost 35 years after COD.

8RECPDCL amended its Rs 55.32 crore-bond ERES-47 bid deadline the day before it fell due, and left COD where it was Amendment-IV, dated 10.08.2026, moved submission from 11 to 18 August, qualified-bidder announcement to 27 August, initial-offer opening to 31 August, the reverse auction to 1 September and SPV transfer from 10 to 21 September — an 11-day shift at the far end. Scheduled COD stays 31.03.2029, so the post-award runway shortens by the same amount. Technical qualification requires Rs 2,766 crore aggregate capex with Rs 553.20 crore per project and Rs 1,106.40 crore net worth. Execution depends on BSPTCL's matching Nawada–Guraru works and space at Jeerat from another entity.

8A 400 kV GIS switching-station RFP has now moved its bid date 48 days without touching a 24-month COD Amendment-III shifts submission from 10 to 24 August, 14 days, against an original RFP date of 7 July; qualification announcement, initial-offer opening and reverse auction all move to 1, 2 and 3 September, and document signing to 21 September. Initial offers and the auction remain one day apart. The bid bond is Rs 12 crore and the performance guarantee Rs 30 crore, with net worth of Rs 250 crore and Rs 600 crore aggregate capex required. LILO conductor, OPGW and earth wire must match existing-line parameters, and bay-extension work may add roads, drainage, trenches and levelling identified only at site inspection. The amendment states the revised timetable and no reason for it. Details

Download tenders and news clips

Aug 11:  For reference purposes the website carries here the following tenders:
 
8Tender for supply of 33 kV, 3CX300 Sq mm HT power cable Details
 
8Tender for supply of M.S forged pins for 33kV pin insulators Details
 
8Tender for supply of electro-pneumatic and resistance to current convertors Details
 
8Tender for requirement of emergency oil pump (EOP) with DC motor for 210/195MW units Details
 
8Tender for carting of 11,500 Nos. of 8 meter PSC poles Details
 
8Tender for supply of 36 kV copper XLPE power cable Details
 
8Tender for erection of new 132/33kV/ 40MVA T/F Details
 
8Tender for rate contract for supply of 33 kV vaccum interrupter Details
 
8Tender for procurement of 02 Nos. 6.6 kV 988 KW ,992 RPM,ID fan motor Details
 
8Tender for procurement of mechanical spare parts of stacker reclaimer Details
 
8Tender for procurement of LT motor above 100KW Details
 
8Tender for supply and installation of 780KWp solar PV modules Details
 
8Tender for annual maintenance contract (AMC) of firewalls installed Details
 
8Tender for AMC to desilting, earthwork, painting and sectioning Details
 
8Tender for certain improvement works Details
 
8Tender for work of shifting of 132KV D/C line Details
 
8Tender for civil works of 400/220kV yard Details
 
8Tender for framework agreement for various industrial operations to be carried out Details
 
8Tender for procurement of complete cartridge assembly for boiler feed pump Details
 
8Tender for construction of soild waste management yard Details
 
8Tender for work of chemical washing of disc insulator strings of various 132kV & 220 kV lines Details
 
8Tender for supply of 66kV isolators at switchyard Details
 
8Tender for supply of various types of clamp for 220 kV switchyard Details
 
8Tender for rate contract for dismantling, lifting, shifting, overhauling & reinstallation of LT motors Details
 
8Tender for supply, erection, testing & commissioning of 66kV D/C line on M/C tower with ACSR panther conductor Details
 
8Tender for construction of control room foundations, cable trench Details
 
8Design, engineering, supply, erection including civil works, testing and commissioning of 11kV single circuit line Details
 
8Tender for miscellaneous civil maintenance works Details
 
8Tender for dismantling of existing transformers and the design, engineering, erection, civil works, testing, and commissioning of 31.5 MVA, 132/34.5 kV power transformers Details
 
8Tender for construction and renovation of sub-station Details
 
8Tender for upgradation/ renovation of lane and drain Details
 
8Tender for diversion of forest land for hydro electric project 81MW including Details
 
8Tender for supply of consumable items for maintenance at power house Details
 
8Tender for supply of material and related work for undergrounding of LT line Details
 
8Tender for renovation, reconductoring and restrengthening of 33 kV feeder Details
 
8Tender for procurement of GI earth pipe B class medium Details
 
8Tender for constructing additional circuit 11kV OH with covered conductor Details
 
8Tender for supply of 1.1 kV XLPE insulated 1Cx150, 1Cx120 and 1Cx95 sq.mm aluminium unarmoured cables Details
 
8Tender for construction of 8 km 110kV double circuit LILO line Details
 
8Tender for upgradation of 66kV substation Details
 
8Tender for constructing 11 kV OH line Details
 
8Tender for rate contract for repair and maintenance works pertaining to 400 kV D/CC transmission line Details
 
8Tender for fixing of rate contract for unforeseen restoration of civil works like protection walls, crate revetment, masonry drains etc pertaining to 400 KV D/C transmission line Details
 
8Tender for providing of services of PLCC and RTU automation engineers for checking/ repairing / rectification of PLCC and telemetry panels installed Details
 
8Tender for work of proximate and ultimate analysis of coal Details
 
8Tender for left over work of design engineering supply erection testing and commissioning of LILO of 220 kV D/C transmission line Details
 
8Tender for miscellaneous civil works Details
 
8Tender for supply of single-phase secondary set with variable frequency and voltage testing kits Details
 
8Tender for strengthening of tower foundation of tower no.63 of 220kV line Details
 
8Tender for supply, design, manufacture, testing, charging and delivery of 220 VDC and 200AH battery bank along with all accessories Details
 
8Tender for annual overhauling of unit 2 and 3, repair of various underwater parts Details
 
8Tender for biennial maintenance of sewer line works, repairing of pits etc. Details
 
8Tender for procurement of different steel items Details
 
8Tender for procurement of fasteners for overhauling job of coal mill, APH ducts, coal burner nozzle Details
 
8Tender for procurement of coal burner spares Details
 
8Tender for laying of 02 Nos. 3X400 Sq.mm. cable for making LILO arrangement Details
 
8Tender for procurement LT shackle hardware (metal parts) Details
 
8Tender for supply of 11kV polymer disc insulators Details
 
8Tender for work of erection of 66kV equipment, structures, control wiring, yard lighting Details
 
8Tender for ARC for laying of HT U/G cable Details
 
8Tender for supply, installation, testing & commissioning of conversion of 66kV line Details
 
8Tender for balanced work of supply, erection, testing and commissioning of additional 1 x 25MVA, 132/33 kV T/F along Details
 
8Tender for work of ash lifting of ESP Details
 
8Tender for supply, erection and commissioning of new street light poles with cable laying Details
 
8Tender for supply of 90/10 cupronickel condenser tubes Details
 
8Tender for job contract for works of attending daily/routine defects, preventive maintenance, shutdown & emergency maintenance of electrical auxiliaries Details
 
8Tender for supply, installation, testing & commissioning of conversion of 66kV line Details
 
8Tender for ARC for laying of HT U/G cable Details
 
8Tender for rate contract of excavation and laying of new power / control / telephone cables Details
 
8Tender for providing RCC chamber with protection wall Details
 
8Tender for work of supply and application of anti-corrosive paint/coating on external surface of various steel structures, pipelines Details
 
8Tender for work of complete o/h of MS & HRH strainers, HP&IP stop and control valves, TG bearings, H2 seal body, generator Details
 
8Tender for supply of I to P converters for 3 x 210 MW unit Details
 
8Tender for ARC for laying of HT U/G cable Details
 
8Tender for work of complete cleaning of boiler Details
 
8Tender for ARC for laying of HT U/G cable Details
 
8Tender for work of U/G 11kV 185/240/300 mm2 XLPE cable laying, fault finding and provide & fixing outdoor, indoor cable box & straight joint kit for work Details
 
8Tender for ARC for laying of HT U/G cable (SI scheme) work Details
 
8Tender for ARC for laying of HT U/G cable Details
 
8Tender for supply of various spares for SWAS system of boiler Details
 
8Tender for ARC for laying of HT U/G cable Details
 
8Tender for ARC for supply erection and commissioning of of GI cable tray Details
 
8Tender for supply of refrigerant gas mafron R-22 and R-134a in cylinders for air conditioning plants Details
 
8Tender for supply and replacement of NDCT components for 1x 800 MW unit Details
 
8Tender for annual maintenance contract AMC for ring main units Details
 
8Tender for providing and fixing of first 20 pole earthing Details
 
8Tender for providing and fixing of first 20 pole earthing of 11kV feeders Details
 
8Tender for supply and application of HVOF (high velocity oxy flame) thermal spray coating in various Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8
1,132 solar plants installed under MSSY across Uttarakhand Details
 
8Number of rooftop solar power plants in western MP crosses 82,000 mark, capacity reaches 500 MW Details
 
8Dilip Buildcon Agrees to Sell Stake in Under-Construction Power Transmission & Solar Projects to Alpha Alternatives Details
 
8Jupiter Wagons wins two BESS project from WBSEDCL Details
 
8Fuel shortage cuts power generation, increases load-shedding Details
 
8South West Pinnacle Exploration secures Letter of Award from CMPDI for coal exploration in Jharkhand Details
 
8Govt Asset Sales Hit 73% of FY27 Goal With Rs 58,154 Crore Realized Details
 
8GE Vernova Expands Wind Footprint in India With 163.4 MW Order Details
 
8Mayr introduces smart wind safety solutions at WindEnergy 2026 Details
 
8India's peak power demand rises 12% in April-June, evening supply gap widens to 3,045 MW: Govt Details
 
8India's Power Sector Revolution: 19.79 Crore Consumers to Get Smart Meters Details
 
8India Solar Power Generation Surges 45.9% in Q2 2026 Details
 
8Nuclear Ambitions: Building capacity for a low-carbon future Details
 
8Aluminium Conductors: Powering India’s Next Generation of Sustainable Energy Details
 
8NPCIL seeks financial autonomy as India accelerates nuclear power push Details
 
8Basudev Hansdah, CEO, Maithon Power Limited Details
 
8Tamil Nadu allocates Rs 15,828 crore for energy sector in 2026-27 budget Details
 
8RPSG Group’s Purvah Green to acquire 1.4 GWp operating solar portfolio for INR 4,859 crore from ReNew Details
 
8Against target of 500 GW by 2030, India registers 300 GW of non- fossil fuel electricity generation as on July 31, 2026 Details
 
8Parliamentary Panel Flags Underutilisation of Govt Funds for India’s Renewable Sector Details
 
8India Records Rs 26.75 Lakh Crore Investment Announcements In FY27 So Far Details
 
8MRF, TD Power and 6 Other Stocks Announcing Q1 Results Today to Look Out For Details
 
8India's Power Demand Hits 270.8 GW Record, Exposing Grid Bottlenecks Details
 
8India's Power Grid Braces for El Niño Supply Gap Through October Details
 
8India Needs 10-Fold Bus Fleet Expansion by 2047: Sector Outlook Details
 
8Sri Lankan MP Elayathamby Sreenath offers prayers at Sri Venkateswara Swamy Temple in Andhra Pradesh Details
 
8CESC Limited: Acquires 1.4 GWp Renewable Portfolio for Rs 4,859 Crore Details
 
You can also click on Newsclips for more Details

Daily Power Sector Tenders Excel update

Aug 11: 8Daily Excel covering new tenders and all published updates including corrigendum, amendment, addendum, clarification and status revisions, along with technical and financial bid opening, evaluation completion and final award actions including AOC and LOA issuance.
Click on Reports for more Details

More than 55,000 MW was outside the online fleet in CEA’s monitored snapshot - while generation still reached 98.2% of programme

Aug 10: 8CEA counted 55,674 MW unavailable across planned, forced and other outage categories while monitored stations still produced 98.2% of programme. The near-target output shows that the remaining fleet carried the day, but the outage burden narrowed the buffer against another large failure. Details

India has certified 78 green-steel units and advanced specialty-steel incentives - but neither measure yet proves how much cleaner steel is being produced

Aug 10: 8India has certified 78 green-steel units and advanced production-linked incentives for specialty steel, creating formal routes for cleaner and higher-value output. The policy architecture is moving, but the disclosed record still does not quantify how much certified low-emission steel has actually been produced or sold. Details

BCCL put a new 2.0 MTPA washery into operation and monetised another - but profit collapsed nearly 90% as production and offtake weakened

Aug 10: 8BCCL started commercial operation of the 2.0 MTPA Bhojudih washery and monetised the 2.0 MTPA Dugda washery through a long-term operating agreement. Those projects could lift domestic washed-coking-coal supply, but profit after tax fell from Rs. 1,240.19 crore to Rs. 128.28 crore as production, offtake and costs moved against the company. Details

Coal India spent Rs. 19,607 crore and added 100 MW of solar - but coal output fell to 768.19 million tonnes, 168.81 million tonnes below its own target

Aug 10: 8Coal India spent Rs. 19,607 crore and commissioned the 100 MW Patan solar project while expanding into critical minerals and a proposed 1,600 MW thermal venture. The diversification advanced, but coal production slipped to 768.19 million tonnes and missed the company’s 937 million-tonne target by 168.81 million tonnes. Details

PFC’s loan book reached Rs. 5.80 lakh crore and net NPAs fell to 0.15% - but annual sanctions dropped Rs. 75,094 crore as fresh commitments slowed

Aug 10: 8PFC ended 2025–26 with Rs. 5.80 lakh crore of loan assets, Rs. 20,051 crore of standalone profit and a net NPA ratio of 0.15%. Asset quality strengthened, but sanctions fell to Rs. 2.86 lakh crore from Rs. 3.61 lakh crore, making the pace and quality of new commitments the next growth test. Details

Inox Wind’s order book reached about 4.4 GW - but quarterly profit fell 34% as its shift toward equipment sales held income growth to 1%

Aug 10: 8Inox Wind reported an order book of about 4.4 GW in July, including a 500 MW firm group order and a 200 MW NLC award. The pipeline is large, but first-quarter profit fell 34% and management’s equipment-sales pivot has yet to show the promised improvement in later quarters. Details

Premier Energies lifted profit 53% and opened 5.6 GW of module capacity - but the new factory must convert nameplate scale into sustained sales and margin

Aug 10: 8Premier Energies raised quarterly profit by 53% and opened 5.6 GW of module capacity, expanding the manufacturing base behind its order pipeline. The new factory changes the company’s scale immediately, but earnings quality depends on utilisation, cell supply, pricing and sustained conversion of capacity into sales. Details

Hitachi Energy’s orders and revenue surged - while Rs. 1,841.66 crore of QIP money still sat unused

Aug 10: 8Hitachi Energy India reported sharp growth in orders and revenue while retaining Rs. 1,841.66 crore of QIP proceeds as unutilised at quarter end. The balance sheet can fund expansion, but the investment case now depends on converting record demand and idle capital into delivered capacity, cash and margins. Details

Amazon’s proposed Mumbai data-centre campus would demand 473 MW and install hundreds of backup generators - but it still lacks final environmental clearance

Aug 10: 8Amazon Data Services’ proposed Mumbai campus would require 473 MW of power and a large diesel-backup fleet across a multi-building development. The scale makes it a major new load, but the committee recommendation is not final clearance, grid sanction or proof of a contracted cleaner supply. Details

CESC’s 3 GW solar-cell plan won environmental clearance only for Phase I - leaving the second phase and construction approvals outside the gate

Aug 10: 8CESC Green Power’s 3 GW solar-cell proposal has environmental clearance for its first phase at Jewar, not for the entire factory. The approval moves a major manufacturing investment forward, but Phase II, construction permissions and operating execution still sit outside the cleared gate. Details

A Vemagiri bus fault cut about 1,150 MW of Andhra Pradesh load in 14 minutes - after overloaded transformers at another station also tripped

Aug 10: 8A Vemagiri bus fault removed about 1,150 MW of Andhra Pradesh demand for 14 minutes while overloaded transformers at another station also tripped. Supply returned quickly, but the scale of the loss shows how a local fault and stressed parallel equipment can combine into a statewide reliability event. Details

Gujarat’s renewable evacuation network suffered repeated single-path failures, including 800 MW and 540 MW losses - making redundancy the month’s unresolved risk

Aug 10: 8Gujarat’s renewable network recorded repeated single-path events, including losses of about 800 MW and 540 MW, across the month’s grid-event register. Individual protection operations may have worked, but the recurrence shows that several generation pockets still depended on evacuation arrangements that did not survive one credible failure. Details

Two simultaneous line trips cut about 130 MW across six Assam load centres - after another 220 kV route was already shut

Aug 10: 8During an approved shutdown of the BTPS–Rangia-I line, all six affected load centres were being supplied through the Sonabil–Depota and Sonabil–Ghoramari paths. Both lines tripped at 15:04, cutting about 130 MW until the network was restored, and turning a planned outage into a direct redundancy failure. Details

A Champa–Kurukshetra HVDC failure cut about 2,680 MW of transfer and triggered Punjab’s defence scheme - but Punjab’s recorded demand drop was about 252 MW

Aug 10: 8A measuring-card failure blocked two poles carrying about 2,680 MW and triggered Punjab’s feeder defence scheme, while the state’s recorded demand changed by about 252 MW. Protection limited the disturbance, but the gap between transfer loss and demand response shows why the event cannot be described as 2,680 MW of consumer load shedding. Details

Thirty coal plants were critical even with 37 million tonnes on hand - because the fleet held only 60% of its normative stock

Aug 10: 8Thirty plants were at critical stock even though total coal holdings reached 37 million tonnes, because the monitored fleet held only 60% of its normative requirement. The national pile therefore concealed plant-level exposure where location and delivery, not aggregate tonnes, determined security. Details

Contracting news for the day

Aug 10: 8Arunachal's Pathar Camp award carries two prices for the same bid, 19.0% apart Financial-opening proceedings record Techno Power at Rs 98.75 crore and Shyam Steel at Rs 119.57 crore; the BOQ comparative chart records Rs 82.98 crore and Rs 100.48 crore — the same 19.0% gap for both bidders. The award settles on the lower BOQ figure. Three of five bidders never reached price opening, falling on unsigned pages, missing OEM authorisations and EHV-licence gaps, leaving a 21.1% spread between the only two survivors. The portal and committee proceedings also cite two different NIT numbers for one tender ID.

8AVVNL's 110 MW rooftop tender now allocates a multi-lot winner's cheapest circle first, not its biggest Corrigendum No. 2 replaces descending lot quantity with ascending quoted price per unit as the allocation sequence — so a bidder that is L1 across several circles can have its highest-priced win displaced once the 20,000-consumer cap is reached. Turnover is tested at 30% of the total value quoted, making a five-lot bid a balance-sheet decision. Nineteen of the 25 technically admitted bids arrived only after the original deadline.

8Ukwa mine tender sets quantity variation at ±20% in one document and 25% in another The technical specification says "+/- 20%"; the GeM option clause permits 25% at issue and a further 25% post-award — a five-point gap across a four-year contract committing nine LHDs, 36 face drills and nine shotcrete machines. The GeM summary also reads "Arbitration Clause: No" while clause 48 sets out a sole-arbitrator regime with Nagpur jurisdiction. Corrigendum C5 declares itself to supersede all prior buyer-added terms.

8PVVNL's conductor tender qualified one bidder "as trial" while simultaneously coding it rejected The evaluation record shows "Rejected-Technical" alongside the remark "Techno Commercially qualified as trial" for the same participant — a status distinct from the seven bidders marked qualified as regular. What trial standing entitles that bidder to, whether its price bid opens, and how trial converts to regular are nowhere defined. Seven of nine reached the 6 August price opening on regular terms.

8JdVVNL's 110 MW rooftop tender makes MNRE guidelines override its own specification Clarification No. 1 states that where the tender's material specification conflicts with MNRE requirements, MNRE prevails — a compliance baseline that can move during a ten-year O&M term. The same package flips lot allocation from quantity-first to lowest-unit-price-first, swaps meter standard IS 14697 for IS 13779, and holds half the 10% performance security to year five and the balance to year ten.

8JVVNL's 18-lot rooftop tender lets a bidder's own price ladder decide which circles it loses Corrigendum No. 1 allocates successful lots in ascending order of quoted unit price, with a lottery in the Chief Engineer's chamber where price and lot quantity tie. Turnover is now tested against the lots actually quoted rather than the full Rs 627.50 crore estimate. The e-procurement record and the specification also carried different original technical-opening times — 3:00 pm against 5:00 pm — before the seven-day extension overrode both.

8NTPC's Rs 200 crore Kaniha ash contract ended with five identical contracts at 10.58% of base value All five awardees hold contracts of Rs 21.156 crore — a 0.0% spread across L1, L2 and L3 — because ranked bidders were invited to match the L1 price. The panel includes L1 through L4 and, unexplained, L9; L5 to L8 do not appear. Clause C's formula for calculating each bidder's cumulative cap against a five-member panel doesn't reconcile with the identical full-value contracts actually issued. Corrigendum C2 fixed a penalty clause that cross-referenced a nonexistent "Clause 16."

8UPNEDA's 40,000-light tender can extinguish a quarterly AMC payment if district verification doesn't happen in time The amended Clause 8.18 requires live RMS data to be verified by the district project officer each quarter and uploaded to RESIMS; failure causes that quarter's payment to lapse with no later claim — against a 15% retention released at 3% a year over five years. Corrigendum-1 separately disabled equalisation charging, which the original spec had mandated every 30±2 days on an LFP battery. Sixteen of 22 bidders cleared technical evaluation.

8BHEL's Bandhabal ASU tender doubled the power baseline used to load bids, from 400 kW to 800 kW The same amendment nets turbine-generated electricity against consumption before applying NPV loading over a 25-year life — so integration, not gross demand, decides evaluated L1. Qualification was cut in the opposite direction: the reference threshold fell from 1,000 TPD oxygen to 500 TPD, the window widened from 10 to 15 years, and required operating history halved to one year. Five closing-date extensions. A bidder's warning that simultaneous LOX and LIN vaporisation would breach the 10 TPH steam cap drew a request for figures, not a ruling.

8NHPC raised the generator performance coefficients on its Rs 641.11 crore Uri-I tender by 20.6% Both the bid-equalisation rate and the shortfall deduction moved from Rs 21.642 lakh to Rs 26.099 lakh and Rs 86.565 lakh to Rs 104.396 lakh — turbine figures rose 5.0%. Corrigendum No. 4 also replaced the cooling-water and HVAC chapters outright, rebased escalation indices from 2011-12 to 2022-23, added partial acceptance, and introduced a contractor-change route that pays nothing for rejected proposals. Deadlines have moved 32 days.

8JVVNL's 25,000-transformer tender withdrew the bid-security relaxation its own registered vendors previously enjoyed Appendix-A removes the Nigam-registration concession and resets performance security at 5%, with additional security where a bid falls more than 15% under estimate. L1 gets only 20% of the volume under the allocation ladder; 50% can go to firms outside the top four. Prior execution acts as a gate — a supplier under 50% delivered on an earlier order may find its bid unopened. Schedule-X prints a June 1 submission deadline for a tender published in August and closing 1 September.

8GETCO's Rs 94.87 crore HTLS tender pays more to bidders who refuse its advance Amended Clause 86.0 splits payment by financing choice: 90% progressive supply payment without the advance, less with it, and 80% versus 70% on erection RA bills — the advance carrying SBI MCLR interest against a 110% BG. Conductor losses are capitalised at Rs 1,60,000 per kW before reverse bidding starts, so the lowest percentage isn't automatically L1. RoW compensation moved to GETCO; RoW fieldwork stayed with the contractor. Security validity is written as "25 Months (60 Months + 01 Month)."

8CSPDCL's Atal Nagar batch bars Class III contractors from its Rs 1.37 lakh package while admitting them to the Rs 1.76 lakh one Only the 33KV isolator replacement at Mungi substation carries the tighter classification — the gate is voltage and operational risk, not value. All five packages share one deadline, one completion figure recorded simply as "30" with no unit stated, and a stated opening time identical to the closing time.

8TANTRANSCO's Rs 271.79 crore GEC-II substation limits escalation to transformers and reactors, and only on 90% of their cost Everything else — civil works, erection, freight, insurance, switchgear installation — stays firm across 24 months that expressly include rainy seasons, with the transformer adjustment itself capped at ±30%. Delay damages start softer than usual at 0.10% weekly, but can be calculated on the entire contract price where partial works can't be beneficially used. Unresolved level-3 ESHS non-conformity cuts interim certificates 33.3%, then 66.6%, then 100%. Guarantee obligations appear as 36 months in the payment documents, 60 months in the technical requirements and five years for ICTs in the Particular Conditions.

8APEPDCL called a hybrid pre-bid meeting for its Rs 143.32 crore SCADA tender one day before queries close Corrigendum-1 fixes the meeting for 18 August; the RFP keeps 19 August at 17:00 as the query cut-off, leaving roughly a working day to convert answers into formal clarifications on OEM responsibilities, field interfaces and FMS economics. The portal describes the meeting as offline while the corrigendum provides hybrid attendance. The BOQ separately requires five-year FMS charges to be at least 20% of SCADA project cost, with the annual figure identical across all five years.

8UPPTCL's conductor tender demands 10% performance security in the SBD and 5% on GeM — and says the SBD wins ITB 41.2 requires a CPBG of 10% of contract price including GST; the GeM page shows a 5% ePBG for 30 months, while BDS ITB 30 expressly gives the SBD precedence over GeM. The turnover threshold diverges the same way: Rs 224.82 crore in the BDS against Rs 56.20 crore on the portal. Positive IEEMA variation stops once supply runs past schedule even with an extension granted; negative variation continues.

8TPCODL halved its own GCC delay penalty on a Rs 44 crore substation conversion, then extended the liability tail to a decade Tender clause 7.1.7 sets LD at 0.5% weekly on unfinished work capped at 5%; the GCC position is 1% weekly on executed value capped at 10%. In exchange, the CPBG stays alive across a 78-month architecture and a five-year latent-defect warranty starts only after the 60-month guarantee ends. Clause 2.2 states there is no guarantee on quantity of job, with release orders issued only after substation-wise joint survey. Turnover requirement: Rs 100 crore against a Rs 44 crore estimate.

8OPTCL's Rs 102.39 crore Narendrapur cable tender can't agree with itself on how many stages it has The IFB describes a "single stage two part system"; the portal field reads "Stage: Two Stages" — a distinction that changes submission and evaluation mechanics for a bidder committing Rs 1.02 crore of EMD. The document-availability window also differs: the IFB closes it 6 July, the portal 8 July at 12:00, with tender closing at 14:00 the same day. The package bundles 132 kV underground cable with bay extensions at two live substations.

8JVVNL's 37-substation RDSS tender states nine months for completion in one part and 12 in another Part 1 gives one month for survey plus eight for execution; SCC GCC 8.1 and 8.2 give three months for commencement inside a 12-month total — and the contract hierarchy puts Part 3 above Part 1. The second 30% supply payment is conditioned on commissioning "a minimum one cluster," defined by electrification of rural households, inside a package that procures 33/11 kV substations. The technical specification also refers to supervision at substations "in state of Uttar Pradesh."

8RVPN's Dholpur line tender lists a bid amount of Rs 1.00 against a Rs 94.48 crore turnover requirement The portal field is economically meaningless beside a Rs 31.49 crore liquidity threshold and a 50 km single-order 400 kV execution test. Subsidiary, associate and subcontractor credentials don't count, and JV bidding is marked not applicable. OPGW installation runs predominantly live-line, with tower structural analysis and any resulting strengthening at no additional cost to the employer, plus a 99.9% availability target requiring a seven-person certified gang, a jeep and a Tata 407.

8NTPC REL extended its 540 MW Anantapur wind tender a day after the original deadline had passed Corrigendum-2 carries a 5 August timestamp; the original bid receipt closed 4 August, and the applicable deadline now reads 17 August. A WTG manufacturer may use only one qualifying route and, under the association route, back only one bidder — multiple participation can void all affected bids. Land acquisition, ROW, the external EHV line to the ISTS substation and ten years of comprehensive O&M all sit inside contractor scope. A 540 MW quote requires Rs 714.04 crore of average annual turnover.

8MPPMCL's 625 MW storage tender now closes six days after the opening date printed in its own schedule The portal header applies 10 August for bid receipt while the NIT table still shows the tender opening event on 4 August and document procurement closing 30 July — an 11-day extension layered over legacy dates never rewritten. Corrigendum-1 and Addendum #2 have both issued. Bid security runs Rs 2.20 lakh/MW across a BOO structure with VGF support and a reverse auction at the end.

8SJVN's 265 MW Haryana storage tender shows an addendum issued and no corrigenda at the same time Addendum #1 is flagged on the tender page while the portal separately records "No Corrigenda Issued," and the clauses it supplements aren't identified anywhere at NIT level. EMD scales with capacity at Rs 2.40 lakh per MWh rather than sitting as a fixed sum, and the Rs 15 lakh processing fee plus GST applies to each project. Degradation, augmentation, availability guarantees and PBG terms all sit outside the published notice. Details

Briefs - Signals to Watch

Aug 10: 8India’s grid frequency left the prescribed band for 21.1% of the day even as the daily average stayed near 50 Hz
8Eastern grid operators cut day-ahead demand error from 7.53% to 1.04% intraday - but only after the operating day began
8Every interstate schedule will carry a 3.62% transmission-loss adjustment this week - but the national factor says nothing about any single project’s efficiency
8Odisha’s hydro stations reported 18.6646 MU, but duplicated rows prevent the table from proving a larger fleet total
8PXIL’s real-time market touched the Rs. 10,000/MWh ceiling - then recorded no trades across the next five reports
8Grid-India’s next security-constrained schedule starts with low-cost generators - but the dispatch plan becomes real only if those units run in the assigned blocks
8Late SCED payments in the eastern region will now attract daily interest - turning settlement delay into a rising cost for every entity shown as payable
8Two states capped reverse-auction bids at Rs. 10,000/MWh - while Rajasthan’s notices left bidders without a ceiling
8POWERGRID’s proposed Mandsaur licence change has entered formal hearing - but the company cannot use the revised terms unless CERC approves them
8Hexa Climate has finished arguing for connectivity relief over land documents - but the project remains exposed until CERC delivers its reserved order
8Gadag Power’s 190 MW solar project has reached the order stage - but its deadline extension and transmission-charge waiver remain undecided
8ReNew’s 73 MW Solapur project keeps interim protection - while final connectivity relief waits
8A new party and affidavit have widened the Tumkur-II transmission case - but they deliver neither the licence nor the tariff the project ultimately needs
8Lakadia-B seeks to push its transmission deadline to November - but force majeure still needs regulatory acceptance
8Solar developers say inverters should qualify for GST-change compensation - but CERC has not decided whether the equipment fits the claimed tax category
8NTPC REL commissioned six more inverters and moved the project forward - but tariff, tax and deadline claims still determine what the delay will cost
8India has opened accreditation for carbon-market verifiers - but no agency can validate credits until BEE completes the approval process
8PSPCL has taken smart-meter reconnection out of local hands - but its order gives no timeline or count for consumers waiting to be restored
8Punjab’s discom wants another settlement window for defaulting consumers - but the regulator is asking why the existing recovery mechanism was not used first
8Haryana ordered utilities to answer renewable-supply claims on a deadline - but kept deviation-settlement relief outside the interim order
8KEC’s CRISIL ESG score rose by five points - but the filing shows no change yet in borrowing cost, orders or operating performance
8Refex’s promoters plan to move 30.94% of the company within their own group - changing the holding structure without bringing in an outside buyer
8Sarda Metals gained Four Star Export House status - but investors still lack any disclosed export, revenue or incentive benefit
8Nuvoco and Nu Vista lost their current appraisal path because mandatory mapping files were missing - forcing both limestone proposals back before any merits decision
8Svaryu Energy asked to surrender its Category V interstate trading licence
8NLC asked CERC to determine the 2024–29 input price for Barsingsar lignite
8AK Renewables wants financial-close and commissioning deadlines aligned with delayed connectivity Details

Projects and Clearances - Investment Advanced, Permissions Lagged

Aug 10: 8Coal-gasification bidders won flexibility on products and technology - but every project must clear the approval gate before an award can be issued
8Amanthin’s Mumbai data-centre expansion seeks 200 MVA and 123 large generators - but its Rs. 6,670 crore plan remains a conditional recommendation
8Mevasa’s bauxite proposal gained an EAC recommendation - but road strength, dump stability and wildlife safeguards remain conditions on the mine
8Jhamarkotra’s phosphate expansion could not clear appraisal - because two foundational land and survey records remain unresolved
8Star Cement can study a 12 MTPA limestone mine - but the ToR does not permit mining
8Hindalco and Ambuja lead a 13-project industrial agenda worth watching - but every proposal still awaits the committee’s merits decision
8SECI is searching for dependable CO? supplies for green urea and methanol - but the exercise offers no tender, buyer or financial commitment
8TERI says solar heat can produce steam for about Rs. 1.20 a kilogram and pay back quickly - but industry still lacks the mission needed to overcome upfront risk
8Anant Raj’s Sonipat IT park would require 26 MW and 36 MVA of diesel backup - but its proposed solar capacity equals only 3% of sanctioned load
8Radiance’s Gurugram cyber park cut its planned load to 8.947 MW - but still pairs the project with large diesel backup and only 269 kWp of solar Details

Corporate Growth and Finance - Scale Expanded, Execution Risk Remained

Aug 10: 8Vikram Solar shipped more modules and lifted revenue 38% - but EBITDA nearly halved as margin fell to 8%
8Northern Coalfields selected only 545 people for 906 apprentice places - leaving 361 training positions unfilled
8Quality Power’s Rs. 19,455 million order book backs strong Q1 profit - but two capacity projects are still in installation and trial stages
8Reliance’s two Jamnagar battery units represent Rs. 3,162 crore of investment - but no ACC incentive had been claimed
8India counted 52,718 EV charging stations - but the government cannot say how many are fast chargers
8GK Energy crossed Rs. 15,325 million of annual turnover - but its Rs. 541 crore order book still has to convert into commissioned systems
8Batteries generated almost two-thirds of HBL Engineering’s quarterly segment revenue - concentrating growth in one business while electronics supplied the balance
8Bajel won a 765 kV interstate line worth at least Rs. 400 crore - but disclosed only a band and a 33-month delivery clock
8Refex can halve a solar loan exposure under a proposed settlement - but payment and legal withdrawals are still conditions
8L&T won ONGC work on subsea pipelines and four offshore platforms - but the Rs. 5,000–10,000 crore value band hides the exact contract economics
8GR Infraprojects led a Rs. 91.60 crore Varanasi logistics-park bid - but a 45-year concession starts with contract and finance risk
8Bajel plans to nearly double tower capacity even as quarterly revenue fell - betting Rs. 170 crore that margins can recover
8Inox Green’s profit rose 86% and a 4.5 GW wind-service acquisition cleared the tribunal - but the portfolio is not fully owned or consolidated yet
8Ola Electric cut operating losses but reversed a Rs. 57 crore provision without ministry approval - keeping the audit qualification alive
8Panasonic restarted dispatches after its Pithampur fire - but the damage is still unpriced and a battery-waste obligation remains unprovided
8NLC’s group generation rose 25% - but profit before tax increased only 9.76%
8IMP Powers multiplied quarterly revenue but still lost money - while auditors say old receivables and assets may be overstated
8Urja Global’s auditors flagged Rs. 34 crore of unreversed tax credits - alongside Rs. 42 crore of ageing receivables
8Anboto Solar says its supply deadline slipped because the ISTS substation was not ready - but status quo protects the project only until CERC decides the delay claim
8Power Mech proposed up to one million employee options at 10%–25% of market price - but shareholders and regulators still have to approve the plan
8Urja Global’s board opened a route to raise up to $500 million - but shareholders have not approved it and no instrument or price has been fixed Details

Regulation and Access - Relief Was Sought, Decisions Stayed Conditional

Aug 10: 8Load despatch centres seek 85% provisional fee billing - but CERC has not authorised the cash flow
8BALCO faces a Rs. 48 crore damages claim from TANGEDCO - but liability is frozen behind a pending review
8Korba Power seeks Rs. 36.88 crore for ash transport and surcharge - but none of it has been awarded
8GETCO listed 800 possible renewable connections - but warned that planned substations may never arrive
8Government support erased Andaman’s approved revenue gaps on paper - after the regulator found Rs. 1,613 crore across two years
8Haryana discoms want to postpone monthly fuel adjustments and recover them with interest - but the regulator demanded the full backlog first
8Two renewable projects want their connectivity clocks moved because the Koppal-II network may not be ready until 2027 - but neither extension has been granted
8Two discoms say Kreate Energy failed to return banked power and want its trading licence revoked - but an appellate status-quo order has frozen the regulatory hearing
8PSPCL approved a 15% wage rise across PESCO worker categories - but the new rate raises the utility’s outsourced labour bill before efficiency gains are known
8PSPCL can now cancel energy bills and optionally reverse late-payment interest - but larger corrections require progressively higher approval
8Goa–Tamnar wants its transmission deadline extended and force-majeure costs compensated - but the regulator has not accepted either claim
8Osmanabad Solar wants four months of 2022 power bills paid - but CERC has not ruled on who must correct the scheduling record
8IL&FS Tamil Nadu says Section 11 benchmark energy charges remain unpaid - but CERC has only opened the merits hearing
8KSK and southern discoms remain locked over 2013 capacity and transmission charges - but the 13-year-old disputes still have no merits ruling
8NHPC wants consumers to fund a 1997 pay-anomaly correction ordered in 2024 - but CERC has not admitted the cost to tariff
8DNH and Daman & Diu seek legacy gas, capacity and imbalance charges for 2006–12 - but the reopened dispute has no liability finding
8SEIL seeks fixed charges for 150 MW it says was available - but Andhra counterparties have not been ordered to pay
8SEIL wants June–July 2022 invoice deductions repaid with surcharge - but CERC has not decided that Telangana’s withholding was wrongful
8Adani Solar says long-term transmission charges are not its liability - but CERC has not allocated the cost Details
  • Aug 12: POLICY AND SYSTEM PLANNING - RELIEF, INVESTMENT AND CAPACITY CLAIMS MEET THEIR IMPLEMENTATION LIMITS:Details
  • Aug 12: REGULATION AND DISPUTES - PETITIONS SEEK MONEY OR RELIEF THAT ORDERS HAVE NOT YET AWARDED:Details
  • Aug 12: STORAGE AND HYDRO - ANNOUNCED CAPACITY STILL WAITS FOR AWARDS, CLEARANCES AND OPERATING EVIDENCE:Details
  • Aug 12: DISTRIBUTION AND CONSUMERS - DIGITAL INVESTMENT EXPANDS FASTER THAN PROOF OF SERVICE IMPROVEMENT:Details
  • Aug 12: COMPANIES AND FINANCE - GROWTH VISIBILITY MEETS HYDROLOGY, CREDIT AND ACCOUNTING RISK:Details
  • Aug 12: COAL AND TRANSITION - LOWER IMPORTS AND NEW LOGISTICS MEET OUTPUT, FUEL AND CONVERSION CONSTRAINTS:Details