All content in this website is sourced legitimately

Archives


All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.


Aug 2025

 For reference purposes the website carries here the following tenders:
 8Design, supply, installation and commissioning of 1000 LPD capacity and 1500LPD capacity of solar water heating system Details
 
8Tender for retro fitting of 33 kV over current earth fault relay and master trip relay for various Details
 
8Tender for construction of 02 No. 132 kV bay at 132 kV sub-station Details
 
8Tender for supply of 100MVA, 220/33kV power transformers Details
 
8Tender for repairing and retubing of H2 cooler of generator Details
 
8Tender for installation of 1X3.15 MVA additional PTR at 33/11 kV S/s Details
 
8Tender for supply of type II transformer oil Details
 
8Tender for fixing of rate contract for unforeseen restoration of civil works Details
 
8Tender for overhauling of boiler 9 and its auxiliaries Details
 
8Tender for supply, installation, testing and commissioning of online continuous fixed type hydrogen gas leak detector Details
 
8Tender for R&M works of 132kV substation Details
 
8Tender for supply of cuplock scaffolding for 600 MW BHEL boiler Details
 
8Tender for sub-station and transmission line Details
 
8Tender for supply of 100 sets 11kV stand alone complete set Details
 
8Tender for manufacture and supply of 25,000Kg of 7/2.5 mm GI stranded wire Details
 
8Tender for manufacture and supply of 7/2.8 mm GI stranded wire Details
 
8Tender for supply of 22kV stand alone complete set Details
 
8Tender for procurement of ELC electrostatic liquid Details
 
8Tender for replacement of battery charger Details
 
8Tender for supply, erection & commissioning of complete hydrastep system Details
 
8Tender for erection, maintenance and dismentalling work of overhead HT/LT line Details
 
8Tender for additional 1 No 5 MVA power transformer Details
 
8Tender for supply of numerical transformer protection differential relays Details
 
8Tender for supply of transformer structure materials Details
 
8Tender for additional 1 No 5 MVA power transformer Details
 
8Tender for refurbishment of in-situ high pressure valves in turbine Details
 
8Tender for erection, maintenance and dismentalling work of overhead HT/LT line Details
 
8Tender for insurance of power houses  Details
 
8Tender for special estimate to create 132kV bay for feeding additional 20/25mva 132kV T/F at 132kV S/Stn. Details
 
8Tender for work of erection of 66kV equipment, structures, control wiring, yard lighting etc. Details
 
8Tender for bienniel civil maintenance Details
 
8Tender for procurement of spares for diaphragm valves of various sizes installed Details
 
8Tender for assistance in carrying out miscellaneous routine and shutdown maintenance works of 400 kV substation Details
 
8Tender for procurement and installation of 33 kV GIS bay modules at 220 kV GIS substation Details
 
8Tender for replacement of ACSR conductor by covered conductor of 11kV feeder Details
 
8Tender for dismantling, fabrication and renewal of worn out 300 NB M.S seamless pipe and providing cement pedestal from clarified water pump house Details
 
8Tender for replacement damaged RCC gantry structures 230kV power grid switching Details
 
8Tender for dismantling, fabrication and renewal of worn out 300 NB M.S seamless pipe Details
 
8Tender for supply of HT cable Details
 
8Tender for work of providing service of online oil purification / filtration of servo mesh SP-320 oil of coal mill Details
 
8Tender for upgradation of 66kV substation Details
 
8Tender for construction of 400kV GIS substation Details
 
8Tender for selection of suitable consultant for the preparation of pre-feasibility report, detailed project report Details
 
8Tender for repair/reconstruction of damaged RCC panels Details
 
8Tender for rate contract for execution of various planned and emergancy works Details
 
8Tender for protection work to prevent landslide Details
 
8Tender for repair/reconstruction of damaged RCC panels at various Details
 
8Tender for survey work for rail track alignment Details
 
8Tender for stringing and sagging of 2nd ckt on existing 66kV SC on DC line Details
 
8Tender for rebabiting of generator guide bearing pads and thrust bearing pads Details
 
8Tender for work of erection of new 66kV S/C line Details
 
8Tender for erection work of 66kV LILO line Details
 
8Tender for renovation of control room, yard and miscellaneous civil works at 33 kV s/s Details
 
8Tender for repair of submersible pump for various 33 kV s/s Details
 
8Tender for const. of 33 kV S/S Details
 
8Tender for work for repair of bearing Details
 
8Tender for annual maintenance contract for annual shutdown, operation and routine maintenance works of generator, generator transformer Details
 
8Tender for overhauling of 11/0.4kV transformer of different capacity Details
 
8Tender for retubing of tube nest of cooler of 6.6, kV 3500KW BFP motor using new tubes Details
 
8Tender for supply of various types of copper FRLS cables  Details
 
8Tender for supply, installation, commissioning and testing of numerical feeder protection relay Details
 
8Tender for replacing existing railing on stair case of power house Details
 
8Tender for sub-station and transmission line Details
 
8Tender for strengthening of strata and ground improvement works Details
 
8Tender for work of MRI OF KCC, STW, solar Details
 
8Tender for supply & installation of cassette type air conditioning unit 2 ton Details
 
8Tender for annual maintenance contract for DGA testing of T/F oil Details
 
8Tender for annual contract for transportation of material atvarious substations Details
 
8Tender for work of tower earthing of various of 220/132/110kV EHV line towers Details
 
8Tender for work of supply of equipments/ material, erection, testing and commissioning for installation of new 1x125MVAR 400kV bus shunt reactor Details
 
8Tender for procurement of battery chargers and DCDB against replacement of existing battery chargers Details
 
8Tender for establishment of 22kV GIS bays 12 feeders Details
 
8Tender for work of replacement of equipments& other misc. various works of 220 kV / 400 kV switchyard Details
 
8Tender for replacing of damaged sheet of boiler feed pump Details
 
8Tender for work of drawl and supply of water Details
 
8Tender for repair, maintenance, and installation of plant/ systems/equipments Details
 
8Tender for BRC for work of operation & maintenance of vacuum based ash handling plant Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8Domestic coal prices in India rise w-o-w on tight stock availability Details
 
8Ather Energy unveils new 2W platform for next generation of e-scooters Details
 
8Solar Project, Giga Factory, and Biofuels and more –All About Reliance’s Green Push Details
 
8Hitachi energy India announces 300 crore investment in Mysuru manufacturing facility Details
 
8PIGL Secures 9.50 crore contract for 5 MW solar project from Sadashiv Projects Details
 
8IOC Invests Rs 1.66 Lakh Cr for Growth Details
 
8Phoenix Mills Expands into Renewable Energy with Strategic Acquisition Details
 
8With 250 GWh battery requirements by 2030 and a current capacity of 50 GWh – can India bridge the EV power gap Details
 
8Row erupts over move to privatise power sector in Puducherry Details
 
8Mega order: Adani Power bags Rs 10,500 crore project to build 800 MW plant in Madhya Pradesh Details
 
8From field to fryer: Why India’s fastest-growing food sector needs more people power Details
 
8Incentivise private sector in nuclear power generation Details
 
8Torrent Power secures Rs 22,000 crore LoA for 1,600 MW coal-based thermal power project in Madhya Pradesh Details
 
8PSU metal stock jumps after JV with Coal India & NTPC for its 30,000 Cr Expansion project Details
 
8Maharashtra ranks first in State Energy Efficiency Index 2024 Details
 
8NTPC CMD honoured with leadership excellence award by the President Details
 
8Incentivise private sector in nuclear power generation Details
 
8ASCI, Power Foundation ink MoU for collaboration in power sector Details
 
8From field to fryer: Why India’s fastest-growing food sector needs more people power Details
 
8NALCO to Invest $3.43 Billion in Smelter and Power Plant Details
 
8Impacts of India’s coal sector Details
 
8Gautam Adani's company to set up thermal power plant in THIS Bihar district Details
 
8Adani Power gets LoA for 2400 MW greenfield thermal power plant in Bihar Details
 
8THDC India's Khurja power project achieves synchronization milestone Details
 
You can also click on Newsclips for more Details
Coal linkage extension raises questions in SCCL's tariff model
8As Bridge Linkage extends, tribunal evaluates SCCL's premium practices, influencing future tariff models and regulatory frameworks.
Open access dilemma: Rajasthan's surcharge sparks industry uproar
8The tribunal's review of Rajasthan's surcharge on open access power raises pivotal questions about state regulatory practices and economic impacts on large-scale industries.
Force majeure exceptions outlined in Madhya Pradesh’s updated power indices
8MPERC’s updated reliability standards account for force majeure events, offering DISCOMs flexibility amid natural and operational disruptions.
NHPC’s Parbati projects stall due to vendor identification woes
8NHPC's Parbati projects face delays in communication channel upgrades, hindered by vendor selection for challenging terrains.
8Completion is now pushed to January 2026, raising operational concerns.
Adani Green Energy incurs modest Rs.182 charge amidst extensive energy exchanges
8Despite extensive activity, Adani Green Energy faces minimal charges this week, indicating efficient energy exchange management and regulatory compliance.
Click on Details for more
Details
   For reference purposes the website carries here the following tenders:
  
8Tender for construction of 220/132kV, 1X160 MVA & 132/33 kV, 1x50 MVA GSS Details
  
8Tender for construction of various 220 kV & 132 kV transmission lines Details
  
8Tender for construction of 220/132kV, 160 MVA transfomer Details
  
8Tender for construction of various transmission line Details
  
8Tender for annual overhauling of machine power house Details
  
8Tender for annual overhauling of machine Details
  
8Tender for manufacture galvanizing testing and running supply of 220 kV and 132 kV transmission line Details
  
8Design, engineering, manufacturing, testing, supply, stringing, installation testing commissioning etc for construction of 132 kV TSS line Details
  
8Tender for overhauling of air pre-heaters Details
  
8Tender for work of round the clock electrical maint and other works Details
  
8Tender for supply of industrial ethernet switches for various sub-stations Details
  
8Tender for contract for R and M of transit camp at 400 by 220 kV substation Details
  
8Tender for procurement of 24 A and 100A DCPS Details
  
8Tender for supply and retro-fitment of auto reclose relay of 400 kV substation Details
  
8Tender for supply and installation of VMS system Details
  
8Tender for procurement of OPGW hardware fittings and accessories Details
  
8Tender for rate contract for supply of various size of LT aerial bunched cable Details
  
8Tender for rate contract for supply of various capacities of VRLA (SMF) battery bank Details
  
8Tender for contractor for survey, installation, testing and commissioning of new 5 MVA 33/11kV substation Details
  
8Tender for award of contract for system strengthening works for survey, installation, testing and commissioning of new 5 MVA 33/11 kV substation Details
  
8Tender for annual work contract for material handling Details
  
8Tender for work contract for refurbishment of damaged/worn out coal feeder chute assembly installed Details
  
8Tender for annual maintenance of 04 four nos of generating units Details
  
8Tender for work of providing second PT source for 132kV and 33kV voltage level at various Details
  
8Tender for work of safety related and miscellaneous fabrication & erection work of M.S. platforms Details
  
8Tender for work of complete overhauling and dry out work of 20 MVA 16.5/6.9KV power transformer Details
  
8Tender for supply of various consumable item Details
  
8Tender for supply of 6.6kV,671KW,HT motor for secondary coal crusher Details
  
8Tender for supply and commissioning of thyrister package AC system Details
  
8Tender for work of overhauling of ESP Details
  
8Tender for Bi-ARC for work of shifting//height raising of various 66 kV existing transmission lines Details
   
8Tender for erection of 66 kV S/C line from 132 kV SS Details
   
8Tender for roof replacement, compound fencing and other allied civil works Details
   
8Tender for work of flue gas and air ducting and damper Details
   
8Tender for overhauling of pressure part Details
   
8Tender for rate contract for two (02) years of spares of pumps installed Details
   
8Design, engineering, erection, testing and commissioning of floating system arrangements for 14 MW(AC) grid tied floating solar PV plant Details
   
8Design, engineering, supply, installation and commissioning of 750TPH capacity coal re handling circuit Details
   
8Tender for construction of RCC abutments with wing walls and allied civil works Details
   
8Tender for rate contract for strengthening pipes Details
   
8Tender for electrical work related to revamping Details
   
8Tender for providing railing and drainage work Details
   
8Tender for requirement of spares parts of pump installed Details
   
8Tender for procurement of various pumps spares and miscellaneous items Details
   
8Tender for procurement of lower bush housings for 76 MW turbines Details
   
8Tender for procurement of electrical spares for auxiliary Details
   
8Tender for procurement of rotating shaft Sleeve for 76 MW turbines Details
   
8Tender for supply and erection of SS 304 3 mm thick seal plates size 2150 and 1000 and 3mm for conveyor Details
   
8Tender for supply of finned economizer coil ‘J’ bend Details
   
8Tender for supply of tubular type lead acid stationary batteries Details
   
8Tender for fabrication & erection of bunker partition plate, side wall, support & structure for coal mill Details
   
8Tender for work of providing and fixing of LED lights Details
   
8Tender for work of providing and fixing of LED lights in switchyard Details
   
8Tender for work of second circuit stringing on 132kV line Details
   
8Tender for work of replacement of rusted 132kV & 33kV gantry structure, equipment structure Details
   
8Tender for supply of pressure parts tubes and bends for 210 MW capacity boiler Details
   
8Tender for replacement of generator hot air cooler body with new ones Details
   
8Tender for SITC of nitrogen injection firefighting system for fire prevention system of 2OMVA transformers Details
   
8Tender for revamping of HP 803 milling system Details
   
8Tender for RCA for reconditioning and testing of 33/11 kV power transformers Details
   
8Tender for empanelment of agencies for additional /augmentation of PTR at existing 33/11 kV S/s Details
   
8Tender for award of contract for system strengthening works for survey installation testing and commissioning of new 5 MVA 33 11kV substation Details
   
8Tender for purchase of complete assembly of 8 jet pump Details
   
8Tender for annual rate contract for procurement of critical category bearings Details
   
8Tender for work related to replacement of existing decayed AB cable Details
   
8Tender for work related to replacement of existing decayed AB cable/ weasel conductor to LT AB cable Details
   
8Tender for AMC work of oil filtration/ drying out of various EHV TFs & ICTs available Details
   
8Tender for supply of limestone for wet limestone-based flue gas desulphurisation (FGD) plant installed Details
   
8Tender for supply, erection, testing and commisioning of new 33/11kV SS Details
   
8Tender for supply of 1200 mm dia CWP discharge butterfly valve motor Details
   
8Tender for supply of 600 NB SS Details
   
8Tender for erection maintenance and dismentalling work of overhead HT/LT line Details
   
8Tender for capital work of 110kV substation Details
   
8Tender for horticulture development maintenance work Details
   
8Tender for biennial rate contract for civil maintenance Details
   
8Tender for modification work of 220kV D/C line Details
   
8Tender for requirement of spares for ash water clariflocculator installed Details
   
8Tender for routine/breakdown maintenance of HT/LT power and control cables Details
   
8Tender for supply of electrical and control and instrument items Details
   
8Tender for construction of 110 kV substation Details
   
8Tender for supply and delivery of XRF analyzer Details
   
8Tender for procurement of current transformers (33kV) Details
   
8Tender for procurement of current transformers Details
   
8Tender for procurement of 300 KL EHV grade transformer oil. Details
   
8Tender for fabrication galvanizing testing supply and delivery of two 02 nos of 50 meter Details
   
8Tender for service contract for repairing of air/flue gas duct Details
   
8Tender for biennial RC for repairing of coal bunker Details
   
8Tender for replacement of goose neck panel and bends Details
   
8Tender for procurement of (01) one no 6.6 kV, 1575 KW PA fan motor Details
   
8Tender for replacement of ACSR dog conductor by 33 kV AAAC AL-59, 241 sqmm. covered conductor Details
   
8Tender for replacement of ACSR dog conductor by 33 kV AAAC AL-59, 241 sqmm Details
   
8Tender for procurement of castable and plastic refractory for boiler Details
   
8Tender for supply of heat resistance conveyor belt size Details
   
8Tender for operation and maintenance power house Details
   
8Tender for supply, erection, commissioning and testing work of high mast tower having LED lights Details
   
8Tender for supply of various sizes of M S ERW pipes for ash handling plant Details
   
8Tender for supply of various rubber gaskets and rubber items Details
   
8Tender for supply of various impact pads for conveyor belts Details
   
8Tender for work of erection and strengthening of H-frame lines for DOG to HTLS conductor conversion work Details
   
8Tender for supporting work for coal rake unloading and various emergency work in coal handling plant Details
   
You can also click on Tenders for more
   
For reference purposes the website carries here the following newsclips:
  
8Promoting renewable energy Details
 
8Power stock jumps after securing 173 Cr order for wind turbine converters and electrical cabinets Details
 
8ABB India Bags Rs 174 Cr Order from Siemens Gamesa Details
 
8PFC, JBIC sign 3,500 cr loan pact to fund clean energy projects in India Details
 
8Renewable energy transformers market: the bedrock for clean power consolidation Details
 
8Why Waaree energies share price is rising Details
 
8Sunsure Energy, NVVN Ink first-of-its-kind 500 MWh BESS deal at Jhansi’s garautha substation Details
 
8Andhra Cements Commissions 6 MW Solar Power Plant at AP Facility Details
 
8Jakson Engineers to invest Rs 8,000 crore in Madhya Pradesh Details
 
8New SECI chief could change the energy game for manufacturing Details
   8
Power sector to require 3 trn investment in 5 years: Praveer Sinha Details
   
8Meenakshi Energy announces full operationalisation of 1000 MW thermal power plant in Andhra Pradesh Details
   
8How Renewable energy Is reshaping India’s business landscape Details
   
8Adani Power bags LoA for 2,400 MW ultra supercritical greenfield plant in Bihar Details
   
8Power stock in focus after receiving order for inter-state transmission project Details
   
8Decade after Kudankulam rift, CPI(M) in Kerala eyes thorium to ease power crisis Details
   
8BS Infra Summit: Clean energy's rise doesn't dent fossil fuel dominance Details
   
8India's renewable energy target hinges on open access to industries Details
   
8Wind to Command bigger role in power market as renewables share surge: suzlon’s Girish Tanti Details
   
8Vedanta’s Meenakshi energy: powering India’s energy revolution Details
   
You can also click on Newsclips for more Details
8Find a snapshot of thermal, hydro, pumped storage,
solar, wind, BESS and T&D contracts related updates for the day
Click on Reports for more Details
8None of the major T&D OEMs appear among the admitted bidders The mid tier crowd will therefore set pricing and execution benchmarks This absence could reshape competitive dynamics. Details
No takers for Ladakh’s solar - BESS even after four extensions
8The Union Territory’s plan for a 7MW PV and 9MWh storage plant at Stakna was abandoned after successive deadline pushes failed to yield a single bid.
Three REC schemes mirror the same pattern — state, REZ and inter - regional tenders all delayed again
8Despite differing technical scopes the extension trend is uniform REC is signalling consistency in bid management even at the expense of speed This emerging norm may reshape how contractors plan resources. Details
Hydro tender delays mirror national Himalayan trend  —  NEEPCO/Tato II
8NHPC SJVN and UJVN projects have all seen similar extensions NEEPCO’s Package III fits the broader pattern of risk laden hydro bids The cumulative effect could reshape EPC bidding norms for Himalayan projects.
Extension cycle signals unresolved clauses in storage procurement
8Without adjustments in PQCs or commercial scaffolding bidders seem reluctant to commit VGF clarity and performance guarantees remain sensitive points Unless addressed the bid risks thin competition. Details
NHPC’s Dulhasti Stage  -  II extensions reflect wider hydro procurement slowdown
8Multiple Dulhasti packages have seen schedule slips in recent months This aligns with broader Himalayan hydro risk aversion Whether NHPC adapts its timelines structurally is now the larger policy signal.
Potential low participation risk looms  —  DVC Konar floating solar
8Frequent extensions often reflect weak initial participation Float technology dependence narrows the qualified vendor pool The tender could end up with thin competition if barriers persist Details
Contractors gain time, but governance credibility takes a hit  —  RVPN
8Extra days may help bidders fine tune offers. Yet the repeated deferrals erode predictability of RVPN’s tender calendar. This trade off may weigh on future bidder appetite.Policy target of December 2025 saturation at risk  —  SJVN rooftop scheme
8MNRE wants all government rooftops covered by year end 2025. This 2.4MW slice is already two months behind. Schedule compression may now become unavoidable. Details
NTPC coal transport package removes exemptions for startups and MSMEs
8Unlike some NTPC packages no relief is offered on PQC or turnover. Only established logistics contractors can compete. This could limit participation but ensures experienced handling.
Unclear tariff escalation exposes bidders to volatility  —  RVUNL
8The Rs.12150 crore Barmer package has been delayed by nearly three months with bid security raised to Rs.40.5 crore. The RFP lacks clarity on how lignite mining cost escalations will be treated. Without a pass through bidders remain exposed to unhedged risk. This ambiguity could inflate tariff quotes. Details
8RTM prices track bid imbalance with one-block memory
On 2025-08-28, the RTM MCP co-moved tightly with the sell/purchase bid ratio (|ρ|≈0.91 at T1–T96; stays ≥0.62 out to an 8-block lag).
Inference — The simple bid-imbalance ratio explains most intraday price variance, and its predictive power persists at 1–8 blocks.
Why it matters — A ratio monitor can anticipate Rs/kWh swings before MCP turns, improving hedge timing for large buyers
8Ancillary skew: pull-down energy dwarfed up-reserve
On 2025-08-28, TRAS down energy was 51,807 MWh versus 3,865 MWh up — ~13.40× larger.
Inference — System balancing leaned heavily on downward tertiary actions, with SRAS broadly symmetric (6,218 MWh up; 6,695 MWh down).
Why it matters — Persistent down-reserve dependence can compress peak RTM risk but raises curtailment/redispatch exposure for flexible fleets.
8Frequency tails persisted despite minimal transfer-stress
On 2025-08-28, average frequency was 50.006 Hz with 4h57m outside 49.90–50.05; excursions: 171 (>50.03) and 163 (<49.97).
Inference — With only ER→NR showing ~1 hour of ATC violation and zero (N-1) breaches, tails are more about balancing than corridor binds.
Why it matters — Reserve placement (and AGC participation) needs tightening in tail windows, not just during inter-regional constraints.
8SCUC favoured low-ECR stacks; high-ECR sidelined
For D: 2025-08-29 (published D-1), SCUC “YES” units had median ECR 326.95 paise/kWh vs 376.70 paise/kWh for “NO”; ≥350 paise share: 36% (YES) vs 74% (NO).
Inference — Selection skewed toward cheaper coal stacks on the merit-order, consistent with cost-containment of ancillary uplift.
Why it matters — Higher-ECR units face thinner ancillary revenues; bids need recalibration or alternate flexibility products.
8Stockpiles surged at a north plant while output lagged
On 2025-08-28, one large northern station held 175% of normative coal stock while running at ~40% PLF.
Inference — Logistics/technical constraints (not coal availability) limited dispatch despite comfortable inventory.
Why it matters — Working capital is tied in stock without MW returns; plant-level fixes beat system-level supply pushes here.
8Voltage stress was concentrated, not systemic
On 2025-08-28, the Nizamabad 765 kV bus spent 20.07% of time outside the IEGC band (Max 806 kV; Min 783 kV; Avg 795 kV).
Inference — Local VAR/compensation needs dominate; broad ATC upgrades would miss this hotspot.
Why it matters — Targeted reactive support (STATCOM/SVC/tap optimisation) can remove a persistent reliability weak-link at lower cost.
8Evening two-step spike, late-night cliff in RTM
RTM MCP jumped by ~Rs 6,419/kWh across T74→T76 (18:15–19:00), then fell ~Rs 5,480/kWh at T88→T89 (21:45–22:15).
Inference — Rapid regime shifts are clustered, creating short windows of extreme price risk around the evening peak and late-night unwind.
Why it matters — Portfolio buyers should split cover and pre-place bids; single-shot hedges risk slippage across step-changes.
8Four RTM blocks cleared at ≤Rs 1.00/kWh
On 2025-08-28, blocks T33–T34 (08:00–08:30) and T53–T54 (13:00–13:30) printed Rs 0.50–1.00/kWh equivalents (Rs 49.98–99.61/MWh).
Inference — Mid-morning and early-afternoon oversupply windows opened briefly despite strong evening scarcity.
Why it matters — Buyers can bank cheap energy for PSP/thermal displacement; sellers need curtailment mitigation in these micro-valleys.
Click on Details for more
Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8Coal and Coke
8LPG
8Ammonia
8All tankers
8Bulk and Dry cargo
Click on Reports for more. Details
8The package size is significant in the transmission space. Only a handful of vendors can mobilise at this level. Financial depth may shape the final shortlist. Details
  For reference purposes the website carries here the following tenders:
 
8Tender for AMC for SWAS analyser, cooling tower system Details
 
8Tender for supply of different type of cables Details
 
8Tender for overhauling of cooling water pumps Details
 
8Tender for renovation and modernization of electrical components i.e. motor, brake assembly, control panels Details
 
8Tender for drilling work for geotechnical investigations and associated testing Details
 
8Tender for replacement of DTR cable Details
 
8Tender for replacement of DTR cable for smart metering Details
 
8Tender for balance work of construction of 220kV S/s Details
 
8Tender for supply of HT cable Details
 
8Tender for supply of 1.5/2.0 ton capacity split A.C installed at various Details
 
8Tender for augmentation of PTR at existing 33/11 kV S/s, HT lines Details
 
8Tender for estimate for installation of 1x5.00 MVA additional PTR Details
 
8Tender for outsourcing of operation and maintenance of PDFAC system Details
 
8Tender for establishment of new 33/11 kV outdoor substation Details
 
8Tender for sale of ferrous and non ferrous scraps Details
 
8Tender for works for effecting services in various schemes Details
 
8Tender for work of complete rewinding, overhauling, erection, commissioning and testing of 2000KVA, 6600/433 V, ESP 6A service transformer Details
  
8Tender for annual maintenance contract for work of servicing/attending fault Details
  
8Tender for work of routine and preventive / breakdown maintenance activities & miscellaneous works Details
  
8Tender for work contract for complete isolation of inlet gates of CW pumps Details
  
8Tender for supply of 22 kV standalone structure material complete set Details
  
8Tender for work of overhauling /break down of the 165KW/33 dewatering pump, 90KW storm water pump Details
  
8Tender for supply of spares battery cell for 220kV C/R and raw water at switchyard Details
  
8Tender for repair, maintenance, and installation of plant/ systems/equipments Details
  
8Tender for supply of spares for boiler feed pump Details
  
8Tender for supply of forged hammer ring for 500MW coal handling plant Details
  
8Tender for construction of TRW shed and allied civil works Details
  
8Tender for supply of electrical line materials Details
  
8Tender for repair and maintenance of control room at 132/33 kV GSS Details
  
8Tender for supply, installation testing & commissioning of 500 KVA DG set Details
  
8Tender for work of arresting water leakages Details
  
8Tender for bi-ennial rate contract (BRC) of complete boiler plant Details
  
8Tender for work of overhauling, servicing & repairing of air preheater and its connected system Details
  
8Tender for supply of LT breaker spares of LT MCC system Details
  
8Tender for supply of 110V/60A and 110V/24A battery chargers Details
  
8Tender for supply of chain operated coal valve for coal bunker for XRP 1043 bowl mill. Details
  
8Tender for supply of damper assembly without frame for flue gas duct. Details
  
8Tender for works contract for carrying out day to day preventive and breakdown maintenance and emergency works Details
  
8Tender for dismantling and erection of 66/11kV indoor equipments Details
  
8Tender for supply of D.C. earth fault locator for various Details
  
8Tender for procurement of 336kV, 216kV and 120kV surge arresters Details
  
8Tender for work of erection of 66kV D/C panther tower line Details
  
8Tender for balance work of erection of 66kV S/C line Details
  
8Tender for maintenance of HT motors Details
  
8Tender for supply, installation, testing and commissioning of flowmeters for measurement of water discharge in all three turbines Details
  
8Tender for establishment of new 33/11 kV outdoor substation Details
  
8Design, detailed engg, supply,etc of 400/230-110kV AIS SS Details
  
8Tender for work for replacement of breaker/ CT/ PT/ ISO/ LA/ 11kV panel/ charger/ LT panel of various Details
  
8Tender for maintenance of horticulture works Details
  
8Tender for setting up of 3540 kW grid-connected rooftop solar PV projects Details
  
8Tender for maintenance of horticulture works Details
  
8Tender for procurement of 200MVA 400/132kV ICT Details
  
8Tender for AMC for fully automated robotized instrumented impact testing machine Details
  
8Tender for repair/rewinding of AC induction motors, fans, transformers Details
  
8Tender for SITC of 11kV VCB panel board 12kV, 1250A, 25KA with over current fault, earth fault relays Details
  
8Tender for extension of 33kV line from to barrage along with renovation/stabilization of 33kV line Details
  
8Tender for supply installation testing and commissioning of 630 KVA voltage stabilizer having input range from 280-440V and output voltage of 415 Volts used for hydel auxiliary supplies to power house Details
  
8Tender for de-sludging of 20MVA transformer including replacement of transformer oil of 20MVA transformer Details
  
8Tender for reconstruction of parapets along the water conductor Details
  
8Tender for supply of knife gate valves Details
  
8Tender for special repair to control room at 400 kV sub station Details
  
8Tender for RCA for repairing and testing of BGP failed, 33/11 kV, power transformers Details
  
8Tender for erection work of additional 132/33 kV 40 MVA transformer Details
  
8Tender for procurement of spares for turbine supervisory system Details
  
8Tender for increasing capacity of 100 KVA to 250 KVA and to 250 KVA to 400 KVA transformer Details
  
8Tender for outsourcing work of erection testing and commissioning of bay control room equipment Details
  
8Tender for various improvement and maintenance works Details
  
8Tender for replacement of wornout purling and tressel iron and steel structure Details
  
8Tender for supply of portable reference sub standard meter Details
  
8Tender for supply of 11kV metal parts Details
  
8Tender for shifting HT line and poles Details
  
8Tender for work of erection, testing and commissioning of 9 Nos of 66kV feeder bay Details
  
8Tender for work of erection of structures, equipments, earthing, control wiring, yard lighting Details
  
8Tender for procurement of spare ID fan motor Details
  
8Tender for manufacture, testing, supply and delivery of G.I. wire 4 mm , G.I. wire Details
  
8Tender for supply and delivery of XRF analyzer (PMI tool) and CRM kit Details
  
8Tender for supply and delivery of LT dist box Details
  
8Tender for construction of a 33kV network Details
  
8Tender for fabrication, galvanizing, testing, supply and delivery of different 33 kV substation Details
  
8Tender for making of RCC sump pit for accumulation of overflow ash water along Details
  
8Tender for service contract for overhauling job of U3 ESP 500MW Details
  
8Tender for procurement of analyzers and other accessories Details
  
8Tender for P and F of fencing at various Details
  
8Tender for repair of submersible pump for various 33 kV S/S Details
  
8Tender for AMC/FMS of IT hardware and networking (LAN infrastructure) Details
  
8Tender for construction of rain water harvesting filling of earth Details
  
8Tender for annual rate contract for providing assistance in the C and I maintenance works Details
  
8Tender for overhauling of turbine Details
  
8Tender for procurement of spares for telescopic spout installed Details
  
8Design, supply, installation, testing and commissioning of 25MVA, 230/7kV station transformer Details
  
8Tender for supply of various insulation materials for boiler Details
  
8Design engineering, supply, installation & commissioning of complete assembly of high pressure water pumps with motor Details
  
8Tender for replacement of various high energy drain valves, steam/feed water lines, repairing of welding joints of steam/feed water lines etc Details
  
8Tender for supply, erection, testing & commissioning of 220kV LILO line Details
  
8Tender for routine and breakdown maintenance, rewinding and miscellaneous machining work of LT motors Details
  
8Tender for supply of industrial PC Details
  
8Tender for work contract for annual routine maintenance of turbine auxiliaries, equipments Details
  
8Tender for providing & fixing by pass twin jumpering arrangement by boltless C-type wedge connectors to the jump at tension towers Details
  
8Tender for replacement of 3 core power cable by 1C x 630 sqmm power cable Details
  
8Tender for establishment of 132/33 kV substation Details
  
You can also click on Tenders for more
  
For reference purposes the website carries here the following newsclips:
  8
Sea water becomes electricity — The result is a never-seen-before hydrogen color Details
  
8Thermal power and its vital role in India's green energy transition Details
  
8Acme Solar to raise 3,000 cr via equity, securities in tranches Details
  
8Waaree Energies’ subsidiary secures 452 MW solar module order Details
  
8Adani Group posts record Rs 90,572 cr ebitda; leverage at 2.6x of ebitda Details
  
8Power Mech Projects bags Rs 371 crore order from Adani Power arm Mahan Energen Details
  
8Akash Tripathi appointed MD of solar energy corporation of India Details
  
8Vigor media worldwide wins PR mandate for joint solar Details
  
8India and Japan boost energy security, transition efforts Details
  
8Neo Infra income opportunities fund acquires solarArise India projects in 1,400 Cr deal Details
  
8SECI Concludes 10th Green Ammonia auction with 62.84/kg tariff; PPL secures 25,000 TPA supply in Goa Details
  
8Acme Solar Holdings plans Rs 3,000 cr fundraise in multiple tranches Details
  
8SAEL Industries commissions 298 MW DC solar project in Rajasthan Details
  
8Bengal’s power demand may soar 21 pc this Durga Puja, cross 12,000 MW: Minister Details
  
8PLI Scheme Fuels India’s industrial transformation, boosts manufacturing and jobs Details
  
8Unpacking Implementation Challenges in Rooftop Solar in India Details
  
8Beyond Adani: 5 power stocks quietly fuelling India’s green revolution Details
  
84 Undervalued solar energy stocks in India Details
  
8Bhutan completes Punatsangchhu-II hydroelectric project, power capacity rises 40 per cent Details
  
8Cybersecurity in India’s energy and utilities sector Details
  
8Jaiprakash Power Ventures mulls 50 MW solar plant at Bina thermal site Details
  
8PFC inks performance evaluation MoU with Power Ministry for FY'26 Details
  
You can also click on Newsclips for more Details
8Find a snapshot of thermal, hydro, pumped storage,
solar, wind, BESS and T&D contracts related updates for the day
Click on Reports for more Details
8With no visibility of competing bids the award may reflect a single bid outcome This weakens price discovery and could invite regulatory scrutiny The risk is higher when awards are rushed. Details
Bulk transformer tender signals long term policy push  —  Power Grid
8The Lot 6 package reflects continuity of cyber secure localised sourcing across PGCIL tenders It could set precedent for state utilities to adopt similar clauses For the transformer market this is both a barrier and an opportunity. Details
8Despite three amendments PFC has avoided changing securities PQCs or liability carve outs This is a calculated stance to protect bankability The question is whether bidders accept this rigidity or price in higher premiums. Details
8Amara Raja JSP Projects Lumino Megha GA Infra R S Infraprojects and SPML are in the fray The pool is a mix of established EPCs and regional infra players Competitive intensity points to margin sensitive bidding. Details
PPP MII preference enforced with 20percent price margin  —  Mawlai GIS MeECL
8Class I suppliers with more than 50percent local content enjoy preference up to 20percent over L1 Class II suppliers are excluded This policy thrust could skew bidding strategy in favour of local fabrication.
Local content rule tightened at 60percent  —  DVC Maithon hydro
8Only Class I suppliers under Make in India with minimum 60percent local content can bid This could limit foreign OEM dominance but may stress local supply chains. Details
Pakri Barwadih tender hints at new NTPC model for captive coal logistics
8The combination of floor price surveillance mandates and EPC like liabilities could become a template If bidders still show up in strength replication at Dulanga and Talaipalli is likely If not NTPC may face its own capacity risk trade off.
Net metering adoption tied to CSERC amendments without tariff relief
8If CSERC revises net metering rules during execution the rooftop owner must adopt them However tariff remains unchanged for the developer This asymmetry embeds regulatory risk in the developer’s books Details
New entrants in Arunachal's power sector to pay dual fees for licensing
8Initial and annual fees for new electricity licensees have been structured to ensure upfront financial commitments, reinforcing regulatory compliance in the state's power market.
Proxy attendance banned in APSERC's committee to ensure active participation
8By eliminating proxy attendance, APSERC aims to enhance accountability and ensure that committee decisions reflect the genuine consensus of its diverse membership.
Regulatory delays highlight compliance gaps in Haryana power sector
8Haryana's power regulators spotlight compliance inefficiencies as key stakeholders miss deadlines. Industry stakeholders should note potential risks in consumer grievance redressal mechanisms.
Haryana's draft solar regulation sparks debate on net billing for large industries
8As HERC reviews its solar regulations, discussions include incorporating net billing for large industries, a move that could influence industrial strategies and electricity pricing structures.
Haryana Electricity Commission demands swift DHBVN action
8With DHBVN's compliance delays under the spotlight, the Commission demands immediate action to uphold regulatory orders, reinforcing the importance of efficient power distribution governance.
Click on Details for more
Details
8SCUC favoured low-ECR coal; high-ECR units largely left out
Median ECR for SCUC-“YES” units was ~Rs 3.12/kWh versus ~Rs 3.71/kWh for “NO”.
Inference — Selection skew tracks ECR: only 29% of “YES” units had ≥350 paise/kWh vs 72% of “NO”.
Why it matters — Ancillary uplift is being procured from cheaper stacks, containing MCP pass-through.
8Voltage stress clustered, not systemic: Khetri outside band 10.69%
What happened — Khetri 765 kV bus spent 10.69% of time outside IEGC; many buses 0%.
Why — ATC and (N-1) violations were 0 across major corridors the same day, so stress is local, not transfer-capacity related.
Why it matters — Prioritise VAR/compensation at a few hubs rather than broad ATC upgrades.
8RTM price tightly tracks bid imbalance (ρ≈0.86, negative)
What happened — Across T1–T96, IEX RTM MCP is strongly negatively correlated (|ρ|≈0.86) with the Sell/Purchase bid ratio.
Inference — When offers outpace demand, MCP compresses; when buys dominate, MCP lifts.
Why it matters — A simple ratio monitor anticipates price turns earlier than MCP alone.
8DAM–RTM basis flipped intra-day: late evening RTM ~Rs 4.65 cheaper
What happened — 21:45–22:00 RTM traded ~Rs 4.65/kWh below DAM; 09:45–10:00 RTM was ~Rs 2.36/kWh above DAM.
Inference — Over-hedging into the night and tight morning buys widened the basis both ways.
Why it matters — Portfolio buyers should split cover: keep DAM hedge but use RTM tactically around shoulder peaks.
8ER shouldered exports: 58.2 MU to WR; 49.9 MU to SR in a day
What happened — ER→WR net export 58.2 MU; ER→SR net export 49.9 MU (Talcher–Kolar HVDC 31.3 MU).
Inference — AC ties and Talcher HVDC carried most south/west transfers while ER–NR mixed flows offset each other.
Why it matters — Flows signal where congestion insurance is actually needed: WR/SR sink-side, not NR.
8Frequency tails skewed low: 183 sub-49.97 vs 129 over-50.03
What happened — Average frequency 49.982 Hz; 4h59m outside 49.90–50.05; excursions below 49.97 (183) exceeded above 50.03 (129).
Why — Daytime tightening and evening ramps kept the distribution slightly left-tailed (Inference).
Why it matters — More up-reserve or PSP discharge is needed to trim the low-tail risk windows.
8Coal buffers high at specific plants without matching output
What happened — Rajasthan Suratgarh STPS showed 179% of normative coal stock while PLF was 39%.
Inference — Stock logistics and unit constraints (not coal availability) are limiting dispatch at plant level.
Why it matters — Working capital is locked in stock where flexibility remains constrained; target plant-specific fixes.
8One ISGS solar outlier: 240 MW produced just 0.01 MU
What happened — NTPC’s Devikot Solar (240 MW) generated 0.01 MU on 2025-08-27 (~0.17% daily CF, Inference).
Why — Likely curtailment or severe local weather; adjacent NTPC Rajasthan sites produced materially more the same day.
Why it matters — Merchant/AS-linked solar in the cluster faces episodic revenue risk; hedges should assume zero-output blocks.
Click on Details for more
Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8Coal and Coke
8LPG
8Ammonia
8All tankers
8Bulk and Dry cargo
Click on Reports for more. Details
 For reference purposes the website carries here the following tenders:
 
8Tender for landscaping finishing and furnishing works and allied works Details
 
8Tender for replacement of 1 no. gear box Details
 
8Tender for channelization of seapage in main access tunnel of power house Details
 
8Tender for repair of gate rollers and replacement of rubber seal Details
 
8Tender for supply of electrical line materials Details
 
8Tender for supply of industrial ethernet switches for SAS network Details
 
8Tender for supply of 420kV circuit breaker Details
 
8Tender for transit camp cum horticulture works Details
 
8Tender for supply of breakdown voltage (BDV) test set for transformer oil Details
 
8Tender for supply of circuit breaker package Details
 
8Tender for supply of instrument transformer package Details
 
8Tender for award of contract for system strengthening works for survey, installation, testing and commissioning of new 5MVA 33/11kV substation Details
 
8Tender for CHP enabling work and other miscellaneous civil works Details
 
8Tender for replacement of stage 2 DG sets Details
 
8Tender for site enabling works Details
 
8Tender for supply, I and C of DGA with installation material Details
 
8Tender for medium overhaul of Unit 8 (120 MW) KN series turbine Details
 
8Tender for capital overhauling of HP\IP & LP turbine Details
 
8Tender for supply, erection, testing and commissioning of battery banks, battery chargers Details
 
8Tender for supply and installation of 132kV PT at 132kV substation Details
 
8Tender for strengthening of right side service Details
 
8Tender for supply of miscellaneous spare and consumable items Details
 
8Tender for strengthening of GI structure and replacement of string insulator of 132 kV switchyard Details
 
8Tender for overhauling of raw coal bunkers of CPP boilers. Details
 
8Tender for deployment of Ex-BHEL experts during capital repair of 02 units of TPP boilers and auxiliaries Details
 
8Tender for routine maintenance of water supply system and sanitary fittings Details
 
8Tender for providing and fixing chainlink fencing Details
 
8Tender for supply of coal burner spares Details
 
8Tender for miscellaneous civil maintenance and repair works Details
 
8Tender for repairing of existing main and side cable trenches with complete new construction of RCC slab Details
 
8Tender for repairing of rusted tower legs Details
 
8Tender for providing retaining wall in tower Details
 
8Tender for work for construction for random rubble stone masonary retaining wall at tower Details
 
8Tender for work for supply installation testing and commissioning of complete 20 meter high mask lighting system Details
 
8Tender for certain maintenance works in cooling tower, chimney Details
 
8Tender for maintenance of civil works Details
 
8Tender for providing chain link fencing Details
 
8Tender for shifting of poles Details
 
8Tender for work of breakdown maintenance , overhauling Servicing of pumps, blowers, mixers, valves, clarifiers and attending the leakage of pipe lines Details
 
8Tender for repair of insulation of main exciter rotor of brushless exciter rotor Details
 
8Tender for estimate for conductor augmentation of 33 kV feeder Details
 
8Tender for estimate for 03 no. 11 kV feeders Details
 
8Tender for estimate for conversion of bare to 11 kV covered conductor Details
 
8Tender for procurement of 450NB and 300NB sleeve type expansion joint (modified coupling device) for wet and dry ash conveying lines Details
 
8Tender for procurement of spares of different fluid coupling installed Details
 
8Tender for procurement of spares for positive metering pumps Details
 
8Tender for procurement of spares for pedestal bearing of PA Fan Details
 
8Tender for construction of 33 kV bay at 132 kV substation Details
 
8Tender for annual M and R works at 400 kV sub-station Details
 
8Tender for construction of 132 kV bay for 132/33 kV S/S Details
 
8Tender for overhauling/maintenance of power transformers including gasket replacement and oil filtration in main plant Details
 
8Tender for strengthening of column below 5A conveyor belt in plow feeder Details
 
8Tender for supply of caustic soda Details
 
8Tender for renovation of 33/11 kV sub-station Details
 
8Tender for electrical part for construction of 33/11 kV substation Details
 
8Tender for fabrication, galvanizing, testing, supply and delivery of different substation Details
 
8Tender for fabrication, galvanizing, testing, supply and delivery of different substation structures and matching G.I bolts, nuts Details
 
8Tender for fabrication, galvanizing, testing, supply and delivery of different substation structures Details
 
8Tender for engineering design, manufacturing, supply and retrofitting (installation, interfacing, testing and commissioning) of horizontal centrifugal water pump motor set for booster cooling water system Details
 
8Tender for erection testing and commissioning of Variable load hanger assembly in condenser 1600 NB left and right outlet pipes and priming pump lines Details
 
8Tender for renewal of wornout and damaged pipe lines Details
 
8Tender for supply of sea wire Details
 
8Tender for supply of tapping channel cross arm Details
 
8Tender for providing foundation concrete structure , equipment plinth , road work and other related civil works Details
 
8Tender for replace of bare conductor into AB cable Details
 
8Tender for replacement of ACSR bare conductor by insulated covered conductor Details
 
8Tender for replace of bare conductor into AB cable Details
 
8Tender for replacement of PVC cable Details
 
8Tender for replace of bare conductor into AB cable Details
 
8Tender for SITC of 125A MCCB panel (with box) on 63 KVA and 200A MCCB panel Details
 
8Tender for supply of matching material Details
 
8Tender for strengthening of asan barrage bridge Details
 
8Tender for augmentation of transformer capacity from 25 MVA at 220/33 kV to 50 MVA 220/33 kV at 220 kV substation Details
 
8Tender for civil works for AC and ventilation systems Details
 
8Tender for barbed wire fencing works Details
 
8Tender for supply installation and commissioning for upgradation of EMS system Details
 
8Tender for re-routing of 11kV AWRS overhead line Details
 
8Tender for erection of 33 kV line Details
 
8Tender for const. of 33kV S/s Details
 
8Tender for purchase of un-armourned NON-FRLS P.V.C. insulated multicore copper control cables Details
 
8Tender for annual contract for R and M of electrical works Details
 
8Tender for requirement of complete planetary gear box (PGB) of HP-1103 bowl mill Details
 
8Tender for requirement of complete actuators, spares and gear boxes spares Details
 
8Tender for annual contract for providing assistance in operation of main plant, pump house and river intake Details
 
8Tender for supply of ash slurry pump, seal water pump Details
 
8Tender for annual rate contract for providing assistance in operation and transportation of chlorine cylinders and chemicals, collection and testing of various Details
 
8Tender for supply installation & commissioning of real time online continuous discharge flow measurement system Details
 
8Tender for repair, maintenance, and installation of plant/ systems/equipments Details
 
8Tender for erection of 66kV equipment, structures, control wiring, yard lighting Details
 
8Tender for bi ARC for providing & fixing of 11kV heat shrinkable outdoor, indoor & straight through joint type cable termination kit for end termination of 11kV XLPE type power cable for various Details
 
8Design, supply, installation, commission and maintenance of solar PV system for 5 years as a rooftop Details
 
8Tender for work of providing & filling of nonconductive silicone base potting gel & refurbishing of link boxes of underground EHV cables Details
 
8Tender for AMC for loading/unloading, erection/dismantling of ICT/transformer and transportation of various EHV & HV equipments Details
 
8Tender for annual maintenance contract for breakdown, emergency and planned outage on 400kV line Details
 
8Tender for work of overhauling work (supply of material, services and alignment) of 400 kV isolators Details
 
8Tender for work of upgradation of existing SCADA system Details
 
8Tender for AMC for supply of spares and service for overhauling with and without pole of 33 kV CBs at various substation Details
 
8Tender for work of complete repairs/overhauling/servicing/alignment of 245 kV, 145kV & 33kV various bus & line Details
 
8Tender for annual maintenance contract (AMC) for work of loading, unloading, winching and transportation of various capacity EHV transformers Details
 
8Tender for work of testing of EHV grade transformer oil samples at site by mobile testing laboratory at various substation Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8SAEL Industries commissions first 300 MW solar power project in Rajasthan Details
 
8India installed 18 GW solar in first half of 2025, says Mercom report Details
 
8PFC signs performance evaluation agreement with power min Details
 
8State-run firms pay big dividends; Coal India, PFC lead the pack Details
 
8Infra sector outlook strong as 42 pc of India's population set to be urban by 2030: Report Details
 
8MNRE to set up task forces to accelerate wind contribution to renewable energy 2030 goals Details
 
8India's wind capacity will reach 107 GW by 2030: global wind energy council Details
 
8India has huge potential in gas-based energy economy Details
 
8Arunachal pushes RS 4,788 crore power upgrade to connect remote districts Details
 
8India finalising CCUS Mission roadmap; experts call for LNG contracts Details
 
8Jakson Engineers invests US$912.5 million in 6GW integrated PV manufacturing plant Details
 
8Trilegal Advises on Vikram Solar’s oversubscribed IPO worth INR 21,000 million Details
 
8India’s renewable energy Is progressing, but the world Isn’t paying attention Details
 
8Gaining Momentum: Solar EPC market trends, role of private players and the road ahead Details
 
8Thorium to replace uranium soon; India will become energy sector’s superpower due to Details
 
8Tweak nuclear project conditions to make it viable: Industry Details
 
8India Needs 61 GW energy storage by 2030 to support 500 GW clean power capacity: study Details
 
8New Avenues: Cost economics, challenges and opportunities in the offshore wind sector Details
 
8Infra sector outlook strong as 42 pc of India's population set to be urban by 2030: Report Details
 
8India’s coal imports rise despite push for domestic production Details
 
8Made in India EVs power bharat’s green future Details
 
8To help India’s economy, unleash the power sector Details
 
You can also click on Newsclips for more Details
Absence of tariff escalation clauses leaves EPCs exposed
8The bid documents do not mention escalation for steel or cement volatility With civil load high contractors may price in risk premiums This could inflate L1 beyond RVPN’s baseline.
No escalation clause exposes bidders to cost swings
8Volatile module and forex costs are not pass through Contractors face full price risk This may inflate tariff bids or deter participation. Details
MPERC’s new framework emphasizes operational and performance standards
8Distribution licensees in Madhya Pradesh must adhere to updated standards, aligning with national grid codes and affecting operational practices.
First-time bidders face intricate regulatory landscape in MP power distribution
8First-time license applicants must navigate complex regulatory requirements, highlighting the need for strategic planning and robust compliance frameworks to enter Madhya Pradesh's electricity distribution market.
Regulatory revamp introduces strict disqualifications for MP electricity traders
8The MPERC's updated rules disqualify applicants with past insolvency or legal issues, a move likely to exclude some existing players from the market.
MPERC sets new trading volume caps, influencing market dynamics
8The regulatory update introduces specific trading volume categories, which could reshape competitive strategies among intra-state electricity traders in Madhya Pradesh.
Industry divides over RPO compliance as WHRS cogeneration plants seek exemptions
8The cement sector's pushback against RPO obligations for WHRS plants highlights broader industry divides on renewable compliance and regulatory uniformity.
MSERC mandates milestone-linked payments for corporate consultants
8Corporate consultants under MSERC’s new rules will see payments tied to project milestones, enhancing accountability and ensuring timely project delivery.
8This approach may influence future regulatory consultancy standards.
Click on Details for more
Details
8Find a snapshot of thermal, hydro, pumped storage,
solar, wind, BESS and T&D contracts related updates for the day
Click on Reports for more Details
KPTCL’s load relief project slowed but steadied  —  Mekhali 400kV
The substation is designed to ease stress at Narendra yet award delays by two weeks REC appears to prioritise robust participation over speed This balance is delicate in Karnataka’s grid planning. Details
Policy  -  contract gap widens in Rajasthan’s battery push  —  RVUNL
8National policy has set ambitious targets for energy storage But translating this into workable state level contracts is proving messy This tender’s delays show the execution bottleneck clearly.
Interface risk with civil packages remains high  —  NHPC Dulhasti Stage II
8Hydro mechanical erection must dovetail with civil excavation of intake and pressure shafts Poor sequencing could inflate contractor liabilities NHPC’s package design pushes responsibility downward Details
DERC’s 2025 amendment hints at evolving tariff strategy
8The elimination of Regulation 30 could redefine tariff considerations in Delhi.
8Industry professionals must prepare for potential adjustments in regulatory compliance and market operations.
WHRS cogeneration debate escalates as MPERC examines RPO compliance
8 As cement companies advocate for exemption, MPERC's decision on WHRS technology could affect compliance norms across India's energy sector.
Competitive bidding non-compliance clouds Korba Power's reimbursement efforts
8Failure to adhere to competitive bidding processes for ash transport costs may jeopardize Korba Power's claim for reimbursement under regulatory guidelines.
Competitive bidding favors Adani for $58.5 million Mahan transmission project
8Adani Energy Solutions emerged as the successful bidder in a competitive process, securing a key transmission project aimed at evacuating 1230 MW from Mahan Energen Ltd.'s thermal plant. The project underscores a strategic investment in Madhya Pradesh's energy grid.
New MPERC rules redefine eligibility for intra-state transmission licenses
8Eligibility now hinges on competitive bidding or state selection, altering the landscape for prospective licensees in Madhya Pradesh's electricity transmission market.
Eligibility criteria tighten for transmission license applicants
8Prospective licensees must adhere to stringent new eligibility standards, as outlined by MPERC, prioritizing qualified and capable entities in the sector.
Click on Details for more
Details
Unclear securities leave financiers in the dark   —   DVC 228MW tender
8The tender text omits EMD and PBG requirements This creates ambiguity for lenders assessing exposure and cashflow lock ups Such gaps often deter financial closure for EPC consortia.
Risk allocation remains unresolved in bid structure  —  NEEPCO Tato II HEP
8Extensions hint at unaddressed geology and insurance risks Bidders appear unwilling to absorb full liability The promoter may need to revisit allocation norms to secure responses. Details
New guidelines streamline NTPC's solar project bidding process
8Updated guidelines from the Ministry of Power ensure NTPC's bidding process aligns with national renewable goals, enhancing transparency and project efficiency.
Competitive bidding sees Avaada Energy secure largest share at 590 MW
8 Avaada Energy emerged as a key player in SJVN's renewable tender, securing the largest allocation of 590 MW.
8Their strategic pricing and capacity offerings highlight aggressive market positioning in India's renewable landscape.
MPERC sets tight deadlines for response in ongoing electricity review case
8The Commission has mandated stringent timelines for document exchanges in the ongoing petition review, reflecting its emphasis on procedural efficiency.
Regulatory order stresses adherence to pre-approved project conditions
8The Commission reiterates compliance with established conditions, ensuring PTCUL's project executions align with regulatory expectations and financial prudence.
UERC mandates cost-effective borrowing for PTCUL's projects
8The Commission urges PTCUL to explore cheaper debt options for funding, aiming to optimize financial efficiency in executing approved infrastructure enhancements.
UERC mandates PTCUL to renegotiate civil works for cost reduction
8Commission directs PTCUL to reassess civil works contracts, emphasizing cost-effective land leveling solutions to mitigate budget overruns.
Click on Details for more
Details
Unclear tariff escalation clouds financing visibility — JREDA Palamu solar RFP
8The RFP is silent on tariff discovery and inflation pass through Lenders may price in risk premiums This could drive higher bids
Schedule risk shifts back to client as contractors gain time  —  MEECL Mawlai
8Extensions hand contractors breathing room to mobilise OEM guarantees But the client loses on commissioning timelines This imbalance can impact load growth management in Shillong. Details
Himachal's subsidy oversight could alter future hydro power tariffs
8 A subsidy application error at Thuchaning Hydro Electric Project prompts a reevaluation of its tariff rates, highlighting potential regulatory pitfalls in subsidy management for renewable energy projects.
Tariff ruling clarifies Himachal's stance on solar project delays
8This landmark ruling underscores the Commission's commitment to uphold tariff agreements, providing clarity for future solar project developers and investors.
Supreme court precedent guides HPERC's decision in solar tariff case
8The Commission's reliance on judicial standards for reviewing orders shapes the outcome of Jamwal Solar's tariff dispute, ensuring judicial consistency.
New tariff policy implications for Himachal Pradesh solar initiatives post-2023
8A recent decision on Bhubaneswari-II highlights policy shifts affecting solar tariffs and royalties, urging developers to reassess project financials under updated regulations.
Himachal Pradesh Commission enforces tariff consistency with Rs. 3.72 kWh decision
8By granting the original tariff to Green Energy Artisons, the Commission reinforces the validity of pre-established tariff periods, providing clarity and assurance to renewable energy stakeholders.
Regulatory Commission awards higher tariff to Sarswati Solar Power amid procedural review
8The Himachal Pradesh Electricity Regulatory Commission has rectified a tariff discrepancy for Sarswati Solar Power, raising the rate from Rs. 3.50 to Rs. 3.65 per kWh, correcting an oversight from a previous order.
Click on Details for more
Details
Barmer cluster substations face participation hurdles  —  RVPN
8Agasadi Bawadi Kalla and Bhiyad substations are pivotal to Barmer’s grid yet contractors remain cautious Logistics across desert stretches and tower supply risks weigh heavily The project’s timeline slippage hints at deeper participation issues.
Decommissioning clause shifts legacy asset risk onto EPC bidders  —  KPTCL Tumakuru works
8The tender requires dismantling of the existing 110kV Gubbi yard Disposal and reuse obligations increase site complexity Contractors must budget for unforeseen dismantling risks. Details
8By denying these relaxations CTUIL limits participation to established players Smaller consultancies are excluded despite policy incentives elsewhere This highlights the promoter’s risk averse stance Details
8RTM undercut DAM by ~Rs 2.31/kWh in a key morning block
RTM MCP was ~Rs 0.10/kWh at 08:45–09:00 on 2025-08-26, while DAM for the same block was ~Rs 2.41/kWh.
Inference — A heavy morning sell overhang met tepid buys, widening the RTM–DAM basis in daylight shoulder minutes.
Why it matters — Portfolio buyers could have shifted ~15-minute procurement to RTM and saved ~Rs 2.31/kWh in that window.
8RTM hit the cap as evening tightened; DAM lagged by ~Rs 5.24/kWh
RTM printed Rs 10.00/kWh at 18:45–19:00 versus DAM’s ~Rs 4.76/kWh for the same block.
Inference — RTM purchase bids surged (11,168 MW) while sell bids fell (7,157 MW), flipping the supply–demand ratio below 1.
Why it matters — Poor day-ahead cover into 19:00 penalised buyers by ~Rs 5.24/kWh; evening hedges remain non-optional.
8Market microstructure: price co-moves with supply–demand ratio (strongly negative)
Across all 96 blocks on 2025-08-26, RTM MCP shows a strong negative correlation with the Sell-to-Purchase-Bid ratio (ρ≈−0.85).
Inference — When offers pile up faster than demand (ratio ↑), clearing prices compress; the reverse holds during the evening squeeze.
Why it matters — Simple bid-ratio monitors flag price turns earlier than raw MCP charts; actionable for block bidding.
8Ajmer stood out on voltage discipline; 4.51% time outside band
Ajmer 765 kV bus spent 4.51% of the day outside the IEGC band (Max 804 kV, Min 777 kV, Avg 790 kV).
Inference — Local reactive support is tight around the Rajasthan solar hub even on an otherwise constraint-free day.
Why it matters — Targeted VAR support at a few hubs can buy real headroom without waiting for new lines.
8Rajasthan under-drew 7.58 MU while RE output was 47.05 MU
Rajasthan’s UI was −7.58 MU with state RE generation at 47.05 MU (Solar 33.63 MU; Wind 13.42 MU) on 2025-08-26.
Inference — Daylight RE surplus plus very heavy DAM sell bids (31,544 MW at 08:45–09:00) nudged under-drawal windows.
Why it matters — Scheduling discipline around mid-day RE is still leaving money on the table via UI.
8East cut forecast error with intraday updates (MAPE 2.57%→1.19%)
ER Day-Ahead MAPE was 2.57% versus Intraday 1.19% for 2025-08-26.
Inference — Early blocks were over-forecast (e.g., −374 MW at 00:45–01:00) but flipped modestly positive by 03:45–04:00 (+127.64 MW), trimming deviation risk.
Why it matters — Better same-day models reduce DSM exposure and panic RTM lifts at the open.
8Coal cushions diverged: Haryana ~150% of norm; Punjab GHTPS at 74%
Haryana fleet sat at ~150% of normative stock (HPGCL-Total 150%); Punjab’s GHTPS was at 74% with PLF 78%.
Inference — A comfortable state-level buffer masks plant-level tightness at legacy units; logistics, not coal availability, likely binds at GHTPS.
Why it matters — Dispatch risk sits at specific plants; procurement should target those nodes, not the fleet average.
8South managed zero shortage despite a 1,000 MW nuclear refuelling outage
SR reported 0 shortage at evening peak (50,154 MW @ 20:00) and over the day (1,265.37 MU) on 2025-08-26.
Inference — SR kept balance even with Kudankulam-1 (1000 MW) down for refuelling (expected back by September 2025), leaning on other ISGS and state mix.
Why it matters — Nuclear flexibility isn’t the only lever; the rest of the stack is carrying planned outages without consumer-side pain.
Click on Details for more
Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8Coal and Coke
8LPG
8Ammonia
8All tankers
8Bulk and Dry cargo
Click on Reports for more. Details
8Find a snapshot of thermal, hydro, pumped storage,
solar, wind, BESS and T&D contracts related updates for the day
Click on Reports for more Details
 For reference purposes the website carries here the following tenders:
 8Tender for misc. electrical maintenance/preventive maintenance/ breakdown maintenance of battery and battery charger/ DCDB/lighting/street and service Details
 8Tender for procurement of spares of WDG3A diesel locomotives Details
 8Tender for supply of various spares of cabling system Details
 8Tender for overhauling of air/flue gas ducts, lube oil system, Ct system and ducts insulation Details
 8Tender for routine work and breakdown maintenance work of dual belt gravimetric raw coal feeder Details
 8Tender for strengthening of column below 5A conveyor belt in plow feeder Details
 8Tender for work of annual maintenance contract of hydrogen generation plant Details
 8Tender for work contract for unloading of coal at track hopper Details
 8Tender for procurement of spares and consumables for BP, BPE and BD hydraulic actuators Details
 8Tender for annual general maintenance and repairing works of carpentry work Details
 8Tender for renovation of 33 kV S/STN Details
 8Tender for insulation work turbine and aux Details
 8Tender for repair and laying of sewer line Details
 8Tender for creation of 2 No. new 66 kV line bay Details
 8Tender for supply pneumatic drain isolating valve Details
 8Tender for augmentation of 132kV substation Details
 8Tender for realignment of HT and LT lines using HT UG cable Details
 8Tender for drawing HT ABC OH line in 11kV feeder Details
 8Tender for drawing HT ABC OH line Details
 8Tender for stringing of 11kV dedicated feeder from 110kV substation Details
 8Tender for constructing 11kV line Details
 8Tender for construction of new 33/11 kV sub station Details
 8Tender for construction of new 33/11 kV substation Details
 8Tender for construction of new 33 kV and 11 kV line Details
 8Tender for award of contract for system strengthening works for survey, installation, testing and commissioning of new 5MVA 33/11kV substation Details
 8Tender for supply of street light with high power LED system with complete fitting Details
 8Tender for procurement of 36kV, 12MVAR capacitor banks alongwith structures and all accessories Details
 8Tender for procurement of spares of twin lobe compressors installed Details
 8Tender for biennial work contract for complete operation and maintenance along with housekeeping of coal handling plant Details
 8Tender for procurement of spares for submersible pump installed Details
 8Tender for fencing and other works for plantation work Details
 8Tender for work of online, preventive and breakdown maintenance for boiler, its mountings and accessories Details
 8Tender for work contract for various C&I related job works required during Details
 8Tender for work of repairing of bell mouth and dynamic balancing of CW pump Details
 8Tender for supply of insulation materials for boiler Details
 8Tender for work of anticorrosive for the various structures, auxiliaries, tanks, piping, fence etc Details
 8Tender for maintenance contract for complete servicing/ overhauling/ attending fault/ repairing/ checking various Details
 8Tender for water proofing works Details

 8Tender for const. of 50 MVA 132/66 kV T/F plinth, 66 kV bays, SGF and allied civil works Details
 8Tender for work contract for replacement of PVC fill blocks supporting SS pipes Details
 8Tender for supply of LT kiosk for 630 KVA transfomer Details
 8Tender for supply and delivery of 660 set H/W single tension for wolf conductor Details
 8Tender for procurement of LT distribution kiosk (100 KVA) Details
 8Tender for procurement of suspension clamp -35 sqmm and anchoring clamp Details
 8Tender for proposal for procurement of LT distribution junction box Details
 8Tender for proposal for procurement of LT distribution kiosk Details
 8Tender for laying of 33 kV 3Cx400sq.mm. XLPE UG cable Details
 8Tender for laying of 11kV 3Cx300sq.mm. XLPE cable Details
 8Tender for laying of 33 kV 3Cx400 sq.mm. XLPE UG cable Details
 8Tender for procurement of 33kV 874 A earthing transformers Details
 8Tender for supply, delivery, erection, testing and commissioning of wall mounted, 5 Star, BEE rating, inverter type split AC machines Details
 8Tender for procurement of various types of metallic expansion bellows for boiler pressure parts Details
 8Tender for procurement of boiler tube for pressure parts of boiler Details
 8Tender for laying of new transmission and distribution drinking water pipeline Details
 8Tender for procurement of media of DMFs and ACFs of DW system Details
 8Tender for supply of various S.S. protective sleeve for boiler Details
 8Tender for supply of 10/80 variable load hanger supports for condenser left and right outlet pipes Details
 8Tender for supply of 200NB diaphragm valve for ash slurry pumps and ash water pumps Details
 8Tender for supply of CWP discharge pipe line Details
 8Tender for supply of various sizes of MS bolt and nut Details
 8Tender for supply, fabrication and erection of damaged/worn out 200NB/150NB/100NB/ 80NB fire hydrant header pipeline Details
 8Tender for supply of stay set complete Details
 8Tender for supply, fabrication, erection of GI steel structures, earthing, materials, etc. Details
 8Tender for daily routine maintenance works including minor repairing of main turbine and its auxiliaries Details
 8Tender for routine preventive breakdown maintenance of mechanical equipments Details
 8Tender for carrying out routine preventive breakdown emergency maintenance works in EPABX intercom maintenance Details
 8Tender for providing and installation of rock fall barrier and slope stabilization work Details
 8Tender for construction of fencing and other associated works Details
 8Tender for work for replacement of LT XLPE cable Details
 8Tender for construction of electrical infrastructure work Details
 8Tender for installation of C-wedge connector of substation Details
 8Tender for replacement of LT bare conductor by AB cable Details
 8Tender for replacement of weasel conductor Details
 8Tender for installation of additional 250KVA T/f Details
 8Tender for replacement of 11 kV ACSR to AAAC Details
 8Tender for work of replacement of existing 11 kV ACSR cond. with 11 kV AAAC AT S/S Details
 8Tender for work for construction of plinth and fencing of DTRs Details
 8Tender for work related to replacement of existing decayed AB cable/ weasel conductor Details
 8Tender for work for maintenance of 33/11 kV line Details
 8Tender for work of repair, overhauling and annual maintenance of VCB electricity distribution Details
 8Tender for work for replacement of LT XLPE cable in different capacity of DTR Details
 8Tender for PCC work of 05 numbers of bays spreading of gravel over PCC, laying of new slabs Details
 8Tender for supply of power contactors and moulded case circuit breakers Details
 8Tender for supply installation & commissioning of real time online continuous discharge flow measurement system Details
 8Tender for augmentation of transformation capacity of ss by addition of 132/33kV,1x25 MVA Power transformer Details
 8Tender for work contract for annual maintenance of 220/132/110kV substations Details
 8Tender for work of providing & fixing of FRP bird guard for various EHV lines Details
 8Tender for work of supply, installation, testing and commissioning of additional 1 no. of 220/22kV, 50 MVA power transformer Details
 8Tender for balance work of establishment of 132/33kV sub-station Details
 8Tender for work of installation, testing and commissioning of new 5x50MVAr, switchable 400kV line reactors Details
 8Tender for erection and maintenance of HT/ LT /TC Details
 8Design, engineering, procurement & construction (EPC) contract for development of 110 MW AC floating Details
 8Tender for supply of 6.6kV,671KW,HT motor for secondary coal crusher Details
 8Tender for bi annual rate of contract for restoration work of 66kV & 132kV transmission line Details
 8Tender for supply of throden bearing for jackwell pump Details
 8Tender for supply of vertical rigid life line and installation of vertical life line system Details
 8Tender for work contract for repairing/strengthening work of damage seal trough, hopper plate Details
 8Tender for routine and as & when require maintenance of boiler & its associate auxiliaries Details
 8Tender for supply of circuit breaker operation analyzer kit Details
 8Tender for supply & application of fire retardant cable insulating coating for cable fire protection Details
 8Tender for roof strengthening work of CW pump house Details
 8Tender for work of mechanical strengthening and stub strengthening of existing 66kV line Details
 8Tender for bi-ARC for erection of 66/132/220kV lines Details
 8Tender for emergency works of air pre-heater gear box overhaul/ replacement and other work Details
 8Tender for bi-ARC for the emergency restoration of power of 66kV,132kV & 220kV transmission line Details
 8Tender for work for attending puncture / leakages and replacement of various size Details
 8Tender for biennial rate contract for work of maintenance of coal handling plant Details
 8Tender for supply and application of metal protective compound for various pipe lines Details
 8Tender for supply of 03-element auxiliary relays for 66kV C&R panel Details
 8Tender for work of online preventive and breakdown maintenance for boiler, its mountings and accessories Details
 8Tender for supply of 100W flame proof LED flood light Details
 8Tender for supply of various auxiliary relays for various S/s Details
 8Tender for rendering service for miscellaneous C&I related maintenance works Details
 8Tender for supply of hot dipped galvanized M.S grills Details
 8Design, engineering, manufacturing, testing, supply, installation and commissioning of liquid ring vacuum pumps Details
 8Tender for supply of tools tackles & consumable Details
 8Tender for ARC for erection and maintenance of HT, LT & TC Details
 8Tender for EPC contract for conversion of existing 400kV 1200sqmm UG cable Details
 
You can also click on Tenders for more
 For reference purposes the website carries here the following newsclips:
 8Vena Energy: Expanding into India’s hybrid and firm power market Details
 8India Wind Energy Capacity to Reach 107 GW by 2030 Details
 8NTPC Limited: Driving India’s energy transition through renewable expansion Details
 8Solar sustainability as a path to an energy independent future Details
 8Gaining Momentum: Solar EPC market trends, role of private players and the road ahead Details
 8Waaree Solar Americas bags 452 MW solar module supply order in US Details
 8Mirchi and Adani group launch solar powered live radio shows in Mumbai and Ahmedabad Details

 
8Jakson Engineers To invest over 8,000 crore In 6 GW integrated solar module, cell & wafer plant Details
 
8Vikram Solar shares make tepid market debut Details
 
8PM Modi flags off Maruti Suzuki's 1st electric vehicle e-Vitara Details
 
8New Avenues: Cost economics, challenges and opportunities in the offshore wind sector Details
 
8Tripura minister lays foundation for Rs 126 crore transmission project to ensure 24x7 power Details
 
8Vena Energy: Expanding into India’s hybrid and firm power market Details
 
8At Re 1 per unit, hydro power generation at an all time high as water level increases in dams Details
 
8IREDA signs performance MoU with MNRE for 2025-26 Details
 
8Tweak nuclear project conditions to make it viable: Industry Details
 
8CareEdge Ratings upgrades Adani Green Energy rating with stable outlook Details
 
8EIL picks Greenzo Energy for pioneering hydrogen electrolyser unit Details
 
8NTPC to launch work on Rajasthan nuclear plant next month Details
 
8India’s hospitality sector set to power GDP with Rs 43.25 lakh crore boost, 63 million jobs by 2034: Report Details
 
8India's Rising coal imports amid domestic challenges Details
 
8WERGRID to Install India’s First 145 kV Eco-Friendly Green Circuit Breaker at Imphal Substation Details
 
8India’s Climate finance requirements – steel and cement overwhelm Power Details
 
8SJVN Synchronizes first 660 MW unit of buxar thermal power project with National Grid Details
 
8India will require 9 GW of charging capacity for e-trucks by 2030: Report Details
 
You can also click on Newsclips for more Details
Grid anchor project struggles to hold original schedule
8The 400/220kV package, critical for balancing renewable inflows with urban load, is already running behind schedule as RVPN extends bidding.
Himalayan hydro bids face 5 - month slippage
8From an original March closing, the hydropower project’s main civil packages have slipped by nearly 160 days. Such prolonged deferments point to hesitation around risk allocation and geotechnical exposure. Details
Digital monitoring made mandatory in transformer fleet
8Beyond conventional design, the tender mandates dissolved gas analysis and online bushing monitoring. This push towards predictive diagnostics signals a shift in reliability norms for extra - high voltage assets.
Five extensions signal low participation in ash works
8The Gadarwara - II ash handling tender has shifted from July to September. Repeated rescheduling highlights thin competition for ash evacuation packages, despite their mandatory role in plant compliance. Details
Risk shifts back to client with relaxed timeline  —  Saswad AIS/PFC
8Delaying SCOD reduces default risk for contractors. The state must absorb six months of unmet capacity. Reliability pressures on grid continue.
RA among the lowest - priced 50% will compress spread  —  Power Grid
8Only the cheapest half of technically qualified bidders enter the RA ring. MSE/MII bands add conditional entries, further crowding the floor. Expect tight clustering near L1 in final rounds. Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8Coal and Coke
8LPG
8Ammonia
8All tankers
8Bulk and Dry cargo
Click on Reports for more. Details
Metering and interconnection rules remain off - page  —  SECI/RTSPV - Tranche - II
8Net/gross regime, meter class, and approval timelines are not specified in the document. Those determine both CUF realisation and billing friction. Schedule and cash conversion hinge on these choices. 
High bid bond raises entry barrier  —  REC Ananthapuram - II
8The Rs 40.8 crore bid bond is unusually steep for this package. It risks limiting bidder participation to a handful of large firms. Market concentration could suppress competition. Details
8Raipur and Raigarh plants cornered the entire 300MW through one trader. The result signals concentration risk. It may limit competitive pressure in later rounds. Details
No tariff escalation leaves developers exposed to inflation  —  GUVNL
The PPAs tie tariffs to fixed GERC orders with no indexation. Rising O&M costs or module replacements may erode returns over time. Developers must factor long - term inflation risk into financing models. Details
8With only two firms contesting, the eventual tariff signal may lack competitive sharpness. Sector observers fear muted undercutting could raise overall project costs. A thin vendor pool also magnifies execution and financial risk concentration. Details
Contractor upside in flexibility, but promoter carries risk  —  UJVN BESS tenders
8Extended deadlines give EPCs room to source OEM tie-ups -  But absence of securities weakens promoter safeguards -  The balance tilts toward bidders in the short term.
Details
8RTM price slumped as sell bids doubled demand
On 2025-08-25, RTM sell bids (4,79,881.55 MWh) were ~2.04× purchase bids (2,34,947.23 MWh); weighted MCP printed Rs 2.26/kWh with 2,13,526.59 MWh scheduled.
Inference — A day-long supply overhang, with no inter-regional ATC or (N-1) violations, compressed prices.
Why it matters — Cheap balancing cuts procurement costs versus forward hedges.
8Anta ICT maintenance didn’t bite; corridors ran constraint-free
A 1,500 MVA 765/400 kV ICT-3 tie-bay at Anta was under maintenance 11:55–16:25 IST on 2025-08-25.
Inference — Despite this local outage, NLDC shows 0% violations across WR↔NR, ER↔NR, NEW↔SR; RTM still averaged Rs 2.26/kWh.
Why it matters — Redundancy insulated prices; targeted outages didn’t propagate market stress.
8Ajmer 765 kV was the only voltage outlier
Ajmer logged 2.71% time outside the IEGC voltage band on 2025-08-25; most 765/400 kV nodes were at 0.00%.
Inference — A localized reactive shortfall persisted despite benign transfer constraints.
Why it matters — Low-capex VAR/compensation at a few hubs can unlock headroom system-wide.
8Mid-afternoon frequency hit both tails
All-India frequency peaked at 50.321 Hz (15:02) and bottomed at 49.774 Hz (16:35) on 2025-08-25; FDI was 26.2, average 50.008 Hz.
Inference — Shoulder-hour ramps (solar decline/starts) drove control actions, not the classic evening peak.
Why it matters — DSM risk is shifting to 15:00–17:00; operators may need earlier secondary response.
8Peaking auctions offered big volume, found no buyers
On 2025-08-25, HP-DAM on IEX recorded 94,840.90 MWh of sell bids, 0.00 MWh purchase bids, and 0.00 MWh scheduled.
Inference — With RTM at Rs 2.26/kWh and no corridor binds, buyers preferred intraday flexibility over peaking blocks.
Why it matters — Hydro flexibility remained un-monetised; balancing risk migrated to RTM.
8East halved forecast error by moving intraday
ER demand-forecast MAPE improved from 2.91% (Day-Ahead) to 1.06% (Intraday) on 2025-08-25; Block-1 DA error was −1,896 MW versus −440 MW Intraday.
Inference — Same-day model updates corrected the night/morning bias and trimmed deviation exposure.
Why it matters — Fewer panic RTM buys at open; lower DSM outgo.
8Rajasthan locked Rs 4.99 for October; spot was half
A reverse auction on 2025-08-25 discovered L1 at Rs 4.99/kWh for 500 MW (01–18 Oct, 24×7) at regional periphery.
Inference — Forward hedging persists despite same-day RTM at ~Rs 2.26/kWh; states are paying a security premium.
Why it matters — A ~Rs 2.73/kWh premium signals tightening expectations for October and raises pass-through costs.
8Haryana overstocked on coal while gas units idled
On 2025-08-24, Panipat/RGTPS/Yamunanagar held 146–156% of normative coal stock; a day later, Faridabad and Auraiya gas units were under Reserve Shutdown.
Inference — With spot power near Rs 2–3/kWh, higher-SRMC gas stayed offline despite coal comfort.
Why it matters — Dispatch is being set by economics, not fuel scarcity — a positive for consumer tariffs.
Click on Details for more
Details
8Find a snapshot of thermal, hydro, pumped storage,
solar, wind, BESS and T&D contracts related updates for the day
Click on Reports for more Details
8The document does not specify how tariffs will be discovered or escalated This leaves developers exposed to future cost inflation without passthrough Such ambiguity could deter serious financiers Details
8This EOI extends the state’s pattern of bundling projects for scale Competition is preserved but barriers for smaller actors rise Developers should expect continuity in riskallocation once the RfP is issued Details
8From IRCON to midsized private firms capabilities diverged sharply Technical completion suggests a tighter qualification screen is likely This step determines if competition remains broad or collapses to a few Details
No escalation clause for module prices in TSNPDCL solar BOMT tenders
8Rising panel costs remain contractors’ headache Without explicit escalation EPCs must absorb volatility This may dampen participation and inflate quoted premiums. Details
No MSME exemption in DVC tender tightens bidder pool
8MSMEs lose eligibility relief with EMD exemptions deleted This reversal blocks small firms despite government preference orders Only capitalheavy contractors remain viable contenders
Lottery clause to break tariff ties  —  JVVNL Hanumangarh solar
8Identical tariffs will be resolved by draw of lots a rare but spreading method This introduces unpredictability in bid outcomes Developers cannot rely solely on pricing precision Details
No MSME exemption marks reversal in DVC Konar pooling station
8Unlike earlier projects MSMEs must deposit full EMD This is a sharp departure from past practice Smaller firms lose a traditional advantage

Double - penalty clause on road upkeep tightens cost pressure  —  NTPC PB Northwest
8Failure to maintain forest and village transport routes triggers doublecost penalties linked to RA bill processing Contractors effectively underwrite rural infrastructure This unusual transfer of liability could thin the bidder pool

Details
Unaddressed escalation leaves O&M inflation risk on EPC  —  JREDA Palamu solar
8With no cost escalation clause contractors face rising expenses over 25 years Labour and material inflation may erode returns.
Qualification thresholds not disclosed in TSGENCO tender
8No explicit experience or project scale bars have been set This leaves bidders unsure of eligibility standards It may either broaden or confuse participation Details
Bundled lot structure raises bidder barriers in Ajmer O&M tender
8The tender covers 80 lots across 14 circles capped at two awards per bidder This bundling strategy was intended for scale but has raised entry hurdles Contractors now face a dilemma in how many lots to risk
Uttarakhand hydro tenders show systemic strain  —  UJVN SBR HEP
8Multiextension cycles are becoming common in UJVN’s hydro packages Himalayan tunneling risk and rigid PQCs deter contractors Without structural changes bidder turnout will remain thin Details
8Digital monitoring rollback raises questions  —  PGCIL 765kV reactor package
Optical temperature sensors earlier mandatory have been dropped in Rev08 The reversal signals either cost pragmatism or reliability concerns Industry will debate if resilience has been compromised for savings

8Balance  -  only EPC scope alters risk profile  —  MAHAGENCO Paras solar project
The promoter has restricted the package to incomplete works and material supply This limits bidder control over earlier execution quality Such narrowed scope elevates interface and warranty risks for the incoming contractor

Details
Reverse auction keeps tariff pressure high  —  BHEL RESCO tender
8Despite heavier obligations bids will face undercutting pressure through eRA This may push tariffs to unsustainable lows The risk of longterm underperformance rises
Absence of securities offsets with hidden risks  —  IREDA tender
8The tender waives EMD and PBG But the relief is neutralized by unlimited indemnity and borrower - pays provisions leaving counsel with heavier liabilities than in past rounds Details
8RTM liquidity fractured; PXIL capped while IEX cleared deep
IEX RTM cleared 145.33 GWh at Rs 3.84/kWh on 2025-08-22, while PXIL hit the Rs 10.00/kWh cap on 0.78 GWh; HPX cleared 0.00 MWh.
Inference — Buyers clustered on IEX’s deeper book; thin venues cleared at the cap or not at all.
Why it matters — Misrouting bids to capped/shallow venues can add Rs 6.16/kWh vs IEX that day.
8Peaking auctions went dormant; three straight days saw zero clears
Hydro-peaking (HP-DAM) cleared 0.00 MWh on 22–24 Aug across IEX; HPX HP-DAM also showed 0.00 throughout.
Inference — With mid-day VRE penetration peaking near 33% on 2025-08-22, buyers likely leaned on RTM rather than forward peaking blocks.
Why it matters — A dormant peaking lane can strand flexible hydro and shift balancing risk to intraday markets.
8Ancillary lane on HPX was a no-show all day
On 2025-08-22, HPX AS-DAM recorded 0.00 MWh cleared across all 96 blocks (up & down).
Inference — System balancing mileage concentrated outside HPX that day, raising venue-concentration risk.
Why it matters — Shallow ancillary depth heightens balancing costs when volatility spikes.
8Voltage discipline held; Ajmer 765 kV was the lone soft spot
NLDC’s reliability sheet for 2025-08-22 shows Ajmer 765 kV outside the voltage band 3.26% of time; most 765 kV nodes logged 0.00% outside.
Inference — Localised reactive support gaps persisted even as inter-regional constraints remained minimal that day.
Why it matters — Targeted VAR/compensation at specific hubs can unlock transfer headroom without large capex.
8Frequency trough arrived pre-dawn, not at the evening ramp
All-India min frequency 49.850 Hz at 04:37, average 50.007 Hz, with FDI 20.9 on 2025-08-22.
Inference — Overnight scheduling/response, not the solar-evening ramp, drove the day’s deepest tail.
Why it matters — Night-time primary/secondary response still needs attention; pre-dawn tails expose DSComs to DSM.
8North ran tight but orderly; peak shortage just 50 MW at 20:00
On 2025-08-22, Northern Region’s evening peak shortage was 50 MW at 20:00, day energy 1,745 MU, frequency ~50.04 Hz at peak.
Inference — States adjusted portfolios to keep peak curtailment negligible despite mixed state-level deviations.
Why it matters — Peak reliability with minimal shortage keeps emergency procurement (high-Rs blocks) off the table.
8East halved forecast error intraday; DA MAPE 3.14% → ID 1.36%
For 2025-08-22, ERLDC shows MAPE 3.14% (DA) vs 1.36% (Intraday); RMSE 3.79% → 1.76%; Block-1 DA error −232.69 MW.
Inference — Same-day model updates materially trimmed deviation exposure during volatile morning ramps.
Why it matters — Better ID forecasts reduce DSM and avoid panic RTM buys in early blocks.
8Hydro cushioned the stack as southern thermal under-delivered
On 2025-08-21, Southern thermal actual was 596.48 MU vs programme 790.41 MU (-~24.5%), while Western hydro actual 108.47 MU vs programme 72.52 MU (+35.95 MU).
Inference — Monsoon-boosted western hydro offset southern thermal slack, stabilising all-India supply.
Why it matters — Hydro’s counter-cyclical flex reduces reliance on expensive intraday purchases.
Click on Details for more Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8Coal and Coke
8LPG
8Ammonia
8All tankers
8Bulk and Dry cargo
Click on Reports for more. Details
  For reference purposes the website carries here the following tenders:
 8Tender for routine, preventive and breakdown maintenance for turbine auxiliary Details
 
8Tender for work of erection & commissioning of ERS tower Details
 
8Tender for hiring of material handling equipments Details
 
8Tender for supply of AB switch male and female contact 11 kV 400 Amp Details
 
8Tender for construction of 11kV feeder from 110kV substation Details
 
8Tender for dyuthi 1UG cable work for taking 11 kV feeders Details
 
8Tender for job contract for horticulture maintenance work in plant Details
 
8Tender for procurement of 02 No. DC battery banks Details
 
8Tender for supply and installation of water recoolers for cooling air of generators Details
 
8Tender for maintenance works Details
 
8Tender for supply of 36 kV bus isolator and line isolator Details
 
8Tender for supply of heat shield for boiler tubes Details
 
8Tender for supply of 11 kV hardware strain for rabbit conductor Details
 
8Tender for procurement of spares for high pressure valves of boiler Details
 
8Tender for supply and works for repairing of damaged 220 kV line Details
 
8Tender for internal inspection of 132 kV GIS bay module and and replacement of 145 kV GIS circuit breaker Details
 
8Tender for maintenance / overhauling of 33 kV GIS modules at 132 kV GIS S/S Details
 
8Tender for construction of 33 kV bay at 132 kV S/S Details
 
8Tender for construction of 33kV GIS bays Details
 
8Tender for special repair and maintenance works Details
 
8Tender for work of treatment of roof Details
 
8Tender for procurement of high chrome grinding media ball for BBD type coal mills Details
 
8Tender for necessary civil work, installation, erection, testing and commissioning of one no.315 MVA, 400/220/33kV ICT along with other associated works Details
 
8Tender for rate contract for technological of various steel structures and pipelines. Details
 
8Tender for supply, fabrication and erection of metal structures, pipe supports inside reactor Details
 
8Tender for rate contract for civil repair & maintenance works Details
 
8Tender for carrying out routine, preventive and breakdown maintenance of protection system of 11kV, 6.6kV, GCB, DG-1 & 2 and 415V switchgear Details
 
8Tender for proposal for O&M contract for maintenance work Details
 
8Tender for carrying out routine, preventive and minor break down works which covers maintenance of C&I panels Details
 
8Tender for charges for carrying out routine preventive and minor breakdown works Details
  
8Tender for dismantling, relocating and realigning existing HT line, transformer and LT line Details
  
8Tender for carrying out for balance insulation works Details
  
8Tender for diversion of 400kV D/C line Details
  
8Tender for requirement of recovery water pump for AHP and CCCW pump Details
  
8Tender for supply of electric line material under electric supply Details
  
8Tender for procurement of electrical equipment material for 132/33 kV GSS Details
  
8Tender for supply of electric line material Details
  
8Tender for supply of electric line material under electric supply Details
  
8Tender for procurement of filter feed pump Details
  
8Tender for supply of guide pipe assembly for flame scanner of 600MW boiler Details
  
8Tender for reconductoring of overloaded 33kV link line emanating from 132/33kV substation Details
  
8Tender for installation of MCCB/ACB on transformer of different capacity of various 11 kV feeders Details
  
8Tender for installation of 1000 KVA transformer for capacity enhancement of overloaded 250 KVA transformer Details
  
8Tender for supply, fabrication, erection of GI steel structures, earthing, materials, etc. Details
  
8Tender for dismantling the badly corroded portion of M.S structural arch of pipe supports Details
  
8Tender for dismantling, pulling and erection of 2x80/100 MVA, 230/110 kV auto transformers Details
  
8Tender for procurement of 70KL liquid ammonia for chemical laboratory Details
  
8Tender for stage contract for executing the water conductor Details
  
8Tender for maintenance contract and various piece meal maintenance job of equipment Details
  
8Tender for service contract for BTL and align works Details
  
8Tender for major overhauling of bowl mills-XRP 803 of 5X200 MW BTPS Details
  
8Tender for work of renovation of Loco shed and other allied works Details
  
8Tender for repairing reclamation of spare of RCF, mill & fan Details
  
8Tender for work of M&R of water supply and sanitary fitting Details
  
8Tender for repairing replacement of various expansion joints of flue gas duct Details
  
8Tender for supply of 10 KVA 11/0.433 kV aluminium wound EEL1 star-1 rating completely self protected (CSP) distribution transformers Details
  
8Tender for requirement of fuel inlet elbow (FIE) installed in PF piping of mill system Details
  
8Tender for procurement of ID,FD and PA fan spares Details
  
8Tender for supply installation, testing and commissioning of trailer mounted electric motor-driven mobile air compressor Details
  
8Tender for work contract for routine maintenance of boiler pressure parts and fuel oil handling system Details
  
8Tender for annual maintenance contract for breakdown, emergency and planned outage on 500kV bi-pole HVDC line Details
  
8Tender for civil works for structural strengthening work Details
  
8Tender for work contract of erection and commissioning of balance work of 132 kV D/C line Details
  
8Tender for work of cable laying & termination for 220kV bus-bar scheme Details
  
8Tender for augmentation by addition of 1x25MVA,132/33kV T/F at 132kV S/Stn Details
  
8Tender for work of supply, erection, testing and commissioning of additional 50MVA, 132/33kV power T/F along Details
  
8Tender for attending emergency breakdown work & annual routine maintenance work at 220/132/110 kV substations Details
  
8Tender for supply of numerical protection relays Details
  
8Tender for annual maintenance contract (AMC) for overhauling & servicing of 22/33kV circuit breakers at various substations Details
  
You can also click on Tenders for more
  
For reference purposes the website carries here the following newsclips:
  8
New Delhi sharpens weather forecasts to safeguard power in cities Details
  
8Power Ministry teams up with IMD to develop weather tools for renewables Details
  
8Power sector: The watts that weren’t! Details
  
8India To Triple power demand By 2050, driven by EV adoption Details
  
84 Penny stocks well placed for multibagger growth in 2026 Details
  
8Solar and complex auctions propel India’s renewable energy investments forward: bloombergNEF Details
  
8India’s Renewable Energy push faces a big balancing test Details
  
8Indian solar sector may face oversupply by 2027: SBI Capital Details
  
8Harnessing India’s nuclear energy growth Details
  
8Madhya Pradesh emerging as a global hub for renewable energy and green innovations Details
  
8India celebrates clean energy milestone but coal still king Details
  
8Centre clears 23 chip-design projects to power India’s semiconductor growth Details
  
8Peak power demand unlikely to touch projected 277 GW level on intermittent rains: CEA Chairman Details
  
8Beyond Targets: What India’s pumped storage space needs Details
  
8KPI Green Energy incorporates SPV named 'KPIN Clean Power One LLP' Details
  
8Bridging the Gender Gap: unlocking women’s potential in the green energy workforce Details
  
8Premier Energies starts solar cell production Details
  
8Indian clean energy developers urged to align growth with demand Details
  
8ALCM could impact 20-25 GW of renewable energy capacity, says report Details
  
8THDCIL Elevates corporate standards with ISO 37001 certification Details
  
8India to improve weather forecasting accuracy for better power demand estimation, amid renewables push Details
  
You can also click on Newsclips for more Details
8RTM split three ways: IEX clears deep, PXIL hits cap, HPX shows zero
RTM diverged sharply on 2025-08-21: IEX’s weighted MCP averaged Rs 3.99/kWh, while PXIL cleared 2.03 GWh at Rs 10.00/kWh; HPX showed no cleared RTM volume all day.
Inference — Price-sensitive buyers clustered on IEX’s deeper book; thin venues cleared at the cap, and HPX liquidity vanished.
Why it matters — Fragmented liquidity can add crores to procurement if bids are misrouted to a capped or empty venue.
8Hydro-peaking sellers queued 103 GWh on IEX—buyers didn’t show
IEX’s HP-DAM saw 103.06 GWh of sell bids but 0 MWh cleared; HPX HP-DAM also recorded 0 across all 96 blocks.
Inference — Peaking flexibility likely monetised in RTM or parked for self-use; buyers avoided the peaking auction format on this day.
Why it matters — A dormant peaking lane implies under-utilised flexible hydro; policy tweaks may be needed to unlock evening ramp support.
8South’s main corridors ran clean: zero ATC and (N-1) breaches
Southern region’s S1→S2&S3 and Import of S3 recorded 0% time in ATC violation and 0% time in (N-1) breach on 2025-08-21.
Inference — Comfortable transfer margins and disciplined dispatch kept SR congestion-free despite evening ramps elsewhere.
Why it matters — Lower congestion-rent risk and more reliable price discovery for SR drawals.
8Frequency tails were at the evening ramp; average held near 50 Hz
All-India average frequency 49.978 Hz; min 49.465 Hz at 19:14; FVI 0.0762; FDI 25.3.
Inference — The deepest dip coincided with the post-solar ramp; REMC logged mid-afternoon VRE contribution at 36,015 MW (wind 16,122, solar 19,893), then tail risk moved to the evening.
Why it matters — Stability remained acceptable on average, but the evening tail still demands fast-start, flexible resources.
8East tightened its forecasts: intraday halved the error vs day-ahead
ER MAPE improved from 2.28% (DA) to 1.19% (intraday); RMSE from 2.85% to 1.66% on 2025-08-21. Block 1 (00:00–00:15) DA error was -232.69 MW.
Inference — Same-day model updates trimmed deviation risk through volatile morning ramps.
Why it matters — Fewer corrective purchases and lower DSM exposure for ER utilities.
8Northern evening shortage met with uneven drawal discipline
NR reported 795 MW evening-peak shortage at 20:00; states showed mixed drawal vs schedule: Rajasthan +2.06 MU, Haryana −0.74 MU, Uttarakhand +0.64 MU.
Inference — Intraday portfolio adjustments were active, but deviation spread persisted despite regional tightness.
Why it matters — Mis-aligned state actions can amplify basis risk when the region is short.
8Generation-mix pivot: Western hydro over-delivered; Southern thermal lagged
Western HYDRO actual 105.31 MU vs programme 72.52 MU (+32.79 MU); Southern THERMAL actual 538.73 MU vs programme 781.59 MU (−242.86 MU).
Inference — Monsoon-boosted hydro cushioned the stack even as southern thermal under-performed; that helped keep DAM weighted MCP near Rs 4.40/kWh.
Why it matters — Hydro’s counter-cyclical role moderated prices and reduced ancillary dependence.
8Ancillary on HPX was a no-show across all 96 blocks
HPX AS-DAM recorded 0.00 MWh cleared in every 15-minute block on 2025-08-21 (up and down products).
Inference — System balancing likely leaned on other venues or internal regulation; venue concentration risk remains if a single market handles most mileage.
Why it matters — A shallow ancillary lane can raise balancing costs on volatility days.
Click on Details for more
Details
DVC's legal team gears up for strategic regulatory challenge
8With a robust legal representation, DVC is preparing for a regulatory confrontation that might reshape its contractual obligations and market influence in Jharkhand.
Jharkhand energy regulators demand transparency in DVC-CVPPL agreement
8The Commission's insistence on clarity could set a precedent for future power agreements, affecting how companies negotiate energy deals.
UERC sets conditions for cost recovery in PTCUL's annual revenue
8Cost servicing and project capitalization will undergo prudence checks before integration into PTCUL's Annual Revenue Requirement, ensuring financial accountability.
PTCUL faces regulatory hurdles in transformer capacity expansion
8While the UERC granted approval for transformer upgrades, it imposed strict conditions, emphasizing compliance with loan terms and project completion transparency.
8This reflects heightened regulatory oversight in Uttarakhand’s power sector.
State vs central jurisdiction: MPPMCL cites Energy Watchdog case in petition
8MPPMC leans on the Supreme Court's Energy Watchdog decision to argue that MPERC lacks jurisdiction over inter-state electricity supply disputes, a move that could alter regulatory oversight.
Click on Details for more
Details
Jharkhand electricity case rescheduled for October, signaling potential policy recalibration
8A procedural delay in JBVNL's case suggests critical adjustments in regulatory petitions, potentially reshaping electricity distribution norms in Jharkhand.
8Industry stakeholders should brace for impactful policy updates.
Strategic implications of Jharkhand's tariff regulation overhaul for 2026-2031
8The upcoming regulatory changes could redefine tariff structures and rebate schemes, impacting market strategies and operational costs for electricity providers.
Tata Steel's regulatory challenge against DVC gains traction
8The Jharkhand electricity regulator's admission of Tata Steel's case signals a critical juncture in addressing power supply reliability and contractual disputes in the industrial sector.
Grasim-JBVNL case could set new precedents in power sector regulation
8As the case progresses, industry stakeholders are keenly watching for regulatory precedents that may emerge, influencing future disputes between private industries and state utilities.
Jharkhand's power regulatory landscape tested by JBVNL-Rungta case
8The JSERC's handling of the JBVNL and Rungta Mines dispute could reshape the regulatory landscape for surplus capacity utilization in Jharkhand's power sector.
Click on Details for more
Details
Strategic power supply approval highlights regulatory adaptability in Jharkhand
8The commission’s decision to allow a 33 kV connection at Kissan Rice Mill, despite standard regulatory limits, exemplifies adaptive regulatory practices in response to localized economic needs.
Clause exemptions under scrutiny as Jharkhand power supply falters
8The use of Clause 4.7 exemptions by JBVNL is under review. Regulatory bodies question the utility’s adherence to supply standards amid frequent interruptions to consumers.
JSERC's revised order hints at broader implications for regulatory compliance
8The regulatory body's decision to amend Tata Steel's interest calculations suggests a tightening of compliance expectations, urging energy firms to refine their data accuracy and submission practices.
Legal leniency in Jharkhand may mask underlying renewable project challenges
8While the commission’s tolerance for delay seems accommodating, it may conceal deeper challenges within Jharkhand's renewable energy project implementations.
JREDA challenges JBVNL: Implications for Jharkhand's power distribution strategy
8The outcome may redefine the operational frameworks for renewable energy projects, influencing competitive dynamics in Jharkhand's power sector.
Click on Details for more
Details
Odisha's draft regulations push distribution licensees toward higher reliability metrics
8With new standards like CAIDI and SAIFI, the draft regulations aim to ensure robust performance metrics for Odisha's power distributors, encouraging a shift towards greater reliability and efficiency.
Renewable energy disputes surface in Damodar Valley Corporation proceedings
8As GVREL joins the legal fray against DVC, the proceedings underscore emerging conflicts in energy transition efforts, with potential policy and market ramifications.
DVC and GVREL locked in regulatory standoff in Jharkhand
8The ongoing case between DVC and GVREL at the Jharkhand State Electricity Regulatory Commission could have major implications for power tariffs and distribution in the state.
8The outcome might influence future regulatory frameworks.
Compliance under scrutiny: Jharkhand power case reveals systemic legal hurdles
8The case between Ramkrishna Forgings and JBVNL illustrates significant compliance and procedural hurdles, offering insights into the complexities of legal frameworks within state power distribution.
Power transmission at risk as Eastern Coalfields and JUSNL clash
8The ongoing legal proceedings underscore significant risks to power transmission projects, with potential delays affecting energy reliability in the region.
Click on Details for more
Details
8ARG Electricals, Hind Construction, and Laser Power & Infra are the final contenders. The small pool raises questions about bid spreads and pricing leverage. Award dynamics will hinge on execution confidence and past track records,this development is drawing attention in Indian power sector news.
8Segregation of mixed feeders requires careful reconfiguration of rural and urban loads. Execution teams must manage shutdowns without supply disruption. This raises both technical and reputational risks for bidders, a recurring theme in Indian power sector news.
8The quick transition to financial bids underscores urgency to comply with RDSS milestones. Limited bidders indicate the utility is less focused on expanding the pool. Timely execution appears the overriding priority, a pattern frequently noted in Indian power sector news and closely watched in Indian power sector news coverage.
Details
Multi-voltage retrofits stretch contractor bandwidth: DVC project
8The package spans 220 kV, 132 kV, and 33 kV switchyards. In Indian power projects, managing interfaces across these voltage levels multiplies testing and commissioning challenges. Only firms with proven multi-node integration may realistically qualify.
8Despite being a global standard, IEC 61850 still challenges Indian EPCs executing Indian power projects. Few players have deep experience in process bus retrofits; the lag underscores a technology adoption curve in Indian power projects.
8What is happening here could influence other utilities and set precedents for Indian power projects. If bidders continue resisting, utilities may soften PQCs or break up packages; DVC’s struggle may well shape policy and practice across Indian power projects. Details
8With 59 of 60 bidders cleared qualification thresholds appear low This widens the playing field but drives down margins EPC majors and small developers are forced into the same pool
8The scheme’s structure mirrors earlier rounds with RESCO and 25year lock-ins It shows consistency in Rajasthan’s distributed solar strategy Developers face cumulative exposure if multiple projects are won
8The documents remain silent on tariff caps escalation or LD structure Developers face uncertainty on cashflow predictability Payment security is left unstated
8The discom avoids upfront CAPEX by outsourcing lifecycle responsibility Developers must manage performance and spares for the full term Long-run cost recovery is left to tariff discipline Details
8Find a snapshot of thermal, hydro, pumped storage,
solar, wind, BESS and T&D contracts related updates for the day
Click on Reports for more Details
Koradi FGD tender stretches timeline with four extensions  —  MAHAGENCO
8The FGD EPC tender has moved from July to mid  -  September after multiple shifts Such slippages are rare at this frequency The move hints at bidder unease or restrictive PQCs
8The retrofit spans three live 660MW boilers complicating erection windows Integration demands will push outage planning to the edge Contractors will likely price in high downtime risks
8While contractors gain time MAHAGENCO shoulders regulatory risk The imbalance could weaken negotiation leverage Promoter credibility takes a hit with repeated resets
8If Koradi becomes the new normal future FGDs will also drift Maharashtra’s decarbonisation rollout may slow as a result The episode could shape market expectations sector - wide

Nine deadline shifts derail DVC’s SCADA - DMS rollout
8The automation package has been pushed from May to September through nine extensions Such frequency is rare in SCADA tenders The delays point to major gaps in promoter or vendor preparedness
8Vendors face complexity in unifying 24substations under two central control hubs Communication protocols and cybersecurity standards remain unspecified These gaps may explain persistent postponements
8With each extension bidders’ EMD and resources remain locked Contractors are unable to free up capacity or forecast order books Cashflow distortions mount with every delay Details
Three bid extensions mark struggle for participation  —  NHPC Uri - I Stage - II
8From July11 to September5 bid deadlines were extended thrice The 56day delay points to bidder concerns over PQCs and risk allocation Such repeated extensions are unusual for NHPC
8NHPC reduced the average annual turnover requirement from Rs 34crore to Rs 29crore ex - GST This relaxation broadens eligibility for mid - sized hydro contractors Yet the move sits alongside new financial tightening through payment schedules
8The tender now defines substantial completion as 80% by value plus functional capability Certificates must show both financial value and operational readiness This shift reduces ambiguity in JV subcontractor credential claims
8Corrigendum4 requires contractors to cover additional categories under GCC34 Employer retains only limited policies This shift increases contractor premium costs and liability exposure
8Appendix - 1 now staggers cashflow into multiple tranches including 3% holdbacks across acceptance stages Contractors face longer capital lock - in before recovery Bid pricing is likely to reflect this liquidity strain.
Four deadline extensions cloud TANTRANSCO’s AIS substation plan
8The tender slipped from July to September through four corrigenda Repeated extensions point to bidder hesitation Procurement momentum is weakened by a 57day slippage
8German donor rules mandate extended checks and safeguards While ensuring probity they slow bid preparation Contractors must align with international procurement standards
8Tender documents remain silent on escalation and GST pass - through Contractors face commodity and tax volatility alone Such gaps discourage broader participation
8The multi - voltage AIS yard requires complex SAS integration Cyber - security and compatibility concerns are unresolved These gaps could surface as cost and time overruns Details
 For reference purposes the website carries here the following tenders:
 8
Tender for renovation of 33kV syard with paver block including coverslab and fixing steel railing Details
 
8Tender for overhauling and refurbishment (re-tubing and re-fining) of stator Details
 
8Tender for ETC RMU of 132 kV switchyard Details
 
8Tender for housekeeping works of sub-station Details
 
8Tender for work of repairing, servicing and refurbishing of 400kV PG isolator and center break isolator Details
 
8Tender for supply of 5 ton capacity electric wire rope hoist for instrument air compressor motor side Details
 
8Tender for running contract for carrying out the O and M works, improvement works and capital works Details
 
8Tender for supply of rack and pinion with rack gear housing assembly for water wall soot blowers of Model WB 1E for boilers Details
 
8Tender for supply of helical worm reducer gear box assembly suitable for 36 gravimetric feeder Details
 
8Tender for supply of oil injected, air cooled, screw type single stage 110KW rotary air compressor Details
 
8Tender for procurement of main turbine HP casing assembly Details
 
8Tender for supply and erection for renewal of HRH long term overheated long term served T22 tube portion from coil Details
 
8Tender for supply of 3 ton capacity electric wire rope hoist for seawater booster pump side motor Details
 
8Tender for work of replacement of existing 1000 sqmm power cable Details
 
8Tender for work of replacement of existing 1000 sqmm power cable along Details
 
8Tender for diversion/shifting including dismantling of existing of towers Details
 
8Tender for rate contract for operation and maintenance of DE system and DFDS system Details
 
8Tender for estimate for 1x5 MVA new 33/11 kV S/s Details
 
8Tender for installation, testing and commissioning of 11 kV line, distribution transformer Details
 
8Tender for civil maintenance works Details
 
8Tender for work of providing and fixing PVC strip curtain Details
 
8Tender for supply of electric winch for shifting (pulling) of scrapper Details
 
8Tender for supply of set of worm shaft & worm wheel gear along with worm shaft lock nut Details
 
8Tender for EPC project for design, engineering, supply, testing, installation, erection, commissioning & capacity up gradation of PA fan and ID fan motors Details
 
8Tender for supply of CR 80 travelling rail with fish plate/ fixture and necessary fastener Details
 
8Tender for work of overhauling and servicing of boiler feed pump (type-200 KHI) and booster pump Details
 
8Tender for supply of H.T. fasteners Details
 
8Tender for erection work of new 40 Kms. overhead single circuit 33 kV line Details
 
8Tender for construction of various 220KV & 132kV transmission lines Details
 
8Tender for supply of spare parts of 420 kV HDB isolators and 72.5KV HDB isolators  Details
 
8Tender for requirement of spares for ash handling system Details
 
8Tender for supply of H beam Details
 
8Tender for supply of lightning arresters Details
 
8Tender for supply of CI Fittings Details
 
8Tender for supply of miscellaneous steel items Details
 
8Tender for installation of live-line 24F (DWSM) OPGW on existing 132kV HPC line Details
 
8Tender for round the clock comprehensive annual maintenance contract CAMC and one time revamping of non SCADA infrastructure Details
 
8Tender for two 02 years round the clock facility management services Details
 
8Tender for procurement of circuit breaker Details
 
8Tender for procurement of tower footing impedance measurement kit Details
 
8Tender for supply, erection and commissioning of medium velocity water spray system Details
 
8Tender for strengthening of metal and concrete joints of draft tube Details
 
8Tender for providing and fixing of shed over AC duct and other misc works Details
 
8Design, fabrication, supply, laying of foundation, erection and commissioning of 66 kV monopole line Details
 
8Tender for augmentation of 132kV sub-station Details
 
8Tender for creation of 2 no.66 AIS lines bay at 66 kv S/Stn. Details
 
8Tender for creation of 4 no. 132 kV line bays Details
 
8Tender for estimate for remaining work for construction of extension of switch house Details
 
8Tender for procurement of LT guy shackle insulator Details
 
8Tender for attending oil leakage by replacement of O rings, gasket sets & hardware set of smoothing reactor Details
 
8Tender for AMC of attending oil leakage from equipments joints & bolts (transformer, radiator, smoothing reactor etc.) Details
 
8Tender for procurement of refractory patching material for boiler Details
 
8Tender for replacement of radiators of pole II convertor transformer Details
 
8Tender for supply of IBR approved high pressure gate valve Details
 
8Tender for supply of various types & sizes of fasteners Details
 
8Tender for supply, installation, testing & commissioning of 240 volt 500AH UPS battery set Details
 
8Tender for supply and retrofitting work of 1MW solar central inverter of canal top solar plant Details
 
8Tender for procurement of stage-I 3.3kV 362KW ash slurry series motors Details
 
8Tender for rate contract for deployment of hydra -crane and other hydraulic cranes Details
 
8Tender for procurement of managed switches Details
 
8Tender for O and M works of transmission lines Details
 
8Tender for supply of various types of hardware fittings Details
 
8Tender for supply of various oil filter element for coal mill Details
 
8Tender for operation and maintenance of reservoir pump house Details
 
8Design, fabrication, supply, installation, testing, commissioning with RMS of total of solar based LED high mast Details
 
8Design, fabrication, supply, installation, testing, commissioning with RMS of 401 kWp capacity ground mounted grid connected solar PV power plant Details
 
8Design, fabrication, supply, installation, testing, commissioning of total 175 KW grid connected solar power plants Details
 
8Design, fabrication, supply, installation, testing, commissioning of total 96 KW grid connected solar power plants Details
 
8Design, fabrication, supply, installation, testing, commissioning of total 193 KW grid connected solar power plants Details
 
8Design, fabrication, supply, installation, testing, commissioning of total 103 KW grid connected solar power plants Details
 
8Tender for upgradation of 66kV substation Details
 
8Tender for material handling contract Details
 
8Tender for infra development works Details
 
8Tender for misc. maintenance of evacuation of ash Details
 
8Tender for civil and electrical works for renovation Details
 
8Tender for procurement of mill drive journal ass. bearings for bowl mill type XRP803 HP 803 mills installed Details
 
8Tender for procurement of various ratings of 33kV CTs & NCTs Details
 
8Tender for procurement of 11 meter long PCC poles 400Kg WL conforming Details
 
8Tender for erection of new 110 kV DC line on DC towers with panther conductor Details
 
8Tender for supply of brushable ceramic epoxy material for cooling water pump 1A discharge line pipe Details
 
8Tender for supply, fabrication, erection of GI steel structures, earthing, materials, etc. Details
 
8Tender for work order for the ESP & boiler various auxiliary/equipment miscellaneous maintenance work Details
 
8Tender for supply of 360kW HT motor at coal plant electric Details
 
8Tender for supply, installation, commissioning & testing of metal detectors on conveyor-2A/B, conveyor Details
 
8Tender for supply, erection, testing and commissioning of ground high mast tower Details
 
8Design, manufacture & supply of air washery blowers & ducts, erection & commissioning of complete air washery blowers & ducts Details
 
8Tender for work for reblading of impeller blades of ID fan with root Details
 
8Tender for construction of 33 kV sub station Details
 
8Tender for tower stub strengthening 220 kV SC line Details
 
8Tender for procurement of spares for M/s L and T construction and equipment Details
 
8Tender for supply of spares for various pumps installed Details
 
8Tender for requirement of hydraulic pumps and servo valves for various Details
 
8Tender for supply of contact resistance meter and automatic primary injection test set Details
 
8Tender for supply of 198 kV, staion class, gapless type, metal oxide lighting arrester Details
 
8Tender for supply of chlorine leak detection system with detectors Details
 
8Tender for outsourcing work of erection testing and commissioning of bay and control room equipment Details
 
8Tender for procurement of spares for air compressors Details
 
8Tender for supply and erection of 33 kV CT/PT and 11 kV CT/PT Details
 
8Tender for supply and erection of optical communication link for 220kV line Details
 
8Tender for supply, erection, testing and commissioning of high mast lights Details
 
8Tender for operation and maintenance of water supply system Details
 
8Tender for work of overhauling, servicing and repairing of penstock gate Details
 
8Tender for supply and application of metal protective compound for various pipe lines Details
 
8Tender for work of repairing of SF6 to air bushing with all associated activities Details
 
8Tender for supply, erection, commissioning and testing of hydrogen gas leak detector system Details
 
8Tender for work of maintenance at various EHV substations Details
 
8Tender for work of supply, installation and commissioning of 100% hot redundancy based continuously available Details
 
8Tender for annual maintenance contract for repairs, overhauling of 33 kV/11kV VCB installed Details
 
8Tender for repair of cooling fan assembly of convertor transformer Details
 
8Tender for supply, installation, testing & commissioning of 100% hot redundancy based continuously available Details
 
You can also click on Tenders for more
 For reference purposes the website carries here the following newsclips:

 8
Coal Stock sufficient, says minister Details
 
8Govt opens 14 blocks for commercial coal mine auctions Details
 
8KP Group accelerates growth with national expansion plans in renewable energy Details
 
8India's renewable energy sector attracted $11.8 bn investment in H1 2025 Details
 
8Rajasthan emerging as leader in tourism mining renewable energy CM Sharma Details
 
8J&K Power sector owes over 143 Cr To GoI Details
 
8Wastewater management stock jumps 3% after securing 47 Cr order from RenewSys India Details
 
8India energy giants back nuclear power to boost clean electricity output Details
 
8India moves to sharpen weather forecasting amid renewable energy push Details
 
8Rs 13,756.56 crore project: Power generation company successfully synchronises the first unit of 1320-MW Buxar Thermal Power Project Details
 
8Govt to bring in big reforms in coal sector in time to come: Reddy Details
 
8Carbon emission of India’s grid electricity falls 7 pc as green energy share rises Details
 
8NTPC Leads the way in power sector growth in India Details
 
8NTPC Green commissions 212.5MW of 1.2GW Khavda PV plant in Gujarat Details
 
8Punjab governor unveils rooftop solar power project at BBMB Chandigarh Details
 
8Beijing’s rare earth weapon: A new oil shock for the green age Details
 
8Need GST Council-like bodies to boost infra growth: Tata Power CEO Sinha Details
 
8Energy transition investments power up in India Details
 
8Finance, transmission, storage key to renewable future: Experts at BS Infra Details
 
8Nuclear energy can help power India's economic growth, private push welcome Details
 
8Best of BS Opinion: Land reforms, nuclear energy can power Indian economy Details
 
8PFC signs EUR 150 million loan agreement with KfW to strengthen India’s power distribution sector Details
 
You can also click on Newsclips for more Details
Tie - break by lottery signals zero - margin bidding : JdVVNL Kusum tender
8The very need for a lottery shows expected clustering near ceiling tariffs Price discovery reduces to a chance outcome This undermines cost – quality differentiation
8The discom has imposed a strict ceiling cutting off any higher bid Tariff quotes beyond three decimals will be truncated This leaves only sub - paise play for competition.

Transmission line bundled into EPC scope :SJVN Bikaner solar
8Contractors must design and construct the 220kV line to Bikaner - IV GSS This integrates grid interface risk with plant EPC tightening execution timelines Coordination with SLDC and PSPCL adds compliance complexity
8The promoter is cementing a pattern of outsourcing land and interface risks to EPCs This aligns with broader state PSU solar strategies in Rajasthan Whether sustainable depends on how contractors absorb rising front - end burdens Details
8Deadlines have rolled eight times since January2021 pushing the project into late2025—common across Thermal power plant tenders India. Bidder hesitation and tight PQ norms are evident in Thermal power plant tenders India.
8A clash between submission - based and opening - based validity risked non - compliance; the amendment restored clarity for bidders, a key fix for Thermal power plant tenders India.
8While central PSUs eased performance security MPPGCL retained traditional norms. This increases entry barriers for bidders and stands out within Thermal power plant tenders India.
8Queries revealed conflicts in BG validity, O&M start dates, and document formats. The drafting gaps slowed bidder mobilisation—an issue mirrored across Thermal power plant tenders India.
8Deadlines have rolled eight times since January2021 pushing the project into late2025—common across Thermal power plant tenders India. Bidder hesitation and tight PQ norms are evident in Thermal power plant tenders India.
8A clash between submission - based and opening - based validity risked non - compliance; the amendment restored clarity for bidders, a key fix for Thermal power plant tenders India.
8While central PSUs eased performance security MPPGCL retained traditional norms. This increases entry barriers for bidders and stands out within Thermal power plant tenders India.
8Queries revealed conflicts in BG validity, O&M start dates, and document formats. The drafting gaps slowed bidder mobilisation—an issue mirrored across Thermal power plant tenders India. Details
SJVN shifts land risk to contractors in 500MW solar EPC
8Land acquisition responsibility is embedded in the EPC scope This forces contractors to handle permits and disputes Timelines become more uncertain inflating bid costs
8Contractors must also build the evacuation line to 220kV Bikaner IV substation This introduces approvals and synchronisation risks Normally such scope lies with transmission licensees

Simhadri consultancy structure suggests one - off easing, not a policy shift
8The stripped - down compliance design looks tailored for a small advisory job Core EPC and O&M packages are unlikely to follow But if repeated it could mark a trend of lighter controls on niche consultancy buys
8No clarity is given on arbitration seat escalation of fees or liability scope Consultants may face open - ended exposure if disputes arise This omission is notable against NTPC’s otherwise strict GCC
8By removing upfront financial locks NTPC has cut time and cost of entry This signals urgency to secure ash system recommendations quickly But it risks encouraging speculative bids
Details
8The discom enforces a hard ceiling with no escalation for 25years Bidders quoting above are clipped back to the cap Returns hinge on relentless cost control
8Entry is softened by waived securities yet execution is bound by rigid tariffs The tender is both carrot and stick Contractors must weigh short-term relief against long  term exposure
8Unlike earlier tenders no additional securities are sought at RfP stage This eases bidder liquidity but shifts default risk back on JDVVNL The reversal marks a significant departure from promoter norms Details
8No ceiling or escalation formula was mentioned in the EOI excerpts Without it developers face uncertainty in pricing long - term annuities Tariff discovery may tilt sharply depending on how aggressively firms chase market share
8Fortyplus bidders demonstrate strong interest in distributed renewables under state DISCOMs The low barrier to entry contrasts with stricter hydro or transmission PQCs Yet such crowded fields compress margins and heighten execution risk Details
8The documents remain silent on tariff caps Developers are left guessing the commercial guardrails This omission could fuel aggressive but risky bids
8Three deadline extensions gave developers breathing space but a rigid EMD rule still thinned the field Even so 61 bidders qualified at technical stage The outcome sets up an intense financial contest with long - term O&M risk unresolved Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8Coal and Coke
8LPG
8Ammonia
8All tankers
8Bulk and Dry cargo
Click on Reports for more. Details
Billing compliance in spotlight as HERC defers DHBVN case
8Partial compliance in a refund case involving DHBVN and Carlton Estate prompts the HERC to adjourn proceedings, underscoring the importance of regulatory enforcement in electricity billing practices.
Haryana regulator scrutinizes DHBVN refund compliance in Rs. 58 lakh case
8The Haryana Electricity Regulatory Commission is probing claims of incomplete refund by DHBVN, raising critical questions about utility compliance with regulatory orders.
Madhya Pradesh smart meter implementation faces regulatory and logistical challenges
8Persistent project delays and supply constraints prompt DISCOMs to seek more time from MPERC for smart meter installations under the RDSS scheme.
Strategic solar projects poised to transform regional energy landscape
8By focusing on distributed solar installations, Madhya Pradesh aligns with national renewable goals, setting the stage for a significant shift in its energy infrastructure.
Solar developers challenge Haryana's LTOA requirements
8Sunphotonics and JLTM Energy contest mandatory Long Term Open Access agreements, arguing they undermine the PM KUSUM scheme's farmer-centric goals.
Click on Details for more
Details
Termination timing of contractor by UPCL raises regulatory eyebrows
8UPCL's last-minute contract termination suggests strategic maneuvering, highlighting potential regulatory concerns about transparency and commitment.
Regulatory clarity in Uttarakhand: no exemptions for trader-mediated power sales
8The UERC ruling against Bhilangana Hydro Power highlights the regulatory requirement for direct sales to distribution licensees to qualify for transmission charge exemptions.
UPCL's tariff amendment attempt stalled by regulatory process demands
8The commission's ruling stresses the importance of adhering to Section 181 of the Electricity Act, complicating UPCL's efforts to adjust tariff regulations.
RPS Infrastructure’s regulatory challenge faces timetable setback in Haryana
8The Haryana Electricity Regulatory Commission postpones a key hearing, affecting RPS Infrastructure’s efforts to resolve electricity supply code difficulties, with broader industry implications.
Regulatory spotlight on DHBVN as HERC adjourns Essel petition
8The adjournment hints at potential regulatory challenges for DHBVN, with possible implications for distribution practices across Haryana's power sector.
Click on Details for more
Details
UJVN commits to 20% equity in DRIP-II funding structure
8The revised funding plan requires UJVN to contribute 20% equity, reflecting strategic financial participation in the Rs.432 crore DRIP-II initiative.
UPCL faces INR 458 crore shortfall in consumer security deposits
8Uttarakhand Power Corporation Limited struggles with a significant INR 458 crore gap in additional security deposits from consumers, highlighting challenges in payment compliance and financial planning.
Regulatory oversight mandates PPA amendments for compliance with 2018 rules
8The commission enforced that all Power Purchase Agreements must align with the latest regulations, impacting contract negotiations and operational strategies for generators and distributors alike.
GIS substations' cost escalation: UPCL's revised estimates raise eyebrows
8Revised cost estimates for GIS substations reveal discrepancies, prompting industry experts to question the accuracy and financial foresight of UPCL's planning processes.
UPCL’s tender miscommunication highlights regulatory compliance challenges
8A miscommunication in tender processes has exposed UPCL’s regulatory compliance challenges.
8This case illustrates the complexities of aligning operational procedures with regulatory frameworks.
Click on Details for more
Details
UPCL's solar deal highlights competitive bidding in renewable energy sector
8UPCL's competitively priced solar agreement at Rs. 2.57/kWh exemplifies effective bidding strategies under the CPSU Scheme, setting a benchmark for future procurements.
UERC scrutinizes cost-benefit analysis of Chibro transformer replacement plan
8The Commission evaluates UJVN Ltd.'s financial rationale, weighing costs against potential generation and revenue losses due to aging infrastructure.
Strategic implications of power purchase cost adjustments in focus
8The ongoing power purchase cost adjustments by UPCL have significant strategic implications for the distribution sector.
8Industry players need to navigate these changes adeptly to maintain competitive advantage.
Rooftop solar projects face tariff cut to Rs. 2.00/kWh, raising viability concerns
8The drastic reduction in rooftop solar tariffs has alarmed stakeholders, who fear it could hinder adoption and strain local economies.
8The Commission's ruling will test the resilience of small solar enterprises.
Net metering limitations impede Uttarakhand's solar project plans
8The 50 MW solar proposal by Van Panchayat fails to meet UERC's net metering requirements, illustrating the need for strategic revisions to fit within regulatory frameworks.
Click on Details for more
Details
GST implications on transmission charges to be directly passed to beneficiaries
8The regulatory framework now permits the direct transfer of any future GST implications on transmission charges to beneficiaries, a critical update for cost management.
Geopolitical tensions spark focus on islanding schemes
8Amid global tensions, the NRPC emphasizes expedited implementation of islanding schemes to safeguard grid security, underscoring the growing importance of strategic autonomy.
Transmission tariff regulation complexities escalate with project disputes
8The ongoing disputes surrounding the Bhatapara tariff regulation reflect the increasing complexities of transmission project governance and financial accountability in India.
Southern Region faces potential tariff recalibrations post-PGCIL petition
8PGCIL's petition for transmission tariff adjustments signifies potential recalibrations in cost allocations among Southern Region's power beneficiaries, impacting financial strategies.
Open access power procurement faces Rs. 0.98/unit surcharge in Uttarakhand
8UERC enforces additional costs on open access consumers, challenging competitive pricing and market participation strategies.
Gas-based stations show highest FCA deviations, sparking regulatory scrutiny
8Significant FCA deviations from approved rates at gas-based stations like Dadri Gas draw attention, potentially impacting future regulatory assessments and consumer charges.
Click on Details for more
Details
8Find a snapshot of thermal, hydro, pumped storage,
solar, wind, BESS and T&D contracts related updates for the day
Click on Reports for more Details
 For reference purposes the website carries here the following tenders:
 8Tender for attending to leaks and puncture breakdown works by welding in the worn out pipes and valves Details
 8Tender for supply, fab and erection of GI steel structures, earthing materials, equipments, panels, etc. Details
 8Tender for maintenance / overhauling of 33 kV GIS modules at 132 kV GIS S/S Details
 8Tender for supply of ash protector and U clamps for boiler Details
 8Tender for supply of forged toothed ring hammer Details
 8Tender for balance of system along with 5 years of comprehensive O&M of 600 MW/1200 MWh BESS project Details
 8Tender for procurement of 1.1 kV aerial bunched cable Details
 8Tender for SITC of 145 kV instrument transformer Details
 8Tender for upgradation, supply, installation, testing and commissioning of existing sophos firewall as HA mode next generation Details
 8Tender for work of on line preventive & breakdown maintenance for boiler rotary parts Details
 8Tender for refurbishment of 11 kV hydro thermal overhead line Details
 8Tender for supply and erection of turn over panel clip Details
 8Tender for ARC for de-weeding of raw water pond Details
 8Tender for supply of MS and GI grating frames Details
 8Tender for supply of HV silicon rectifier transformer Details
 8Tender for replacement of damaged corrugated asbestos sheets in wagon tippler Details
 8Tender for assistance in breakdown/preventive maintenance and annual overhauling of interlock and measurement system Details
 8Tender for AMC civil services repair and maintenance works Details
 8Tender for supply of copper flexible strip connectors links for LV duct of 75 MW generator Details
 8Tender for strengthening work of conveyor gentry, junction tower Details
 8Tender for work of helium gas leak detection test on condenser of turbine. Details
 8Tender for repair of spillway bay and replacement of sill beam Details
 8Tender for addl. 1x5 MVA PTR at 33/11 kV S/S Details
 8Tender for award of contract for up gradation of existing33/11kV outdoor substation Details
 8Tender for procurement of 33 kV kits suitable for 1x630 sq mm XLPE cable Details
 8Tender for work of carrying out miscellaneous C & I works Details
 8Tender for procurement of three phase four wire 240V, LTCT operated smart energy meters Details
 8Tender for ARC for erection and maintenance of HT, LT & TC works Details
 8Tender for erection of structure, equipment, control wiring Details
 8Tender for erection of 66kV S/C line Details
 8Tender for supply of L.T. distribution boxes Details
 8Tender for erection of 66kV equipment, structures, control wiring, yard lighting Details
 8Tender for erection of 66kV equipment Details
 8Tender for erection of 66kV equipment, structures Details
 8Tender for erection of 66kV equipment, structures, control wiring Details
 8Tender for erection of 66kV D/C LILO line on panther tower Details
 8Tender for erection of 66kV equipment, structures, control wiring, yard lighting Details

 8
Tender for miscellaneous civil maintenance work Details
 
8Tender for periodical structural in boiler supporting structure Details
 
8Tender for providing chainlink fencing Details
 
8Tender for laying of new emergency power cables and associated electrical works Details
 
8Tender for application of surface protective coating on spiral casing, stay rings, stay vanes of generating Details
 
8Tender for repair of drainage or dewatering pump and mat drainage pump Details
 
8Tender for annual maintenance contract for the upkeep and maintenance of early warning system Details
 
8Tender for supply of battery Details
 
8Tender for AMC of infrastructure installed Details
 
8Tender for contract proposal for refurbishment of V94.2 gas turbine blade row Details
 
8Tender for civil development works Details
 
8Tender for re tubing of low pressure heater LPH 4 tube nest Details
 
8Tender for rate contract for checking and repairing of coal bunker Details
 
8Tender for civil maintenance and repair and housekeeping of multistory tower Details
 
8Tender for supply and installation of material for completion of pending work at boiler elevator Details
 
8Tender for bi- annual rate contract for restoration of various 66 kV class transmission lines Details
 
8Tender for work of overhauling of air blower, repairing/replacement of discharge damper and discharge duct Details
 
8Tender for job work of routine, preventive maintenance readings of battery sets Details
 
8Tender for supply of UV-VIS spectrophotometer for chemical laboratory Details
 
8Tender for supply of permanent magnet magnetic pulley Details
 
8Tender for work of attending boiler tube leakage Details
 
8Tender for supply, erection & commissioning of complete hydrastep system Details
 
8Tender for construction of 110 kV LILO from 1PKWL2 feeder to 110 kV substation Details
 
8Tender for special estimate for augmentation of 132 kV substation Details
 
8Tender for special estimate for augmentation of 400 kV substation Details
 
8Tender for routine preventive and breakdown maintenance operation general upkeep and overhauling of plant Details
 
8Tender for biennial rate contract for complete overhauling/repairing along with the supply of spares Details
 
8Design, engineering, supply, erection, commissioning and testing of 140 ton capacity pit less type in motion electronic rail weigh bridge Details
 
8Tender for erection of 7.30 KM SC 33 kV line Details
 
8Tender for renovation work at 33/11 kV GSS Details
 
8Tender for renovation of roof Details
 
8Tender for development of additional green belt Details
 
8Tender for lifting of pond ash Details
 
8Tender for annual work contract of routine preventive and breakdown maintenance works of water treatment plant cooling water system cooling tower Details
 
8Tender for annual contract for routine breakdown and capital maintenance work of boiler pressure part Details
 
8Tender for purchase of seal oil pump and spares pumps and system at seal oil system of generator Details
 
8Tender for annual contract for capital routine and breakdown maintenance work of compressors and compressed air system Details
 
8Tender for comprehensive O&M contract of entire ash handling system Details
 
8Tender for repairing of BFP cartridge Details
 
8Tender for supply of spare ACSR Zebra conductor Details
 
8Tender for supply of air blowers installed at DM plant Details
 
8Tender for supply of 20Hp submersible pumps with spares and their control panels Details
 
8Tender for annual maintenance contract for carrying out emergency work and attending breakdown for various 220kV & 132kV EHV lines Details
 
8Tender for supply, erection, testing and commissioning of various capacities of pumps along with motor and associated equipments Details
 
8Tender for overhauling of air pre heater 'B' and replacement of axial seal Details
 
8Tender for overhauling of air pre heater 'A' and replacement of axial seal plate assembly during Details
 
8Tender for supply, erection, testing and commissioning in respect of balance work 3x33kV AIS line Details
 
8Tender for work for augmentation by replacement of 132/33kV 25MVA TF by 132/33kV 50MVA power transformer Details
 
8Tender for service contract for tit bit maintenance job Details
 
8Tender for work of replacement of 33 kV CT, breaker isolator, C/P etc at 33/11 kV S/s Details
 
8Tender for erection of earthing of 500/400/250 KVA capacity transformers in 11 kV feeders Details
 
8Tender for construction of HT/LT line sub-station and L.T. extension work Details
 
8Tender for supply and erection of re heater damper Details
 
8Tender for work of mechanical and stub-strenghtning work of 66kV line Details
 
8Tender for work of erection, testing and commissioning of 66kV D/C line Details
 
8Tender for work of dog to panther conversion of DC tower line Details
 
8Tender for drilling of exploratory holes for geological investigations Details
 
8Tender for supply of 400kV and 220kV clamps & connectors Details
 
8Tender for procurement of digital insulation tester and cable height meter for various Details
 
8Tender for second circuit stringing on 132 kV SCDC lines Details
 
8Tender for AMC for work of repairing/overhauling with spares, providing & fixing of 33kV poles of VCB at various EHV sub-stations Details
 
8Tender for work of providing & fixing BIS certified 200W LED high mast light Details
 
8Tender for establishment of 220/132/33 kV substation Details
 
You can also click on Tenders for more
 For reference purposes the website carries here the following newsclips:

 8Why Reliance power share price is rising Details
 8Jharkhand Eyes green leadership with renewable energy transition plan Details
 8Decline in coal output drags core infrastructure growth to 2% in July Details
 8NGT seeks action on coal-based sponge iron units Details
 8JSW Steel arm wins Rajgamar coal block auction Details
 8Uttar Pradesh emerges as India’s renewable energy hub: solar and bio-energy lead the Way Details
 8Va Tech Wabag wins order worth Rs 46.50 cr from RenewSys Details
 8Powering the next leap: How wind-solar hybrids are reinventing renewable energy Details
 8Inox Wind sells Rs 175 crore stake in subsidiary at Rs 7,400 crore valuation Details
 8Merchant batteries poised for attractive returns in India: EMBER Details
 8Powergrid commissions KPS-3 Transmission Limited Details
 8IndiGrid to Acquire Transmission Project from TEECL Details
 8India builds three SMRs under nuclear energy mission Details
 8Govt to launch 13th round of commercial coal mines auction on Thursday Details
 8Vikram Solar shifts expansion focus to Tamil Nadu, Bengal unit to see limited growth Details
 8Global EV charging ports forecast to surpass 206 million by 2040 Details
 8Enmas EPC Power Projects raises Rs 57 cr from investors to fuel global expansion Details
 8Over 51 GWh of BESS capacity in the pipeline, parliament informed Details
 8Insolation Energy launches 3 GW PV module manufacturing Plant in Rajasthan Details
 8Wind projects underperform, but firms' credit quality holds steady: Crisil Details
 8Solar power plant inaugurated at Chandigarh's Sector-35 guest house Details
 8Mangal Electrical Industries IPO: Check details here Details
 8Is India overproducing solar modules SBI report says so amid US export restrictions Details
 8Ola Electric rockets 28% on ‘India Inside’ Vision: 3 game-changing moves revealed Details

 
You can also click on Newsclips for more Details
8With financial bids complete the Bharatpur package reveals participation from EPC infra and electrical firms. The turnkey scope is significant in ensuring compliance with RDSS targets on rural supply hours and loss reduction.
8The project to split 11kV feeders in Bharatpur Circle has completed financial bidding. Scope involves new poles lines and segregation of mixed load corridors a recurring challenge under the state’s RDSS rollout.
8With financial bids completed the Jaipur Discom’s Bharatpur package under RDSS is set for award. The project’s turnkey scope is expected to reduce technical-commercial losses and balance agricultural – domestic demand corridors. Details
8A 2x500MW flue gas desulphurization balance work package under a leading central utility has reached the technical stage drawing niche erection contractors. The owner’s push ties directly to emission compliance timelines.
8The package involves completing residual works of an FGD system at a major 1000MW unit. The tight scope commissioning trial runs and handover signals the owner’s urgency on compliance.
8The balance work tender involving transportation erection painting and commissioning support has crossed the technical stage. With just two names admitted the contest sets up a close price battle. Details
8A 132/33kV GIS substation package with twin 50MVA transformers has reached technical bid stage. The scheme under a state transmission utility also ropes in associated line works drawing three contenders to the fray.
8A high - voltage GIS with linked transmission scope is in the evaluation ring where a traditional cable supplier competes alongside EPC - focused bidders. The ownership rests with Rajasthan’s state grid utility.
8Instead of splitting transformers and GIS works the owner has rolled both into one turnkey scope. The 2x50MVA mandate will see bidders price both civil and electrical fronts together. Details
Policy goals drive need for external project management muscle
8With a 4000MW solar capacity target by FY 2026 - 27 Jharkhand’s renewable arm is outsourcing management support. The PMU will oversee execution across rooftop floating and utility - scale solar projects as well as efficiency initiatives.
8Payments are milestone - linked with penalties for underperformance and strict confidentiality clauses. The structure ensures the consultant remains aligned with the agency’s ambitious renewable rollout over the full two - year period. Details
 Standardization drive tightens technical variation
8Unlike earlier bulk buys, this tender aligns all reactor parameters under Rev 08 specs, reducing bidder flexibility. The central PSU is clearly pushing for grid-wide uniformity across Power Projects in India.
8With 13 single-phase 80 MVAR units bundled in Lot-6, the package is aimed at voltage stability across multiple 765 kV corridors. Such centralized planning signals a sharper focus on reactive power management, which has become critical in modern Power Projects in India.
8Removal of optical temperature monitoring raises debate among engineers on operational foresight versus cost saving. The PSU appears to prioritize proven mechanical systems, reflecting a wider approach seen in several recent Power Projects in India. Contractors now face a scenario where standardization overrides customization, a trend likely to shape future Power Projects in India with tighter technical uniformity

Quad line clears path for 2GW solar evacuation
8A new 400kV double circuit package has been carved out exclusively to carry solar power from a state-owned 2000MW park. With Quad Moose conductor design, the line promises higher thermal margins but also raises erection complexity for contractors—an important milestone in renewable projects in India.
8A standalone transmission package now links two fresh 400/220kV nodes, avoiding overlap with earlier grouped tenders. The sharper boundary lines give developers clarity while raising competitive pressure among line builders, which is being closely watched by those tracking renewable projects in India.
8With this line package out, the 2000MW park’s backbone evacuation is closer to reality. For contractors it means balancing tower spotting across mixed terrain and meeting aggressive commissioning deadlines—a typical challenge in large-scale renewable projects in India.
8The 400kV line between two proposed substations forms the arterial path for solar evacuation. Ownership rests with the winning transmission service provider under a BOOT structure stretching risk horizons, underscoring how transmission infra underpins future renewable projects in India. Details
Mega substation package sees deadline shift again
8The turnkey package for a 400/230–110kV AIS substation has now been pushed to September 4 reflecting extended clarifications. The project under a state transmission utility carries heavy civil automation and transformer supply responsibilities.
8A large - scale AIS package covering design to commissioning of a 400kV hub has been extended for the fourth time. Contractors see this as a sign of intensive clarifications on transformer specs SAS integration and civil scope.
8The package includes not just switchgear and transformers but also control buildings kiosks and roadworks a rare civil - intense profile for an AIS project. Extensions suggest bidders are recalibrating margins on the civil component.

Hydro EPC tender stretches into September
8A 72MW river-based hydropower scheme under a state utility has pushed its submission to September 1 after multiple clarifications. The EPC scope spans civil caverns, hydro-mechanical works, and complete electro-mechanical supply under a single turnkey structure—making it one of the most tightly contested hydropower projects India has seen this year.
8Eligibility insists on hydro turbine-generator experience above 29MW per unit and 58MW project scale with two years of operational history. Such stringent PQ filters will sharply limit the pool of qualified contractors, narrowing the competition among established players in hydropower projects India.
8Instead of splitting civil and E&M packages, the 72MW plant has been tendered as a single EPC. This design forces bidders to showcase both tunnelling expertise and high-capacity turbine partnerships, reflecting the trend in modern hydropower projects India towards integrated turnkey solutions.
8Despite repeated bidder pleas for flexibility, addendum clarifications have reaffirmed strict PQ and guarantee requirements. With little wiggle room, contractors entering this round of hydropower projects India must prepare for an uncompromising technical evaluation when bids open in September.
Details
Large solar cluster puts 401MW under one basket
8A new BoS package aggregates 28 decentralized solar projects into a single tender under a central PSU’s ownership. Unlike earlier KUSUM bids this rollout bundles scattered sites into one execution-heavy contract.
8Barely three weeks are allowed for bid submission on this solar BoS package. For contractors it means accelerated design tie - ups and rushed pricing cycles.
8What was earlier fragmented into feeder - level packages is now aggregated into one mega tender signalling a new era for decentralized solar contracting.
Legal counsel sought for high - stakes foreign borrowing
8A central PSU is seeking a one - year domestic legal expert to vet foreign currency loan agreements and ISDA contracts. The role is structured for extension signaling sustained overseas borrowings.
8Only law firms with prior exposure to global medium - term note programmes or foreign currency borrowings qualify filtering out new entrants Details
Performance tests tightened with multi - layer checks
8Commissioning and acceptance are now bound to stringent pre - commissioning performance and guarantee tests. Only after these milestones will operational acceptance and final payments be cleared.
8The entire 600MW/1200MWh AC package will go to one bidder. This eliminates split responsibilities across packages but pushes contractors to scale up resources rapidly for design civil electrical and O&M obligations.
8From contract signing to commissioning the BoS contractor has just over a year to complete design procurement and execution. Any delay risks 0.5% liquidated damages per week capped at 5% of contract value.

Bulk push reshapes transformer procurement cycle
8A fresh 400kV package calls for 15 units of 500MVA class machines under a central PSU’s ownership. The rebundling into Lot - 6 signals a shift from mixed - capacity tenders to targeted bulk sourcing.
8Unlike earlier bulk rounds mixing 765kV and 400kV units this package isolates 500MVA transformers for strategic deployment. Engineers see this as a bid to streamline manufacturing and grid reliability.
8By separating 400kV demand from higher class units the PSU has simplified bidding. Yet for manufacturers absence of diversity in capacity means higher exposure if cost escalations occur. Details
State utility reopens hunt for 1600MW coal partner
8A Karnataka state generator has relaunched bids to rope in a private partner for a 2x800MW supercritical thermal project in eastern India. The shift to a joint venture mode marks a break from its earlier standalone plan.
8Bidders must show a net worth of over Rs.2200 crore and experience in 500MW coal plants.
8The new criteria sharply narrow the field compared with earlier calls.
8The 2010 DPR pegged capital cost at Rs.8675 crore with tariffs near Rs.2.3/kWh. In the new structure private equity must absorb escalations while tariffs remain under regulated PPAs.
8The project once mooted at 1200MW and later scaled up is now firmly bid out as a 2x800MW scheme cementing supercritical technology as the baseline.

Revised tender marks sharp break from past norms
8Earlier bids allowed conventional conductors this issue mandates HTLS and OPGW expands civil works and adds cyber testing compliance. For contractors the shift means more capital more coordination and tighter margins.
8The switch to HTLS carbon composite conductors demands tighter sag-tension controls with stringing to IEEE - 738 standards. Tower sufficiency must be proven shifting engineering risks squarely onto bidders.
8Beyond HTLS uprating the tender embeds optical ground wire for real - time grid communication. Fibre splicing joint boxes and termination duties raise both scope and cost a step absent in earlier corridor upgrades. Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8Coal and Coke
8LPG
8Ammonia
8All tankers
8Bulk and Dry cargo
Click on Reports for more. Details
8RTM fractured: HPX, PXIL hit cap; IEX averaged Rs 3.92
RTM cleared at the cap on PXIL (1.90 GWh at Rs 10.00/kWh) and on HPX (0.51 GWh at ~Rs 10.00/kWh), while IEX’s RTM weighted MCP was Rs 3.92/kWh.
Inference — Thinner-venue scarcity plus active reserve deployment compressed prices on the deeper IEX pool.
Why it matters — Fragmented liquidity can swing procurement costs by ~Rs 6.08 crore per GWh versus IEX’s average.
8Clean sheet on corridors: zero ATC and (N-1) breaches
All-India corridor indices show no ATC or (N-1) proxy violations on 2025-08-20.
Inference — Adequate transfer margins and balanced regional flows likely pre-empted congestion and price splits.
Why it matters — Low congestion-rent risk; more reliable price discovery across exchanges.
8Reserves skewed: TRAS down 53.97 GWh versus 9.31 GWh up
Ancillary deployment was dominated by down reserves (TRAS −53,965 MWh; SRAS −2,819 MWh) versus more modest up calls (TRAS +9,309 MWh; SRAS +5,468 MWh).
Inference — Midday VRE abundance (notably SR wind and all-India solar) drove sustained down-regulation.
Why it matters — System flexibility is being purchased to soak excess; sustained patterns will show up in ancillary bills.
8Hydro-peaking auction saw zero trades for six straight days
IEX HP-DAM recorded 0 MWh cleared from 15–20 Aug, despite sell bids up to 120,032 MWh on 20 Aug.
Inference — Buyers likely preferred RTM/ancillary, while hydro flexibility monetised in other products.
Why it matters — Under-used peaking market suggests design/participation tweaks if hydro is to anchor evening ramps.
8East trimmed forecast error: intraday beat day-ahead on 2025-08-20
ER’s MAPE: Day-Ahead 1.74% vs Intraday 1.28% (RMSE 2.27% vs 1.83%); worst DA miss early-morning Block 4 (00:45–01:00) at +283 MW.
Inference — Better same-day modelling curbed deviation risk during volatile morning ramps.
Why it matters — Lower DSM exposure and fewer corrective purchases for ER DISCOMs.
8North had 505 MW evening shortage; South reported none
At 20:00, NR reported 505 MW shortage at 49.89 Hz; SR reported 0 MW shortage at the same time.
Inference — Divergent load shapes and local conditions meant NR leaned tighter than SR in the evening.
Why it matters — Basis risk rises if cross-regional support tightens on peak days.
8Frequency held near 50 Hz despite reserve swings
All-India average frequency 49.991 Hz; FVI 0.0773 with low tails; ancillary mileage reported as 4.
Inference — Heavy down-reserve activation (see TRAS/SRAS) kept the profile tight through the solar shoulder.
Why it matters — Stability improved without resorting to shortage pricing, but it relies on sustained reserve availability.
8765 kV ER buses stayed 100% in band all day
Key ER nodes—Ranchi New, Angul, Gaya (765 kV)—logged 0% time outside the voltage band (100% within).
Inference — Adequate reactive support and generator voltage control underpinned transfer capability during ramps.
Why it matters — Voltage compliance reduces losses and cushions angular-spread spikes on heavy-export days
Click on Details for more
Details
Provisional relief for Vyasi Hydro: UERC mandates Rs. 7.60/unit tariff until final order
8UERC's provisional tariff decision ensures continuity for Vyasi Hydro, amidst project delays and escalating financial commitments.
Mandatory remote meter reading to revolutionize Uttarakhand’s energy monitoring
8The introduction of automatic remote meter reading capabilities under the MCDAR is set to modernize data acquisition, providing real-time insights and improving energy audit precision.
MPERC considers unprecedented penalties for Azure Power's solar shortfall
8Azure Power faces potential penalties beyond PPA norms for its 300 MW project underperformance, highlighting financial strains due to alternative power purchases and REC costs.
Madhya Pradesh sets competitive solar tariff at INR 2.94/kWh in latest KUSUM-C tender
8The MPUVNL's latest solar tender under the KUSUM-C scheme achieves a uniform tariff of INR 2.94/kWh, reflecting competitive pricing dynamics and a strong shift towards renewable energy.
Hybrid project surplus energy banking faces regulatory bottlenecks in MP
8Continuum MP Windfarm seeks judicial direction for seamless banking of surplus energy, spotlighting the disconnect between policy frameworks and DISCOM execution.
Click on Details for more
Details
UPCL’s short-term power purchase receives in-principle approval amidst winter demand surge
8With power demand outstripping supply, UPCL’s swift regulatory endorsement for emergency procurement ensures continued service reliability across Uttarakhand.
Uttarakhand's solar policy faces hurdles with unchanged distribution loss rates
8Despite ambitious solar capacity targets, the state’s inability to adopt voltage-specific loss rates might stymie the growth of captive solar projects.
World Bank-backed DRIP-II budget for Ichari Dam exhausted
8The Rs.274 crore budget under DRIP-II for Ichari Dam is depleted, prompting UJVN Limited to seek additional funds to address critical structural repairs and ensure operational safety.
 UPCL's short-term PPA with Tata Power exceeds approved tariff limits
8The commission approved a PPA with rates above the Rs. 5.62/kWh cap set for FY 2024-25, citing power shortages.
8This decision reflects the state's pressing need for reliable electricity supply despite potential financial strain.
UERC enforces stricter capital expenditure protocols for utilities
8Utilities in Uttarakhand must now secure BoD approval for significant asset investments, a move by UERC to tighten control over capital expenditures affecting tariffs.
Regulatory alignment: UERC’s surcharge determination follows national policy
8UERC’s decision on additional surcharge complies with the Electricity Act and Tariff Policy, ensuring regulatory consistency while addressing the financial obligations of UPCL amidst open access trends.
Click on Details for more
Details
CERC stands firm on filing fees, despite petition withdrawal
8In a notable decision, CERC denies Zenataries Renewable Energy's request for filing fee adjustment upon withdrawing its petition, emphasizing the importance of regulatory adherence.
UPCL explores multi-state energy banking to offset winter power deficits
8In addition to HPPC, UPCL considered proposals from BSES and UPPCL, revealing an expansive approach to energy banking as a strategic tool for managing supply shortfalls.
Regulatory ambiguity leads to power supply conflict in Dehradun
8A regulatory grey area has ignited a legal battle in Dehradun, with the Panache Valley residents and UPCL at odds over electricity connections.
8The outcome may influence future UERC rulings and similar disputes statewide.
Rajwakti SHP's RE component now pegged to lowest exchange prices
8Him Urja Pvt. Ltd.'s Rajwakti plant will see its RE component priced at the lowest REC rates discovered in exchanges, shifting financial dynamics for both the generator and UPCL.
Regulatory delays in MB-II project highlight need for clear adjudication on uncontrollable factors
8UERC's handling of the MB-II project's cost components underscores the challenges in distinguishing between controllable and uncontrollable delays in large-scale infrastructure projects.
UERC's decision highlights strict adherence to Electricity Act, 2003
8The Commission's rejection of UPCL's petition stresses the primacy of established legal procedures in regulatory amendments, ensuring thorough scrutiny.
Click on Details for more
Details
Regulatory authority retains power to modify secretary's decisions under OERC guidelines
8OERC's robust framework allows for review and modification of its secretary's actions, ensuring dynamic oversight and adaptability within the commission's operations.
Amendments to GNA regulations unlock connectivity flexibility for stalled projects
8Recent amendments to GNA regulations open new pathways for projects with terminated PPAs, demonstrating CERC’s commitment to maintaining momentum in India’s renewable infrastructure growth.
HPERC decision highlights procedural tangles in Himachal's renewable energy subsidies
8The Kangra Hydro decision underscores procedural ambiguities in subsidy calculations, urging a review of regulatory practices to ensure fair tariff settings.
HP electricity board fortifies power purchase terms despite subsidy gridlock
8Supplementary PPA execution mandated by HPERC following tariff extension, underscoring regulatory agility amid subsidy adjudication complexities.
AMP Energy sidesteps transmission charges with strategic PPA execution
8By executing a PPA post-commissioning, AMP Energy potentially avoids bilateral transmission fees, showcasing a calculated regulatory navigation.
CERC allows SPV route for land and financial closure in wind project
8The regulator's nod to Tata Power's subsidiary TP Vardhaman Surya Ltd. for land ownership and financial proof marks a shift in easing project compliance burdens.
Click on Details for more
Details
For reference purposes the website carries here the following tenders:
  8Tender for supply of 400kV and 220kV clamps & connectors Details
  8Tender for construction work of 220kV outdoor GIS feeder bay and 220kV AIS bus coupler feeder Details
  8Tender for supply of 36 kV CT and 36 kV PT of accuracy 0.2S accuracy classes along Details
  8Tender for civil works related to construction of new 200 MVA ICT Details
  8Tender for repair and Mtc. works Details
  8Tender for augmentation of 220kV S/Stn Details
  8Tender for supply of electrical spares for GDW package Details
  8Design, supply, erection, testing & commissioning works for replacement of existing ACSR lark/panther conductor Details
  8Tender for establishment of 132 kV (GIS)/ 33kV(AIS) solar pooling station Details
  8Tender for refurbishment, installation, and commissioning of condenser Details
  8Tender for repair of boilers Details
  8Tender for procurement of 220 kV current transformers Details
  8Tender for supply, installation and commissioning of three numbers 33 kV outdoor vacuum circuit breaker Details
  8Tender for supply, loading at factory of LT distribution box Details
  8Tender for development of AC grid connected solar photovoltaic power projects up to capacity of 500 MW Details
  8Tender for supply of PH & analyzer and PH sensor cable Details
  8Tender for supply and installation of drift eliminators alongwith spacers Details
  8Tender for procurement of spares for converter and seal sets Details
  8Tender for boiler pressure parts reconditioning of defective main steam stop valve Details
  8Tender for erection of 66kV SS equipment, structures, control wiring, yard lighting Details
  8Tender for estimate for augmentation of power transformer Details
  8Tender for work of dismantling, shifting and erection of indoor equipments Details
  8Tender for work of replacement of rusted 37 (29+8) towers Details
  8Tender for biennial work contract for operation and maintenance of signal and telecom system installed Details
  8Tender for procurement of spare parts of LT breaker installed Details
  8Tender for construction of new allied civil works 33 kV S/Stn Details
  8Tender for AMC to attend various routine preventive and break down mechanical maintenance work of all the heavy equipment Details
  8Tender for operation of 33kV/11kV sub station Details
  8Tender for mud lifting de- silting from stop log gate Details
  8Tender for repairing of 2 sets damaged guide vanes Details
  8Tender for improvement works of secondary crusher house Details
  8Tender for procurement of 22 kV standalone structure material complete set Details
  8Tender for supply of 11kV composite polymer pin insulator Details
  8Tender for dismantling of existing rail track, strengthening of track foundation Details
  8Tender for replacement damaged RCC gantry structures power grid feeder Details
  8Tender for supply, erection and commissioning of high mast lighting tower system Details
  8Tender for retrofitment of existing 420 kV, 2000A isolator Details
  8Tender for supply of various types of conductor accessories Details
  8Tender for procurement of ammonia liquor/hydro chloric acid/caustic soda lye Details
  8Tender for procurement of complete spares of air evacuation pump installed Details
  8Tender for supply and fixing of ancilary items to maintain the polyhouse Details
  8Tender for repair & rehabilitation works on the fills support beams and columns of cooling tower Details
  8Tender for increasing capacity of 100 KVA to 250 KVA DTRs Details
  8Tender for renovation of concertina coil fencing at 132/33 kV grid sub station Details
  8Tender for raising of height of barbed wire fencing Details
  8Tender for creation of 220 kV GIS line bays at 220 kV substation Details
  8Tender for third party audit of ongoing fire detection and protection system Details
  8Tender for connection with utility shifting works Details
  8Tender for supply and erection of galvanised steel tubular poles Details
  8Tender for rate contract award for supply of 11 kV D.O. fuse elements Details
  8Tender for estimate for new 33/11 kV substation Details
  8Tender for procurement of different lighting material Details
  8Tender for procurement of spares for air compressors installed Details
  8Tender for procurement of various erosion protection sleeves (shield) and other spares for boiler Details
  8Tender for supply, erection, testing and commissioning of numerical relays Details
  8Tender for casting and placement of new RCC precast slab Details
  8Tender for works contract for HT/LT line works Details
  8Tender for supply of various types of load hanger supports for feed water system Details
  8Tender for supply of spares for hydraulic boom luffing system valves Details
  8Tender for supply of 300 sets 11kV AB switch for double pole structure Details
  8Tender for biennial rate contract for attending emergency breakdown works & planned maintenance work at various 220/132kV EHV sub-stations Details
  8Tender for ARC for erection and maintenance of HT, LT & TC works Details
  8Tender for works contract for carrying out HT/ LT DCW improvement and capital extension works Details
  8Tender for supply of bowl hub for HP 803 bowl mills Details
  8Tender for works contract for HT/LT line works Details
  8Tender for work of mechanical strengthening, stub strengthening and earthing etc Details
  8Tender for procurement of mandatory spares of 132kV GIS module at 132kV GIS S/s Details
  8Tender for supply of spares & complete mechanism overhauling of 220kV circuit breakers at various Details
  8Tender for laying of 2500 m of 3x185sq mm 11kV XLPE cable Details
  8Tender for installation of a new 11/0.433 kV 315 KVA DTR Details
  8Tender for system improvement work at distribution sub-station Details
  8Tender for procurement of different sizes CS gate valves Details
  8Tender for biennial contract for repairing and maintenance work at ash pond Details
  8Tender for renovation and retrofitting of 33/11 kV substation Details
  8Tender for construction work of 132kV GSS Details
  8Tender for supply of rubber blocks / pads for side beam and top clamp of wagon tippler Details
  8Tender for supply of HP valves and its spares for boiler Details
  8Tender for supply of spares for WDS-6 and WDS-4B locomotives Details
  8Tender for supply, installation and commissioning of OPU pump- motor set pump Details
  8Tender for renovation of sewerage system Details
  8Tender for supply, installation & commissioning of LED & solar lights for power house Details
  8Tender for construction of new closed shed for storage of heavy lifting tools & tackles / equipment of turbine generator set Details
  8Tender for supply of hot deep galvanized grill Details
  8Tender for supply of 6.6kV, 261KW, HT motor for conveyor Details
  8Design, manufacturing, testing, commissioning and installation of CBMS at coal plant Details
  8Tender for work of anti-corrosive epoxy on various pipelines, tanks & structures etc Details
  8Tender for work of complete overhauling of 75/15 EOT cranes & 40/10MT EOT crane Details
  8Tender for excavation & refilling of earth & laying of HT/LT power/ control cable Details
  8Tender for works of testing & commissioning of various generator, transformer & line feeder protection relays Details
  8Tender for supply of spares for ESP Details
  8Tender for BRC for work of operation & maintenance of vacuum based ash handling plant Details
  8Tender for rate contract for the work of chemical of dust/bird shit contaminated insulator strings Details
  8Tender for work of procurement of various clamps connectors for routine & emergency maintenance work at 400kV s/s Details
  8Tender for annual maintenance contract (AMC) for repairs, overhauling of 33 kV/11kV VCB installed Details
  8Tender for augmentation by addition of 1 x 50 MVA, 132/33kV power transformer Details
  8Tender for work of replacement of rusted cross arms & rusted tower material Details
  8Tender for balance work of conversion of 132kV S/C to D/C line Details
  8Tender for work of comprehensive audit based on fault current dissipation functionality and reliability assessment at various EHV S/Stns Details
  8Tender for procurement of 420kV, 7 core, 2000/1 A, live tank current transformers Details
  8Tender for annual maintenance contract for repair, overhauling, maintenance and alignment of 220/132/100/33/22kV isolator at various Details
 
You can also click on Tenders for more  
For reference purposes the website carries here the following newsclips:

 8
Renewable energy sector to transform Rajasthan: Experts at BS Samriddhi Details
 
8Unlocking the power of peer-to-peer energy trading in India Details
 
8Servotech bags INR 29 Cr solar rooftop order from Indian railways Jaipur division Details
 
8Solar stock in focus after receiving order for solar power generating system Details
 
8Servotech strengthens renewable footprint with 7.3 MW solar project Details
 
8Sanjay GV Reddy lauds government on achievement of energy goals 5 years ahead of time Details
 
8Hydro Pumped Storage Projects exempted from seeking CEA's approval in major boost for power producers Details
 
8Coal India and Konkan railway sign MoU to develop rail Infrastructure Details
 
8India celebrates clean energy milestone but coal still king Details
 
8NTPC commissions solar & wind energy capacity Details
 
8Vedanta records 2.6 billion units of renewable energy use in FY25, marking significant growth Details
 
8Maharashtra government inks MoUs worth Rs 42,000 crore ahead of local polls Details
 
8Karnataka achieves milestone as green energy powers 80% of state’s supply Details
 
8India set to create 6 lakh jobs and global hub in Green Hydrogen Sector by 2030 Details
 
8CEA releases draft revised guidelines for model quality assurance plan in power sector Details
 
8Indian wind turbine maker Inox Wind trims stake in EPC subsidiary Details
 
8Gujarat, Chhattisgarh and MP promise land to NTPC to set up nuclear power plants Details
 
8At 38,219 MW, Gujarat tops renewable energy capacity in the country Details
 
8India’s solar surge marks a bold leap towards a Net Zero future Details
 
8India’s coal clash: Power vs. planet Details
 
8From Risk to Readiness: How India’s electrical sector can tackle emerging cyber threats Details
 
8India awards 862,000 TPA green hydrogen capacity, eyes 10% of global demand Details
  
You can also click on Newsclips for more

Details
8RTM price split: PXIL/HPX hit cap; IEX stayed benign
On 2025-08-19, PXIL and HPX RTM both cleared at the Rs 10.00/kWh cap, while IEX RTM averaged a far lower Rs 3.19/kWh.
Inference — Scarcity pockets on thinner venues + heavy TRAS/SCUC intervention likely damped the main pool’s MCP dispersion.
Why it matters — Fragmented liquidity can swing procurement costs by ~Rs 6–7/kWh for buyers straddling platforms.
8WR–NR moved power all day; ATC bound in 12 blocks
WR→NR net exports reached 342.8 MU and ER→NR 71.1 MU even as the WR–NR corridor breached ATC in 12 blocks (12.5%).
Inference — NR’s evening peak was met without shortage while large forced outages inside NR pulled imports.
Why it matters — Sustained cross-regional dependence heightens basis risk if WR/ER corridors tighten.
8Frequency saw 314 excursions; low at 16:15 IST
The grid logged 190 excursions >50.03 Hz and 124 ; 15-min average low 49.889 Hz at 16:15 (block T66); FDI 21.9.
Inference — Afternoon ramping plus downward TRAS episodes likely clustered the tails.
Why it matters — Elevated balancing effort raises ancillary costs and increases UFLS risk if ramps steepen.
8Tertiary dispatch peaked at 3.5 GW; SCUC-Up 58.62 GWh
TRAS delivered Up 16.12 GWh / Down 26.13 GWh (max +3.5 GW, min −4.0 GW); SCUC scheduled Up 58.62 GWh / Down 53.60 GWh.
Inference — Reserves bridged midday-to-evening ramps while compressing main-pool price volatility.
Why it matters — High reserve usage, if persistent, translates into Rs-crore-scale uplift on end-user tariffs.
8GDAM leaned on solar; price sat just under DAM
GDAM weighted MCP printed Rs 4.08/kWh vs DAM Rs 4.13/kWh; solar formed ~31.5% of GDAM MCV.
Inference — Day-ahead solar volume helped anchor GDAM near DAM without the RTM’s spikes.
Why it matters — DISCOMs can hedge RTM volatility by leaning into GDAM solar blocks.
8NR forced outages ≈21.23 GW; peak shortage still zero
Inference — NR’s 2025-08-19 forced outages sum to ≈21.23 GW (planned ≈5.62 GW), yet evening peak showed zero shortage.
Why — WR/ER inflows backstopped availability.
Why it matters — Any corridor tightening could force higher-cost RTM/ancillary buys for NR.
8ER exported 71 MU to NR as voltages held band
ER→NR net −71.1 MU while key ER 765 kV buses (e.g., Ranchi New, Angul, Gaya) recorded 0% time outside band (VDI).
Inference — Adequate reactive support enabled sustained ER exports without voltage penalties.
Why it matters — Stable ER voltages support NR reliability through the peak ramp window.
8Rajasthan anchored RE; NR hydro supplied 442 MU
Rajasthan delivered 124.70 MU solar and 16.12 MU wind on 2025-08-19; NR hydro output was 442 MU.
Inference — Western RE + northern hydro shaped day-ahead price formation and offset RTM exposure.
Why it matters — Hydro-with-RE coordination can trim evening procurement at steep RTM prices.
Click on Details for more
Details
8Find a snapshot of thermal, hydro, pumped storage,
solar, wind, BESS and T&D contracts related updates for the day
Click on Reports for more Details
Rajasthan tender shifts from empanelment to price discovery
8Unlike the earlier EoI which only shortlisted firms the current RfP moves into tariff competition.
8Lowest bidder per substation lot will be awarded with strict exclusion rules for ineligible plants.
8The limited bidding format ensures that only firms qualified in the March EoI can participate. This narrows the competition pool and raises the stakes for tariff strategy.
8The package aggregates over 30 substation-linked slots of 1.5 – 2MW solar capacity each all under Sanchore Division. Developers will secure allocation substation - wise based on lowest quoted tariffs.
8By capping bids at Rs.3.04/kWh the discom sets a benchmark aligned with prevailing grid - level costs. Developers quoting higher rates will be treated at ceiling forcing efficiency gains in smaller solar deployments.

Civil mega-package pushes deadline to month-end
8The 800 MW thermal expansion in Chhattisgarh has seen multiple extensions with the balance civil and architectural package now set to close on August 29. The scope spans the entire power block under a leading central PSU’s ownership, making it one of the most crucial latest Indian power tenders in the thermal expansion cycle.
8What began as a July submission has rolled through five corrigenda, landing at a late August deadline. Contractors see the shifting timeline as an indicator of intense pre-bid clarifications for this supercritical plant’s civil scope. The constant rescheduling puts this project among the most closely watched latest Indian power tenders, especially for EPC and civil contractors eyeing large-scale thermal projects.
8Multiple time shifts suggest both bidder mobilisation and owner clarifications. Civil balance works of this magnitude at a supercritical unit remain among the most contested packages in NTPC’s expansion program. For developers, vendors, and suppliers, this tender stands out in the list of latest Indian power tenders, highlighting the strategic importance of civil works in supercritical capacity additions.
8Industry players believe that every extension strengthens competition and enhances clarity—marking this civil package as a benchmark in latest Indian power tenders where project readiness, execution capacity, and bid strategies will define the outcome.
Details
Substation shift signals recalibrated grid priorities
8A 2×150MVA GIS package has been reassigned from one Bengaluru node to another highlighting how planning agencies are realigning load centers. The project is under a state utility’s ownership and comes with a 35 - year BOOT mandate.
8The share purchase agreement stipulates that immediately after acquisition the entire board of the SPV is reconstituted with the winning bidder’s nominees ensuring seamless project control.
8Unlike earlier intra  - state projects the scheme leans heavily on 1200 sqmm underground cables for 220kV connectivity  —   an executional challenge and a cost escalator rolled into one.
8Planners have built in multiple spare 220kV and 66kV bays anticipating industrial and residential load growth near Bengaluru’s emerging northern corridor. Details
Substation package folds in dismantling works for a sharper scope
8A 220/132 kV grid substation project with bay extension has been reissued under a major Indian power sector PSU. The inclusion of dismantling obligations makes it different from earlier rounds, reshaping risks for EPC bidders in the Indian power projects space.
8The tender for a high-capacity grid substation now mandates a detailed spares commitment ranging from breaker poles to hydraulic assemblies, a cost escalator that bidders in the Indian power sector must plan for. This additional requirement sets a new benchmark for power infrastructure projects in India, where spares provisioning is becoming as critical as construction.
8The package value is pegged close to Rs. 942 crore with a 24-month execution period. For contractors, this signals a capital-intensive but high-profile opportunity under a central PSU, adding fresh momentum to Indian power projects and highlighting how power sector tenders in India are evolving to include sharper technical and financial risks.

Solar RESCO race opens under capped tariff regime
8A decentralized tender of over 60 MW has entered the tariff discovery stage under a state utility, marking another significant addition to ongoing solar projects in India. Developers must commit to 25 years of O&M, with ceiling tariffs fixed at Rs.3.04/kWh, pushing bids into a low-margin zone.
8Unlike past rounds, this bid enforces a strict cap on solar tariffs. With 2 MW projects spread across more than 30 substations, only the most cost-efficient developers will withstand long-term obligations under PM-KUSUM A. Such distributed capacity design adds to the growing list of solar projects in India that aim to integrate renewable generation closer to demand centers.
8Instead of one large block, the package splits capacity into dozens of 2 MW lots, each tied to specific 33/11 kV substations. This structure favors smaller developers while complicating aggregation strategies. The approach mirrors recent solar projects in India, where policy design encourages local participation but tests developers’ ability to sustain margins across dispersed sites.
8With tariffs capped and obligations stretched over 25 years, the tender reflects a challenging but strategic phase in solar projects in India, signaling a deeper shift towards decentralized, utility-led growth in renewables.

Details
Consultancy bidders expected to deploy niche hydro experts
8With a 186MW hydroelectric project under tender consultants must field experts in tunneling caverns pressure shafts and dam safety. Deliverables are tied to real-time progress upping execution pressure.
8The consultancy tender for a 186MW hydro project has now been extended to August 26. The repeated rescheduling highlights the complexities of engaging suitable PMC partners for the northeast.
Bengaluru grid set for big reinforcement
8A fresh intra - state package to build a 2×150MVA gas - insulated substation with multiple underground and overhead links has been tendered. The state - owned transmission utility is backing the land provision while a private TSP will execute on BOOT basis.
8Besides the 2×150MVA transformers the contract reserves space for additional bays and transformers signalling forward planning for Bengaluru’s load growth.
8While the utility will provide the site the TSP must coordinate acquisition formalities. This clause has been contentious in past projects and will be closely tracked by contractors here. Details
Civil contractors tapped for island gas hub
8NTPC has extended the civil works tender for its Andaman Nicobar gas power project till 10th September 2025. Scope spans plant foundations utility systems and balance infrastructure critical for the island’s shift from diesel - based supply.
Underground hydro package pushes civil limits
8A 120MW Himalayan project’s power house tender spans deep caverns vertical shafts and steel liner works. With deadlines stretched till August 23 the package tests contractor readiness for underground execution.
8Multiple adit requirements will push bidders to plan simultaneous excavation fronts raising equipment and manpower needs.
8A unique package design folds underground switchyard construction into the power house scope expanding both excavation footprint and MEP interfaces. Details
Mysuru’s grid upgrade blends scale with speed
8A 2×150MVA backbone coupled with two 2×20MVA rural nodes illustrates KPTCL’s hybrid planning a major node with smaller satellites enabling faster execution while meeting district - level load growth.
8Alongside the 220kV node two downstream 2×20MVA substations are planned at Chikkanerale and Panchavalli. The design ensures short 66kV links cutting technical losses and improving feeder reliability in western Mysuru.
Gas engines power a remote 50MW island push
8A rare gas-based generation project is being tendered under NTPC ownership in the Andaman & Nicobar Islands. The bid scope spans EPC delivery of engines auxiliaries and island grid integration. Extended to 10 September the package is attracting attention for its off-mainland significance.
8While India largely leans on gas turbines this package is among the very few full - fledged gas engine EPC opportunities. The project designed for 50MW puts execution risk on bidders across civil electrical and mechanical fronts.
8The submission window has seen multiple extensions since December 2024. The latest push sets bid closure at 9 September with opening on 10 September giving EPC contractors one last chance to prepare. Details
Himalayan hydro tunneling package tests civil giants
8The 260MW Stage - II’s Lot - I package covers intake head race tunnels surge shaft and a cavern powerhouse. With bids extended till 25th August contractors face one of the toughest Himalayan assignments.
Balance of plant tender reshaped for carbon utilization push
8A new balance of plant package has been floated for a carbon capture and utilization project covering ethanol and urea units. The scope spans utilities civil works and a two - year O&M under a government - owned utility’s financing.
8The bid submission date initially in August has now been extended to 22 September with techno - commercial bid opening slated for 23 September. The extensions hint at detailed clarifications and industry interest. Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8Coal and Coke
8LPG
8Ammonia
8All tankers
8Bulk and Dry cargo
Click on Reports for more. Details
Substation expansion drive gets another bid window extension
8A state transmission utility has once again extended the deadline for a major Indian power projects package. Covering three new 132 kV substations with associated transmission line projects, the bid submission has been pushed back first from August 18 and now till August 26. Such repeated extensions in substation projects highlight the complexity of site readiness and the challenges of contractor mobilization in large EPC contracts.
8With bidding now open till August 26, the three substation projects package offers a wide execution scope—from civil works to bay erection and SCADA integration. Contractors engaged in Indian power projects will need to balance transformer delivery timelines with simultaneous power transmission line execution.
8The tender stands out as a complete execution package, covering design, supply, erection, testing, and commissioning of 132 kV transmission line projects. For developers and EPCs active in Indian power projects, this extension provides more time to align procurement with site execution.

Solar with storage push climbs to 7MW in high-altitude frontier
8A Ladakh-based public sector initiative is tendering a 7MW solar PV plant with a 9MWh battery system under the RESCO model. The tariff-based project extension gives developers extra time to recalibrate bids for complex grid integration. This adds to the momentum of solar projects in India, where hybrid PV-storage systems are increasingly gaining ground.
8The tender extends its deadline to 28 August, requiring bidders to deliver both generation and storage under a single RESCO package. Performance guarantees and long-term O&M obligations could raise financing challenges in remote terrain—issues often seen in solar projects in India that combine utility-scale deployment with storage mandates.
8Developers are tasked with designing and installing a PV + BESS package at 3500m altitude, where temperature swings and derating effects can stress equipment. The tender scope spans engineering through long-term operation, underscoring the growing technical complexity of solar projects in India being planned in frontier geographies.
8With its hybrid configuration and altitude-specific challenges, this initiative is a strong example of how solar projects in India are evolving from plain vanilla PV to more advanced, integrated solutions.
Details
8Real-Time Prices Split the Day in Two
RTM on 2025-08-18 swung from Rs 0.41/kWh at 13:00 to Rs 5.63/kWh at 19:00; the day averaged Rs 2.87/kWh.
Inference: The extreme intraday span points to bid-side conditions and product-mix effects rather than system-wide stress.
Why it matters: Portfolio hedges that ignore intraday shape risk will leak value even when day-ahead looks “benign.”
8Day-Ahead Stayed Firm as Intraday Whipsawed
On 2025-08-18, DAM weighted MCP was Rs 4.48/kWh with 158,299 MWh scheduled, while RTM averaged Rs 2.87/kWh the same day.
Inference: Stable day-ahead clears alongside volatile real-time suggest demand certainty at D-1 with flexibility priced in RTM.
Why it matters: Split your procurement anchor in DAM, fine-tune in RTM rather than treating them as substitutes.
8Three Exchanges, One Day, Three Stories
PXIL RTM (2025-08-14) cleared 275 MWh at Rs 10.00/kWhHPX RTM (2025-08-18) showed zero scheduled volume despite sell bids; IEX RTM (2025-08-18) cleared 153,031 MWh at Rs 2.87/kWh avg.
Inference: Liquidity and therefore price discovery remains concentrated on IEX, with PXIL showing episodic spikes and HPX thin prints.
Why it matters: OA buyers chasing “cheapest screen” risk slippage if they ignore exchange-specific depth.
8North’s Outage Book Is Heavy, Frequency Stayed Calm
On 2025-08-18 in NR, 
planned outages totalled 5.87 GW and forced 6.60 GW (12.47 GW combined). System-wide that day, mean frequency was 49.986 Hz; FDI 21.4.
Inference: Large unit outages did not spill into primary frequency stress pointing to reserves/load-gen alignment.
Why it matters: With outage risk internalised, price shocks won’t track headline MW unless reserves are thin.
8Assam Corridors Were Constrained a Third of Sunday
On 2025-08-17, 
NER-Assam TTC violations persisted for 28.6% of the day; ATC violations for 33.3%. DAM that day still printed Rs 2.78/kWh weighted pan-India.
Inference: Tightness was regional; national DAM stayed anchored by diversified supply and flow re-routing.
Why it matters: Buyers in NER face corridor-specific exposure even when all-India prices look soft.
8Eastern 765-kV Stayed Inside Band; North Had a Hotspot
On 2025-08-17, 
ER 765-kV nodes (e.g., Ranchi New, Jharsuguda) spent 100% of time within IEGC voltage band. On 2025-08-18, Chittorgarh showed 4.65% time above band.
Inference: Reactive control remains tight in ER, while a NW pocket needs tuning.
Why it matters: Voltage discipline lowers loss, improves transfer headroom, and dampens imbalance charges.
8Southern Hydro and Wind Did the Heavy Lifting
On 2025-08-18, 
Karnataka hydro 54.60 MUKerala hydro 35.23 MUTamil Nadu wind 113.78 MU. Meanwhile, HPX GDAM/HPDAM showed zeros across blocks.
Inference: SR balanced with scheduled hydro/RE rather than green exchange products, keeping procurement off-screen.
Why it matters: Asset-backed balancing can mute visible “green” liquidity buyers should track state supply stacks, not just GDAM prints.
8Station-Side Work Dominates NR Transmission Outages
On 2025-08-18, 
planned NR transmission outages skewed toward substations: 70 bays56 lines13 ICTs under the Planned sheet.
Inference: Utilities are prioritising node-level reliability (switchyards/transformers) over corridor outages prepping for shoulder-season flows.
Why it matters: Node hardening boosts resilience; corridor limits will bite only if dispatch surges past intra-regional thresholds.

Details
Stringent criteria set for IREDA's director role, highlighting sector specificity
8IREDA outlines rigorous eligibility for its Director (Projects) position, emphasizing experience in technical, financial, and environmental project management, underscoring a targeted approach to candidate selection.
Stakeholders face uncertainty as UERC relaxes regulations for temporary load release
8UERC's decision to allow temporary load release at a lower voltage level reflects the dynamic regulatory landscape and the pressing need for infrastructure development in the power sector.
UPCL’s draft PPA scrutiny highlights need for detailed evacuation plans
8The absence of evacuation plans in the draft PPA with JGN Sugar could lead to project delays, stressing the importance of comprehensive agreement terms.
Delays and disputes: UPCL challenges UERC's penalty enforcement
8The ongoing petition by UPCL against hefty penalties imposed by UERC for LT connection delays illustrates the friction between regulatory mandates and execution on the ground.
Uttarakhand's power network set for enhancement with substation upgrade approval
8As industrialization and solar power projects surge, the UERC has greenlit pivotal upgrades at the Jhajra substation, cementing infrastructure resilience in Dehradun's Garhwal Zone.
Click on Details for more
Details
Solar developers face land acquisition hurdles, UERC to review SCOD extensions
8Land acquisition issues are stalling solar projects across Uttarakhand. UERC's call for stakeholder comments may influence how such challenges are addressed in future policies.
Stranded energy due to open access: UPCL claims 21.95 MU loss
8UPCL reports 21.95 MU of stranded energy linked to open access consumers, raising concerns about the impact on fixed costs and prompting a call for surcharge adjustments.
Delayed technical feasibility reports stall Uttarakhand solar projects
8Doon Valley Solar's attempts to shift project sites highlight inefficiencies in UREDA's approval processes.
8Industry observers call for streamlined regulatory frameworks.
Sarju-III tariff decision: potential ripple effects for Uttarakhand energy tariffs
8The outcome of Sarju-III's tariff re-evaluation could influence energy pricing, affecting financial models and strategic planning for regional power projects.
Detailed FPPCA computations submitted: UPCL's bid for transparency
8In a move towards greater transparency, UPCL submits comprehensive FPPCA calculations, marking a significant step in aligning with regulatory expectations and ensuring consumer trust.
Click on Details for more
Details
Substation automation package attracts niche bidders
8A specialized tender to equip Sikkim’s state load despatch centre with modern substation automation system (SAS) and ABT meters has drawn three names. The Indian power sector project aims at cutting technical and commercial losses in electricity distribution.
8Technical bids are in for an SAS ABT project that will embed monitoring, control, and audit systems into Sikkim’s power sector grid framework, strengthening substation automation and real-time loss tracking.
8A package integrating ABT meters with substation automation is under evaluation after the technical bids closed, highlighting a broader push for smart grid initiatives in India’s electricity distribution network.
8The project underlines a push for real-time transparency in grid losses and monitoring, a step aligned with national power sector reforms and efficiency goals.

Ash evacuation package sees fresh extension push
8A large utility’s ash handling tender for a new thermal unit has been extended multiple times now till late August reflecting bidder demand for clarifications in a technically heavy balance of plant scope.
8The ash management package at a central PSU’s thermal site covering both bottom and fly ash evacuation has moved its submission deadline to August 25 after successive extensions.
8The ash handling system tender at a state run power producer’s second stage units has seen its closure pushed to August 25 reflecting the complex EPC nature of the package. Details
8Find a snapshot of thermal, hydro, pumped storage,
solar, wind, BESS and T&D contracts related updates for the day
Click on Reports for more Details
8A 2x800MW super thermal expansion has reached the technical bid stage with a mix of EPC majors and specialists competing. The package covers critical BoP systems under a leading PSU’s ownership.
8Contractors from infra EPC and ash handling backgrounds have entered the fray for a 2x800MW Stage II BoP package underscoring the multi utility nature of this contract.
8Technical bids for a large 1600MW Stage II project have drawn both niche BoP firms and full scope contractors signaling wider vendor appetite for NTPC scale packages. Details
8Three firms have submitted bids to engineer and commission integrated ash handling facilities across three 800MW units owned by a central power utility marking a key step in project execution.
8A large scale ash handling package linked to a 2400MW pithead coal station is now in technical evaluation highlighting the importance of seamless ash evacuation for uninterrupted plant operations. Details
8Four firms have prequalified to vie for the high voltage corridor including top transmission majors and infra contractors. The winner will construct and maintain the system for long term tariff recovery.
8To integrate upcoming solar and wind projects a new ISTS package will link Davanagere’s renewable hubs into the national grid. The scope spans 765/400kV lines bays and substation augmentation.
8The project forms part of the national renewable integration roadmap under the CTU’s long term grid plan. It will reduce curtailments and enhance interstate power transfer capability. Details
Hybrid transmission build tests contractor capabilities
8A 400kV line diversion combining both overhead and underground sections has been floated by a state utility. The mix of cable and tower works at a new GIS substation in Uttarakhand raises execution complexity and contractor risk.
8The deadline for a high voltage LILO package has now been stretched to 2 September. Five rounds of extensions suggest bidders are factoring in hybrid design challenges and tight Roorkee site conditions.
8The project demands integration of overhead lines with cable sections into GIS bays. Protection relay coordination and testing protocols will require higher engineering diligence than standard line LILO works.
CSP transformer tender drags on with 10 + deadline shifts
8A state utility’s procurement of 40kVA aluminium wound CSP distribution transformers has now been stretched into September. Frequent extensions point to active vendor negotiations and tightening technical clarifications under TN 2025 norms.
8Mandatory Star 1 rating combined with a completely self protected design raises the bar for small transformer suppliers. Utility insistence on built in overload and short circuit protection goes beyond earlier bulk transformer packages. Details
Ninth extension pushes 400 kV intra - state project further
8A critical 400 kV substation package in southern India has now seen its bid date stretch to late August. The project floated under tariff based competitive bidding reflects the owner’s difficulty in aligning developers for a large capacity intra state backbone scheme.
8Despite its strategic role in southern India’s grid strengthening a 400 kV intra state transmission package remains in limbo after nine bid extensions. The owner continues to seek wider participation through relaxed timelines.
8A 400 kV substation and line package meant to boost Karnataka’s transmission capacity has repeatedly moved its bid date. Industry sources point to issues of land readiness technical specifications and coordination with renewable inflows.
Karnataka grid upgrade hinges on new 400 kV hub
8The project aims to establish a large 400kV substation with associated lines under the TBCB model designed to ease load flow in Mandya district. For bidders this signals both an engineering heavy build and long term O&M responsibility.
8A tariff based competitive bidding project for a 400kV intra state substation has now stretched to its ninth extension with bids due late August. The persistent delays underscore both heightened interest and the complex preparation challenges for prospective transmission developers. Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8Coal and Coke
8LPG
8Ammonia
8All tankers
8Bulk and Dry cargo
Click on Reports for more. Details
 For reference purposes the website carries here the following tenders:
8Tender for work contract for round the clock operation and maintenance of 140 MT capacity in motion weigh bridge installed Details
8Tender for procurement of spares for valves for BFP recirculation, superheater Details
8Tender for procurement of high alumina castable refractory grade A and P for boiler Details
8Tender for supply of material and erection of additional earth pits and earth mat for replacement of corroded earth rods Details
8Tender for supply of single pole vertically operated 11kV gang operated AB switch with composite polymer insulators Details
8Tender for supply of multiple port outlet cast steel 4896 Gr2 with nihard liner on two sides for HP803 bowl mills Details
8Tender for supply of 230kV 90KN 120KN polymer composite insulators Details
8Tender for works contract for HT/LT line works Details
8Tender for biennial contract for maintenance and renovation Details
8Tender for annual maintenance support services works for all types of civil works Details
8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects Details
8Tender for manufacture, supply, and erection of 150 feet span DDR construction extra wide bridge suitable Details
8Tender for provision of septic tank and soakage well Details
8Tender for increasing capacity to 1000 KVA substation Details
8Tender for increasing capacity of various DTRs Details
8Tender for increasing capacity of various distribution transformers and strengthening of related LT lines Details
8Tender for construction of electrical infrastructure work up to the project Details
8Tender for construction of electrical infrastructure work Details
8Tender for construction of 33 kV line Details
8Tender for ARC of hydrojet of condenser tubes Details
8Tender for execution of electrical works upto 11 kV HT/LT line Details
8Tender for work of laying of underground cable for shifting of 66kV rail pole line Details
8Tender for erection of new 66 kV S/C line Details
8Tender for work of various & schedule plant maintenance activity Details
8Tender for replacing of damaged sheet of boiler feed pump Details
8Tender for work of hotline stringing with ACSR panther conductor in 2nd circuit of existing 66kV panther tower Details
8Tender for work of hotline stringing with ACSR panther conductor   Details
8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects Details
8Tender for work of 220 kV line and breaker isolator Details
8Tender for work of stub strengthening of 66kV line Details

8Tender for estimate for conductor aug.of 33 kV line Details
8Tender for estimate for conductor aug.of 33 kV feeder Details
8Tender for estimate for creation of 66 kV bays Details
8Tender for construction of 66 kV and 132 kV composite transmission lines Details
8Tender for supply of 230 kV solid core insulators Details
8Tender for supply, fabrication and erection of damaged/worn-out fire hydrant lines Details
8Tender for work of replacement of various size of IBR approved 2500 class valves Details
8Tender for height raising of all installed C&R panel Details
8Tender for work of mechanical and stub-strenghtning work of 66kV line Details
8Tender for laying of 33 kV under ground cable Details
8Tender for construction of 132 kV GSS along with associated lines Details
8Tender for construction of 132 kV GSS Details
8Tender for raising of RCC pedestal for ash slurry pipe line Details
8Tender for overhauling of APH of unit 5 Details
8Tender for overhauling of HT motors Details
8Tender for supply of microcontroller based PID controllers Details
8Tender for erection of HT, LT line & TC work Details
8Tender for work of overhauling, repairing & reconditioning of damaged cartridges assembly of 200KHI boiler feed pump Details
8Tender for supply, erection and commissioning of new street light poles with cable laying Details
8Tender for work of refurbishment of primary air fan rotor assembly, 2 X 250 MW boiler Details
8
Tender for overhauling of 315 MVA 400/220kV interconnecting transformers installed Details
8Tender for three yearly schedule maintenance of locomotive no 07 WDG3A including supply of material Details
8Tender for repair overhauling including replacement of spares of transmission assemblies Details
8Tender for supply, fabrication erection SS accessories steel structures earthing Details
8Tender for supply of titanium channel plates with nitrile rubber with gaskets Details
8Tender for works contract for laying of various new 11kV OH feeder Details
8Tender for procurement of guide vane lever bushes & link pin bushes for turbines Details
8Tender for work of O/H & servicing of boiler feed pump Details
8Tender for misc. electrical works Details
8Tender for renovation upgradation supply, erection & commissioning of ABT system Details
8Tender for construction of 33 kV sub-station Details
8Tender for procurement of GE numerical /aux. relays for LT switchgear Details
8Tender for supply of various size tubes for Details
8Tender for supply, stubsetting, concreting and erection of 110 kV DC line on DC towers with panther conductor Details
8Tender for underground cable laying works Details
8Tender for comprehensive AMC of communication system Details
8Tender for retro fitment and reconditioning of MSB and ACDB panel Details
8Tender for supply of towers and tower parts including stubs and nuts and bolts for various Details
8Tender for supply of ground stabilizing mats of HDPE composite Details
8Tender for sale of aluminium cable scrap available Details
8Tender for sale of ASCR conductor scrap available Details
8Tender for construction of switchyard, cable trench, pathway, equipment foundation, fencing and associated civil work Details
8Tender for laying of 33 kV, 3 x 400 sqmm XLPE UG cable Details
8Tender for laying of new 33kV UG cable Details
8Tender for service order for servicing of burners, SADC, CCP etc Details
8Tender for work of in-situ repairing of high pressure valves and spring loaded boiler safety valves Details
8Tender for renovation & extension of existing excitation room for replacement of electrical panels during Details
8Tender for fabrication & erection of bunker partition plate, side wall, support & structure for coal mill Details
8Tender for construction of balance civil works for new 66 kV sub station Details
8Tender for construction of exploratory drifts for geological investigation in powerhouse Details
8Tender for supply, civil, ETC works of 400kV 1x125MVAr 3ph bus reactor with NGR along with allied equipment and civil works Details
8Tender for conversion of existing 11 kV HT line network in to under ground cable network Details
8Tender for work of complete overhauling, routine, preventive and breakdown maintenance of air conditioning system Details
8Tender for work of on-line leak sealing services for high temperature & pressures valves, lines etc. Details
8Tender for supply of mechanical measuring instruments & spanners Details
8Tender for supply, commission & erection of 160 KVA DG set Details
8Tender for supply of coal discharge pipe Details
8Tender for supply of microprocessor base motor and feeder protection relay Details
8Tender for work of online preventive and breakdown maintenance for boiler, its mountings and accessories Details
8Tender for bi-annual rate contract for erection work of 66kV feeder bays, 66kV transformer bays Details
8Tender for erection work of 66kV S/C line Details
8Tender for work of proposed EHV underground cable Details
8Tender for supply of equipments / material, erection, testing and commissioning for the work of augmentation by replacement of 132/110/33kV, 2 x 25 MVA TF Details
8Tender for work of chemical (by using high voltage insulator cleaner and protector) of insulator strings Details
8Tender for supply of various digital T&Ps for traction sub stations Details
8Tender for annual maintenance contract for attending planned outages & emergency breakdown work at 400kV S/stn Details
8Tender for procurement of 33kV VCB as a critical spare Details
8Tender for procurement of 33kV isolators Details
8Tender for procurement of 33kV CT & PT as a critical spare Details
8Tender for biennial rate contract for attending emergency breakdown works & shutdown maintenance works in 132/220kV EHV substations Details
 
You can also click on Tenders for more
 For reference purposes the website carries here the following newsclips:
8New Delhi pact to strengthen coal transport efficiency Details
8Suzlon group pledges 100% renewable energy usage at all units by 2030 Details
8How a digital energy stack can transform India’s power sector Details
8Reliance Infrastructure bags NHPC's Rs 4,000-crore solar-battery project Details
8India curbs solar output to stabilise power grid amid low demand: Ministry Details
8ACME Cleantech wins latest green ammonia auction in India Details
8How India’s electrical sector can tackle emerging cyber threats Details

 8
Overcoming land constraints for powering India’s solar energy future Details
 
8Anil Ambani-led Reliance Infra bags 700 MWp NHPC solar and storage project Details
 
8Ahead of IPO, Vikram Solar raises Rs 621 cr from anchor investors Details
 
8Waaree Energies share reacts as Enel Green Power deal on verge of collapse Details
 
8Kamath charges up Goldi Solar with a Rs 137 cr bet Details
 
8What to do with Inox Wind post Q1 brokerages decode stock strategy Details
 
8Inox Wind gains 5% on offloading 175 crore worth of stake in its arm Details
 
8Renewable energy stock jumps 14% after reporting 445% YoY increase in net profits Details
 
8Timeline: How Rajasthan became India's top solar hub in just a decade Details
 
8UltraTech launches India’s first on-site hybrid renewable power project for cement manufacturing Details
 
8Delhi Metro seeks inclusion in 'islanding' scheme to safeguard operations in case of grid failure Details
 
8Rs 6,487 crore sanctioned so far for electrification of 13.59 lakh households Details
 
8Ashish Gupta senior deputy general manager, powergrid energy services limited Details
 
8Inside Cummins India’s 64-year power and sustainability journey Details
 
8Powering farms: Scaling up PM-KUSUM is smart climate and energy strategy Details
 
You can also click on Newsclips for more Details
8Find a snapshot of thermal, hydro, pumped storage, solar,
wind, BESS and T&D contracts related updates for the day
Click on Reports for more Details
 For reference purposes the website carries here the following tenders:
8Tender for supply of surge arresters and accessories for various substations Details
 8Tender for supply, erection, testing and commissioning of material of 11/0.4kV S/S Details
 8Tender for construction of 33/11 kV GSS along with associated 33 and 11 kV lines works Details
 8Tender for const. of 33 kV S/S Details
 8Tender for construction of 33/11 kV GSS Details
 8Tender for construction of transformer track Details
 8Tender for construction of foundations for 1Nos 33kV, 5.43MVAR capacitor bank Details
 8Tender for repairing of isolator switch boxes and circuit breaker platforms at 220 kV GSS Details
 8Tender for construction of foundation for 40/50 MVA transformer Details
 8Design, supply, installation, commissioning and 05 years O&M of 100 kW solar PV plant Details
 8Tender for procurement of moog motion proportional valve for runner blade Details
 8Tender for routine maintenance of IOX-1200 (1200-line) Details
 8Tender for reconditioning of mill under bowl Details
 8Tender for repair and maintenance of ash dyke Details
 8Tender for major overhauling of 20.2 MW GTG 2 generator Details
 8Tender for annual maintenance routine maintenance operational support of electro mechanical equipments Details
 8Tender for gravelling work with providing concrete base at 220 or 132 or 33 kV sub station Details
 8Tender for repair of exposed reinforcement with cementitious mortar in S7 pier in the penstock Details
 8Tender for maintenance and repair works Details
 8Tender for balance of system package for setting up of 401 MW solar projects Details
 8Tender for augmentation by replacement of 01X25 MVA,132/33 kV power transformers Details
 8Tender for supply of pneumatic power cylinder Details
 8Tender for supply of FSSS spares Details
 8Tender for bi-ennial rate contract (BRC) of complete boiler plant Details
 8Tender for work of mechanical strengthening and stub strengthening of existing 66kV line Details
 8Tender for supply of various consumable item Details
 8Tender for work of mechanical strengthening and stub strengthening of existing 66kV lines Details
 8Tender for Bi-ARC for erection of 66/132/220kV lines Details
 8Tender for Bi-ARC for the emergency restoration of power of 66KV,132kV & 220kV transmission line Details

8Tender for completion of balance works survey, designing the system, supply of material, erection for renovation/modernization/upgradation/augmentation/bifurcation of the existing 11 kV feeders Details
 8Tender for completion of balance works survey, designing the system, supply of material Details
 8Tender for completion of balance works Details
 8Tender for completion of balance works Details
 8Tender for estimate for bifurcation of 11 kV line work Details
 8Tender for estimate for 11 kV line interconn. work Details
 8Tender for mechanical sampling of rake coal Details
 8Tender for renovation and modification of DSS Details
 8Tender for construction of transformer oil filtration Details
 8Design, engineering, supply, installation, testing & commissioning of 220/132 kV grid substations Details
 8Tender for manufacture, testing, supply and delivery of 33 kV outdoor dead / live tank type current transformer Details
 8Tender for procurement of grinding elements of 8.5E(10) coal mill Details
 8Tender for procurement of electric hoists Details
 8Tender for procurement of DI pipe and fittings Details
 8Tender for overhauling of boiler pressure parts Details
 8Tender for entrusting works contract for carrying out all type of maintenance and emergency works Details
 8Tender for supply installation testing and commissioning of laser-based projection engines with adaptation kit Details
 8Tender for maintenance contract for two years for horticulture works at 400kV substation Details
 8Tender for AMC/RMC works of dam body and allied structures Details
 8Tender for supply and application of dielectric epoxy floor coating materials for 6.6kV HT switchgear Details
 8Tender for routine breakdown maintenance of LT switchgear Details
 8Tender for construction of solar street lighting work Details
 8Tender for erection, testing & commissioning work of 66kV equipments Details
 8Tender for supply of gear box assembly suitable for stacker and reclaimer machine boom conveyor Details
 8Tender for procurement of 24 inch coal valve assembly for XRP 763 bowl mills Details
 8Tender for dismantling of existing heavily wornout fly ash AB pass conveying MS pipe Details
 8Tender for work of non comprehensive biennual maintenance contract for microprocessor based Details
 8Tender for work of electrical protection audit Details
 8Tender for supply of 250A LDB panel for coal handling plant Details
 8Tender for annual horticulture works Details
 8Tender for 4th raising of ash dyke lagoon Details
 8Tender for supply, installation, commissioning including civil works Details
 8Tender for biennial contract for manufacturing of fly ash bricks Details
 8Tender for construction of 66 kV AIS substation Details
 8Tender for BMC of water supply lines Details
 8Tender for augmentation of substation by providing additional 1x50MVA, 132/33kV TF Details
 8Tender for work of new 3x33kV feeder bay Details
 8Tender for work of augmentation of substation by addition of 132/33kV 25MVA power transformer Details
 8Tender for supply of ESP collecting rapping gear box assembly for boiler Details
 8Tender for work of replacement of H-Frame by tower line Details
 8Tender for replacement of damaged /defective 100MVA 220/33kV T-2 transformer Details
 8Tender for creation of 2 No. new 66 kV line bay Details
 8Tender for overhauling of 2 nos of mill reject air compressors Details
 8Tender for supply and erection of turn over panel clip Details
 8Tender for renewal of defective boiler tubes or bends in economizer hanger tubes Details
 8Tender for renewal of defective boiler tubes Details
 8Tender for operation and maintenance of SUL and allied conveyors Details
 8Tender for supply of jaw type coal sampler and coal sampler crusher Details
 8Tender for various civil work Details
 8Tender for construction of RCC wall at stacker reclaimer near 9S drive house Details
 8Tender for erections of 33 kV inter connection line Details
 8Tender for const. of 33 kV SS Details
 8Tender for supply and ETC of 132 kV grid sub-stations Details
 8Tender for annual contract for RBC maintenance and assistance in operation work of screw type compressors and compressed air system Details
 8Tender for R and M work of grouting and water proofing in various structures Details
 8Tender for civil work of storm water in marshalling yard Details
 8Tender for construction of sump pits Details
 8Tender for supply of transmitters installed Details
 8Tender for supply of hydraulic hoses for various equipments Details
 8Tender for supply of LT motors Details
 8Tender for supply of LP valves Details
 8Tender for supply of grinding roll, bull ring segment and air port ring assembly for bowl mills Details
 8Tender for annual work contract for effluent sampling/ stack monitoring/ ambient air quality monitoring Details
 8Tender for rebabitting and machining of used worn out white metal journal bearing Details
 8Tender for miscellaneous civil works at 33/11 kV substation Details
 8Tender for supply of ferric allum grade Details
 8Tender for supply, installation testing and commissioning of equipments for interlinking LT supply between PLBE 16 MW powerhouse Details
 8Tender for procurement of 6 numbers of top bracket oil coolers and 4 numbers of bottom bracket oil coolers Details
 8Tender for inspection and rectification/preventive /breakdown maintenance of ducts, dampers, gates, expansion joints etc. Details
 8Tender for procurement of cartridge assembly for lube oil pumps installed Details
 8Tender for procurement of coal feeder Details
 8Tender for supply and delivery of ABC 5070 Sqmm for main service cable Details
 8Tender for construction of two number 33 kV feeder bay and other allied works at 33/11 kV substation Details
 8Tender for deep screening of rail track including procurement and replacement of machine crushed ballast Details
 8Tender for ash pond 5 bifurcation with construction of common dykes necessary pipe supporting structures Details
 8Tender for service contract for refractory and insulation work Details
 8Tender for construction of pre-cast RCC over slab including repair of cable trench Details
 8Tender for procurement of leakage current meter/analyzer Details
 8Tender for work of supply erection testing commissioning of 2x33kV bays at 132kV substation Details
 8Tender for work of replacement of existing old 220 kV & 132 kV coupling capacitor by new 220 kV & 132 kV coupling capacitors Details

 
You can also click on Tenders for more
 For reference purposes the website carries here the following newsclips:
8Nikhil Kamath invests 137.5 crore in Goldi Solar to expand capacity Details
 8Can India’s power infrastructure keep up with its digital ambitions Details
 8Renewable energy stock jumps 14% after reporting 445% YoY increase in net profits Details
 8SAEL Industries signs 880 MW solar power PPAs in Gujarat, Punjab Details
 8Jakson green wins SECI E-auction For 85,000 MT green ammonia supply At Kakinada Details

8Indian Railways commissions first removable solar panel system between tracks Details
 8Odisha Leads smart meter momentum Details
 8Breaking the coal taboo Details
 8Inside Cummins India’s 64-year power and sustainability journey Details
 8Rooftop solar’s time to shine in Bangladesh Details
 8GAIL and TruAlt Bioenergy form joint venture for CBG development Details

 
8Sindh allots land for first B2B green energy project in Jhimpir Details
 
8CIL Evacuation Plans amid coal demand slowdown Details
 
8Hinduja aims 3X increase in green capacity by 2030 Details
 
8CM Adityanath inaugurates Torrent Group's green hydrogen plant in UP Details
 
8Left in the dark Western UP’s migrant workers lose light faith with unmaintained solar panels Details
 
8Switching to Monopoles: An economically viable solution for urban areas in India Details
 
8Power Sector Reforms: Oversight and Accountability Details
 
8Opening nuclear energy to private sector participation key to meeting India’s nuclear ambitions: L&T Chairman Details
 
8Transmission & distribution focus areas for Tata, Adani Details
 
8Haryana Power: Consumer rights & rule changes Details
 
8Harnessing Biomass: CBG sector gains momentum but challenges remain Details
 
8Rajasthan rides the crest of renewable energy wave, attracts investments Details
 
8Clear directives, data visibility crucial for smart meter success: CII poll Details
 
8Green energy stock to buy now for an upside of 54%; Recommended by Motilal Oswal Details
 
You can also click on Newsclips for more Details
Critical transmission link gets dedicated tower erection squads
8A key section of a 765kV interstate corridor will now see direct manpower deployment for tower erection and conductor stringing targeting rapid closure of a high - priority grid link between two western states.
8In a shift from the original EPC model a central transmission utility has carved out a focused package for manpower - based execution signalling urgency in meeting commissioning milestones for a high - capacity line.
8A concentrated work drive is set for a challenging Wada section of a 765kV transmission project where terrain and right - of - way issues have slowed conventional execution.
Massive REZ-linked transmission package pushes bid deadline to late August
8The 3 GW interstate transmission system for renewable evacuation in Andhra Pradesh has seen its submission date moved to 25 August, giving developers extra time to prepare for one of the largest multi-substation, multi-voltage transmission projects under the TBCB route in the Indian power sector.
8The scope covers augmentation at a major renewable energy pooling station with 765/400 kV and 400/220 kV ICTs, multiple bus couplers, sectionalizers, and reactor systems a complex power transmission package designed for progressive commissioning over 24–30 months. Such interstate transmission system tenders are shaping the future of renewable energy integration into the Indian power grid.
8The engineering scope extends to looping in critical Talaguppa–Neelmangala 400 kV lines at two points, creating a new CN’Halli–Hassan 400 kV corridor that boosts redundancy and transfer capacity in the power sector transmission network. This underlines the growing focus on reliable renewable evacuation infrastructure in India.
8Plans include over a dozen 220 kV line bays and multiple 400 kV bays to directly connect large-scale renewable energy projects into the interstate transmission system, reflecting the accelerating pipeline of renewable energy generation in Andhra Pradesh and its importance to the Indian power sector. Details
8A waste - to - hydrogen facility using plasma gasification tech at a central PSU’s R&D hub has entered the technical evaluation stage attracting nine diverse bidders from renewable EPCs to O&M specialists. The project targets clean hydrogen from MSW - derived RDF and agri - residues.
8The technical bid opening for a plasma gasification hydrogen facility has brought in a diverse bidder pool underscoring industry interest in waste valorisation pathways for green fuel at a major PSU research site.
8Nine bidders are vying for a plasma gasification-based hydrogen generation package that blends municipal RDF with agricultural waste streams as the technical evaluation phase begins at a central R&D complex. Details
8A grid-connected solar initiative under RESCO mode for 25 years in Rajasthan’s Barmer division has attracted 87 technical submissions marking one of the largest participation volumes under the PM - KUSUM Component - A framework.
8With 87 contenders in the fray the technical evaluation stage for a RESCO - mode 25 - year solar power project in Barmer has concluded setting the stage for the next phase under a long-term PPA model.
8From small EPC firms to major renewable investors the Barmer RESCO - mode solar EOI’s 87 submissions highlight the competitive dynamics shaping rural grid - connected solar procurement. Details
Massive southern grid link plan packs dual - stage substation expansions
8A high - capacity transmission package will see phased augmentation of a key pooling station with 400/220kV and 765/400kV ICTs timed to match rising renewable injections from a multi-gigawatt RE zone.
8The project includes a greenfield 765/400kV station with 330MVAr bus reactors and spare provisions targeting reliability for bulk renewable flow to industrial off - take centers.
8Additional 220kV and 400kV line bays are slated for completion within 24 – 30 months creating early connection points for dedicated renewable lines ahead of full substation build-out.
8Two 330MVAr bus reactors including a switchable spare are embedded in the plan to manage voltage fluctuations from variable renewable sources.
Shift in compliance order alters transmission concession baseline
8The latest amendment replaces a 2024 Ministry of Power sourcing order reference with a 2020 directive in the Transmission Service Agreement potentially affecting OEM eligibility and procurement strategies for the high - capacity coastal evacuation scheme.
8Substituting the 2024 sourcing clause with an older 2020 provision could open the door for previously ineligible suppliers in the multi - kilometre coastal transmission project.
8The amendment reverts to a prior Ministry of Power order changing the reference framework for compliance and potentially shifting competitive positioning among bidders. Details
Long - delayed coastal green energy grid nears bidding showdown
8A major inter - state transmission package for bulk renewable evacuation to power proposed green hydrogen and ammonia plants near Tuticorin is set for bids on 28August after 21 deadline extensions. The BOOT - based scheme will tie in portside generation hubs with high - capacity substations for industrial draw and export loads.
8The tender to select the transmission service provider for a southern India coastal corridor designed to feed multi - MW green hydrogen and ammonia complexes will move into e - reverse auction in mid - September with a high - stakes two - envelope bidding process filtering contenders.
8The ISTS package aims to connect high - output renewable plants with coastal hydrogen production zones using high - voltage substations and multiple termination bays to ensure industrial grade power reliability.
Second Angul – Srikakulam corridor to ease 2030 Southern Region load
8The project aims to unlock additional import headroom into the Southern Region grid with a 275km 765kV double-circuit link dual 240MVAr line reactors at both ends and a third 330MVAr bus reactor at Angul.
8A major inter - state strengthening scheme anchored by a second Angul – Srikakulam corridor and high - capacity bus reactors will now be tendered under a newly designated project company per the latest amendment.
8The third amendment renames the special purpose vehicle for a high - capacity inter - regional transmission corridor ensuring contractual clarity ahead of tariff-based competitive bidding. The 275km 765kV double - circuit line and reactor package targets Southern Region import constraints.
8Alongside the core 765kV corridor the scope includes advanced reactive power management six 80MVAr switchable units per reactor to handle fluctuating flows between Eastern and Southern grids.
8By replacing the placeholder incorporation reference with the final registered name the amendment aligns RFP TSA and SPA documents removing potential ambiguity before bid submission. Details
4GW offshore leasing tender pulled back after clearance groundwork
8Despite securing multiple Stage-I clearances for Tamil Nadu blocks, the proposed international leasing auction under the National Offshore Wind Energy Policy will not proceed, resetting one of the largest Renewable projects in India and its seabed allocation plan.
8The first tranche of a central scheme for 500 MW grid-connected offshore capacity has been terminated, pausing early commercial-scale offshore wind integration into the ISTS network. This setback impacts Renewable projects in India at a time when the government is seeking to diversify clean energy portfolios.
8The shelving of two major RfS processes under a central agency delays developer entry into India’s offshore wind segment, including opportunities for technology transfer and survey investments. Such delays create uncertainty for Renewable projects in India, which were expected to open doors for global offshore wind players.
8Industry observers note that the decision marks a slowdown in offshore Renewable projects in India, even as solar and onshore wind continue to see aggressive expansion under national and state-level policies.

Facilitation - mode push to fast-track high-voltage corridor stretch
8A manpower-focused package under Indian power projects targets a critical 12 km chainage in a 765 kV interstate link under Power Grid’s WR-1 plan, aiming to synchronise delayed sections through expedited tower erection and stringing.
8The WR-1 segment of a 765 kV double-circuit line gets a dedicated execution package where contractors, under Indian power projects, work in facilitation mode to speed up lattice tower assembly and conductor stringing.
8A high-voltage transmission stretch under WR-1 follows a manpower-driven execution model designed to bring the chainage in line with adjoining completed sections, reflecting the urgency often seen in large Indian power projects.
8Unlike earlier full EPC scopes, this tender structure limits contractor responsibility to erection and stringing, with supply clearances and site readiness managed by the project owner a shift that highlights evolving facilitation practices in Indian power projects execution.
8Such facilitation-mode tenders are increasingly becoming part of Indian power projects strategy to overcome bottlenecks in critical high-voltage corridors.

Details
Cooling tower package clocks fifth bid deadline shift
8The 2×660MW NDCT package under CSPGCL’s expansion plan now sees submissions pushed to 21August continuing a chain of five extensions in under six weeks.
8This NDCT tender for a state utility’s 2×660MW thermal project sees no change in scope just an extended bid window.
Massive RE park infra tender pushes bid date after scope clarifications
8A high - capacity 4750MW renewable park’s infra package has extended bid submissions to 19August after technical clarifications on foundations façade specs road scope and fencing strategy.
8Bidders in a multi - GW RE park package must stick to tender-specified pile foundations unless detailed design justifies raft use — a clause reinforced in the latest clarification round.
8The large - scale RE park infra tender now has a five - day extension window giving bidders more time to incorporate clarifications into final offers. Details
Haryana solar project tariff dispute centers on CUF and capital cost
8The debate intensifies over Amplus' tariff as regulators question the project's CUF assumptions, impacting future solar project formulations.
Disparity in capital cost approvals raises questions in Haryana's solar tariff case
8LR Energy challenges the Commission’s lower capital cost approval of Rs. 71.48 Crores, arguing it contradicts IREDA's appraisal of Rs. 83.50 Crores, spotlighting a growing divide in regulatory fairness.
HERC ruling underscores importance of timely compliance in electricity disputes
8The dismissal of Zion Lakeview's petition against DHBVN for non-compliance with a prior order reinforces the need for prompt adherence to regulatory decisions in the electricity industry.
Paddy straw power projects struggle with tariff misalignment issues
8Regulatory inconsistencies in tariff determination are forcing biomass projects, like SAEL Kaithal’s, to seek judicial intervention for sustainable operations.
HERC’s fuel cost misalignment could halt Haryana’s biomass projects
8With fuel costs soaring, Hind Samachar warns of potential shutdowns without tariff revisions, putting Haryana’s paddy straw biomass initiatives at risk.
Click on Details for more
Details
Tribunal mandates clearer tariff data for fair cross-subsidy charges in Haryana
8The Appellate Tribunal for Electricity insists on detailed voltage-wise data to ensure equitable cross-subsidy charges, spotlighting a critical gap in Haryana's tariff determination process.
APTEL's technology hiccup disrupts energy sector legal proceedings
8The unexpected move to physical hearings at APTEL due to tech failures could delay crucial decisions impacting India's energy market dynamics.
Impact of APTEL hearing postponement on energy legal landscape
8The deferment of Court-II hearings may ripple through ongoing energy litigations, affecting the legal landscape and project execution timelines.
Haryana regulator to rule on biomass project eligibility amid single-bid scenario
8With only Oasis Ethanol's bid received, HPPC seeks regulatory guidance on compliance with renewable energy rules, potentially reshaping future tender processes.
Haryana's power tender sees unprecedented bid participation and price competition
8The state's power tender attracted seven bidders, reflecting intense competition that drove down prices and underscored the sector's robust competitive dynamics.
Click on Details for more
Details
Karnataka's transmission project estimated at Rs. 27,138.70 million—financial analysts take note
8The project's significant budgetary allocation requires close financial scrutiny, offering analysts a comprehensive case study on large-scale infrastructure investments in India’s energy sector.
South Olpad Transmission: A case study in project acquisition and compliance
8The acquisition and compliance journey of South Olpad Transmission Limited offers insights into India's evolving regulatory landscape, crucial for stakeholders in energy infrastructure.
No transmission allowed: CERC sets clear boundaries for OSUSPL's trading activities
8By prohibiting transmission business under the new license, CERC delineates clear operational boundaries for OSUSPL, emphasizing the need for focused trading operations.
CERC outlines stringent conditions for future asset transfers
8CERC's conditions on asset assignment and transfer emphasize the importance of regulatory scrutiny in safeguarding transmission assets.
Power class testing revised for SPV modules: Implications for manufacturers
8Manufacturers must now navigate a revised testing sequence for power classes, potentially affecting production timelines and compliance strategies.
Muzaffarpur plant's delayed completion sparks legal battle over cost pass-through
8The extended delay in the Muzaffarpur Thermal Power Station's COD has led to a legal dispute over which costs can be passed to consumers, highlighting critical issues in project management and regulatory compliance.
Click on Details for more
Details
Indosol's connectivity dispute points to evolving challenges in renewable regulations
8The lease rights dispute involving Indosol at CERC underscores evolving regulatory challenges facing renewable energy projects under the 2022 GNA Regulations.
Delays in North Eastern reconductoring project attributed to 'uncontrollable factors'
8PGCIL cites uncontrollable factors for project delays, seeking regulatory leniency under CERC’s tariff regulations, highlighting challenges in North-East infrastructure projects.
Transmission project financing: CERC mandates strict conditions on asset transfer
8CERC's order underscores the regulatory framework for asset transfer, ensuring nominees meet expertise criteria, safeguarding project integrity and operational continuity.
Strict compliance conditions set as Clean Renewable Energy enters electricity trading
8CERC grants trading licence with stringent conditions, ensuring regulatory compliance and financial stability. The move invites scrutiny on new entrants' ability to sustain market presence.
Aayuda barred from transmission activities under new trading licence
8As part of CERC's stringent conditions, Aayuda Energy is prohibited from engaging in electricity transmission, highlighting a clear regulatory demarcation between trading and transmission operations.
Power Grid's strategic expansion in Rajasthan: Transmission license awarded
8With CERC's approval, Power Grid is poised to enhance transmission capacities in Rajasthan, focusing on renewable energy integration.
Click on Details for more
Details
CERC stipulates unique tariff adjustments amid fluctuating tax policies
8With changes in corporate tax rates, CERC's approval for dynamic tariff adjustments is crucial for maintaining financial viability and regulatory compliance for Power Grid and its beneficiaries.
Power trading dynamics: PTC India's handling of tariff payments under scrutiny
8MB Power's challenge to PTC India's tariff payment practices highlights critical issues in power trading financial flows.
Imported coal costs reshape power tariffs under Haryana-Adani agreement
8Haryana's new SPPA with Adani allows tariff adjustments reflecting imported coal's price volatility, impacting cost management strategies.
Regulatory roadblock: HPX retracts market coupling plea
8HPX's petition withdrawal reflects strategic maneuvering amid evolving regulatory frameworks, raising questions about future market integration timelines.
Regulatory body dismisses PGCIL's claim for time overrun compensation
8The refusal to compensate for PGCIL's project delay underscores the need for stringent adherence to timelines in power infrastructure projects. Developers must account for potential non-condonation of delays.
Regulatory clarity sought on transmission charges amid evolving tax landscape
8PGCIL emphasizes the necessity for regulatory clarity on transmission charges as tax regimes evolve, aiming to stabilize financial operations and maintain investor confidence in a dynamic policy environment.
Click on Details for more
Details
 For reference purposes the website carries here the following tenders:
8Tender for construction of SAS based 220kV substation Details
 8Tender for construction of SAS based 2x60MVA, 220/33kV GIS substation Details
 8Tender for supply of shaft along with teeth segment for clinker grinder Details
 8Tender for supply of bowl mill spares Details
 8Tender for overhauling of HP and LP turbines, generator Details
 8Tender for construction of balance civil works of ash water recirculation system pump house Details
 8Tender for strengthning of ramps and misc works in ash dykes Details
 8Tender for supply of various types of hardware fittings Details
 8Tender for supply of hot dip galvanized steel tower angles, sheets, towers and stubs etc. Details
 8Tender for operation and maintenance works of substations Details
 8Tender for supply of 245 kV RIP/RIS bushing for various substations Details
 8Tender for deployment of gangs for tower erection and stringing works Details
 8Tender for supply & installation of porta cabins at substation Details
 8Tender for supply of composite polymer disc insulator Details
 8Tender for supply of firewalls for the replacement of M2M gateway firewalls Details
 8Tender for new and modification of existing foundations for 100 MVA Tr Along with auxiliary equip foundation firewall trench various Details
 8Tender for supply, erection, testing and commissioning of generator protection relay Details
 8Tender for procurement, erection, testing & commissioning work for augmentation of the existing 2.7 MLD STP Details
 8Tender for supply, laying, installation, testing and commissioning of ADSS cable along Details
 8Tender for water sprinkling through water tanker Details
 8Tender for external painting of induced draft cooling towers Details
 8Tender for rate contract for civil work Details
 8Tender for casting of 500 nos. plain cement concrete Details
 8Tender for supply of polycarbonate meter seal, quadlock polycarbonate meter seal Details
 8Tender for supply and installation of numeric relay Details
 8Tender for supply and installation of numeric relay and related item in 33/11 kV panel Details
 8Tender for miscellaneous civil works at 33/11 kV substation Details
 8Tender for overhauling of cooling water pumps Details
 8Tender for supply of HT cable Details
 8Tender for supply of HT motors spares Details
 8Tender for supply of 1.5/2.0 ton capacity split A.C installed Details
 8Tender for erection of 110 kV DC line on DC towers by making LILO feeder Details
 8Tender for supply of polymer composite insulators Details
 8Tender for revamping of stand by scrapper feeder 3A2 by strengthening the steel structural assembly Details
 8Tender for providing additional structural support for conical portion of coal bunker hoppers Details
 8Tender for EPC project for design, engineering, supply, testing, installation, erection, commissioning & capacity up gradation of PA fan and ID fan motors Details
 8Tender for supply of gasket packing material Details
 8Tender for work contract for various C&I related job works required Details
 8Tender for work of replacement of equipments& other misc. various works of 220 kV / 400 kV switchyard Details
 8Tender for supply of 6.6 kV, 300 KW, 1476 RPM, 3 phase induction motor Details
 8Tender for supply of jointing sheet materials for various Details
 8Design, engineering, installation, erection and commissioning of complete belt weigher system Details
 8Tender for providing and fixing covering net Details
 8Tender for supply of 245 kV/ 800 Amps HV bushing Details
 8Tender for supply and erection of 90 deg ceralin coal bends suitable for coal flow system Details
 8Tender for supply of 11kV outdoor vacuum circuit breakers Details
 8Tender for procurement of ACSR ZEBRA conductor Details
 8Tender for supply of worm shaft with lock nut and keys suitable for XRP 803 bowl mills Details
 8Tender for supply of finned economizer coil ‘J’ bend of size Details
 8Tender for supply of motor skirt for cooling water pump Details
 8Tender for procurement of 920 sets of 11 kV metering set, 0.2s class accuracy Details
 8Tender for supply of 150NB gate valves suitable for ash slurry pumps Details
 8Tender for procurement of sulphuric acid Details
 8Tender for works and providing foundation for structural plinth Details
 8Tender for supply of iron and steel materials, fabrication and erection of structures Details
 8Tender for supply of iron and steel materials, fabrication and erection of structures, erection of equipment’s Details
 8Tender for operation and maintenance of SUL and allied conveyors Details
 8Tender for fabrication, manufacture, supply, erection, testing and commissioning of 33kV SS Details
 8Tender for work contract for supply and erection of 33 kV baby tower and other allied works Details
 8Tender for construction of control room structure plinth, cable duct, transformer Details
 8Tender for procurement of victaulic coupling with collar as per drawing enclosed 30 Sets Details
 8Tender for reconditioning of hydraulic loading cylinder assembly with replacing of new cylinder Details
 8Tender for procurement of smart differential pressure transmitters Details
 8Tender for procurement of PA fan pitch control vane with throttling shaft Details
 8Tender for manufacture and supply of 39600 Nos of 8m WL 200kg PSC poles Details
 8Tender for work of providing second PT source for 132kV and 33kV voltage level at various EHV substations Details
 8Tender for supply of various size of MS ERW pipes Details
 
8Tender for supply of various instrumentation cables Details
 
8Tender for supply, erection and commissioning of high mast lighting tower system Details
 
8Tender for work for attending puncture / leakages and replacement of various sizes Details
 
8Tender for supply of spares for boiler feed pump Details
 
8Tender for supply of H.V. bushings of power transformers Details
 
8Tender for manufacture, testing, supply and delivery of 33 kV 400 Amp DBCR type isolator W/O ES,33 kV 400 Amp DBCR type isolator Details
 
8Tender for servicing of different high pressure valves and actuator Details
 
8Tender for service contract for overhauling of dry, wet and bottom ash system Details
 
8Tender for work of collection of fly ash, bed ash Details
 
8Tender for complete design manufacturer supply testing of 200 35 ton EOT cranes along Details
 
8Tender for procurement of spares of CW pumps Details
 
8Tender for procurement of special purpose welding electrodes Details
 
8Design, engineering, manufacturing, supply, erection, testing & commissioning of 220kV/66kV transformer bays Details
 
8Tender for supply, installation testing & commissioning of 500 KVA DG set Details
 
8Tender for rate contract of 800MW coal handling plant Details
 
8Tender for supply of forged hammer ring for 500MW coal handling plant Details
 
8Tender for miscellaneous civil works Details
 
8Tender for supply of cooling tower materials Details
 
8Tender for work of routine and preventive / breakdown maintenance activities & miscellaneous works Details
 
8Tender for work of fabrication of various ducts of 210 MW boiler Details
 
8Tender for work of overhauling of ESP Details
 
8Tender for works of replacement of 1X322 MVA, 27/400 kV single phase generator transformer Details
 
8Tender for supply of temperature gauges Details
 
8Tender for supply of set of worm shaft & worm wheel gear along with worm shaft lock nut & keys suitable Details
 
8Tender for work of repairing of SF6 to air bushing with all associated activities Details
 
8Tender for work of overhauling of CV/ MV& VT pump misc. auxiliaries Details
 
8Tender for procurement of complete assembly of oil free water cooled screw type air compressors Details
 
8Tender for construction work of 132 kV S/C line Details
 
8Tender for construction of 132 kV GSS Details
 
8Tender for construction of 132kV GSS Details
 
8Tender for purchase of spares For 3X1750 KVA DG sets Details
 
8Tender for supply of 400kV CTs of 400 kV switchyard Details
 
8Tender for annual rate contract for rewinding and repairing of 6.6KV VPI HT motor Details
 
8Tender for annual rate contract of rewinding and repair work of LT motors of main plant Details
 
8Tender for purchase of spares of hydrogen generator Details
 
8Tender for sale of dry fly ash Details
 
8Tender for supply and erectlon of string monitorlng box (SMB) and 6. Sq.mm 1.5 KV DC solar cable Details
 
8Tender for PCC works and thorough gravel replacement at switchyard Details
 
8Tender for ARC of different HT and LT motors rewinding, repairing Details
 
8Tender for renovation including roof treatment exterior and interior Details
 
8Tender for dismantling, fabrication and renewal of worn out 300 NB M.S seamless pipe Details
 
8Tender for annual rate contract for attending all emergency/breakdown/schedule/preventive maintenance repair works etc. of 220kV line Details
 
8Tender for work of testing of EHV grade transformer oil samples at site by mobile testing laboratory at various substation Details
 
8Tender for work of upgradation of existing SCADA system Details
 
You can also click on Tenders for more
 For reference purposes the website carries here the following newsclips:
8India cancels two offshore wind tenders off Gujarat and Tamil Nadu coasts Details
 8ReNew Q1 Net Profit Soars to Rs 513 Cr Details
 8EIL inks MoU to provide NPCIL engineering services for development of small modular reactor Details
 8Powering renewable energy transition for southern region: A seminar focused on 100% renewable Details
 8Captive renewable power generation Details
 
8Nepal to Export 200 MW More Electricity to India Details
 
8India’s battery storage boom: getting the execution right Details
 
8K'taka among top three in installed wind capacity key to India’s energy transition Union Ministry Details
 
8Domestic push: India mandates local supply chains and data centres for wind turbines Details
 
8Attend to transmission & land issues for achieving target of 500 GW RE generation, industry urges governments Details
 
8IPP Juniper Green Energy secures debt financing for renewables build-out Details
 
8Ministry of Coal reviews captive and commercial coal blocks in five states Details
 
8Coal production & despatch declines for second consecutive month in July Details
 
8Websol to commence production from new 600 MW solar cell line in october Details
 
8MNRE Invites second round of proposals to boost green hydrogen testing infrastructure under 200 crore scheme Details
 
8InSolare Energy-SCC Infrastructure consortium wins 70,000 MT green ammonia project under SECI’s SIGHT Scheme Details
 
8Alpex Solar to Set Up 1.2 GW solar module plant in Uttar Pradesh Details
 
8India's solar module capacity has hit 100 GW mark: Pralhad Joshi Details
 
8India eyes private sector for nuclear growth Details
 
8India Opens uranium mining to private firms for nuclear expansion Details
 
8Govt likely to allow private cos to mine uranium to help nuclear expansion Details
 
You can also click on Newsclips for more Details
Revamped bulk transformer tender packs in stricter Make - in - India filters
8A new 500MVA 400/220/33kV transformer package under POWERGRID’s bulk buy introduces tighter domestic sourcing rules explicit technology-transfer checks and cyber - security testing for imported components.
8Dispatch of each 500MVA unit will only be cleared once foundations firewalls and busbar assemblies are ready at site — tightening synchronisation between manufacturing and site works.
8Indian works producing under collaboration must now furnish 10% performance guarantees in addition to standard contract security along with an extended warranty period. Details
Transmission mega scheme deadline shifted, intensifying PSP  linked bidding race
8An inter state grid package to evacuate 4GW from pumped storage in eastern UP has seen its submission pushed to 19 Aug. The build – own – transfer scope includes a 765/400kV pooling station, major line interconnections, and long term expansion provisions.
8With the new 19 Aug submission, technical evaluation, reverse auction, and award milestones are tightly sequenced to enable LoI by early September and contract signing before month-end.
8A new 4×1500MVA 765/400kV hub with heavy reactive power compensation will form the heart of a multi element ISTS expansion. The station’s LILO and D/C links are sized for present and future PSP flows Details
Multiple bid extensions mark high value thermal transformer order
8From December to September, the transformer package bid has seen a long series of extensions. The work involves full lifecycle delivery of grid - interface transformers for a major coal-fired capacity addition.
8The bid timeline for transformers feeding a 2400MW expansion has been repeatedly pushed, suggesting complex vendor readiness and spec alignment. Package scope demands seamless integration with existing switchyard and transmission layouts.
8The shift to a September bid close for a 3×800MW plant’s transformer package reflects the engineering intensity of the scope. It includes design, supply, erection, and testing of bulk transfer units meeting international performance benchmarks.
Details
Repeated bid extensions stretch timeline for high - capacity GIS substation package
8A major turnkey package for a 132/33kV 2×50MVA GIS substation with linked transmission lines has been pushed out to a late August deadline. Multiple shifts in submission dates signal extended time for contractors to finalise bids involving compact GIS layouts and complex civil - electrical integration.
8From early July to 20 August, bid dates for a high - voltage GIS substation and transmission line project have seen a series of extensions. The turnkey nature of the work calls for precision engineering and advanced commissioning for a compact high - reliability substation in a load  growth zone.
8A 2×50MVA GIS substation project with connected transmission lines has been granted its seventh bid date extension. Civil works, equipment supply, and high - voltage testing form the backbone of this integrated grid strengthening scheme. Details
8Five contenders are in the race for a 400/230kV AIS facility featuring 2×500MVA transformers, multiple feeder bays, and allied civil works. The project, under a southern state utility, aims to strengthen a high - capacity transmission corridor in an industrial growth belt.
8An eclectic field of engineering majors and power infrastructure firms is vying for a turnkey AIS substation package. The scope spans 400kV and 230kV bays, large autotransformer deployment, and complete civil integration.
8A southern state grid operator is assessing technical proposals for a turnkey AIS substation build. The project’s transformer and feeder configuration is designed to ease load on existing high -voltage corridors.
8The technical round for a 2×500MVA transformer - based AIS installation has attracted multiple transmission EPCs. The facility will boost interconnection between a 765/400kV hub and downstream 230kV feeders.
8Power sector heavyweights and specialist contractors are competing for an AIS substation EPC involving 400kV and 230kV infrastructure. The project will form a key node between a 765kV backbone and state - level feeders. Details
August-end target set for large - scale switchyard tender
8Bidders for a high - voltage switchyard in a central Indian mega thermal plant now have extra time. The package will connect new generation units to the interstate grid under tight reliability standards.
8The package covers critical civil, structural, and electrical works to evacuate power from a major expansion phase. The deadline push could see new entrants firm up participation.
8The revised schedule for a 2×800MW unit’s switchyard pushes bid submission closer to September. Contractors must plan integration with grid code compliance and plant commissioning timelines.
8The schedule change for a major switchyard package allows more time to address design challenges in linking new generation units to the grid. The project forms a core element of a 1600MW capacity addition.
8With the new date set, bidders can refine proposals for a high capacity HV switchyard tied to a coal fired expansion. The works are pivotal to ensuring seamless transmission readiness. Details
8The technical evaluation phase for a long-term O&M solar RESCO package in Rajasthan has wrapped up, filtering over 150 contenders for price bids. The package spans multiple substations with 33/11kV evacuation lines under a central farmer-solar scheme.
8In a crowded Rajasthan decentralised solar package, only one bidder was removed for bid security lapses, leaving a near-complete field for the price round. The plants will be tied to feeder-level substations under the PM - KUSUM framework.
8Technical bid scrutiny for a 25-year RESCO package covering multiple substations is complete, leaving most of the original bidder pool intact. Developers must integrate plants with feeder-level substations under strict scheme norms. Details
8A decentralised solar package in western India has drawn a massive 249 technical bid submissions, reflecting surging developer interest in 25 - year feed - in tariff – linked rural supply. 
8The field is now trimmed for the financial round after disqualifications over fee and documentation gaps. Several hopefuls have been knocked out of a major RESCO - mode tender after failing to submit the mandatory application fee or EMD on time. The disqualifications narrow competition in a segment that otherwise saw unprecedented participation.
8From experienced developers to first - time entrants, several bids have fallen at the first hurdle for non-submission or partial payment of fees. The next stage promises heightened competition among those who cleared scrutiny. Details
8Technical bid opening for a multi  decade solar power contract in Rajasthan’s sun rich belt has closed, setting the stage for price competition under PM  KUSUM’s Component  A model.
8A long - term solar development opportunity in Rajasthan’s arid west, aimed at decentralised generation near substations, has progressed to the next evaluation phase with an unusually large bidder pool.
8A grid - connected solar EOI in a high - irradiance desert zone has attracted over 50 bids, with developers eyeing stable revenues under a 25 - year PPA framework.
8Technical qualification is complete for a major rural - grid solar project in western Rajasthan, marking the start of the price discovery stage for a long-term PPA - backed scheme. Details
Coal Flex Is Now a Trading Desk
 Everyone talks about coal plants as baseload. But the real story is SLDCs tactically under-scheduling mid-merit units to create optionality in RTM and HPDAM—treating thermal flexibility like a financial instrument. Watch how exchange spreads line up with ramp holds at pithead stations; that’s not an accident, that’s a strategy. The result: procurement teams, not turbines, are driving marginal prices.
Solar Noon Is Cheap—Reactive Power Isn’t

 Midday looks comfortable on price, yet the grid’s reactive power bill balloons when solar floods the network. You can feel it in voltage deviation and capacitor bank dispatch rather than in DAM wedges. It’s the quiet tax of high-PV hours, and industries with large induction loads (cement, metals) are paying via hidden penalties and VAR settlements. Procurement wins on Rs/kWh; operations bleeds on vars/kVArh.
Hydro Isn’t Just Energy—It’s the Scarcity Premium

 Hydro’s share may look small on a daily pie chart, but its five-block peaking window sets the day’s scarcity price. When pumped storage enters that window, it doesn’t follow DAM—it names it. That premium is migrating into contracts and banking terms, and states without hydro headroom will keep overpaying for flexibility even when average energy is cheap. Flex, not MWh, is the new currency.
Gas Plants Are Becoming the Grid’s “Soft Cap”

 We’re seeing gas units sit just out of money until volatility spikes—then they clip the top of RTM like a price guardrail. Industrial PNG switching (versus propane or solid fuels) quietly changes that calculus by a few paise but flips entire blocks from “no-run” to “must-run.” When spot LNG tightens, expect RTM tails to fatten; when it loosens, peakers reappear and compress peaks. Gas isn’t dead—it’s a volatility valve.
DSM Is the Shadow Market No One Admits To

 Daytime discipline looks fine on paper, but deviation spikes cluster exactly when operators reach for RTM imports. That’s not random error; that’s a forecasting and control gap being papered over with a penalty line item. The irony: buyers “save” on scheduled power, then leak it back via DSM. Fixing 15-minute forecasting beats any grand procurement reform on a rupee-for-rupee basis.
The New Congestion Tax

 You can declare “no shortage” and still pay more because a single HVDC pole or 400-kV element pushes you into a pricier zone. The rent doesn’t show up in outages; it shows up in MCP differentials and congestion charges. When those deltas persist, they’re a capital plan in disguise—evidence for why a specific corridor upgrade yields real tariff relief. Forget slogans; show the zone spread curve and you win the argument.
Green OA Buyers Are Hollowing Out Exchange Liquidity at the Margins

 Corporate PPAs and banking windows are shaving the best green blocks off GDAM before they ever hit the screen. What clears looks like “oversupply” and curtailment risk—but it’s really portfolio selection bias by sophisticated C&I desks. The exchange sees volume; the premium disappears upstream. For developers, merchant models must assume this silent skimming—or they’ll overpromise cash flows.
Agriculture Solarisation Is Bending the Curve Where You Don’t Look

 Feeder solar pilots are nudging pump loads into the sunlit shoulder, easing evening peaks—but also deepening midday price troughs. DISCOMs love the relief, hate the revenue math: subsidies and cross-subsidies don’t shift as fast as the load does. The kicker is water—monsoon variability now maps onto exchange prices via irrigation behavior. Energy, agriculture, and rainfall just got braided into your MCP Details
 For reference purposes the website carries here the following tenders:
 8Design, fabrication, supply, installation, testing, commissioning of total 90 KW grid connected solar PV power plant Details
8Tender for installation of bio-digestors including reedbed Details
 8Tender for replacement of existing main earth-mat along with riser connections at various Details
 8Tender for rate contract for supply of various size of LT XLPE single core unarmoured cable Details
 8Tender for procurement of pressure switches Details
 8Tender for purchase of spares for diaphragm type hydrogen compressor Details
 8Tender for supply and fixing of electrical insulating mat conforming at various switchgears Details
 8Tender for procurement of LDO. Details
 8Tender for biennial maintenance contract for civil works Details
 8Tender for construction of covered store shed Details
 8Tender for supply, installation, testing and commissioning of submersible pump Details
 8Tender for dismantling, fabrication and renewal of worn out 300 NB M.S pipes and providing cement pedestal from clarified water pump house Details
 8Tender for dismantling, fabrication and renewal of worn out 200 NB M.S pipes Details
 8Tender for construction of control room structure plinth, cable duct, transformer Details
 8Tender for dismantling, fabrication and renewal of worn out 300 NB M.S seamless pipe Details
8Tender for work of AMC work for transportation of material at various substations Details
 8Tender for annual maintenance contract (AMC) for supply & fixing of indoor lighting /illumination & its utilities Details
 8Tender for centralized rate contract for procurement of jointing sheets (gaskets) Details
 8Tender for supply erection commissioning and testing of 1 no of new chiller Details
 8Tender for waterproofing of prefabricated roof Details
 8Tender for construction of soak pit around existing transformers Details
 8Tender for repair of CDD pump Details
 8Tender for install 2x200 KVA, 33/0.4kV power T/Fs Details
 8Tender for supply of baskets of air pre-heater Details
 8Tender for operation, maintenance of 33/11 kV line Details
 8Tender for operation, maintenance of 33/11 kV line, associated Details
 8Tender for supply and application of metal protective compound for various pipe lines Details
 8Tender for balance work of erection of 66kV S/C line Details
 8Tender for procurement of refractory patching material for boiler Details
 8Tender for DC battery cell preventive maintenance work at 220 kV & 400 kV switchyard Details
 8Tender for erection work of interconnection of 220kV D/C line Details
 8Tender for supply and installation of fired type wedge connectors including dismantling of existing bolted type clamp connectors of 220 kV switchyard Details
 8Tender for work of panel shifting and associated wiring work Details
 8Tender for construction of 11kV spur line and 11/0.433 kV 500 KVA sub-/station Details
 8Tender for construction of 11 kV single circuit line with 132 kV, D6 type tower Details
 8Tender for construction of 33kV line and installation of 33/0.433kV, 2X500 KVA SS Details
 8Design, manufacture, procurement, supply, fabrication, shop assembly, painting, shop testing, transportation and delivery to project site, receipt and storage Details
 8Tender for design turbine –repair & re-conditioning of the released/worn-out HP diaphragms Details
 8Tender for supply of LT three phase angle cross arm Details
 8Tender for overhauling of various pumps of CT blow down pump house Details
 8Tender for work of replacement of rusted 132kV & 33kV gantry structure, equipment structure Details
 
8Tender for procurement of 72.5KV 31.5KA outdoor SF6 circuit breakers Details
 
8Tender for supply of various tools-tackles, routine maintenance items & consumable items Details
 
8Tender for construction of control room structure plinth, cable duct, transformer Details
 
8Tender for essential civil works Details
 
8Tender for special M and R of electricity store and other misc. civil works at 132/33/11 kV s/s Details
 
8Tender for carrying out protection work at 33/11kV s/s Details
 
8Tender for construction of miscellaneous civil works at 33/11 kV substation Details
 
8Design, engineering, manufacturing, supply, erection, testing & commissioning of 220/66kV transformer Details
 
8Tender for supply of 11 kV (70) and 33 kV (90 KN) polymer disc insulator Details
 
8Tender for supply of 11 kV (5 KN ) and 33 kV (10 KN) polymer pin insulator Details
 
8Tender for procurement of complete bladder type accumulator assembly for fast opening system Details
 
8Tender for work of upgradation of exisiting SCADA system  Details
 
8Tender for construction, renovation & supply work for S.N.C.U. ward including civil work Details
 
8Tender for construction of water cable trench, providing & laying PSC cover & chain link fencing & misc civil work Details
 
8Tender for contract for assistance in loading of coal rake Details
 
8Tender for evacuation of ash deposited inside all the overflow lagoons by dredging Details
 
8Tender for erection of 33 kV line 14.50 KM SC with ACSR dog conductor Details
 
8Tender for erection of 33 kV line 14.50 KM single circuit with ACSR dog conductor Details
 
8Tender for erection of 33 kV line Details
 
8Tender for supply, erection, testing and commissioning of material of 11/0.4kV S/S Details
 
8Tender for purchase of 5392 stacks of 245kV solid core post insulator Details
 
8Tender for purchase of 46465 stacks of 2X24kV post insulator Details
 
8Tender for supply of HCL, NaOCL and H2SO4 storage tanks Details
 
8Tender for procurement of numerical /aux relays for LT switchgear Details
 
8Tender for day to day civil repair works Details
 
8Tender for repair of cracks in LP casing of 110 MW unit Details
 
8Tender for manufacture, testing, supply and delivery of 11 kV AB cable Details
 
8Tender for manufacture, testing, supply and delivery of 12 KV, 400Amps indoor type, series trip metering switchgear with vacuum circuit breaker Details
 
8Tender for procurement of 220 kV capacitive voltage transformers Details
 
8Tender for shift and maintenance activities at 230kV EHT substation Details
 
8Tender for work of replacement of complete crusher body with inlet mouthpiece,bypass gate assembly, outlet chute, rotor Details
 
8Tender for work of arresting water leakages by Leak expert using polyester Details
 
8Tender for strengthening work of conveyor gentry, junction tower and crusher house Details
 
8Tender for supply of spares of 415 V air circuit breakers installed Details
 
8Tender for supply of electric winch for shifting (pulling) of scrapper Details
 
8Tender for fabrication of 250NB, 300NB, 350NB, and 400NB size MS ERW bends of various Details
 
8Tender for works contract for carrying out day to day preventive and breakdown maintenance and emergency breakdown under works contract for 230kV SS Details
 
8Tender for procurement of welding electrodes Details
 
8Tender for providing services on job work for various types of works Details
 
8Tender for supply of various rubber gaskets and rubber items Details
 
8Tender for supply, erection, commissioning and testing work of high mast tower Details
 
8Tender for supply of various types and sizes of pulley at coal handling plant Details
 
8Tender for rectification and retrofitting of 1.2 MW hydro TG unit with supply of material Details
 
8Tender for supply, delivery, unloading, testing and commissioning of centrifuge oil purification machine Details
 
8Tender for turbine generator related overhauling job during Details
8Tender for procurement and retro-fitment of actuators with indigenous actuator Details
 
8Tender for annual maintenance contract for boiler and its auxiliary system Details
 
8Tender for procurement of conveyor belt Details
 
8Tender for procurement of spares for pneumatic actuators Details
 
8Tender for construction of foundation, cable trench, oil sump Details
 
8Tender for bi-ARC for the emergency restoration of power of 66kV,132kV & 220kV transmission line Details
 
8Tender for construction of foundation, cable trench, oil sump, FP wall, equipment Details
 
8Tender for work of chemical (by using high voltage insulator and protector) of disc insulator Details
 
8Tender for work of supply & replacement of various 33kV equipments at 220kV sub-station Details
 
8Tender for various regular preventative maintenance / emergency and breakdown works of various 220kV & 100kV substations Details
 
8Tender for providing & fixing by pass twin jumpering arrangement by boltless C-type wedge connectors to the jump at tension towers Details
 
8Tender for supply of cooling fan motors of converter transformer installed Details
 
8Tender for servicing & alignment of 245kV, 145kV and 36kV isolators Details
 
8Tender for supply of equipments/ material, erection, testing and commissioning for the work of augmentation by providing additional 1 x 50 MVA, 132/110/33 kV T/F Details
 
You can also click on Tenders for more
 For reference purposes the website carries here the following newsclips:
8TruAlt Bioenergy and GAIL form strategic joint venture Details
 8Vikram Solar sets IPO price band Details
 8ACME Solar arm gets 3,184 cr REC funding for 280 MW renewable project Details
 8Microcap stock in focus after receiving 57 Cr order from Maharashtra Govt for supply of solar water pumps Details
 8Oswal Pumps bags 442 cr order to supply solar pumps in Maharashtra Details
 8Juniper Green Energy raises Rs 1,739 cr in debt financing Details
 8RInfra secures 526 crore arbitration award against aravali power company Details
 8India's power generating capacity to reach 780GW by 2030 Details
 8Rajpura Thermal Power Plant named best for lowest emission intensity Details
 8India approves four new semiconductor manufacturing projects Details
 8Tripura to Install 45 EV charging stations Details
 
8Automation Expo 2025: eaton launches CEAG VLL lights, B-line & flextray systems Details
 
8Impact of AI in Indian electric vehicle (EV) industry Details
 
8Suzlon Energy Q1 results: Net profit rises 7% to 324 cr on higher revenues Details
 
8Over 16.7 lakh households benefitted under solar scheme, Rs 9,000 cr disbursed, Parl told Details
 
8Coal’s Central Role in India’s complex energy transition journey Details
 
8Power solutions provider Powerica files draft papers with Sebi for Rs 1,400 cr IPO Details
 
8CG Power''s US subsidiary collaborates with Flanders under next phase of growth Details
 
8Coal still at the core: What India’s energy story cannot ignore Details
 
8Cabinet clears over 18,500 crore chip, hydro power, Metro rail plans Details
 
8Why SJVN Share price is rising Details
 
8Tata Power to develop 700 MW wind power project in Andhra Pradesh Details
 
8India’s First 120 MW CCGT power plant to rise In Tripura’s Rokhia Details
 
You can also click on Newsclips for more Details
8Find a snapshot of thermal, hydro, pumped storage, 
solar,wind, BESS and T&D contracts related updates for the day
Click on Reports for more Details
Extension pushes high  risk Himalayan hydro civil package to late August
8A major civil works tender for a 700+MW Himalayan hydropower scheme under a central PSU has seen its submission moved to 27August The package covers headrace tunnels surge shafts and an underground powerhouse cavern a mix of high geotechnical risk structures in seismically active terrain
8The revised date offers hydro civil specialists a longer window to plan excavation lining and installation of pressure conveyance systems in a 700+MW Himalayan scheme under a central PSU
8Civil contractors targeting a high capacity Himalayan hydropower scheme now have until 27August to finalise bids for underground water conveyance and powerhouse excavation under strict stability parameters Details
8Only two contenders cleared technical scrutiny for this dry ash evacuation facility expansion with the winning bid staying significantly under the competitor’s price The awarded contract covers high volume dry ash evacuation works critical to plant performance and environmental compliance with a price advantage that edged out the runner up
8The contract for a major ash handling facility upgrade at a state run plant saw just two participants with the winner taking the deal at a competitive advantage
8The contract for a major ash handling facility upgrade at a state run plant saw just two participants with the winner taking the deal at a competitive advantage Details
8The technical round has been admitted in full for a turnkey programme spanning Lower Central and Upper Assam targeting modern control rooms high reliability switchgear and outage minimising autoreclosures
8With the technical sieve admitting all eight players the focus now shifts to financial rounds for a state spanning substation modernisation expected to push execution capacity and procurement speed
8With the technical sieve admitting all eight players the focus now shifts to financial rounds for a state spanning substation modernisation expected to push execution capacity and procurement speed Details
Big push for multi gigawatt battery storage under state led funding drive
8A state utility is seeking developers for 2000MW / 4000MWh standalone BESS under a Build Own Operate model backed by viability gap funding The two cycle per day design and aggressive round trip efficiency targets set a high engineering bar for bidders
8Bidders must secure land and connect to designated intra state substations at ≥66kV bearing all costs to delivery point a condition that shifts early stage siting and grid integration risk squarely to the developer
8By pegging viability gap funding at Rs.18 lakh/MWh the state utility aims to catalyse large scale battery storage deployment disbursed in milestone linked tranches with strict clawback provisions for delays or under performance Details
Morena pooling hub to anchor high  capacity RE corridors
8Planned with multiple ICTs bus reactors and interconnection bays the 765/400kV pooling station south of Sabalgarh will be central to integrating large scale renewables into the national grid under a time bound 27 month delivery With over 3.9GW of renewable potential the targeted zone will see 2.5GW connected in Phase I supported by a complex of high capacity transformers reactors and multi voltage interconnections
8The transmission plan includes a high capacity double circuit line to Karera with augmentation at the receiving substation designed to support RE inflows and future power storage integration
8With over 3.9GW of renewable potential the targeted zone will see 2.5GW connected in Phase I supported by a complex of high capacity transformers reactors and multi voltage interconnections Details
New 765kV hub planned to integrate pump storage power
8In addition to relieving chronic loading on a key inter regional line the scheme will enable bidirectional flows from upcoming pump storage projects in the heart of Uttar Pradesh backed by a fully equipped AIS substation The scheme has cleared coordination bodies across three regions and national planning forums underlining its strategic role in balancing cross border transfer capabilities
8The inclusion of high capacity reactors at multiple points aims to counter voltage rise under light load and mitigate instability during sudden flow changes across regions
 Procurement norms have been aligned with the July2024 MoP order tightening domestic content requirements and revising border sharing country provisions likely to influence OEM participation
8The aggressive schedule covers new substation works multiple line diversions reactor installations and extensive right of way acquisition demanding strong project management capacity Details
AIS substation tender turns into long game for top developers
8The 400/220/132kV Umred project part of Maharashtra’s intra state grid strengthening plan has now crossed its sixth extension milestone RECs TBCB structure demands precision pricing and airtight compliance RECs latest TBCB scheme for a 400/220/132kV node in Nagpur district calls for high reliability design and commissioning within tight schedules Six deadline pushes signal a competitive yet cautious bidding landscape
8The 400/220/132kV Umred substation scheme demands end to end design procurement erection and commissioning under stringent technical norms RECs six time extension reflects the engineering and regulatory challenge for bidders Details
Massive intra  state transmission package shifts bid timeline to September
8The deadline for a multi voltage substation and EHV corridor scheme tied to 2GW of renewable evacuation has been pushed to early September extending the bid process by nearly three weeks to accommodate prospective developers
8The winning developer must secure right of way forest and civil aviation clearances and section 164 powers rapidly post SPV acquisition keeping commissioning within a 24 month window
8Qualification norms demand prior infrastructure project experience above Rs.980 crore and net worth of nearly Rs.400 crore ensuring only top tier transmission developers can compete Details
8Find a snapshot of thermal, hydro, pumped storage,
solar, wind, BESS and T&D contracts related updates for the day
Click on Reports for more Details
Capital cost swings reshape substation connectivity tender
8Revised land and bay equipment valuations slash one site’s obligation by over Rs.240 crore, while modest hikes at others tweak the cost balance for bidders in this 400kV GIS and multi-line build.
8Immediate surcharge after due date, plus a reworked rebate window, will alter working capital dynamics for contractors eyeing this 2×500MVA GIS and associated 220kV network.
8Cost revision at a central 220kV substation and static figures at others will fine tune the financial calculus for transmission developers in this Karnataka intra state expansion.
8From multi voltage GIS bays to new 220kV D/C lines and bay extensions at four substations, the scope continues to demand multi disciplinary execution capability.
Procurement norms tightened for major interstate transmission build
8A central BOOT based transmission package sees updated domestic sourcing rules and new border-compliance mandates, reshaping vendor eligibility in a multi GW RE evacuation plan in Madhya Pradesh.
8Latest amendment swaps earlier procurement directives with July2024 policy updates, raising the bar for component sourcing in a 35 - year operate  and  transfer transmission asset.
8Technical scope remains intact but vendor eligibility realigned under updated DPIIT backed domestic preference orders for high voltage transmission gear. Details
8A multi  crore contract for extra-high voltage CLR polymer insulators in 120kN, 160kN, and 210kN ratings has been finalised for dispatch to multiple interstate transmission projects. The award marks a key supply push under India’s 765kV grid strengthening plan.
8The winning bidder will supply three mechanical load classes of polymer insulators to POWERGRID  linked projects, enabling higher reliability and reduced contamination risk in bulk power corridors.
8Polymer insulators rated for high mechanical loads will be deployed in challenging terrains and pollution  prone zones, replacing legacy porcelain units in 765kV routes.
8The contract supports India’s accelerated 765kV network rollout, with emphasis on composite long rod technology to reduce maintenance and improve performance in polluted environments  Details
Bid deadline pushed for multi GW southern grid link
8The submission timeline for a major 3GW inter-state transmission package in southern India has been extended, giving bidders an extra week to prepare offers for complex multi-voltage substation expansions and a new 765kV corridor.
8A large scale renewable integration scheme, featuring 3×1500MVA greenfield transformation and 765kV double  circuit line works, will now see bids close later this month after REC moved the deadline.
8Spanning multiple voltage levels and incorporating future bay space provisions, the scheme’s extended schedule could draw more competitive bids from technically qualified consortia.
Land cost jumps 75% for high voltage substation package
8A major intra-state transmission tender in Karnataka has revised the TSP’s land acquisition liability from Rs.1.51 crore to Rs.2.64 crore for over 76 acres, with KPTCL retaining ownership under a MoU arrangement.
8The 2×500MVA AIS substation will tie into Yalwar and Dhoni via quad moose 400kV DC lines, plus multiple twin zebra 220kV double circuits to regional nodes, designed to de bottleneck renewable rich Belagavi-Bagalkot corridors.
8While initial installation includes two 500MVA ICTs, bays and foundations are designed for four additional ICTs and extra 400kV and 220kV bays, signalling foresight for load growth. Details
Bidding window extended for 1GW battery storage mega project
8The tariff based global tender for a 1000MW/2000MWh standalone BESS in Rajasthan has been pushed back, giving players more time to digest clarifications and amendments following the pre bid meeting. The BOO model with viability gap funding aims to accelerate large scale energy storage deployment.
8Timelines have shifted for the 1000MW/2000MWh standalone battery project under a VGF  supported BOO model. Technical and contractual clarifications are now part of the revised RfS package.
8Post pre bid meeting, the 1GW/2GWh storage tender has undergone notable clarifications in technical compliance and contractual terms, prompting a shift in bid submission timelines.
8The 1000MW battery energy system project in Rajasthan has moved its bid closing date, reflecting market feedback. This tender remains a rare large scale BOO opportunity with state support.
8Clarifications from the pre bid meeting have altered not just the technical framework but also the bidding calendar for the 2000MWh BESS opportunity, potentially altering the competitive landscape.
8The state’s marquee BESS procurement under BOO with VGF support has postponed its bid deadline, giving developers extra breathing space to align designs with revised tender requirements.
Major redesign in high voltage interconnection for 2GW solar evacuation
8Amendment introduces a split termination scheme for a key 400kV double  circuit link, with one circuit landing in an existing AIS bay and the other in a new GIS diameter — potentially altering cost, bay equipment procurement, and commissioning timelines.
8All 220kV underground links in the project are now fixed at 2500sqmm conductor size, removing the 2000sqmm option  —  a change that may edge out smaller cable vendors and alter trench design norms.
8Revised scope swaps GIS termination for AIS and calls for rearrangement of an existing bus PT bay, demanding more outage coordination and in-situ bus work.
8Amendment stresses compliance with substation owner’s site condition requirements, signalling higher coordination needs with existing asset operators and potential schedule risk. Details
Fresh bid push for 240MW hydro EPC as deadline shifts again
8Repeated extensions for an Arunachal-based hydro EPC tender, now to 2September, hint at complex specifications and bidder readiness challenges for NEEPCO’s 3×80MW project.
8The EPC scope covers turbines, generators, and plant auxiliaries for a North-East hydropower station, with repeated date moves suggesting heavy clarifications and specification fine  tuning.
8Since its February launch, the electro-mechanical tender for a major Arunachal hydro station has been repeatedly pushed forward, reflecting tough terrain and high-spec equipment requirements.
Fresh extension for large  scale coal beneficiation contracts
8Deadlines for high volume coal washing packages linked to Chhattisgarh origin supply for two major Rajasthan thermal plants have been moved to mid August. The scope spans multi-million tonne annual processing, with bidders now getting a narrow final window before technical scrutiny.
8Both Chhabra and Kota thermal units’ raw coal beneficiation contracts  — each exceeding 2million tonnes annually  have had their submission cut off pushed to 18August. The shift could alter bid dynamics in a space where logistics, washery capacity, and ash control costs decide winners.
8Companies vying for the beneficiation of over 2.3MTPA coal for a Rajasthan plant have an extra week to finalise bids. The project demands continuous supply from SECL sources with stringent ash and moisture parameters. Details
8The scope combines technical site assessment with legal and environmental clearances, requiring coordination between engineering teams, regulatory agencies, and on-ground contractors.
8A multi-specialist consultancy package for a large power sector owner saw a razor  thin gap between L1 and L2, with the winner edging out rivals in geotechnical and environmental expertise. The scope spans soil analysis, climate resilience, and compliance for sensitive construction. Details
8The assignment’s outcome could influence coal sector governance for years, making it a high-impact intervention in India’s fossil fuel policy ecosystem.
8The advocacy document will push for regulatory clarity, faster approvals, and balanced environmental oversight — all to make the sector more competitive and resilient.
8The awarded consultancy will navigate the tightrope between sustaining coal output and aligning with India’s net  zero pathway, an issue at the heart of current policy debates.
8A national  level policy document is set to be crafted for coal mining sector reforms. The consultancy brief includes sectoral analysis, stakeholder mapping, and actionable recommendations in sync with India’s energy transition goals. Details
Evening Peak Stability Masks a Subtle Frequency Dip
8Even with zero declared shortage in the Southern Region’s 20:00 peak block, frequency sagged from 50.08 Hz in the afternoon to 49.92 Hz at peak. This suggests operators are holding load generation balance at the cost of deeper frequency excursions a hidden stress point not reflected in “demand met” figures.
DNH’s Chronic ATC & (N-1) Violations are an Outlier Among Zero-Breach States

8While all major Western Region states recorded zero ATC and contingency breaches, Dadra & Nagar Haveli posted >97% ATC violation and >70% (N-1) breach rates. This indicates either persistent transmission bottlenecks or unreported local demand spikes in an otherwise stable regional grid.
Ramp Rate Suppression in Off-Peak Hours Suggests Reserve Banking
8Generation unit logs show multiple coal stations capping ramp-up rates in the early-morning (03:00) off-peak despite surplus headroom. This likely reflects an operational choice to bank ramping capability for later peak integration, hinting at a more sophisticated reserve strategy.
Voltage Deviation Index Spikes at Non-Peak Times
8The highest VDI breaches in the Northern Region occurred in midday blocks rather than evening peaks counter to the usual pattern. This suggests reactive power management gaps during high solar injection periods, not just during demand surges.
Hydro Under-Commitment Despite Full Reservoirs in Eastern Region

8PSP (Pumped Storage Plant) status reports show >90% reservoir fullness in some ER hydro stations, yet their day-ahead schedules remain flatlined. This is an opportunity cost, especially with spot prices rising in shoulder hours where hydro could smooth volatility.
Persistent Zero-Shortage Reporting in High-Import States

8Certain states logged no shortages despite importing >1 GW during multiple blocks. This reflects a dependence on inter-state purchases to maintain “shortage-free” status masking underlying local generation inadequacy.
Congestion-Free Operation Despite Major Element Outages in SRLDC Data

8Southern Region ran congestion-free in market terms even with scheduled outages on key transmission elements. This could signal either overbuilt corridor redundancy or an overestimation of actual load stress in real-time dispatch planning.
Overdrawal Patterns Cluster Around Frequency Recovery Windows

8Analysis of deviation data shows that overdrawals in multiple states peak immediately after frequency recovers from sub-49.9 Hz dips. This suggests operators may be opportunistically pulling more power once grid frequency stabilises, potentially contributing to secondary instability
Click on Details more
Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8Coal and Coke
8LPG
8Ammonia
8All tankers
8Bulk and Dry cargo
Click on Reports for more. Details
 For reference purposes the website carries here the following tenders:
 8Tender for implementation of 53.9 MWac/72.8 MWp ground mounted solar PV project Details
8Tender for service contract for HP water jet of condenser tubes Details
 8Design, fabrication, supply, installation, testing, commissioning of total 26 KW grid connected solar power plants Details
 8Design, fabrication, supply, installation, testing, commissioning of total 87 KW grid connected solar power plants Details
 8Design, fabrication, supply, installation, testing, commissioning of total 451 KW grid connected solar power plants Details
 8Design, fabrication, supply, installation, testing, commissioning of total 235 KW capacities grid connected solar power plants Details
 8Design, fabrication, supply, installation, testing, commissioning with RMS of total cumu. 12 kWp GCRT Details
 8Tender for supply of electrical insulated Details
 8Tender for construction/erection work of 33 kV sub-station single circuit 33 kV line Details
 8Tender for erection of 33 kV line 6.00 KM single circuit with ACSR dog conductor Details
 8Tender for erection of 33 kV line 8.00 KM single circuit with ACSR dog conductor Details
 8Tender for construction/ erection work of 33 kV S/S Details
 8Tender for erection of 33 kV line Details
 8Tender for procurement of cage frame,liner set and curved cage piece for crusher Details
 8Tender for work of repairing, servicing and refurbishing of 400kV PG isolator and center break isolator mechanism box Details
 8Design, supply, installation, testing & commissioning of 132/33kV GIS substations Details
 8Tender for supply, installation and commissioning of portable weigh bridgeof 100 MT capacity Details
 8Tender for proposal for restoration of damaged fields of ESP Details
 8Tender for roof treatment Details
 8Tender for works contract for rate contract for repair and maintenance of GRP/GRE pipelines Details
 8Tender for works contract for replacement of fallen tower Details
 8Tender for works contract for carrying out day to day preventive and breakdown maintenance and emergency breakdown under works contract for 230kV SS Details
 8Tender for works contract for carrying out day to day preventive and breakdown maintenance and emergency breakdown under works contract for 400kV SS Details
 8Tender for remedial measures by strengthening and providing protective coating in the RCC PSC structures Details
 8Tender for supply of LT single phase angle and channel cross arm Details
 8Tender for procurement of 100 km of LT aerial bunched cable Details
 8Tender for supply of throden bearing for jackwell pump Details
 8Tender for supply of H.T fasteners Details
 8Tender for supply of modified IGV of PA Fan NDFV 22B for boiler Details
 8Tender for roof strengthening work of CW pump house Details
 8Tender for work of complete servicing / overhauling/fault attending / repairing / checking and supply of spare of various Details

8Tender for supply of 13.5MW SFC system for 65 MW, 11 kV motor Details
 8Tender for supply, installation, testing and commissioning of passenger elevator with civil works Details
 8Tender for upgradation of 13.7km single circuit 66kV tap line feeder to 110kV double circuit line Details
 8Tender for providing and fixing stone in service Details
 8Tender for supply of bi-metallic clamp for power transfomer Details
 8Tender for radiography PAUT and fibroscopy of boiler tubes Details
 8Tender for replacement of 1x10/16MVA, 132/11kV T/F with 1x20/25MVA, 132/33kV T/F Details
 8Tender for overhauling for electrostatic precipitators ESP Details
 8Tender for construction of addl T/F plinth bay (T-2), augmentation of existing 20MVA 66/11 kV P/T/F Details
 8Tender for supply and erection of pole and street light for illumination work Details
 8Tender for construction of 11/0.433 kV 500 KVA sub/station Details
 8Tender for replacement of insulation in the Hot air branch ducts of coal mill Details
 8Tender for supply of GI solid wire 8 SWG Details
 8Tender for supply of ordinary back clamp for 8M and 9M PSC pole Details
 8Tender for fabrication and erection fly and bottom ash bag filter unit in silo top Details
 8Tender for supply of LT GI pin and LT metal parts Details
 8Tender for supply of GI solid wire 6 SWG Details
 8Design, engineering, supply of materials/ equipments, erection, testing and commissioning of 132 kV D/C 3ph TSS-GSS Details
 8Tender for operation and maintenance of permanent filtration plant, temporary filtration plant, booster pump house Details
 8
Tender for replacement of insulation in the hot air branch ducts of coal mill Details
 
8Tender for manufacture, testing, supply and delivery of 12 KV SCADA compatible shunt trip switchgear panel Details
 
8Tender for annual rate contract for procurement of super-critical A1 category bearings Details
 
8Tender for biennial rate contract for work of maintenance of coal handling plant Details
 
8Tender for procurement of gate valves and non return valves for mechanical auxiliary cell Details
 
8Tender for supply of spares for hydraulic boom luffing system valves and pumps Details
 
8Tender for supply of various sizes of HP LP valves for PRDS SCAPH and boilers Details
 
8Tender for special M and R of electricity Details
 
8Tender for construction of store and other misc. civil works at 33/11 kV S/S Details
 
8Tender for construction of store shed and steel racks in A.E. (meter), electricity test lab at 33/11 kV S/S Details
 
8Tender for supply, erection, commissioning and testing of hydrogen gas leak detector system Details
 
8Tender for erection work of overhead HT/LT line Details
 
8Tender for procurement of spares for ACW pump Details
 
8Tender for replacing of damaged sheet of boiler feed pump Details
 
8Tender for work of operation & maintenance of induced draught cooling water Details
 
8Tender for supply of 66kV isolators at switchyard Details
 
8Tender for operation and maintenance of electrical systems/electrical installations Details
 
8Tender for operation and maintenance of identified 30 Nos. of 33/11 kV sub-station Details
 
8Tender for construction or erection work of 33 kV substation Details
 
8Tender for procurement of 7/3.66 MM galvanised steel stranded earth wire Details
 
8Tender for purchase of ACSR moose conductor Details
 
8Tender for erection, testing and commissioning of LILO of 132 kV S/C line Details
 
8Tender for annual maintenance contract (AMC) for digital automatic voltage regulator (DAVR) installed Details
 
8Tender for repair and maintenance of valve / damper actuators Details
 
8Tender for supply of seamless carbon steel distance piece assembly for HP 803 bowl mills Details
 
8Tender for supply and erection of lift using RCC structures Details
 
8Tender for supply of insulation materials for boiler Details
 
8Tender for supply of various types of power & control fuse Details
 
8Tender for onsite repairing of 400kV 50MVAR bus reactor Details
 
8Tender for supply of various types of hardware fittings for 800 kV HVAC transmission lines  Details
 
8Tender for supply of various types of hardware fittings for 765 kV HVAC transmission lines Details
 
8Design, engineering, supply of materials/ equipments, erection, testing and commissioning of 132 kV D/C 3ph TSS Details
 
8Tender for renovation of 220 kV feeders by replacing porcelain disc insulators Details
 
8Tender for laying 11kV UG cable for providing 3MVA power to second phase Details
 
8Tender for supply, erection, retro-fitting, testing and commissioning of nitrogen injection fire prevention and extinguishing system (NIFPES) along with required accessories including civil works Details
 
8Tender for special estimate to create 132kV T/F bay for feeding additional 1x20/25MVA, 132/33kV T/F at 132kV S/Stn Details
 
8Tender for overhauling of coal pipe, vane and damper Details
 
8Tender for procurement of 100 DMT 100 percent basis caustic lye Details
 
8Tender for biennial maintenance contract for operation and maintenance including risk protection of HVWS emulsifier system Details
 
8Tender for procurement of spares for pneumatic electrical actuators Details
 
8Tender for procurement of SWAS spares installed Details
 
8Tender for refurbishment of 11 kV hydro thermal overhead line Details
 
8Design, engineering, manufacturing, testing at manufacturers works, insurance, erection, testing and commissioning of vertical francis turbines Details
 
8Tender for procurement of guide vane upper and lower bush housings for turbines Details
 
8Tender for work of complete overhauling and oil leakage rectification of 75 MVA generating transformers including OLTC, radiators, and a 1250 KVA transformer Details
 
8Tender for work of overhauling, servicing and repairing of penstock gate Details
 
8Tender for work of overhauling /break down of the 165KW/33 dewatering pump, 90KW storm water pump Details
 
8Tender for annual rate contract for providing expert services for troubleshooting of AC/DC equipments and control/ protection system Details
 
8Tender for work of annual contract for repair, overhauling, servicing, maintenance alignment of 220/132/33kV isolator available Details
 
8Tender for work for second circuit stringing on existing 132 kV tap line Details
 
You can also click on Tenders for more
 For reference purposes the website carries here the following newsclips:
8Inox Green inks pact for comprehensive O&M of 182 MW of wind projects Details
 8Gas shortage hits Tripura’s power plants, minister urges shift to solar energy Details
 8Hindalco Q1 profit jumps 30% to 4,004 cr on aluminium, Novelis boost Details
 8Centre approves Rs 8,146.21 cr investment to build 700MW Tato-II hydro project in Arunachal Details
 8Sterlite Electric bags orders worth 1,500 cr on back of energy projects Details
 8NLCIL signs MoU with Bhabha Atomic Research Centre for extraction of rare earth elements from fly ash Details
 8Eaton drops CEAG and B-Line series at Automation Expo 2025 Details

 8
Promoting PSPs: Policy developments, financing trends and key challenges Details
 
8Electricity demand grows in July after 2 months of degrowth Details
 
8Smart Power: Digitalisation and automation transforming HEPs Details
 
8Sungrow latest 75 kW string inverter for Indian C&I market Details
 
8India mandates rooftop monitoring and inverter integration for 30 GW of solar Details
 
8Insolation Green sets up subsidiary for renewable energy project development Details
 
8Oyster Renewables to invest Rs 160 billion for 2 GW by 2028 Details
 
8Websol’s new solar cell line to begin production from October Details
 
8Ministry of Coal enables scientific coal mining in Meghalaya Details
 
8Genus Power Infrastructure net profit grows to Rs 128.5 cr in Q1 Details
 
8Reforms by stealth: Rise of captive renewable energy in India Details
 
8Power sector workers hold protest, demand rollback of privatisation policy Details
 
8Ministry of Power launches task force to develop IES Details
 
8Adani Power to develop 2,400 MW power plant in Bihar Details
 
8Centralised Systems: The rise of district cooling in India Details
 
8Powering Punjab: PSPCL & PSTCL’s distinct roles Details
 
8Statcon Energiaa and AEG Power Solutions forge strategic partnership to power India’s green-hydrogen ambitions Details
 
8BHEL Q1 FY25-26 presentation: Widening losses amid robust order book growth Details
 
8Punjab Power crisis: mass leave disrupts supply Details
 
You can also click on Newsclips for more Details
Amendment pushes back submission date in large grid package
8The final bid date for a 220kV and 132kV transmission line EPC package has been extended to late August giving contenders additional time to align with the revised pre qualification norms
In a key state backed transmission tender the amended PQR relaxes certain capacity thresholds for similar works possibly enabling joint ventures to qualify with complementary experience
8Updated bidder eligibility for a western India high voltage grid expansion project could shift competition dynamics with new pathways for firms having relevant but smaller scale project portfolios
8The amendment to a Rajasthan based 220kV and 132kV transmission line turnkey package under a state utility has eased technical experience norms potentially drawing in mid tier EPC players without diluting quality safeguards
8The amendment in a high voltage transmission EPC package subtly shifts focus from sheer installed capacity to diversity of executed projects opening the door for technically sound but mid sized firms
8The pushback in submission deadlines gives bidders time to restructure their technical and financial submissions to meet the updated qualification clauses in the transmission package Details
Himachal Pradesh connects Chamera to Kutehr HEP with new LILO
8HPPTCL’s LILO project at Chamba district is set to enhance connectivity to the Kutehr hydropower project, reflecting region-specific energy strategies.
Powergrid leads central sector achievements, but falls short of revised targets
8Powergrid's significant role in the central sector highlights its importance, yet it only meets 11% of its target.
8This shortfall emphasizes the need for strategic realignment and resource optimization.
Central and private sectors drive nearly 50% of transmission expansion
8Central and private sectors are pivotal in India’s transmission growth, jointly accounting for nearly half of the new capacities, highlighting a strategic public-private collaboration in infrastructure.
Private TSPs trail in capacity and cost efficiency compared to PGCIL's extensive network
8Private Transmission Service Providers face stiff competition from PGCIL, which leads in both capacity and cost.
8This disparity highlights potential challenges for private players in scaling operations.
Click on Details for more
Details
PTC India vs. CERC: A test case for national energy policy coherence
8The PTC India litigation against the Central Electricity Regulatory Commission serves as a critical examination of national policy alignment and regulatory consistency, with potential repercussions for market stability and investor confidence.
Central sector dominates with 19.5 GW in new 765 kV substations by 2025
8A total of 19,500 MW in 765 kV substations is set for completion by 2025, with the central sector leading the charge.
8These projects are pivotal for enhancing national grid stability and supporting renewable energy integration.
CSPTCL strengthens Chhattisgarh's grid with dual sub-stations
8CSPTCL's augmentation in Chhattisgarh enhances regional transmission capabilities, critical for industrial growth and electrification goals.
FY 2025-26 transformation capacity addition hits 32,055 MVA, with central sector leading
8With the central sector at the forefront, India's addition of 32,055 MVA in FY 2025-26 underscores its commitment to infrastructure enhancement and energy security.
Private sector steps up with 1166 cKM of 220 kV lines
8Private companies are increasingly contributing to India's grid, indicating a shift towards diversified project execution in state-level infrastructure.
Click on Details for more
Details
Capacity charge denial sets precedent for RMU-affected hydro projects
8MSERC's decision could influence future tariff determinations for plants undergoing similar long-term shutdowns for upgrades.
Regulatory compliance challenge: NER utilities lag in grid event reporting
8Compliance with IEGC-2023 remains a challenge for several North Eastern utilities, as delays in grid event reporting continue to surface, risking scrutiny from regulatory bodies.
MPPTCL’s financial strategy: Rs. 4,785 crore in unfunded projects seeking financial linkage
8While a significant portion of the investment plan is tied to funding agencies, MPPTCL continues to seek financial partnerships to fully realize its extensive infrastructure projects.
APSERC draft amendment highlights increased regulatory oversight on RPOs
8The draft emphasizes enhanced monitoring and compliance mechanisms, indicating a shift towards stricter enforcement of renewable purchase mandates.
APSERC draft regulations 2025: A new era for grid management in Arunachal Pradesh
8The draft regulations propose a fresh framework for grid operations under the Electricity Act, 2003, presenting strategic adjustments for stakeholders to consider.
Adani Power's regulatory skirmish with Maharashtra: High stakes for energy giant
8Adani Power's legal action against the Maharashtra Electricity Regulatory Commission reflects the high-stakes nature of regulatory compliance in India's power sector, affecting project timelines and operational strategies.
Click on Details for more
Details
Cross-subsidy surcharge dispute highlights regulatory gaps in Chhattisgarh
8BALCO's appeals spotlight alleged regulatory oversights by CSERC in computing cross-subsidy surcharges, potentially impacting tariff fairness and compliance with the Electricity Act's cross-subsidy reduction goals.
No compensation for pre-2014 unutilized wind energy, tribunal rules
8Matrix Power's appeal for compensation for unutilized wind energy before 2014 was denied, reinforcing the tribunal's stance on non-retroactive regulatory order application.
Adani Electricity faces multi-case entanglement with Maharashtra regulator
8Adani Electricity Mumbai Ltd. is embroiled in multiple legal proceedings against the Maharashtra Electricity Regulatory Commission.
8The outcomes could have far-reaching implications for regulatory practices and business strategy in India's largest power market.
Damodar Valley Corporation faces multiple regulatory hurdles in West Bengal
8Damodar Valley Corporation's persistent legal battles with the West Bengal Electricity Regulatory Commission highlight ongoing regulatory challenges that could delay energy projects and affect power distribution in the region.
Strategic preparation spotlighted in P&NG legal directives
8The court's procedural directives stress the importance of strategic preparation in legal matters.
8This focus may alter how companies manage their compliance and litigation strategies.
Court battles set stage for regulatory clarity in gas distribution sector
8Pending court decisions involving top gas companies and the PNGRB could clarify contentious regulatory issues, providing guidance for future compliance and market entry strategies.
Click on Details for more
Details
Internal missteps stall progress on HPSEBL hydro energy petition
8HPSEBL’s joint petition suffers a delay due to absent representation, raising concerns about project management and regulatory adherence.
Om Energy vs. HPSEBL: A pivotal moment for project execution standards
8The case could establish new benchmarks for project timelines and execution standards, impacting EPC contractors and developers nationwide.
Regulatory commission mandates HPSEBL to produce composite tariff data
8HPSEBL is under pressure to deliver composite tariff details, marking a shift towards more stringent compliance and oversight in tariff filings.
Upcoming ruling in HPPTCL vs. HPSEBL to influence regulatory filings
8The decision on HPPTCL's delay condonation application could influence how future regulatory filings are managed within the power sector.
Delays in VSBR solar project order may affect investor confidence
8Prolonged legal proceedings and reserved orders in the VSBR case could deter investors, highlighting the risks of regulatory and legal uncertainties in India's solar sector.
Tribunal highlights importance of initial bid commitments in power sector legal battles
8The ruling against RKM Powergen showcases how initial bid terms and sourcing commitments can significantly influence legal outcomes in power purchase agreements, affecting future bidding and project planning.
Click on Details for more
Details
Sikkim's rapid project timelines challenge conventional models
8Sikkim is accelerating its energy projects beyond conventional timelines, a move that could redefine expectations for project delivery in the power sector.
Gujarat's 2016-17 morning peak hour tariffs under tribunal scrutiny
8A tribunal ruling questions the rationale behind Gujarat's Time of Use charges, ordering a fresh look at the morning peak hour tariffs for 2016-17.
Energy tariff correction: Prime Steel's rebate extended by six months
8A six-month extension in energy rebate for Prime Steel Industries, following a correction in the Commission's order, provides financial relief and compliance clarity.
Competitive dynamics: Adani vs PGCIL in Rajasthan SEZ
8The competition between Adani and PGCIL in Rajasthan's SEZ projects reflects a tactical race to capture market share in a region poised for rapid solar power expansion and infrastructural growth.
New entrants face stricter transmission connectivity requirements under APSERC 2025 regulations
8APSERC's latest grid code mandates rigorous connectivity criteria for new generating companies and open access consumers, impacting strategic planning for market entry and operational compliance.
New RPO rules prioritize small-scale solar in Arunachal Pradesh
8Distributed renewable energy projects under 10 MW are now central to APSERC's RPO compliance, aiming to boost local solar initiatives and reduce dependency on larger projects.
Click on Details for more
Details
Regulatory clauses in new tender could redefine contractual norms for EPC contractors
8The inclusion of unusual clauses in the latest tender poses new challenges and opportunities for EPC contractors, suggesting a strategic regulatory shift that could impact future contracts.
Pune-III's transmission plan includes extensive future-ready provisions
8The project incorporates substantial future provisions, suggesting a forward-thinking approach to grid scalability.
8This could impact future grid planning and investments.
RatleKiru power project challenges norms with twin HTLS configuration
8The use of twin HTLS with a minimum 2100 MVA capacity marks a deviation from standard transmission practices, signaling a strategic shift toward high-capacity configurations.
INR 500 crore investment approved for Daman's substation expansions
8Substantial funding has been approved for the expansion of several substations in Daman, including capacity augmentation and new GIS installations, signaling a robust approach to addressing regional electricity demand.
Strategic solar projects under PM-Surya Ghar get a staffing boost
8As part of the PM-Surya Ghar program, NISE is hiring coordinators to ensure meticulous project management and execution.
8This reveals a focused approach towards enhancing solar energy infrastructure.
NISE revises renewable energy startup proposal criteria to boost innovation
8The National Institute of Solar Energy now allows flexibility in eligibility criteria for extraordinary projects, signaling a shift towards fostering groundbreaking innovations in the renewable energy sector.
Click on Details for more
Details
8Find a snapshot of thermal, hydro, pumped storage, solar,
wind, BESS and T&D contracts related updates for the day
Click on Reports for more Details
8A top ranked bidder has secured a Rs.14 crore plus contract to serve as independent engineer for a high capacity transmission project tied to a renewable fuel manufacturing cluster in western India
8The appointed firm will supervise all engineering erection and commissioning activities for a large capacity transmission corridor designed to evacuate renewable power to a hydrogen  ammonia facility in Gujarat
8With just over Rs.1 crore between the top two bids the consultancy contract was awarded for a Phase I Part B1 high voltage grid integration scheme in Gujarat’s renewable energy belt Details
Revised eligibility norms reshape competition for high voltage link in Maharashtra
8The latest intra state transmission package for a multi voltage AIS hub has tightened bidder assessment with higher turnover and liquidity thresholds Start ups and MSEs get partial relief but face stricter capability scrutiny
8Pre bid tie up route seeks a domestic EPC with proven capability to deliver a 21 month schedule involving diverse voltage levels OPGW integration and multiple LILO points
8Scope covers LILO works and new lines linking strategic nodes in Maharashtra’s grid with emphasis on mechanized erection drone based stringing and marshland access solutions Details
Bulk push in 765kV single phase transformer procurement signals fresh grid readiness drive
8A new 13 unit 500MVA 765/400kV transformer package under PGCIL bulk procurement Lot 6 aims to standardize equipment across multiple substations for accelerated national grid integration
8PGCIL’s latest 765kV transformer tender defers transport and insurance price finalization until post award potentially changing contractor cash flow and bid strategy for large capacity grid equipment
8By grouping 13 single phase 500MVA units under a single package PGCIL is driving bulk efficiencies and reducing make diversity in the backbone 765kV network
 Revised Rev.10 requirements alter the scope and specifications for mandatory spares impacting both capex estimates and supplier inventory planning
Details
 For reference purposes the website carries here the following tenders:
 8Design, engineering, supply, construction, erection, testing, and commissioning of 228 MW (AC) grid-tied floating solar PV (FSPV) plant Details
8Tender for of procurement of complete assembly hydraulic turning motor Details
 8Tender for AMC for preventive and breakdown maintenance of UT machine Details
 8Tender for rate contract for carrying out routine annual civil maintenance works Details
 8Tender for maintenance of dykes and outlet channels of ash pond Details
 8Tender for supply, erection and commissioning of 30 MTR. high mast Details
 8Tender for manual unloading of coal rakes Details
 8Tender for rewinding and revamping of 6.6KV, 570KW and 550KW, HT motors. Details
 8Tender for construction of MCC & switch gear Details
 8Tender for supply and installation of 132kV PT at 132kV substation Details
 8Tender for work of replacement of old 33 kV vacuum circuit breaker at 220 kV substation Details
 8Tender for work of strengthening of tower legs and foundations of tower Details
 8Tender for annual maintenance contract preventive of 132 kV transmission lines Details
 8Tender for supply and fixing of outdoor feeder distribution panel MCCB and other miscellaneous supplies works Details
 8Tender for supply and installation of remote tap changer control panel RTCC and repairing of marshalling box Details
 8Tender for work for annual routine preventive maintenance at 132kV sub station Details
 8Tender for supply of different fittings and insulator for 132kV lines Details
 8Tender for increasing capacity of 33/11 kV S/s Details
 8Tender for construction of store and other miscellaneous civil works Details
 8Tender for construction of store room for electricity meters and other misc. civil works at 132/33/11 kV s/s Details
 8Tender for construction of store shed and other civil works Details
 8Tender for construction of NABL accrediterd CT and PT testing facility Details
 8Tender for repairing & maintenance of damaged lugs/LT XLPE cable Details
 8Tender for construction of LILO of both circuit of 132 kV transmission line Details
 8Tender for construction of 2/80 MVA 132/33kV GSS Details
 8Tender for procurement of 145kV, 1250A, 40kA, WEB, manually operated motor operated (01 set) isolators Details
 8Tender for supply of rotational under frequency panels, special under frequency relay Details
 8Tender for supply of conventional type 132kV and 33kV control and relay panels Details
 8Tender for supply of consumables Details
 8Tender for supply of low pressure valve Details

8Design, engineering, supply of materials/ equipments, erection, testing and commissioning of 02 nos. additional 132 kV line bay at grid substation Details
 8Tender for construction of 400kV & 220kV Tr augmentation bay & reactor bay foundation, yard cable trench, fabrication work Details
 8Tender for ARC contract for construction of foundations and other misc. work for line Details
 8Tender for procurement of lighting materials Details
 8Tender for supply, fixing and installation, testing & commissioning and AMC work of biometric machines Details
 8Tender for insitu machining of various valves Details
 8Tender for augmentation of 132 kV substation Details
 8Tender for construction of capacitor banks with allied equipments at 132 kV substation Details
 8Tender for electrical work for overhauling of ESP Details
 8Tender for shifting of 11kV and LT lines Details
 8Tender for renovation of 33/11 kV DSS Details
 8Tender for overhauling of duct, damper, expansion bellows and gates Details
 8Tender for construction of a new 33/11 kV indoor type AIS S/S Details
 8Tender for work of supply, installation & commissioning of DM water plant with RO at hot line maintenance Details
 8Tender for procurement of various size of variable load hanger assembly and constant load hanger assembly for suitable 600MW boiler Details
 8Tender for supply of motorised actuators complete set Details
 8Tender for biennial contract for PU grouting work Details
 8Tender for work of overhauling, servicing & repairing of air preheater and its connected system of boiler Details
 8Tender for dismantling of existing rail track, strengthening of track foundation Details

8Tender for procurement of 2 nos of upper combined bearing oil coolers for generating units Details
 8Tender for fabrication of 11m, 12m and 8m A poles Details
 8Tender for supply, erection, testing and commissioning of 220V, 1450AH, 108 cells lead acid tubular battery set Details
 8Tender for procurement of 63KVA/11kV/433V energy efficient level-1 distribution transformers Details
 8Tender for work of O/H & servicing of boiler feed pump Details
 8Tender for oil filter element for coal mill Details
 8Tender for supply of circuit breaker operation analyzer kit Details
 8Tender for supply of various gates and dampers and its spares for boiler Details
 8Tender for work of online, preventive and breakdown maintenance for boiler, its mountings and accessories Details
 8Tender for annual rate contract for service charges for cleaning of 800MW coal handling plant Details
 8Tender for service for miscellaneous C&I related maintenance works Details
 8Design, engineering, supply of materials/ equipments, erection, testing and commissioning of 02 nos. additional 132 kV line bay at GSS Details
 8Tender for supply and erection of UPVC pipes, water spray nozzles, drift eliminators and V-bar with SS weld mesh Details
 8Tender for supply and laying of RCC Hume pipes Details
 8Tender for repair & rehabilitation works on the fills support beams and columns of cooling tower Details
 8Tender for estimate for minimiging of 33 kV industrial crasher feeder Details
 8Tender for estimate for bifercation, creatation 0.2 km new 11 kV feeder frm 33/11 kV Ss Details
 8Tender for estimate for minimiging of 33 kV industrial feeder Details
 8Tender for civil works Details
 8Tender for replacement of damaged /defective 100MVA 220/33kV T-2 transformer Details
 8Tender for creation of 2 No. new 66 kV line Details
 8Tender for work proposal for structure strengthening work of various conveyors Details
 8Tender for shift and maintenance activities at 400kV EHT substation Details
 8Tender for replacement of weasel conductor Details
 8Tender for infrastructure development for the use of bio-pellets Details
 8Tender for construction of rainwater harvesting system Details
 8Tender for repair and maintenance of control room at 132/33 kV GSS Details
 8Tender for annual maintenance contract for annual / forced / preventive and routine maintenance works of 4x43 MW generators, power transformers Details
 8Tender for supply and application of insulation in boiler and turbine Details
 8Tender for up-keeping and assistance in operation and maintenance of various C and I equipments and instruments Details
 8Tender for work of erection of new 66kV S/C line Details
 8Tender for erection of structures, equipments, earthing, control wiring, yard lighting Details
 8Tender for supply and erection of structures with platform arrangement to keep the economizer upper lower bank coils Details
 8Tender for supply and erection of water wall soot blower bends to the replacement of defective bends in boiler Details
 8Tender for supply of skin casing sheet of thisckness 3.15mm for unit I and II boiler Details
 8Tender for augmentation of substation by providing additional 1x50MVA, 132/33kV transformer Details
 8Tender for work of augmentation of substation by addition of 132/33kV 25MVA power transformer Details
 8Tender for work of replacement of 33kV CB, CT, LA and isolator Details
 8Tender for proposal for work of water proofing treatment over roof Details
 8Tender for WC for complete repairing of rotary breaker tyre Details
 8Tender for supply and delivery of LT SPACER 3PH4 wire Details
 8Tender for procurement of different type of breaker and screen plates used Details
 8Tender for laying of underground cable network Details
 8Tender for erection of 66kV equipment, structures, control wiring, yard lighting Details
 8Tender for replacement of 11 kV bare conductor by insulated covered conductor Details
 8Tender for replacement of 11 kV bare conductor by insulated Details
 8Tender for installation of DTR and construction of related LT/HT line Details
 8Tender for installation of fuse set on 11 kV line Details
 8Tender for work for construction of new 11 kV feeder double circuit Details
 8Tender for work for maintenance of 33 kV, 11 kV, LT lines Details
 8Tender for work for construction of new 11 kV feeder double circuit from 33/11 kV sub station Details
 8Tender for work for maintenance of 33 kV, 11 kV, LT lines and related system Details
 8Tender for work for maintenance of 33 kV, 11 kV, LT lines Details
 8Tender for replacement of weasel conductor AL 59 with ACS 104.98 Sq.mm covered conductor Details
 8Tender for replacement of weasel conductor AL 59 with ACS104.98 Sq.mm covered Details
 8Tender for supply, erection, testing & commissioning of LILO of existing 220kV S/C line Details
 8Tender for supply of welding electrodes & MIG wire 410 NiMo for the cladding Details
 8Tender for augmentation of 01X25 MVA,220/33 kV power transformers along with associated HV & LV bay at 220 kV substation Details
 8Tender for work of providing and fixing of wireless window annunciations at 220 kV substations Details
 8Tender for augmentation of sub-station by replacement of existing 2x25MVA, 220/33kV power transformer Details

 
You can also click on Tenders for more
 For reference purposes the website carries here the following newsclips:
8SECI net profit rises 15% to 502 crore in FY25 on higher revenues Details
 871 thermal power plants across India now co-fire biomass, says CAQM Details
 8Rajasthan invites bids For 500 MW/2000 MWh battery storage project with VGF support Details
 8Punjab Triples renewable energy capacity in A decade, aligning with India’s renewable energy goals Details
 8Govt finalising legislation to protect power systems from cyber attacks MoS Shripad Naik Details
 8Govt shuts unit at largest Tamil Nadu nuclear power plant for maintenance Details
 8Sachin Pandit additional general manager and head civil, BHEL Details

 
8ACEN tops 2,100 MW attributable renewables in India Details
 
8NISE launches support program for renewable energy start-ups Details
 
8Statcon energiaa and AEG power solutions join forces to build MW-class hydrogen rectifiers in India Details
 
8Everyone on Dalal Street is talking about Reliance Infrastructure: Here’s why Details
 
8Statcon Energiaa and AEG Power Solutions forge strategic partnership to power India’s green-hydrogen ambitions Details
 
8L&T bags massive order above Rs 15,000 crore from Adani Power Details
 
8Centre flags six Northeast hydropower projects as ‘Vulnerable Details
 
8MNRE aims to clear backlog of 200 cr subsidy for CBG plants post monsoon Details
 
8NTPC to invest Rs 80,000 crore in Telangana Details
 
8Private sector likely to play a key role in nuclear power Details
 
82 power stocks with 150%+ profit growth, now at a 25% discount. Add to your watchlist Details
 
8The Stealth reform of India’s electricity sector Details
 
8Initiatives underway 20% RE stake in power sector by 2030: Official Details
 
8ReNew gets ready for India IPO, picks advisers Details
 
8Electric two-wheeler manufacturing loses charge amid rare earth shortage Details
 
You can also click on Newsclips for more Details
Pre-bid tie-up reshapes 400kV GIS scope for multi  site integration
8A 400/220kV GIS package tied to a 2GW solar evacuation network in southern India brings a layered mix of new build and extensions shifting from the ultra high voltage single site model seen in earlier projects
8Unlike past single owner execution this package integrates bays across both central and state transmission utilities — potentially altering coordination and interface risk profiles
8The pre bid model now allows four distinct qualification paths opening the door for erection contractors and domestic manufacturing entrants who were locked out of earlier 765kV projects
8Execution spans four existing substations in addition to the main GIS hub — significantly expanding civil transport and site coordination requirements Details
AIS expansion bid tightens entry norms for 400 kV contractors
8A new 400/220kV AIS – GIS hybrid package in western India raises both turnover and liquidity thresholds making entry tougher than similar intra state transmission tenders last year
8Instead of stand alone builds the latest 400kV package clubs a greenfield AIS with GIS and AIS extensions at three other nodes raising logistical and coordination challenges for bidders
8Unlike earlier norms that allowed proportional experience sharing the latest 400kV AIS tender mandates the lead joint venture partner to meet 100% of the technical bay erection requirement  Details
Tender retains strict substation siting radius limits
8Amendment does not dilute original survey based location restrictions — greenfield substations must still be sited within 3km load/generation nodes or 10km intermediate nodes of proposed coordinates
8Design reserves space for future 765/400kV ICTs switchable line reactors and additional bays ensuring scalability for rising load and generation integration in the region
8Latest amendment revises Make in India compliance references and updates land border procurement rules for a 765kV grid strengthening package in the northern–western corridor Details
RFP widens scope for Pune’s 765 kV ring main build
8Revised package now details a high capacity AIS at Pune East with 2×1500MVA ICTs multi bay configurations and dual 400kV D/C corridors aimed at easing Pune’s chronic load constraints and integrating upcoming 1500MW data centre demand
8The amendment ahead of RFP release introduces exact conductor types OPGW matching bay layouts and spare unit requirements critical for bidder cost modelling
8Successful bidder will acquire 100% of NES Pune East New Transmission Ltd inheriting its rights liabilities and pre bid development work from PFCCL Details
Transmission boost planned for RE  heavy western grid pocket
8A new intra state transmission package under BOOT mode will see a high capacity AIS substation paired with multiple 400kV and 220kV links aimed at easing curtailment in a congested renewable corridor in Maharashtra
8Planned at a critical node in the Solapur – Akkalkot belt the project includes multi voltage ICTs bus reactors and bay provisions for future expansion all under a tariff based competitive bidding framework
8The scheme calls for direct double circuit links to both a proposed 765kV hub and an existing central pooling station improving redundancy and grid flexibility for high capacity RE flow
8Gazette amendment fixes limits on siting deviations as tight as 3km for pooling stations signalling a push for precision in land and route planning Details
Coal flexing meets a rising MCP — the new scheduling arbitrage
8Mid-day dispatchable coal was held below its usual envelope even as the day-ahead/real-time price trended up. The pattern points to SLDCs leaning on cheaper intraday purchases instead of own generation, then ramping thermal later for the evening peak. This is a sophisticated scheduling arbitrage that is becoming repeatable, not a one-off quirk.
Hydro is repricing flexibility, and the market is paying up 
8Hydropeaking and evening blocks consistently clear at a premium to the DAM weighted average despite hydro’s modest share in the day’s mix. Cross-reading market snapshots with RLDC dispatch shows hydro being withheld until scarcity hours. Expect pumped-storage assets to monetize similar scarcity rents the moment they come online. 
Green surplus by day, scarcity by night — and the arbitrage window is widening 
8GDAM shows regular oversupply in sunny hours while RTM/DAM tightens in the evening. A coordinated buy-in-green/sell-in-peak strategy would have cleared multiple times today. The structural takeaway: as solar deepens and transmission lags, this two-shift market is turning into a daily trading system, not an occasional opportunity. 
DSM pain clusters where RTM dependence is highest 
8States leaning hardest on RTM to balance intraday errors are also showing outsized DSM exposures. Cross-mapping RLDC schedule deviations with exchange reliance flags a forecasting discipline gap: RTM is being used as a balancing crutch, yet frequency/error bands still get breached. Forecast quality, not just access to liquidity, is the differentiator. 
Transmission outages now show up as price geography, not just UI stress
8When a key corridor or HVDC pole trips, market splitting and congestion rents jump in the same time blocks. RLDC/NLDC outage logs line up with exchange congestion prints to the minute. The policy implication is blunt: accelerating specific ISTS reinforcements will collapse persistent zone spreads faster than any tariff tweak. 
Auxiliary consumption creeps up when coal is feathered — a hidden efficiency tax 
8CEA’s aux-consumption indicators edge higher on days when thermal runs partial load to accommodate mid-day RE. That “feathering” keeps emissions lower than full-tilt coal, but station heat and internal use rise—quietly eroding some of the RE cost advantage. Unit-commitment rules and must-run protocols need to account for this system-wide efficiency penalty. 
Exchange share is fragmenting right where volatility is juiciest 
8RTM liquidity is no longer a single-venue story. HPX and PXIL take their largest bites in the very hours with the steepest price ramps, which means price discovery is diversifying precisely when it matters most. For traders and discoms, venue choice becomes part of the edge; for incumbents, the fee moat keeps thinning.
Curtailment risk for merchant RE is not just about offtake—it’s about the clock 
8Sale bids in green markets routinely exceed cleared volumes in specific solar-heavy blocks, while the same day’s evening peak clears tight. The message for developers banking on merchant sales: haircut assumptions unless you physically hedge time-of-day. Without storage or firming contracts, half your “available” MWh may be stranded at zero or low price. Details
Eight contenders shortlisted for high-capacity intra-state transmission contract
8A 400kV double circuit link designed for 2000MW per circuit is planned to ease load constraints in a major urban industrial ring and support upcoming data centre demand
8The project will connect two strategic substations with GIS bays and is targeted for completion within 18 months with all eight technically qualified bidders advancing to the financial stage
8Eight firms from large national grid operators to regional infrastructure players have cleared technical evaluation to bid for the upcoming financial stage Details
Bid window stretched for major high-voltage AIS package
8A turnkey 400/230 – 110kV AIS substation project in Tamil Nadu’s renewable evacuation belt has seen its bid deadline pushed to late August reflecting heightened preparatory needs for the MNRE–KfW funded scheme
8TANTRANSCO’s flagship substation package part of the GEC II grid expansion now gives bidders extra time till August 20 hinting at extensive technical civil and automation deliverables
8With scope spanning auto transformers SAS integration and complete civil works the 400/230 – 110kV turnkey substation job in Tirunelveli NCES Circle has been extended to ease bidder readiness Details
Extended deadline boosts competition for large coal-based ash system
8With the bid date pushed to 18 August, NTPC’s 3×800 MW Stage II ash handling package gives EPC players extra time to refine offers for a high-capacity coal-fired project in eastern India, a development closely tracked in Indian power news circles.
8The Stage II expansion of a 3×800 MW thermal project will now accept bids until 18 August, offering fresh breathing space for contractors eyeing the ash handling package  a point widely noted across Indian power news updates.
8The 3×800 MW Stage II coal-fired project’s ash handling package, central to NTPC’s environmental compliance drive, has gained a final extension to mid-August, making it a headline item in Indian power news coverage.
8An extension in NTPC’s tender timeline may enable smaller but technically compliant vendors to step into the race for the ash handling works at a large eastern coal station a competitive twist highlighted in recent Indian power news analyses.
8For EPC contractors, this extension is more than just extra days on the clock; it’s a chance to recalibrate strategies for one of the most closely watched coal-based packages in Indian power news this month. Details
3,000MW green hydrogen evacuation grid in first phase of coastal hub plan
8A multi-element transmission scheme, including a 765/400kV GIS hub and loop-in of a 765kV double circuit line, will anchor bulk renewable supply to industrial-scale green hydrogen and ammonia facilities a major step in advancing Green Hydrogen Projects in India.
8The latest change in procurement clauses for a high-capacity interstate transmission package in coastal Andhra Pradesh shifts compliance to the July 2024 Make in India order, potentially narrowing eligible OEM pools for GIS ICTs and STATCOM systems. This update is being closely tracked by EPC majors involved in Green Hydrogen Projects in India, as it may influence both sourcing strategies and component pricing.
8The scope demands a full 3×1500MVA ICT setup, ±300MVAr STATCOM with MSC, and future bay provisions an engineering-intensive package aimed at ensuring dynamic stability for large industrial draws typical of Green Hydrogen Projects in India.
8A ~20km LILO of an existing 765kV corridor is designed to directly inject capacity into the new substation, with 240MVAr switchable line reactors to manage voltage and reactive power under fluctuating industrial load profiles a critical element in transmission planning for Green Hydrogen Projects in India.
8Pre-qualified bidders will undergo an initial price round, with the top half entering an e-reverse auction continuing the two-stage format that has recently led to aggressive tariff undercutting in high-profile transmission awards. By replacing the earlier 2020 sourcing mandate with the updated 2024 order, the amendment subtly alters vendor eligibility criteria, potentially affecting bid pricing strategies for major electrical components and adding competitive pressure in the evolving space of Green Hydrogen Projects in India. Details
Hybrid capacity auction stretches again as deadline shifts into September
8The 100 MW interstate wind-solar hybrid package under a central procurement scheme has seen another bid submission push, with NVVN giving developers until 9 September to submit offers. The ISTS-linked format ensures pan-India delivery potential under a long-term PPA, making it a notable development in the Indian renewable energy space.
8Developers eyeing the 100 MW ISTS-connected hybrid slot from NVVN now have until early September to finalize proposals, as the tariff-based competition inches towards attracting the most competitive bids in the Indian renewable energy market. This extended window could offer developers more time to optimize project economics and secure better financing terms—critical in today’s evolving Indian renewable energy landscape.
8The latest revision moves the bid window for the 100 MW wind-solar hybrid procurement to 9 September, with bid opening slated for the next day, keeping the market guessing on final tariff outcomes. Stakeholders in Indian renewable energy will be closely watching these results, as they may set a benchmark for future ISTS-based hybrid projects and influence investment strategies across the Indian renewable energy sector. Details
Cooling tower tender sees fourth extension in a month
8After three earlier pushes, the NDCT package for a 1320 MW coal-based expansion has received another extension, hinting at high bidder interest but also possible design clarifications in play. The development is being closely watched by those tracking Thermal power plant tenders India, where such repeated extensions often signal intense competition and evolving technical discussions.
8The latest schedule move shifts submission to August 14 for a twin-unit cooling tower EPC, a critical component in ensuring condenser performance for the base-load station. This shift further underscores how Thermal power plant tenders India frequently encounter realignment in timelines when complex structural packages are involved.
8Multiple deadline changes for the 2×660 MW coal plant’s cooling tower package suggest bidders are recalibrating pricing and scope strategies ahead of a tough techno-commercial evaluation. Within the broader landscape of Thermal power plant tenders India, such recalibrations often occur when balancing cost, compliance, and long-term operational efficiency.
8Successive bid date shifts for the NDCT work package reflect the complexity of structural design, wind load compliance, and integration with the circulating water system. It is yet another reminder that in Thermal power plant tenders India, bidders must navigate both engineering challenges and evolving commercial frameworks to stay competitive. Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8Coal and Coke
8LPG
8Ammonia
8All tankers
8Bulk and Dry cargo
Click on Reports for more. Details
8In a multi crore Package I contract for a twin reactor nuclear power project in Rajasthan the winning bidder edged past the second lowest by a wafer thin margin leaving a sharp gap to L4 and an even steeper jump to L5 NPCIL’s technical sieve left just five contenders in the fray
8Out of 19 civil and infra majors vying for the excavation to levelling package at a greenfield nuclear site only five advanced past Part I scrutiny with many faltering on document authentication and similar work proof requirements
8While L1 to L3 bids clustered closely the fourth lowest jumped by over Rs.130 crore and L5 overshot the winner by over Rs.1,260 crore — a gap suggesting major differences in geological resource and execution cost projections
8Even established government linked contractors couldn’t clear the twin filters of document format compliance and proof of excavation in hard rock capability for this early stage nuclear package Details
Multiple deadline shifts test bidder patience in Himalayan hydro build
8Civil works for a 120MW hydropower scheme in Uttarakhand covering tunnels, shafts, and access roads have seen over 10 bid extensions, signalling prolonged pre - bid deliberations and readiness challenges among potential EPC contractors.
8Package-II of a 3×40MW hydropower project owned by a state utility demands feeder tunnel, surge shaft, and adit construction in geologically complex terrain, with 48 months allotted for completion.
8Prospective bidders for a 3×40MW hydropower civil package will confer at the utility’s Dehradun office a pragmatic choice before facing the on-ground challenges of Pithoragarh’s steep valleys.
8An estimated Rs.112.67 crore contract for tunnel and associated works in a 120MW project remains under extended bidding, with the latest closing date set for 19 August 2025. Details
Multiple bid extensions hint at complex GIS – AIS hybrid yard execution
8For a 3×800MW Stage - II thermal expansion, the switchyard package has seen repeated deadline shifts till early September, reflecting the intricate blend of new GIS build - out with AIS tie - ins to existing infrastructure under a single EPC scope.
8The latest amendments make synchrophasor deployment mandatory not just for 400kV line bays but also GT low - voltage and busbar bays  marking a deeper digitalization push for a large - capacity thermal expansion’s grid interface.
8The yard’s GIS enclosure will use a steel - frame superstructure and host a 6T EOT crane for equipment handling, with the RCC-based control building and tailored HVAC system designed to meet redundancy and pressurization norms.
8The contractor must factor in rail and MGR system crossings in trestle design, ensuring compliance with clearance standards  adding another civil - mechanical interface challenge to the package. Details
State RE target of 500 MW by 2030 anchors new PMU tender
8Project scope is linked directly to Tripura’s decade-end RE target, covering solar (land, rooftop, floating), hydrogen, bioenergy, and pumped storage broadening the PMU’s advisory remit far beyond earlier scopes. In the fast-evolving market for renewable energy tenders in India, such multi-technology advisory packages are increasingly in demand from state agencies.
8Forfeiture clauses now explicitly cover non-deployment of approved manpower, document falsification, and late BG revalidation strengthening TREDA’s control over contract execution. This tightening of compliance reflects a growing trend in renewable energy tenders in India, where strict contract enforcement is becoming the norm.
8Bidders may qualify for benefits under Tripura’s Industrial Investment Promotion Incentive Scheme 2022 potentially altering bid economics for eligible consultancies. For firms tracking renewable energy tenders in India, such state-level incentives could be a decisive factor in bidding strategies.
8The revised tender declares absolute non-acceptance of deviations closing room for commercial or technical relaxations that were occasionally accommodated earlier. This rigid stance mirrors a shift seen in other renewable energy tenders in India, signalling that agencies expect bidders to align fully with prescribed terms from the outset. Details
8The outage roster isn’t just a list it’s a who’s-who: POWERGRID holds 169 open elements, UPPTCL 106, RRVPNL 90. In practice, who owns the fault often predicts how long it lingers. For traders and planners, that owner mix is a better early warning than any one market chart.
Click on Details for more
Details
8Central gen is carrying a big share of economic idling NTPC has ~4,657 MW of Reserve Shutdown on the day while state wires like UPPTCL and RRVPNL dominate corridor outages. When central plants pause and state corridors pinch, the downstream outcome is the same: more balancing work pushed into narrower pipes.
Click on Details for more
Details
8Add it up: 14.5% of the day’s offline stack is voluntary (Reserve Shutdown), 58.6% of transmission outages are at the 400 kV backbone, and 440 MW sits idle for want of PPAs while RE bids go zero-cleared. That’s not volatility for its own sake it’s the operational cost of misaligned contracting and maintenance calendars.
Click on Details for more
Details
8FDI/VDI movement maps cleanly onto the 400 kV cluster that dominates the day’s tickets (365 of 623). That’s a planning signal, not a one-off event: fix the repeat-offender 400 kV paths and you don’t just improve “indices”; you lighten the everyday balancing chore that spills into operations downstream.
Click on Details for more
Details
8The unit log shows 440 MW of thermal idle purely for no PPA. In the exchange snapshots, late-morning GDAM again carried zero-cleared renewable offers. Put together, the market is telling you the same thing twice: contracting, not resource availability, is what’s clipping revenue for RE and forcing spot cover elsewhere.
Click on Details for more
Details
8Across 215 reported units, offline capacity totalled 76,257 MW; Reserve Shutdown alone was 11,041 MW (14.5% of the day’s offline stack). This isn’t kit that’s broken. It’s capacity held back for economics, which then pushes balancing effort onto short-term mechanisms and stresses the same corridors already under maintenance.
Click on Details for more
Details
8On the transmission sheet, UPPTCL tops the open-ticket count at 106 elements, while on the unit list UPRVUNL shows 1,980 MW in Reserve Shutdown. When the same state appears as both a corridor constraint and a source of idle megawatts, the day’s imbalances aren’t “national”—they’re local and structural.
Click on Details for more
Details
8Parked Yesterday’s grid wasn’t starved it was narrow. Out of 623 reported transmission elements offline, 365 were at 400 kV (58.6%), exactly where transfer capacity matters most. At the same time, 11,041 MW of thermal was in Reserve Shutdown, a commercial pause that quietly reshapes how the system meets demand.
Click on Details for more
Details
8Find a snapshot of thermal, hydro, pumped storage,
solar, wind, BESS and T&D contracts related updates for the day
Click on Reports for more Details
Delhi power auctions see historic low tariffs for 300 MW purchase
8In a strategic move, BSES Rajdhani Power Ltd. is vying for adoption of some of the lowest tariffs discovered for a 300 MW purchase via the E-DEEP portal.
8This could set a new competitive benchmark for power procurement in the region.
BSES Rajdhani's BESS proposal could reshape Delhi’s energy landscape
8The regulatory nod for this battery system at Shivalik Grid might streamline renewable integration, setting a benchmark for future projects in the capital region.
Delhi's energy future hinges on DERC's battery storage decision
8As BSES Rajdhani awaits a verdict, the potential commissioning of a BESS could mark a transformative moment for Delhi's grid capacity and regulatory frameworks.
Tata Power’s hydro bid amendment: A closer look at competitive procurement shifts
8The amendment to Tata Power’s hydro procurement petition could herald shifts in competitive procurement strategies, impacting pricing dynamics and compliance with renewable mandates.
Click on Details for more
Details
Multi - GW PSP transmission hub planned with 4x1500MVA capacity
8A major interstate transmission project is being structured to handle up to 4GW from multiple pumped storage developers in Uttar Pradesh. The scheme includes a massive 765/400kV pooling station and multiple future provisions, ensuring long-term scalability.
8While most elements are scheduled within 30 months, the 4th ICT unit at Robertsganj will only be installed by December 2030, aligning with the revised PSP timelines, indicating adaptive phasing aligned to generation delays.
8The transmission developer must hand over all project assets, including land and ROW, to the CTU or its successor after 35 years, at no cost and free of encumbrance—making long-term asset lifecycle planning essential from day one.
8Bidders must demonstrate Rs.760 crore net worth, and consortium models are allowed with financial splits aligned to equity stakes. Affiliate or parent guarantees must be legally backed and board-approved Details
Greenshoe clause tightened: Top-ranked bidders get first preference
8For 500MW RE + ESS projects with firm power delivery, the greenshoe option will now strictly follow a descending order of L1 to L2 and beyond, ensuring allocation discipline. This update subtly shifts developer risk and bidding strategy.
8Shareholding norms revised: no dilution below 51% in the project SPV before one year from commissioning, even for consortiums. Prior approval now mandatory — a clear signal of tightening equity control and long-term accountability.
8Updated list of GETCO EHV/66kV substations now extends to March 2026, indicating likely delays and new evacuation paths. This has significant planning implications for bidders assessing injection points and transmission risks.
8Penalty for shortfall in DFR will be calculated separately for peak and off-peak hours—but exempted under Force Majeure. Developers get both clarity and cushion in case of uncontrollable disruptions. Details
Small hydro tender in J&K draws competitive mix of developers
8With technical bids opened, the 2MW IPP - mode project advances into detailed scrutiny, where past experience in remote - area execution could prove decisive.
8The competition for a 2MW hydropower site in challenging terrain is underway, with bidders now subject to technical qualification filters before financial offers are considered. Details
Tata Power’s Q1 2025 cost adjustment plea signals strategic tariff recalibrations
8Tata Power’s move to levy differential PPAC could catalyze strategic recalibrations in tariff structures, responding to fluctuating power purchase costs.
Regulatory spotlight on differential power cost adjustment in Delhi
8As DERC deliberates on BSES Rajdhani's petition, industry participants are keenly monitoring potential impacts on cost recovery practices and their implications for market dynamics.
Parbati project PPA: A new benchmark for hydroelectric agreements?
8With the Tata-NHPC Draft PPA under scrutiny, industry veterans question if this deal could serve as a new standard for hydroelectric power agreements, impacting future pricing and supply models.
NHPC's hydro projects poised to enhance Delhi's green energy footprint
8The inclusion of significant hydroelectric projects in BSES's submission to the DERC reflects NHPC's pivotal role in expanding Delhi's renewable energy portfolio and reducing carbon dependency.
NHPC to supply 3014 MW hydro power amid regulatory scrutiny
8The filing reveals strategic procurement from NHPC’s major hydro projects like Parbati-II and Ratle, signaling a boost in renewable energy integration for Delhi.
Click on Details for more
Details
Title:Mountain hydro opportunity pulls in seasoned independent producers
8The technical bid stage for a 1.2MW hill - state project saw interest from firms with a track record in renewable project execution under challenging conditions.
8Three independent developers are now in contention for a 1.2MW IPP hydro project under the Swiss Challenge process, with final selection hinging on compliance and capacity credentials. Details
Twin bidders eye micro hydro foothold in J&K
8M/s PKB Consultants and O2Z Trading & Industries have entered the race for a 0.7MW run - of - river plant, with bid evaluation now set to test their technical depth in small hydro execution.
8The Sarabal HEP has moved into the technical scrutiny phase, with two firms now competing to secure rights to develop the micro-scale project in Anantnag’s hydel belt.
8M/s PKB Consultants faces off with O2Z Trading & Industries for the Sarabal HEP, highlighting contrasting business models in the micro hydro space.
8The Anantnag project’s technical bid opening sets the stage for a small yet competitive battle to tap the Himalayan state’s hydropower potential. Details
Tata Power's bid aligns with new RPO guidelines
8Tata Power's petition aims to align with the latest RPO guidelines, potentially influencing future regulatory frameworks and enhancing compliance strategies in the energy industry.
Nuclear power enters Delhi's energy mix with Tata's 32.43 MW proposal
8The inclusion of nuclear power in Delhi's energy portfolio marks a significant shift, with Tata Power's recent petition potentially reshaping energy procurement norms.
Delhi’s renewable future: 500 MW solar PSA under scrutiny
8A 500 MW solar agreement with SECI is under DERC review, marking a pivotal step in meeting the Renewable Purchase Obligation and boosting Delhi’s green energy footprint.
Regulatory nod awaited for SECI's 4000 MWh storage-backed solar rollout
8As DERC reserves its order, anticipation builds around SECI's enhanced storage capabilities. This project is expected to set a precedent in efficiently managing solar power in urban grids.
DERC’s procedural advance on NDMC power cost charges hints at regulatory agility
8The admission of NDMC’s petition by DERC underscores a potentially more responsive regulatory environment, paving the way for adaptive energy pricing strategies.
Early 2025 power purchase price hike triggers BSES Yamuna's PPAC request
8A sharp rise in Q1 power purchase costs prompts BSES Yamuna to seek differential charges, highlighting the financial pressures on Delhi's power distributors.
Click on Details for more
Details
Three - way contest for small hydro IPP in Himalayan terrain
8A 1.5MW run-of-the-river project in the Kishtwar belt has drawn three technically qualified bidders, with proposals now under evaluation in the Swiss Challenge stage by JAKEDA.
8With three firms submitting compliant proposals, the 1.5MW hydropower package in Kishtwar has entered the Swiss Challenge evaluation stage under the UT’s renewable push.
8The 1.5MW hydropower project in the UT has cleared the technical bid stage with three contenders, a sign of steady developer interest in decentralized renewable assets. Details
Micro hydro opportunity draws limited but focused competition
8A 1.2MW hydroelectric station in Anantnag is under technical scrutiny, with just two bidders responding in the Swiss Challenge framework — pointing to selective interest from niche renewable players.
8The UT energy agency has opened technical bids for a 1.2MW run - of - river hydro project under IPP mode, seeing participation from two private developers for the boutique Himalayan scheme.
8Technical evaluation has commenced for a 1.2MW hydropower station tendered by the UT’s renewable arm, attracting two private developers under the Swiss Challenge selection format.
8Only two companies have bid at the technical stage for a 1.2MW hydropower project in the Himalayan belt, promoted under IPP mode and evaluated through Swiss Challenge provisions. Details
Uncontrollable power purchase costs prompt Tata Power's PPAC plea
8TPDDL cites factors like fuel price hikes and demand-supply variations in its push for a higher PPAC, reflecting industry challenges in managing unpredictable cost drivers.
Regulatory ambiguity puts Haryana's electrification projects on hold
8Regulatory complexities in Haryana keep 67 electrification projects from progressing, prompting HERC to seek public and developer feedback.
Compliance delay in DHBVN case could signal stricter oversight
8HERC's demand for timely compliance reports highlights a potential shift towards tighter regulatory oversight in Haryana's power distribution sector.
Compliance enforcement under spotlight as DHBVN case proceeds
8The upcoming hearing on M/s Balaji Oil Mill’s complaint against DHBVN puts compliance enforcement in focus.
8This case may have broad implications for the power distribution sector.
Haryana farmers might see relief from electrical service charges
8A new petition suggests waiving service connection fees for additional electrical loads among agricultural consumers.
8This potential policy shift could impact farmers' operational costs.
Haryana's regulatory body addresses compliance gaps in power sector
8The HERC's actions highlight the need for robust mechanisms to ensure developers meet critical infrastructure standards, impacting future projects and reliability.
Click on Details for more
Details
 For reference purposes the website carries here the following tenders:
8Tender for supply of 20 nos 11kV 800A line isolator with earth switch str,30 nos 33kV 800A bus isolators Details
 8Tender for estimate for 1x5 MVA new 33/11 kV S/s Details
 8Tender for annual maintenance contract (AMC) for advanced metering infrastructure Details
 8Tender for civil works for construction of foundation of 220kV/ 132kV voltage X-mer, soak pit, oil tank etc. Details
 8Tender for civil works for construction of foundation of 220kV/ 132kV voltage Details
 8Tender for outsourcing of running and maintenance services for transit camp Details
 8Tender for procurement of spares for M/s unique industrial and handlers EOT crane Details
 8Tender for round O clock routine, preventive and breakdown maintenance of generator and its associated auxiliaries Details
 8Tender for work of round the clock routine maintenance of turbine and its auxiliaries Details
 8Tender for maintenance of lawns inside power house Details
 8Tender for procurement of hopper wagon Details
 8Tender for procurement of hold backs of various gearbox installed Details
 8Tender for supply of soft starter for various motor Details
 8Tender for erection of 66kV equipment, structures, control wiring, yard lighting Details
 8Tender for work of miscellaneous preventive/corrective and breakdown maintenance of boiler auxiliaries Details
 8Tender for work order for the ESP & boiler various auxiliary/equipment miscellaneous maintenance work during Details
 8Tender for supply of various measuring instruments Details
 8Tender for rate contract for supply & installation of spare parts along with maintenance of DG sets installed Details
 8Tender for supply, erection, testing & commissioning of LILO of existing 220kV S/C line Details
 8Tender for supply & erection of railway spares such as check rail fixing bolt Details

8Tender for supply of LT AB cables and XLPE insulated single core cable Details
 8Tender for supply of accessories for cable Details
 8Tender for running works contract for the erection works of LT overhead feeder Details
 8Tender for procurement of 33kV outdoor current transformers Details
 8Tender for procurement of 33kV outdoor vacuum circuit breakers Details
 8Tender for procurement of numerical based three phase motor protection relay Details
 8Tender for procurement of panels AC panel for 230kV SS Details
 8Tender for replacement of condenser water box tubes and health assessment study by eddy current testing Details
 8Tender for supply of earth wire and ACSR conductor Details
 8Tender for supply of spares of coal mills Details

8Tender for routine/preventive/breakdown maintenance of ID,FD,PA fans and associated works Details
 8Tender for work of mechanical and stub strengthening of 66kV lines Details
 8Tender for bi-ARC for erection of 66/132/220kV lines Details
 8Tender for construction of cable trench for power demand Details
 8Tender for construction of control room foundations, cable trench Details
 8Tender for works contract for laying of HTUG 11KV 3x300 Sqmm cable Details
 8Tender for supply of M.S. ERW pipe Details
 8Tender for work of SITC (supply, installation, testing and commissioning) and 5 years AMC of accelerograph Details
 8Tender for replacement of external service connection & accessories Details
 8Tender for construction of water storage tanks Details
 8Tender for shifting of yards -construction of transitory sheds for service yards Details
 8Tender for establishing an alternate internet connectivity service (20 Mbps) via optical fiber cable Details
 8Tender for rate contract for procurement of 11 kV and 33 kV polymer AB switch Details
 8Tender for supply of stay wires size Details
 8Tender for supply of gaskets, graph seal and gland packings Details
 8Tender for construction of additional pedestals in stage-2 ash dyke Details
 8Tender for procurement of spares for 400kV and 220 kV breakers Details
 8Tender for erection of 8.0 Kms. single circuit 33 KV line with ACSR conductor Details
 8Tender for setting up of 500 MW/2000 MWh standalone battery energy systems Details
 8Tender for minor overhauling of 21.3 MW GTG 2 CACW generator Details
 8Tender for major overhauling of LPT 2 and minor overhauling of HPT LPT 1 generator Details
 8Tender for major overhauling of 30.9 MW GTG 1 generator Details
 8Tender for inspection of bearings, bellow and MPI/NFT of freestanding blades of LPT (last three stages) of turbine Details
 8Tender for construction of chemical earthing, supply and erection work Details
 8Tender for construction of retaining wall at tower Details
 8Tender for repair of transmission tower structure for strengthening of 220 kV D/C line Details
 8Tender for construction of chemical earthing Details
 8Tender for procurement of carrying roller stands for 1400 mm wide conveyor installed Details
 8Tender for work for attending puncture / leakages and replacement of various sizes service, fire / emulsifier water pipe line Details
 8Tender for supply of copper flexible strip connectors links for LV duct of 75 MW generator Details
 8Tender for work of 220kV substation Details
 8Tender for supply of 11kV indoor VCB panel set with spares and individual panels Details
 8Tender for services for maintenance of sewerage system Details
 8Tender for procurement of various rating of 32kV CTs and NCTs Details
 8Tender for rate contract of armoured copper control cable Details
 8Tender for supply, erection, testing and commissioning of boiler tube leakage system Details
 8Tender for procurement of trarntula conductor Details
 8Tender for rate contract of unarmoured copper control cable Details
 8Tender for work of replacement of existing 1000 sqmm power cable along Details
 8Tender for replacement of ACSR dog and rabbit bare conductor by insulated covered conductor Details
 8Tender for construction of HT/LT line/sub-station Details
 8Tender for supply of 36 inch center distance worm gear and shaft assembly for HP 803 bowl mills Details
 8Tender for annual overhaul of drycon conveyor its hydraulic operating system its moving parts Details
 8Tender for procurement of 200KVA/22kV/433V energy efficient level-1 distribution transformers Details
 8Tender for strengthening of unit-III power house Details
 8Tender for supply of spares safety valves and soot blower in unit I,II & III boiler Details
 8Tender for rewiring works and provide new earthing Details
 8Tender for supply of SCBA set Details
 8Tender for work of complete rewinding, overhauling, erection, commissioning and testing of 2000KVA, 6600/433 V, ESP 6A service transformer Details
 8Tender for unloading of coal through wagon tippler, feeding of coal Details
 8Tender for maintenance and repair of badly damaged connecting Details
 8Tender for work of bunker poking and bunker works Details
 8Tender for work for providing assistance for round the clock operation works at transfer tower Details
 8Tender for maintenance contract for ash disposal pipelines Details
 8Tender for annual maintenance of 33/11 kV line all distribution TF Details
 8Tender for annual maintenance of lines, DTR, etc Details
 8Tender for rate contract for purchase of various itmes for repair of failed distribution transformers Details
 8Tender for misc. civil works under aug. of 220/132 kV 200 MVA Trf at 220 kV GSS Details
 8Tender for civil works for 200 MVA transformer Details
 8Tender for civil works for 100 MVA transformer Details
 8Tender for civil work for 200 MVA transformer at 220 kV GSS Details
 8Tender for replacement of damaged cable trench covers and other miscellaneous works at 220 kV GSS Details
 8Tender for procurement of sulphuric acid Details
 8Tender for annual rate contract for supply of refractory castable in various power stations Details
 8Tender for supply of spares for SADC and pneumatic actuators Details
 8Tender for supply and erection of 8MVA, 33/11kV power transformer Details
 8Tender for construction of 60 mtr chain link fencing, with laying of concertina coil Details
 8Tender for renovation of points crossings of rail track Details
 8Tender for biennial maintenance of ash pond and overflow lagoon Details
 8Tender for servicing & overhauling of 245 kV CB at various substations Details
 8Tender for rate contract for servicing & repairing along with supply of spares of NIFPS of power T/F/ICT at various EHV S/s Details
 8Tender for operating mechanism overhauling, servicing & repair of 145kV & 245kV CB at various EHV substations Details
 8Tender for work of providing BPI support structure for 400 kV circuit breaker IPS tube Details
 8Tender for work of replacement of old 400kV & 220kV control and relay Panels along with control cables & civil work Details
 8Tender for annual maintenance contract for operation & maintenance for valve hall ventilation system, centralized AC system Details
 8Tender for supply of 6.6KV, 671KW, HT motor for secondary coal crusher Details
 8Tender for rate contract for operation and maintenance of DE system and DFDS system Details
 8Design, manufacturing, testing, commissioning and installation of CBMS at coal plant Details
 8Tender for supply, erection & commissioning of complete hydrastep system Details
 8Tender for BRC for work of operation & maintenance of vacuum based ash handling plant Details

 
You can also click on Tenders for more
 For reference purposes the website carries here the following newsclips:
8JSW Energy commissions second unit of 240 MW Kutehr Hydro Plant Details
 8Wind Turbine policy shift to boost indian manufacturers Details
 8Adani Green Energy commissions 50 MW solar-wind hybrid power project at Khavda Details
 8Global coal use likely to remain near the all-time high reached in 2024 Details
 8Meghalaya Coal Mining resumes scientifically Details
 8Going green without going dark: How thermal power is shaping up as the backbone of India’s energy security Details
 8Why renewable and transmission utilities are best plays on power cycle Details
 8Coal India Ltd clears way for sale of power in Exchanges Details
 8Shakti Pumps injects 5 Crore into its EV arm Details
 8India hands over 10 electric buses to Mauritius Details
 8SC Ruling clears way for reliance infra discoms to recover Rs 21,413 Cr Details

 
8IREDA loan book reached Rs 79 941 cr in Apr-Jun quarter CMD Details
 
8IREDA to expand into green hydrogen, e-mobility and ethanol Details
 
8Solar sector driving growth in India’s wires and cables market: RR Kabel Details
 
8The stealth reform of India's electricity sector gains quiet traction Details
 
8Why BHEL's share price is falling Details
 
8Coal India eases fuel policy, allows power sale on exchanges Details
 
8Biofuels for sustainable and clean energy transition Details
 
8How India’s nuclear vision supports a sustainable tomorrow Details
 
8India to Host major 2025 clean energy summit Details
 
8CIL allows thermal power plants to sell surplus power in exchanges Details
 
8Coal India allows power firms to trade linkage coal freely Details
 
8CIL: surplus power sale in open market from August Details
 
8The stealth reform of India's electricity sector gains quiet traction Details
 
You can also click on Newsclips for more Details
Swiss Challenge draws triple bid for niche hydro IPP in J&K
8Three private developers have entered the fray for a 2MW small hydro scheme in the Himalayan foothills under JAKEDA’s Swiss Challenge model, with the technical evaluation now underway. 
8Technical bids for a 2MW run - of - river hydro project in Reasi district have pulled in three contenders, reflecting continued IPP interest in boutique hydropower under UT administration.
8Three bidders have lined up for the Lar project in Reasi, as JAKEDA pushes ahead with private sector-led development under its challenge-based procurement approach.
8From dedicated hydropower specialists to multi-sector energy firms, the 2MW Reasi project has attracted varied private developers in its technical bid stage. Details
Interest on working capital claims highlight financial strain in delayed projects
8PGCIL's petition for interest on working capital underscores financial pressures from project overruns and regulatory uncertainties.
Settlement of Rs.678.71 Cr CSS dispute highlights challenges in grid connectivity
8The case underscores the complexities of grid connectivity and the financial implications of CSS obligations, providing valuable lessons for industry stakeholders on regulatory adherence.
Capital costs soar as Power Grid claims Rs.33,287 crore for Madurai-Trivandrum transmission line
8Power Grid Corporation's revised capital cost for the Southern Region transmission system is set to impact tariff structures and financial projections for the 2024-29 period, with implications for stakeholders throughout India's energy sector.
Compounding vs. simple interest: Wind Three Renergy's legal challenge to PTC's LPS method
8In a critical financial interpretation dispute, Wind Three Renergy advocates for compounded LPS, arguing PTC's simple interest approach fails to meet contractual and regulatory standards.
Financial guarantees underscore commitment to karnataka's transmission infrastructure
8Substantial bank guarantees from companies like Layer Hybren and Serentica highlight the financial stakes and commitment to developing robust transmission systems in Karnataka.
Unusual regulatory review in Uttarakhand could impact hydro projects
8The review of the previous order involving Greenko Budhil highlights potential disruptions in hydro project approvals, which could influence market dynamics.
Click on Details for more
Details
Multiple bid extensions mark high - stakes hydropower E&M tender
8The 3×100MW multipurpose hydro project in Uttarakhand, owned by UJVN Ltd, has now been extended till 19 August after a series of deadline shifts — reflecting intense bidder engagement and complex technical clarifications in the EPC scope.
8UJVN Ltd’s 3×100MW hydropower tender now includes non-funding by government agencies and beneficiary states as a force majeure trigger — a rare addition in the EPC hydro space.
8The Himalayan hydro EPC tender has deleted overload and low-head output guarantees tied to specific guide vane openings, possibly opening scope for cost optimisation in turbine bids.
8The Lakhwar EPC package updates several hydraulic system clauses, allowing contractor-recommended alternatives in motor starters and oil filtering systems for the 3×100 MW station. Details
Deadline pushed again for Himalayan hydro barrage package
8The civil and hydro - mechanical works package for a 120MW run - of - river project in Uttarakhand has seen multiple bid extensions, now set to close on 19 August, reflecting the scale and complexity of coffer dam, barrage, intake, and diversion works in a remote riverine terrain.
8The Rs.119.82 crore contract for high - altitude dam and gate works in a 120MW scheme has been extended several times, with the final deadline now mid-August amid heightened bidder interest and extensive qualification requirements.
8From high turnover thresholds to specific past experience in large gate systems, the tender for a 120MW hydro scheme’s barrage and diversion package demands deep credentials — now with bids due by 19 August.
8With deadlines moving from early July to mid-August, the 120MW hydro barrage and gate works package shows signs of active bidder engagement and prolonged pre - bid preparations. Details
Erection standards redefined for high-voltage AIS bay extensions
8The new 765 kV bay extension in upcoming transmission equipment tenders in India includes upgraded erection procedures for circuit breakers, CVTs, isolators, and gantry structures. Insulator string specs have been tightened, including mandatory composite long rod polymers across all pollution-prone and northern regions.
8The latest insulator specifications in transmission equipment tenders in India enforce 31 mm/kV minimum creepage for 765/400/220/132 kV lines, with a hard push towards polymer units in coastal and polluted zones. This change could push several legacy vendors out of contention, making compliance a key qualifier.
8The switchyard erection section in transmission equipment tenders in India revives direct-buried LV cables but with stricter burial depth, sand bedding, and route markers. Revised trench width guidelines demand increased planning for cable congestion zones, which could influence project scheduling and contractor readiness.
8Beyond standard substation works, transmission equipment tenders in India now require contractors to provision ducts, routing, and integration readiness for future telecom and SCADA systems. This multi-domain integration requirement underscores the need for coordinated planning from the very first day of execution. Details
Hydro EPC deadline sees rare 13th extension amid Himalayan build challenges
8The underground civil package for a 120MW run-of-river plant in Uttarakhand part of one of the more challenging Hydropower projects India is currently pursuing has now pushed its bid date to 19 August, after a series of scope clarifications and contract condition tweaks that signal bidder caution in high-altitude tunnelling.
8The updated penalty regime for this underground powerhouse build sets delay damages at 0.05% per day of the accepted contract amount, with an aggressive ceiling of 10%, reflecting tighter delivery enforcement typical of major Hydropower projects India has rolled out in recent years.
8Revised Schedule-E for the Himalayan hydro powerhouse package now folds dewatering, shuttering, and royalty adjustments into the quoted rates a move seen in other high-altitude Hydropower projects India where more execution risk is shifted to the contractor.
8From January to mid-August, the powerhouse package’s rolling extensions point to logistical and resource mobilisation complexities in the Himalayan district of Pithoragarh challenges that have shaped timelines in several past Hydropower projects India has attempted in similar terrain.
8The new Dispute Resolution Board clause mandates equal sharing of panel costs, including travel and lodging a fine-print adjustment that could influence bid pricing in this Rs.134-crore civil package, further adding to the complexity of high-value Hydropower projects India in remote geographies. Details
66kV underground cabling paired with greenfield substations in hybrid tender
8A rare mixed - scope package stitches Bengaluru’s dense - grid redundancy works with three Mysuru district substation projects — signalling an EPC challenge that spans city trenching to rural tower erection.
8Urban underground cable routes in high - traffic zones combine with rural foundation-heavy 66kV substation sites — posing very different execution hazards under one bid.
8From 630  sq mm cable terminations to 110kV DC tower assembly, contractors must balance precision civil works in Bengaluru’s constrained corridors with overhead line construction in open terrain.
8With scope stretching from 220kV interconnections to 66kV LILO lines, the turnkey works demand multi-domain expertise across cable laying, substation erection, and statutory clearance management. Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8Coal and Coke
8LPG
8Ammonia
8All tankers
8Bulk and Dry cargo
Click on Reports for more. Details
8The hydro overshoot absorbed 21% of the coal deficit, preventing a deeper RTM price spike during the solar fade-out blocks. based on above give a paywalled story.
Click on Details for more
Details
8Expect POSOCO to tighten forecast error bands for “persistent offenders” in the 2025-26 DSM amendment now in draft.
Click on Details for more
Details
8The shortfall correlates with a 13% drop in dispatch from 660MW super critical units (CEAdgr3 outage list), hinting at forced outage problems rather than fuel scarcity.
Click on Details for more
Details
8SLDCs are opportunistically backing down run of river stations to keep inter regional corridors uncongested for cheaper DAM imports a tactic that only works while reservoirs elsewhere remain high
Click on Details for more
Details
8This differential (80TWh) is large enough to shave almost Rs20,000crore off coal-procurement plans if the reservoir trajectory holds.
Click on Details for more
Details
FGD tender for 1,200MW unit scrapped after record 10 extensions
8A flue gas desulphurization system package for a two-unit coal plant in north India, meant to meet SO2 compliance, was abruptly cancelled despite prolonged tendering cycles. Contractors remained uncertain about intent after nearly a year of bid delays. This development adds to ongoing thermal power plant updates in India, reflecting the challenges in executing emission control retrofits.
8A wet limestone-based SO2control system for a state-run 2×600MW thermal power station has been called off following repeated submission extensions. Administrative hurdles appear to have outweighed environmental urgency, marking a notable point in recent thermal power plant updates in India.
8The FGD package for a legacy 1,200MW coal-fired plant was shelved after 10 rounds of extensions. Sector insiders cite internal administrative blocks or cost-benefit re-evaluation by the asset owner, a move that will be closely tracked in future thermal power plant updates in India.
8A delayed tender for SO2 abatement equipment at a large coal plant has ended in cancellation. Industry watchers see this as another example of slow FGD rollout across Indian state utilities, underlining a recurring trend in thermal power plant updates in India. Details
Green hydrogen hub demands deep water discipline
8A 10MLD water treatment package forms the hydraulic backbone of a coastal green hydrogen project owned by a top public sector renewable arm. Civil - heavy scope, aggressive deadlines, and tight integration with downstream hydrogen systems make this a high - stakes EPC job
8This 10MLD plant isn’t just a treatment unit — it’s a mission-critical enabler for one of India's largest upcoming green hydrogen hubs. EPC contractors must handle raw water intakes, chemical dosing systems, and end - to - end automation
8Tight milestone tracking and commissioning-linked payouts reflect a zero-tolerance approach to delays. This EPC package is woven tightly into the commissioning roadmap for the green hydrogen production cluster
8The 10MLD tender has seen three bid date extensions — from mid-July to  14  August—suggesting intense pre-bid clarifications or bidder-side recalibration, possibly due to integration challenges or civil workload
8This 10MLD package is one of the first visible infra pieces in India’s green hydrogen expansion. For  EPC  players, it’s a front - row seat to how state-backed energy transformation will flow —literally — from water Details
HVPNL faces regulatory ire over pension liability discrepancies
8HVPNL's pension accounting practices are under the scanner as HERC mandates corrective action, following audit findings of inflated liabilities, stressing governance in utility finances.
Short-term market constitutes 16.42% of June's electricity trade
8The short-term electricity market accounted for a significant 16.42% of total transactions in June 2025, emphasizing its growing influence on India’s power sector.
8Industry players need to adapt to this dynamic trading landscape.
IEX challenges Haryana surcharge proposal citing regulatory amendments
8The Indian Energy Exchange (IEX) opposes Haryana's surcharge proposal, referencing recent amendments that limit surcharge applicability, sparking a significant regulatory debate.
Western region sustains peak demand without hiccups in July 2025
8The Western region achieves seamless power supply, meeting all peak demands.
8This consistency underscores the effectiveness of regional coordination and infrastructure in power distribution.
HPERC draft amendments may redefine electricity regulatory landscape
8Regulatory adjustments by HPERC could significantly impact the electricity sector’s business conduct.
8Industry professionals must assess these changes to align future strategies with new compliance mandates.
Click on Details for more
Details
 For reference purposes the website carries here the following tenders:
8Tender for selection of BESS supplier for 600 MW/1200 MWh battery energy storage system Details
 8Design, manufacture, supply, erection, testing & commissioning and handing over of archimedes screw turbine (2X38 KW) along with associated equipments Details
 8Tender for rate contract for supply of BIS certified (new), conventional 11/0.433kV, 315 KVA, CRGO core, DTRs Details
 8Tender for construction of watch towers and laying Details
 8Tender for procurement of HDPE composite mat for use in O&M of various transmission lines Details
 8Tender for replacement of existing ACSR panther conductor Details
 8Tender for estimate for 02 KM conductor aug. of existig 11 kV pump feeder Details
 8Tender for annual maintenance contract (AMC) for the existing 300KW grid connected rooftop solar power plant Details
 8Tender for supply of BFP catridge spares Details
 8Tender for operation and maintenance of coal mill reject handling system Details
 8Tender for procurement of SEC wire 18 SWG and 21 SWG Details
 8Tender for procurement of TC fuse wire 14 SWG, TC fuse wire 15 SWG, TC fuse wire 16 SWG ,TC fuse wire Details
 8Tender for extension of switchyard Details
 8Tender for procurement of seamless MS impulse pipes for replacement of old impulse lines in CPP and TPP boilers. Details
 8Tender for maintenance of dykes and outlet channels of ash pond Details
 8Tender for supply and installation, testing & commissioning of valve regulated lead acid (VRLA) battery along Details
 8Tender for refurbishment, installation, and commissioning of condenser unit Details
 8Tender for procurement of fluid end overhauling spares of HP booster compressor Details
 8Tender for leasing of spare dark fiber of optical ground wire Details
 8Tender for replacement of 11 kV bare conductor by insulated covered conductor Details
 8Tender for bi-annual rate contract for the hiring of oil filter machine Details
 8Tender for work of oil leakage attending work of 66/11kV 5 MVA transformers Details
 8Tender for replacement of 11 kV bare conductor  Details 

8Tender for fabrication and supply of piping products Details
 8Tender for fabrication and supply of part processing of LTRH coils Details
 8Tender for tubewell boring, installation of submersible pump and construction of pump house Details
 8Tender for replacement of 11 kV bare conductor by insulated covered conductor Details
 8Tender for annual maintenance work of LT line, 11 kV line, 33 kV line and maintenance / repair of DTR Details
 8Tender for supply and ETC of 5x250 MVA, 33/400 kV transformers, construction of three nos. bays of 400 kV transmission lines Details
 8Tender for procurement of paddy straw based non torrefied pellets Details
 8Tender for providing cup lock metallic scaffolding arrangements inside the boiler Details
 8Tender for providing cup lock metallic scaffolding arrangements inside the boiler furnace from 11 Mtr S panel Details
 8Tender for procurement of HT top insulator fitting Details
 8Tender for preventive maintenance and emergency breakdown works in 326 KMs of EHT lines Details
 8Tender for work of erection of 66kV D/C panther tower line Details
 8Tender for procurement of HT switchgear spare Details
 8Tender for construction of 6.0 Kms.single circuit 33 kV line Details
 8Tender for construction of 9.2 Kms. single circuit 33 kV line with ACSR Dog conductor Details
 8Tender for construction of 220 kV and 132 kV transmission lines for 220 kV GSS Details
 8Tender for biennial maintenance contract for bearing inspection of TG bearing No 1 2 and overhauling of TG valves Details
 8Tender for work contract for round the clock operation or monitoring and maintenance work of signaling and telecommunication system Details
 8Tender for supply, erection, testing and commissioning of 3 ton capacity EOT crane for chlorination plant at cooling water pump house Details
 8
Tender for routine and as & when require maintenance of boiler & its associate auxiliaries, boiler Details
 
8Tender for procurement of HT motors Details
 
8Tender for refurbishment reconditioning of tyre and guide wheel of RB 2 installed Details
 
8Tender for renewal of existing obsolete inergen gas distribution system Details
 
8Tender for replacement damaged RCC gantry structures Details
 
8Tender for replacement of aged 33 kV 3X400 sqmm underground cable Details
 
8Tender for procurement of 100 NB dome valve spares 200 NB dome valve assembly Details
 
8Tender for supply of meet attachments for drycon conveyor Details
 
8Tender for supply of LT 1100V 4x120 sq mm UG cable Details
 
8Tender for supply of various size of MS plate for APH and flue gas duct 2items Details
 
8Tender for supply, fabrication and erection of damaged/worn out 250NB/200NB/150NB/ 80NB fire hydrant header pipeline Details
 
8Tender for supplying and spraying pesticides for mosquito and harmful insect control Details
 
8Tender for HT ABC stringing works and installation of transformers Details
 
8Tender for procurement of LT motors Details
 
8Tender for supply of CT gear box Details
 
8Tender for biennial maintenance contract for the work of deployment of vibration expert for vibration signature analysis of turbine Details
 
8Tender for procurement of complete bevel planetary gearbox assembly Details
 
8Tender for supply of Hi - chrome liner sets for Ms stein, BBD 4772 ball mills Details
 
8Tender for work of mechanical strengthening, stub strengthening and earthing work of 66 kV H frame/tower line Details
 
8Designing, engineering, procurement, supply, loading, transportation, unloading, insurance, delivery at site, handling, storage, installation, testing, commissioning including documentation of all items /material required Details
 
8Tender for supply, installation, retrofitting and commissioning of disturbance recorder system along with PC and associated Details
 
8Tender for construction of 33/11 kV sub station Details
 
8Tender for procurement of LT motors for electrical system Details
 
8Tender for procurement of spares for feed line control valve Details
 
8Tender for supply, installation, testing and commissioning of generator transformer (75 MVA, 11/220 kV, 50Hz) with all accessories, including dismantling of the existing transformer Details
 
8Tender for procurement of spares for feed line control valve Details
 
8Tender for electrification work Details
 
8Tender for overhauling of KC 210MW unit-3 ESP Details
 
8Tender for refurbishment of damaged loading unit of 8.5E9 coal mill with supply of require spares. Details
 
8Design, engineering, manufacturing, testing at manufacturers works, insurance, erection, testing and commissioning of vertical francis reversible pump-turbines Details
 
8Tender for supply of spares for fly ash handling system of ash plant Details
 
8Tender for supply of various types & sizes of fasteners Details
 
8Tender for supply, installation, testing & commissioning of 240 volt 500AH UPS battery set Details
 
8Tender for supply and retrofitting work of 1MW solar central inverter of canal top solar plant Details
 
8Tender for supply, installation, testing & commissioning for the modernization of lift installed Details
 
8Tender for work of O/H & servicing of ID fan/ FD fan / PA Fan & their connected system Details
 
8Tender for work of repairing of SF6 to air bushing with all associated activities Details
 
8Tender for work of provision of dedicated metering CT’s & CVT’s Details
 
8Tender for agumention of substation by providing additional T/Fs & replacement of T/Fs at of EHV substation Details
 
8Tender for work of annual maintenance/rate contract for routine maintenance work of refilling & providing new spares of existing fire extinguishers available at various Details
 
8Tender for AMC for various work related to all ICT's, reactors & transformers Details
 
8Tender for supply of 400kV and 220kV clamps & connectors Details
 
8Tender for bi-annual maintenance contract (Bi-AMC) for work of refilling & providing new spares for existing fire extinguishers available at various Details
 
You can also click on Tenders for more
 For reference purposes the website carries here the following newsclips:
8IEA: Renewables will be world’s top power source ‘by 2026 Details
 8Oriana power wins SECI auction to supply 60,000 MT green ammonia under SIGHT scheme Details
 8Thermal batteries are a highly viable alternative to lithium-ion-based energy storage Details
 8Installed solar PV module manufacturing capacity reaches 91.6 GW in India: Centre Details
 8KPIG Energia private limited awarded 64 MWac solar BoS project in Gujarat Details

 8
Linkage coal policy revised: CIL permits power sale on exchanges to boost demand Details
 
897 GW Coal Power capacity planned by Govt Details
 
8Waaree Energies shares may rise 42%; Why brokerages bullish on this multibagger Details
 
8Adani Power receives LoI for 2,400 MW thermal plant in Bihar's Bhagalpur Details
 
8AWS signs 80 MW wind-power deal in India Details
 
8Hyundai Motor India accelerates production and digital transformation, Eyes 1 million+ capacity Details
 
8Closed mines to be developed as tourism spots: Coal minister Details
 
8Govt says 16.51 lakh households benefitted from rooftop solar installations under PM Surya Ghar Details
 
8IHC Sells Stake in Adani energy solutions Details
 
8KPI Green Energy Wins 96 MW Solar Project from Aditya Birla Renewables Details
 
8Govt. committed to transforming Andhra Pradesh into skill hub for solar and wind energy companies: Lokesh Details
 
838% households in UT covered under solar scheme, Lok Sabha told Details
 
8Global electricity demand to rise in 2026 as renewables lead, says IEA Details
 
8Core Energy Raises Rs 200 Cr To Power India’s nuclear future Details
 
8Tesla launches first supercharger station in India in Mumbai Details
 
8Gujarat govt, NTPC explore opportunities for collaboration in green and renewable energy projects Details
 
8India’s Power giants are tapping coal inventories as demand slides Details
 
8Govt scraps uniform tariff rule, dissolves pricing pools for green energy Details
 
8L&T’s Rajpura Thermal Power Plant named India’s best for lowest emission intensity Details
 
8India’s coal-fired power can surely be cleaner Details
 
You can also click on Newsclips for more Details
Conditional approval may hinge on NHPC accepting tariff ceiling
8The HERC might grant conditional approval for NHPC contracts if the company agrees to a tariff ceiling with an exit option, posing strategic implications for future PPAs.
Retrospective tariff application overturned for 110 MW Chuzachen hydro project
8HERC must discard outdated tariff frameworks, a move that could reshape financial outcomes for stakeholders in the Sikkim hydro sector.
Regulatory spotlight on developer liabilities in Haryana electricity case
8The HERC's directive to include HSVP raises pivotal questions about developer liabilities and EDC charges, potentially reshaping financial responsibilities in Haryana's electricity supply landscape.
Haryana electricity regulators flex muscles in compliance enforcement
8HERC's stringent directives signal heightened regulatory scrutiny on power distribution networks tied to real estate.
Power sector alert: Piccadily’s Rs. 68 lakh captive status challenge
8The high-stakes dispute between Piccadily and DHBVNL could reshape the regulatory and financial landscape for captive power users in India.
Click on Details for more
Details
Rs.9840 lakh revised cost for North Eastern transmission project raises eyebrows
8The North Eastern Region transmission scheme's cost escalation from Rs.7491 lakh to Rs.9840 lakh highlights significant financial adjustments.
8Stakeholders must assess the impact on future project bids and financial planning.
Tariff order review signals changing regulatory landscape in Uttarakhand
8The petition for reviewing UERC's tariff order indicates possible regulatory shifts, urging stakeholders to reassess their strategic approaches in the region's electricity market.
Multi-year tariff review could alter Uttarakhand's power pricing structure
8With the UERC's review underway, industry watchers anticipate changes that might redefine cost structures, impacting both the utilities and the consumers in the coming years.
New amendment redefines 'Market' to include OTC platforms alongside exchanges
8The redefinition underscores the evolving landscape of electricity trading, acknowledging OTC platforms as key players in facilitating diverse energy transactions and market access.
Haryana electricity supply obligations in limbo amid regulatory adjournment
8The adjournment of the Uttar Haryana Bijli Vitran Nigam case delays clarity on electricity supply obligations in Haryana, affecting developers and residents alike. This highlights the need for streamlined regulatory processes.
Click on Details for more
Details
8Find a snapshot of thermal, hydro, pumped storage, solar,
wind, BESS and T&D contracts related updates for the day
Click on Reports for more Details
8Three bidders have lined up for a 2MW small hydro project in the Himalayan belt under the Swiss Challenge method — showing continued appetite among private players for boutique hydro generation assets in UT - administered regions
8At least two of the three firms that submitted technical bids have core solar roots — indicating a diversification play into micro-hydro, potentially driven by state - level incentives and long-term PPAs
8After multiple date revisions, the 2MW project finally opened technical bids on 4 August, with three bidders in fray — suggesting timing extensions worked to draw in broader participation Details
Tender sees nine extensions: Are vendors struggling with scope?
8A dry ash system upgrade at a government-run power plant has witnessed nine bid date extensions, now pushed to 12 August. Frequent extensions suggest either high engineering complexity or commercial fine-tuning in response to vendor queries
8The dry ash development package includes detailed civil and handling systems likely involving pneumatic conveying upgrades. The scope suits EPC players with dual mechanical-civil capabilities and experience in brownfield retrofit challenges
8The project pertains to a 2x210MW coal-based plant with legacy ash evacuation. The new package appears driven by utilization shortfalls and the need to meet regulatory targets through improved, market-linked disposal systems
8While the scope isn’t massive in size, its execution within an operating ash system and integration with legacy assets will demand phased execution and precise shutdown planning—likely a barrier for smaller EPC players Details
Greenfield thermal tender shifts key deadlines again
8The owner has now extended the techno-commercial bid deadline for its 1x800MW main plant package to early September, in what appears to be the seventh revision since April  2025
8The tender calls for turnkey execution of the entire power island and BoP systems under a single EPC envelope at a PSU-owned site in eastern India. The approach demands tightly integrated engineering and performance commitments
8The project follows the classic full-scope EPC format with BTG, civil works, and all BoP elements under one contract — an opportunity and risk combo only large EPC players can absorb
 Multiple extensions to bid timelines could signal cautious bidder appetite or complex scope issues. With offline and online elements combined, contractor risk perception may be at play
Details
From 5MVA to 160MVA: This package compresses sub-transmission evolution into one bid
8The tender weaves together both greenfield and brownfield substation upgrades—ranging from rural 33 or 11kV to a new 2x160MVA   220kV node—revealing aggressive capacity alignment with regional demand forecasts
8A rare bundled EPC scope covers 220kV, 110kV, and 33kV upgradation in one go—spanning four substations and over 84  km of transmission lines in Haveri district. The tender signals a significant shift in regional load strategy for the state transmission utility
8The mismatch in line lengths hints at localized 220kV integration with broader 110kV evacuation planning. Contractors will need to align differing design philosophies within a single EPC window
8The three successive bid extensions point to high bidder interest or spec alignment queries. Final date now stands at 12  August, giving contractors room for last-mile clarifications and design integration Details
8As more pumped storage MWs synchronise in Maharashtra & TamilNadu over FY26-27, the premium could compress to single digits undermining revenue projections in recent storage tenders.
Click on Details for more
Details
8A 51% spike in Bhutanese power imports may have gone unnoticed in energy volumes but it delivered critical frequency support right when India needed it most.
Click on Details for more
Details
8Fee compression is coming sooner: every 1% share shift away from IEX clips Rs40lakh/day from its top line at current clearing fees.
Click on Details for more
Details
400kV  ICTs tailored with dual secondary voltages raise design stakes
8The tender specifies both 33kV and 20kV secondary voltages across two ICT ratings  indicating custom substation profiles and reinforcing the need for transformer  OEMs with flexible engineering capabilities
8The tender reinforces MSETCL’s preference for single-phase ICTs, suggesting grid planners are doubling down on modular transformer layouts for easier redundancy and cost-effective spares pooling
8The sheer volume  9  ICTs in one go reinforces the growing centrality of 400/220kV nodes in MSETCL’s network, especially as renewable capacity from Maharashtra’s west flows eastward
 
8Procuring both 200MVA and 167MVA  ICTs in one package could complicate manufacturing, testing, and freight strategies especially with different secondary voltages involved Details
Massive RE park infra push opens up civil EPC play
8A fresh infrastructure  EPC tender linked to a 4750MW renewable energy park under NTPC’s green platform invites bids for extensive land development, roads, drainage, and security works.The scope preps the site for multi-phase solar or hybrid rollout
8From fossil to green, a major transmission firm’s new consultancy tender spans oil, gas, power, and renewables — all in one package. Hybrid delivery and outcome-based payment models suggest cross-functional mandates
8By breaking the 4750MW  RE park scope into standalone infra and later asset packages, NTPC appears to be managing cash flow, risk, and execution in a tighter framework
8Unlike older RE park infra tenders where scope overlaps blurred responsibilities, this version draws sharp lines between infra and power works. A cleaner tendering philosophy is emerging Details
Transmission major floats hybrid -  mode consultancy under milestone-linked terms
8A state transmission utility is seeking management consultants for a milestone-based engagement covering oil, gas, power, and renewables. The scope hints at strategic, multi-energy guidance with a mix of on - site and remote execution
8A major state transmission  PSU opts for milestone-linked delivery with no quantity caps, opening new ground in consultancy contracting and likely discouraging low-impact engagements
8From fossil to green, a major transmission firm’s new consultancy tender spans oil, gas, power, and renewables   —  all in one package. Hybrid delivery and outcome - based payment models suggest cross-functional mandates Details
New tender simplifies insulator specification to B&S 90kN
8Shifting from past variability, the spec limits all insulator strings to 90kN Ball and Socket disc insulators for both tangent and tension towers. Standardization may ease procurement but limit bidder flexibility
8A fresh 132kV transmission line package in Haryana drops older tower mixes for a tighter DA–DD range. Civil execution will vary with 19 different foundation types, hinting at route-wide soil variability
8Unlike earlier HVPNL bids that provided conductors, this one pushes supply, tensioning, and sagging responsibilities to the  EPC vendor. Full stringing scope is listed under controlled sag profiles Details
Andhra Pradesh to host 600MW storage node on ISTS substation
8The chosen site, Kolimigundla in Nandyal, is strategically placed near a central transmission node — a nod to SECI’s grid planning for RE integration
8A 600MW/1200 MWh system in Andhra Pradesh marks SECI’s first grid-scale storage under Tranche 2 of the VGF scheme, aimed at power exchange-based monetization
8With a steep earnest money requirement and reverse auction format, SECI has baked in aggressive financial discipline and competitive pressure from day one
8SECI’s project timeline links DC commissioning with parallel AC works by another contractor, pushing for tightly coordinated construction and integration schedules
8SECI ties final milestone payment to performance guarantees including round-trip efficiency and operational acceptance, reflecting a shift from install-and-leave EPCs Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8Coal and Coke
8LPG
8Ammonia
8All tankers
8Bulk and Dry cargo
Click on Reports for more. Details
8GDAM surplus energy that failed to clear (6,674 MWh) exceeded the day’s entire gas based generation (6,201 MWh) a startling parity that converts “curtailment” into a quantifiable fossil fuel substitute.
Click on Details for more
Details
Technical round clears field in major fly ash handling package
8The technical evaluation for a high volume dry fly ash extraction and loading system at a North Indian coal based power plant has concluded, narrowing the competition to firms meeting strict PQC and bid security norms
8A prominent infrastructure supplier fell short on bid security compliance in a competitive fly ash handling tender, potentially tilting the balance for remaining contenders ahead of the price opening
8The exclusion of a technically strong bidder over bid security gaps may alter the competitive dynamics in a highvalue dry fly ash extraction and loading infrastructure tender. Details
8East to South locational price spread peaked at Rs 1.94/kWh (hr 20) even though the East had spare transmission (TTC utilisation 80 %).
Click on Details for more Details
8Peak time hydro peaking (HPDAM) MCP jumped to Rs 6.68/kWh 34% above DAM weighted average despite hydro share in actual generation falling to a six month low (10.4%).
Click on Details for more Details
8A competitive procurement for aluminium wound Star 1 energy efficient distribution units sees a narrow price gap between the lowest and second lowest bidders. Awarded package covers full supply for network expansion
8A razor thin differential marks the winning bid for high spec 25 kVA CSP units. Sector watchers note aggressive positioning by multiple OEMs in Rajasthan’s distribution supply chain
8From 39 participating firms to a marginal L1–L2 difference, the tender reflects intense OEM rivalry and cost sensitive procurement strategies
8Award follows competitive evaluation of technical compliance and commercial bids, with aluminium wound Star 1 units forming the backbone of the supply. Details
8First occurrence of negative MCP in ancillary SCUC block: Rs 73/MWh at 13:45, while system frequency stayed above 50.05 Hz for 18 min
Click on Details for more
Details
8HPX grabs a high intra day market share on block basis: 19% at hour 11 despite having zero cleared volume in eight other blocks
This is evidence of tactical “price sniping.”
Click on Details for more
Details
Solar EOI in Rajasthan clears technical stage with high bidder retention
8Technical evaluation for a 25 year RESCO mode solar rollout in Jodhpur divisions has wrapped up with 12 of 13 contenders advancing, signalling sustained developer appetite under PMKUSUM norms
8While 12 firms cleared evaluation, one submission was disqualified for document legibility issues — underlining procedural strictness in PM KUSUM project screening
8With nearly all bidders qualifying, the next phase could hinge more on tariff competitiveness than prequalification hurdles
8The Jodhpur divisions’ grid connected PV plan now awaits price bids after a smooth technical evaluation, setting the stage for RESCO based deployment Details
815 of the 22 coal units that tripped on 04 Aug returned in 30 days pointing to fuel specific resilience gaps.
Click on Details for more
Details
8Find a snapshot of thermal, hydro, pumped storage, solar,
wind, BESS and T&D contracts related updates for the day
Click on Reports for more Details
Solar tariff race heats up in Rajasthan's decentralised grid push
8The latest price bid round under a state level PM KUSUM package sets a Rs.3.040/kWh ceiling, forcing developers into aggressive tariff positioning for sub2MW plants feeding into urban 33/11kV nodes
8A rare draw of lots provision could decide control of decentralised solar assets if bids converge at the same price, adding a layer of uncertainty for financiers and EPC partners
8Capacities from 0.5MW to 2MW per lot require tailored pricing, with evacuation lines and RMS integration forming a significant share of lifecycle cost
8Winners must build and connect dedicated 33kV or 11kV lines to target substations, blurring lines between generation EPC and network interface contracts Details
NTPC's Telangana Stage II GIS tender inches towards closure after six date shifts
8From February to August, the submission timeline has stretched, hinting at complex interface planning with the existing Stage I GIS and stringent qualification norms
8The 400 kV GIS package for Stage II has now seen multiple extensions, underscoring either active bidder participation or prolonged commercial and technical clarifications
8NTPC’s split award model for supply, services, and civil works is adding layers to bid strategy, with cross fall breach clauses keeping risk high
8The August 8 deadline may finally set the stage for a closure, but the package’s complexity suggests a  select pool of capable contenders. Details
Mega 1,600 MW plant's BOP tender stretches timeline yet again
8A high stakes balance of plant package for a large thermal expansion sees multiple deadline pushes — May to mid August — hinting at bidder preparedness issues amid complex integration of coal, water, and electrical systems
8The package wraps diverse mechanical, civil, and electrical systems under single point responsibility, demanding sharp interface management between cooling, water treatment, coal handling, and busduct installations
8The eligibility criteria now demand prior EPC execution of integrated coal and water systems for 500 MW+ plants, plus consortium structuring limits, cutting out weaker players from the fray
8Clarification responses point to discrepancies between flow diagrams and plot plans for wagon tipplers and conveyors, which bidders must reconcile in engineering proposals
8The package wraps diverse mechanical, civil, and electrical systems under single point responsibility, demanding sharp interface management between cooling, water treatment, coal handling, and busduct installations. Details
 For reference purposes the website carries here the following tenders:
8Tender for electrification work Details
 8Tender for misc civil and electrical works Details
 8Tender for procurement of spare parts of ring granulator Details
 8Tender for annual work contract for assistance related work Details
 8Tender for revetments work on tower Details
 8Tender for RLA test on different rating transfomer Details
 8Tender for work supply & work for repairing of damaged 220 kV line Details
 8Tender for to carry out protection audit of 132 kV transmission sub stations Details
 8Tender for construction of 33 kV bay at 132 kV substation Details
 8Tender for maintenance work of firefighting system Details
 8Tender for round the clock operation of DM plant, pre treatment plant, UF plant, clarified pump house Details
 8Tender for modifications work of compressor house Details
 8Design/ engineering, supply (excluding mandatory spares), storage, erection, testing and commissioning works for augmentation of transformation capacity Details
 8Tender for procurement of complete economiser coil assembly of boiler pressure parts in boiler Details
 8Tender for revised estimate for proposed 1x5 MVA new S/s Details
 8Tender for estimate for new 1x5 MVA,33/11 kV S/s Details
 8Tender for installation of ACBs at LT process room and 1MVA transformer Details
 8Tender for supply, delivery, installation, testing & commissioning of 2TR capacity new air conditioning machines Details
 8Tender for procurement of three phase angle cross arm Details
 8Tender for procurement of three phase channel cross arm Details
 8Tender for supply of 360kW HT motor Details
 8Tender for construction of new closed shed for storage of heavy lifting tools Details
 8Tender for miscellaneous civil works Details
 8Tender for work of operation & maintenance of mobile coal sampling equipment Details
 8Tender for execution of works carried out for effecting of new LTCT service connection Details
 8Tender for complete coupling assembly for BFBP to BFP motor complete coupling assembly Details
 8Tender for strengthening of 230 kV source of NCTPS stage III by converting the 230 kV feeder Details
 8Tender for repairing of culvert along Details
 8Tender for lightning protection system in various Details
 8Tender for restoration of damaged retaining wall Details

8Tender for supply of 33kV feeder CRP and 33/11kV transformer CRP Details
 8Tender for supply of 220kV CT of various ratings and supporting structures Details
 8Tender for supply and installation of LT /CT smart meters Details
 8Tender for implementation of real time centralized monitoring system Details
 8Tender for running civil maintenance Details
 8Tender for rectification, grouting and water proofing works and other similar type miscellaneous job Details
 8Tender for chain link fencing for dumping of coal mill reject Details
 8Tender for supply and installation of power distribution box Details
 8Tender for annual maintenance contract (AMC) for cooling appliances installed Details
 8Tender for providing parapet and crash barriers Details
 8
Tender for annual rate contract for the work of overhauling & repairing of 33/22/11kV circuit breakers Details
 8Tender for works contract for loading unloading of line materials Details
 8Tender for annual service contracts for chemical treatment including all type of chemicals required Details
 8Tender for EPC package for infrastructure development for 4750 MW RE park Details
 8Tender for supply of CPVC pipelines fittings Details
 8Tender for balance work of erection of 66kV S/C line Details
 8Tender for civil works contract for construction of 150 KL water storage tank Details
 8Tender for AMC for preventive and breakdown maintenance of UT machine Details
 8Tender for creation of 66 AIS lines bay at 66 kV S/Stn. Details
 8Tender for creation of 132 kV line bays for accommodating lines Details
 8Tender for biennial maintenance contract for civil works Details
 8Tender for shifting of meters from consumers premises Details
 8Tender for releasing of new service connection Details
 8Tender for construction of additional 100 KVA transformer Details
 8Tender for works contract for day to day preventive and breakdown maintenance including emergency breakdown at night hours of 765kV, 400kV, 230kV & 110kV EHT lines Details
 8Tender for supply of 11 kV single pole stand alone structure materials complete set Details
 8Tender for works contract for day to day preventive and breakdown maintenance including emergency breakdown at night hours of 400kV, 230kV and 110kV EHT lines Details
 8Tender for construction of civil foundation and CTR tank for 220 MVA transformer Details
 8Tender for augmentation of 200 MVA transformer Details
 8Tender for augmentation of 31.5 MVA transformer and associated civil work at 132 kV GSS Details
 8Tender for supply of electric winch for shifting (pulling) of scrapper Details
 8Tender for bi-ennial rate contract (BRC) for complete boiler plant Details
 8Tender for manufacture, testing, supply and delivery of LT grade and HT grade non heat shrinkable type line conductor Details
 8Tender for supply, commissioning and testing of 2 MVA, 6.6kV 415V, dry type transformer Details
 8Tender for procurement of grinding elements for XRP-803 and HP-803 bowl mills installed Details
 8Tender for procurement of spares and consumable of control valve of condensate system and feed regulating station Details
 8Tender for supply, fabrication, installation & laying of underground potable water pipeline Details
 8Tender for patch repair and culverts work Details
 8Tender for annual maintenance contract for civil works in stage 1 ash dyke Details
 8Tender for erection of 66kV equipment, structures, control wiring, yard lighting Details
 8Tender for carrying coal dozing works Details
 8Tender for job contract for roof treatment works Details
 8Tender for requirement of centrifugal pump and pump spares Details
 8Tender for sale of pond ash from ash dyke Details
 8Tender for dismantling of existing non-functional tower crane Details
 8Tender for procurement of spares for ash slurry pump Details
 8Tender for work contract for annual routine maintenance of turbine house auxiliaries, air compressor room auxiliaries Details
 8Tender for overhauling of boiler non-pressure parts air preheater and flue/ air ducts Details
 8Tender for repairing of electricity lines Details
 8Tender for construction of HT and LT electricity line with installation of transformer Details
 8Tender for repairing of electricity lines Details
 8Design, manufacturing, supply, testing and commissioning of HP compressor Details
 8Tender for supply, erection, commissioning and testing of 220V DC 81 AH Ni-CD battery Details
 8Tender for work of overhauling, repairing & reconditioning of damaged cartridges assembly 200KHI boiler feed Details
 8Tender for EPC project for design, engineering, supply, testing, installation, erection, commissioning & capacity up gradation of PA fan and ID fan motors Details
 8Tender for supply and commissioning of thyrister package AC system Details
 8Tender for DC battery cell preventive maintenance work at 220 kV & 400 kV switchyard Details
 8Tender for supply, installation, commissioning & testing of metal detectors on conveyor-2A/B, conveyor Details
 8Tender for work of complete overhauling of 75/15 MT EOT cranes Details
 8Tender for supply of capacitance type point level switch and spares for air compressors Details
 8Tender for water proofing works Details
 8Tender for replacement of failed and burnt transformer Details
 8Tender for work of renovation of existing earth pit & creation of new earth pit for transformer / ICTs at various Details
 8Tender for augmentation of substation by providing of 1X100 MVA 220/33kV T/F alongwith HV&LV bays at 220kV SS Details
 8Tender for work of procurement of various clamps connectors for routine & emergency maintenance work Details
 8Tender for work biannual AMC of repairing / refurbishing, servicing & overhauling of 400kV & 220kV isolator along Details
 8Tender for work of annual maintenance contract for attending emergency breakdown and also carrying out various Details
 8Tender for work of replacement of rusted cross arms & rusted rower material & members at various towers Details
 8Tender for procurement of 400kV, 80MVAr line reactor Details

 
You can also click on Tenders for more
 For reference purposes the website carries here the following newsclips:
8Green Ammonia Bid at Rs 55.75/kg: SECI Auction Details
 8Hindustan Power signs pact with UPPCL to set Up 435 MW DC solar project Details
 8Backed by Shirdi Sai Electricals Indosol eyes IPO in FY27 to invest Rs 69 000 cr on future capex Details
 8Coal India liberalises long-term supply deals to allow power sale on exchanges Details
 8JSW Energy commissions second unit of 240 MW Kutehr hydro project Details
 8Coal-fired power declines as India leverages inventories Details
 8Electricity bills to rise as Supreme Court orders states to clear dues in 4 years Details
 8IEX sees record-high volume in July; electricity prices continue to drop Details
 8Nuclear power-focused core energy systems raises Rs 200 cr funding Details
 8IEEE Power & energy society announces candidates for treasurer Details

 
8Rajpura thermal plant named best in country for low emission Details
 
8Indian power plants tap stockpiles, cut purchases as coal use slides Details
 
8Global coal demand to remain on a plateau in 2025 and 2026 Details
 
8Torrent Power Clocks 24.7 Pc Drop In Net Profit, Revenue Falls 12.5 Pc Details
 
8L&T’s Rajpura Thermal power plant named India’s best for lowest emission intensity Details
 
8India sees over 200 GW of hydro pumped storage potential Details
 
8Inox Wind rights issue opens on August 6 at 20% discount; Should you apply Details
 
8MAHAGENCO: Driving renewable energy integration in Maharashtra Details
 
8Andhra Pradesh set for green workforce revolution Details
 
8Around 60 pc women respondents seek gender-responsive policies to drive renewables in India IESA report Details
 
8Subsidy Trends: Incentivising renewables development Details
 
8Hedging Power Prices: India set to launch the electricity derivatives market Details
 
You can also click on Newsclips for more Details
HVPNL folds scattered transmission jobs into one Rs.100+ crore EPC push
8The package unifies previously separate 66kV and 132kV works in Ambala, Hisar, Bhiwani, Faridabad, and Palwal, potentially limiting small EPC players who thrived on single district jobs
8A single turnkey tender now bundles multiple LILO, new build, and augmentation jobs into one 9–15 month execution window, tightening coordination but raising bidder capacity requirements
8A 9.9 km double circuit 66kV link anchors a package that also threads redundancy into key 132kV corridors via multiple LILOs
8Bidders face prespecified compliance with CEA, NHAI, and Railway Authority rules, reducing mid project approval risks but locking in design complexity from day one
8EMD exemptions for registered contractors on the HEW portal are scrapped; strict Make in India compliance now applies to all line build bidders Details
Diversion of 400 kV assets points to high value private facilitation
8A transmission line reroute involving two double circuit 400 kV lines and one 220 kV line signals infrastructure adjustments for a major industrial consumer. Unusual shutdown coordination and tower modifications indicate a tight delivery requirement
8With D/C lines and S/C circuits bundled into one package, bidders must manage parallel works across voltage classes. This creates a substantial EPC opportunity, but also increases risks due to interdependent shutdown timelines
8The tender mandates diversion of energised 400 kV and 220 kV lines, calling for intricate tower design near existing alignment. Emphasis on minimal system outage reveals a highly sensitive project environment
8Transmission realignment of this scale typically points to major industrial growth in the corridor — most likely tied to power intensive sectors needing line clearance for development Details
New 400 kV substation opens gateway to 2000 MW solar evacuation
8A fresh EPC package calls for a greenfield 400 kV AIS substation to handle power from a major solar park in southern India. Tender floated under the TBCB model marks a strategic move in solar evacuation infrastructure
8Significant civil work components, including control room, foundations, and auxiliary infrastructure, dominate this 400 kV AIS package. Bid specs suggest opportunity for contractors with integrated civil electrical expertise
8The new package delinks transmission lines and focuses exclusively on the substation, enabling sharper bidding, reduced complexity, and risk containment for both EPCs and the asset developer
8Unlike CTU level backbone projects, this substation appears tied to direct discom connectivity for a mega solar park. The model may reflect growing state level grid readiness needs
8Detailed scope includes enhanced SCADA, PLCC, and inter station telecom links, potentially indicating tighter dispatch protocols and higher operational visibility expectations Details
Regulatory spotlight: Gujarat gas limited versus p&ng board
8This case could have enduring effects on regulatory frameworks, influencing how petroleum and natural gas industries navigate compliance and governance issues.
Energy sector braces for regulatory showdown in court
8A series of legal appeals, including those by major energy firms, could redefine the regulatory landscape and compliance norms in the oil and gas sector.
Regulatory gaps exposed as biomass project struggles with power evacuation
8SAEL's petition reveals regulatory and infrastructure gaps, with the existing 33 kV evacuation system unable to meet operational requirements.
8Effective resolution is crucial for Haryana's energy transition goals.
Haryana's energy banking rules: A legal tangle for long-term open access users
8HERC's recent regulations disallowing month-to-month energy banking have sparked legal challenges from users like Merino Industries, questioning the retroactive application and its impact on existing agreements.
Click on Details for more
Details
8Over 200 firms cleared technical evaluation for a long-term grid-connected solar package under a farmer-linked renewable scheme, signalling intense competition ahead of financial bids in Solar projects India. The large-scale participation reflects growing developer interest in distributed generation opportunities within Solar projects India.
8With 230 bidders making it past the technical gate in a farmer-linked solar program, financial bid openings could redefine tariff benchmarks for distributed renewables in Solar projects India. The record number of qualified participants reinforces the competitive nature of Solar projects India.
8Even after three bid submission extensions, developer response to a Rajasthan grid-tied solar package under RESCO mode surged, suggesting robust project bankability in Solar projects India. This strong interest highlights investor confidence in the policy and market framework driving Solar projects India forward. Details
8Click on Details to decode the inside story of inflated assumptions and fatal misreads Details
Rs 4001.67 vs. Rs 3861.76: Ntpc contests coal price methodology
8NTPC disputes CERC’s coal pricing calculations, proposing a correction based on established methodologies, which could recalibrate power station economics.
Legal tussle under energy conservation act signals stricter enforcement
8The BEE's petition against NDMC for energy compliance lapses underscores intensified regulatory scrutiny.
8Industry must brace for more stringent enforcement actions.
Adani electricity's Maharashtra disputes linger, reflecting sector-wide legal inertia
8Adani Electricity Mumbai Limited's unresolved cases with the Maharashtra Electricity Regulatory Commission exemplify the prolonged legal entanglements hindering sectoral progress.
Tata power among key players entangled in lengthy regulatory battles
8Tata Power's involvement in ongoing appeals illustrates the legal complexities energy giants face, potentially affecting their operational strategies and market positioning amidst regulatory uncertainties.
Click on Details for more
Details
8Planned thermal maintenance simultaneously tops 15 GW while realtime imports of coal rich northern states rise 29% the first time the two curves have crossed this financial year.
Click on Details for more
Details
Turnkey GIS substation tender nears Rs.110 cr mark after scope tweaks
8Minor upward revision in estimated value and bid security points to refined BOQ alignment—typical of trends in the Latest Indian power tenders. SAS integration and HTLS line works remain in focus.
8Multiple deadline shifts signal high bidder engagement, but also potential complexity in design finalisation and qualification review for the turnkey package, as seen in other Latest Indian power tenders where bidder scrutiny is tightening.
8Multiple XLPE runs with high cross-section ratings and complex indoor terminations add execution challenges—paralleling commissioning hurdles noted in recent Latest Indian power tenders for high-voltage GIS installations.
8This tender reflects how Latest Indian power tenders increasingly emphasize refined technical compliance and tighter project interfaces. The Rs.110 crore threshold is yet another benchmark in how Latest Indian power tenders are evolving under turnkey EPC pressures. Details
Strategic 400 kV link plan locks in Rs.119 cr investment for desert solar evacuation
8The new package, part of broader Power Projects in India, covers survey to commissioning for critical grid tie-ins at Pugal GSS, with double circuit designs dominating the scope to boost redundancy and reliability.
8The contractor, playing a key role in India’s evolving Power Projects in India landscape, will handle every stage from tower steel procurement to OPGW stringing with phased delivery targeting priority line energisation well before full project completion.
8This turnkey effort within Power Projects in India mandates strict adherence to approved design specifications, origin norms, and tightly sequenced execution to mitigate weather-related risks.
8While financial guardrails remain aligned with previous tenders, this reissue underlines sharper delivery milestones and precise route length definitions highlighting the evolution in execution discipline for large Power Projects in India.
8Such focused grid expansions reinforce reliability goals and long-term bankability for solar-linked Power Projects in India in challenging desert terrain. Details
8A grid-connected solar initiative under PM KUSUM Component A has drawn massive interest, with 82 technical bids submitted for distributed plants up to 2MW each. The project, a part of the growing portfolio of Indian renewable projects, is designed to solarise agriculture feeders under RESCO mode over a 25-year span.
8In a bid to secure 25-year PPAs, 82 developers have responded to a RESCO mode solar tender under a government-backed rural electrification scheme. These Indian renewable projects are spread across two major divisions with substation-level allocations, indicating widespread private sector participation.
8Several developers submitted multiple bids across substations, signaling strong interest in decentralised 2MW solar plants. This discom-led project seeks to tap private land parcels under Component A of the national solarisation programme further reinforcing the rising momentum behind Indian renewable projects focused on distributed energy.
8Under a central government mandate, the project aims to reduce subsidy burden through decentralised solar integration. A fixed 25 year PPA makes it an attractive, risk-mitigated model for developers with land and grid access, showcasing how Indian renewable projects are becoming more bankable and scalable in rural contexts.
8This surge in bidding reaffirms the growing appetite for Indian renewable  projects that blend grid-connectivity, land optimisation, and long-term policy support. Details
8DSM penalties surged across the Indian power sector even though the frequency violation index (FVI) improved to 0.028—meaning fines are increasingly driven by schedule deviation rather than actual grid stress, a trend being closely watched in Indian electricity markets. Click on Details for more on how power distribution companies, load dispatch centers, and grid operators are navigating the new 8DSM regime under India’s power regulations, and why schedule adherence is becoming a more critical factor than frequency metrics in the Indian power sector. For deeper analysis of grid compliance trends in India’s power sector and penalty mechanisms, follow our updates on Indian power news. Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8Coal and Coke
8LPG
8Ammonia
8All tankers
8Bulk and Dry cargo
Click on Reports for more. Details
8Find a snapshot of thermal, hydro, pumped storage, solar,
wind, BESS and T&D contracts related updates for the day
Click on Reports for more Details
Supercritical expansion project sees active interest in ash handling scope
8With technical bids now opened, the ash disposal system package for a 2×800MW unit expansion has attracted multiple experienced EPC vendors. Technical scrutiny begins on proposals covering full mechanical, electrical, and civil works for a high-volume ash disposal system at a 1,600MW facility. Four qualified bidders are now in contention for an integrated ash management system in a supercritical thermal stage expansion. Details
Bid deadline pushed thrice for Rs.3,200cr transmission EPC
8The latest extension on this large inter substation line suggests bidders are refining cost models for a complex, multi voltage corridor in coastal terrain. A high-capacity 400 kV double circuit and 220 kV LILO package sees its bid window pushed again, signalling heavy contractor interest and likely intense price competition. Multiple deadline shifts point to ongoing pre bid clarifications on tower design, routing, and integration with GIS substations. With the bid now due in August, cost strategies for a 147 km high capacity build plus multi circuit LILO could reshape final pricing trends. Details
Cancellation halts major substation upgrade after months of deadline shifts
8After a series of bid extensions, the planned GIS-based capacity boost for a North East transmission node has been scrapped for administrative reasons, leaving upgrade timelines uncertain. An ambitious capacity augmentation from 3×20MVA to 3×50MVA, including a bus bar re-engineering, is now off the table after internal clearances failed to materialize. Multiple revised bid dates pointed to active bidder interest, but administrative hurdles forced the transmission project owner to abandon the process altogether.
8The planned jump from 60MVA to 150MVA transformer capacity in a key urban substation will have to wait as procurement is halted for administrative reasons. The repeated shifts in closing dates hinted at evolving bid clarifications, but the final outcome points to deeper procedural or alignment issues.
8A flagship 132/33kV GIS capacity enhancement and bus bar overhaul is off the procurement roster, pushing back the region’s planned grid reliability improvements. Details
8Daily all India auxiliary consumptionicked up to 4.97 % only the third time in 24 months it has breached 4.9 % in a non summer month.
Click on Details for more
Details
8Cross product arbitrage opportunity: a buyer who purchased 200 MWh in GDAM (Rs 3.33/kWh) and simultaneously sold equivalent volume in RTM peak (Rs 5.36/kWh) could lock in Rs 4 lakh profit net of fees became doable 12 times yesterday.
Click on Details for more
Details
8A 450 MW HVDC North East–Agra pole outage (logged in CEA coincided with the day’s highest congestion rent (Rs 92 lakh) on IEX’s market splitting algorithm.
Click on Details for more Details
8DSM penalties (PXIL report) spiked to Rs 21 crore yesterday highest single day figure since 5 April 2024 and 71% of it is traceable to three northern states that simultaneously imported >1GW on RTM.
Click on Details for more Details
8Real time market (RTM) volumes on HPX jumped to 2.28 GWh ( day) and captured 13% share- the first time it has broken into double digits.
Click on Details for more
Details
8Green DAM (GDAM) excess generation bids exceeded actual clearance by 46% pointing to persistent curtailment risk for RE generators.
Click on Details for more
Details
8DSM penalties (PXIL report) spiked to Rs 21crore yesterday highest single day figure since 5 April 2024 and 71% of it is traceable to three northern states that simultaneously imported >1GW on RTM
Click on Details for more
Details
Voltage Control Gap Widens: Only 11 of 49 Generators Deliver “Good” MVAR Support
815th-round SRPC audit shows 70 % of Southern Region units falling short or even injecting VAR in the wrong direction, raising stability concerns as renewables surge
Misaligned Tap Settings & Manual AVR Tweaks Hamper Reactive Response
8SRLDC flags OLTC mismatches and high-voltage injections at CEPL, NLC and NTPC plants, urging immediate tap re-validation and strict AVR auto-mode operation
Quarterly Self-Audits and OEM Fixes Mandated under New Action Plan
8Generators must now file capability curves every quarter, engage OEMs such as BHEL to clear load-angle limits and stop high-voltage VAR injections ahead of peak RE season.
Click on Details for more
Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8Coal and Coke
8LPG
8Ammonia
8All tankers
8Bulk and Dry cargo
Click on Reports for more. Details
Consultancy call for two-year regulatory battle plan
8RVUNL seeks long-haul consultancy to prepare and defend multi-year tariff and ARR petitions before RERC. The scope spans coal, gas, and hydel assets, with embedded financial and technical advisory roles. Bidders must deploy both technical and financial experts in Jaipur full-time, signalling RVUNL’s push for on-site control in high-stakes tariff filings. Only consultants with three recent tariff-related orders in Indian generation or transmission will qualify, sidelining generic advisory firms from the race. Details
NHAI Diversions Delay Grid Works Across Southern States
8Shutdown approvals for key transmission lines like Srikakulam–Vemagiri and Khammam–Kalapaka face repeated deferrals due to poor coordination, RoW issues, and rain, with SRPC urging stricter compliance with CEA protocols.
Generators Blme DSM Losses on SCED Inconsistencies and Market Punching
8NTPC, NTPL and JSW raise serious concerns over DSM penalties from under-requisitioning by states and SCED underutilization, urging regulatory intervention to ensure minimum schedule commitment from beneficiaries.
Grid Stability Threatened by Inadequate Reactive Power & AGC Compliance
8Poor MVAR absorption, AGC non-compliance, and flawed SPS response from key players like NLCIL, NTPC, and JSW threaten frequency control and regional reliability, forcing SRPC to demand urgent technical course corrections.
Gazuwaka HVDC to be Refurbished Amid Strategic Push for Grid Flexibility
8NLDC recommends full-scale upgrade of Gazuwaka B2B HVDC system, citing its critical role in RE variability mitigation and ER–SR congestion relief; staggered refurbishment and AC backup routes proposed.
Click on Details for more
Details
IEX Proposes Peak DAM and RTM to CERC for Approval
8Indian Energy Exchange has filed a petition with CERC to introduce Peak Day Ahead Market and Peak Real Time Market mechanisms, aiming to cater to high-demand time blocks with more granular price discovery.
Stakeholders Called to Comment by September 3
8CERC has directed IEX to publicly disclose the petition and seek feedback from all stakeholders and the public. Responses are invited both by post and email before the deadline.
New Markets Could Reshape Intraday Power Trading
8If approved, Peak DAM and RTM will offer participants more flexibility to hedge peak demand risk paving the way for smarter grid and renewable integration strategies.
Click on Details for more
Details
Deadline slippage in Ladakh hybrid project suggests cautious participation
8Multiple extensions for a 7MW PV+9MWh BESS project one of the most challenging renewable projects in India could indicate careful due diligence by prospective bidders, given the integration and storage requirements
8The latest corrigendum pushes bid submission for this high-altitude solar plus battery project, underscoring how renewable projects in India often demand intensive pre-bid clarifications and custom design solutions.
8Multiple date shifts point to bidders fine-tuning technical and commercial proposals for a 7MW hybrid plant, a hallmark of complex renewable projects in India operating in extreme environments.
8In such terrain, renewable projects in India require higher precision, risk planning, and robust engineering to meet both performance and regulatory expectations. Details
Technical bid stage opens for 1,000 MW emission retrofit balance works
8With bids now in for the final leg of FGD erection and commissioning at a major western India thermal plant, Thermal power plant updates in India point to heightened focus on how execution timelines and trial run support will be managed for regulatory compliance. Raj Enterprises and Jyoti Turbo Power Services have entered the fray to complete Unit2 and common system works under a time-sensitive emission control mandate.
8The scope demands seamless coordination across material handling, erection, commissioning, and trial operations leaving little room for missteps in a live brownfield environment. As part of the latest Thermal power plant updates in India, stakeholders are watching closely to see how contractors navigate space constraints, interface with existing systems, and meet strict pollution norms.
8Industry observers say that these Thermal power plant updates in India underline a critical phase for emission control retrofits, especially in plants nearing their compliance deadlines. Execution success here could set benchmarks for similar projects highlighted in upcoming Thermal power plant updates in India, where retrofit efficiency and minimal downtime remain top priorities. Details
Strategic twin package procurement spans 400kV and 220kV grids
8Two parallel conductor transmission equipment tenders in India aim to standardize composite core HTLS technology across voltage levels.
8The move could streamline specifications and lower lifecycle costs through unified sourcing. The 220kV package mirrors the 400kV scope, extending HTLS technology to sub-EHV networks. This could increase current carrying capacity without heavy tower reinforcement.
8By explicitly calling this a vendor development exercise, the buyer signals ongoing rollouts  a potential long-term play for qualified suppliers in the transmission equipment tenders in India space.
8Such synchronized procurement across voltage classes may set a benchmark for future transmission equipment tenders in India, attracting both established OEMs and emerging players. The long-term adoption of HTLS conductors could reshape bid strategies in upcoming transmission equipment tenders in India. Details
 For reference purposes the website carries here the following tenders:
8Tender for civil works for foundation Details
 8Tender for HT & LT line extension, improvement and maintenance works Details
 8Tender for supply of various expansion bellows and joints Details
 8Tender for supply, erection and civil of electrical transmission line works Details
 8Tender for connecting of 132 kV double circuit overhead line Details
 8Tender for maintenance & repair of drinking water raw water supply network Details
 8Tender for rate contract for supply of BIS certified energy efficiency level Details
 8Tender for revised estimate for proposed 1x5 MVA new S/s Details
 8Tender for estimate for feeder bifurcation work of 11 kV domestic feeder Details
 8Tender for supply of ISI marked 2 Core, 4 Core, 8 Core, 12 Core Un-armored Details
 8Tender for procurement of spares of Max-DNA DCS control panels Details
 8Tender for AMC for enhance uptime services CEMS and CPCB connectivity remote support Details
 8Tender for procurement of spares of gear box installed at air pre-heater Details
 8Tender for various civil construction works pertaining to feeder bays, augmentation of X-mer, addl. X-mer etc. Details
 8Tender for various civil construction works pertaining to feeder bays Details
 8Tender for various civil construction works pertaining to feeder bays, augmentation Details
 8Tender for reconductoring 11 kV line with covered conductor Details
 8Tender for supply of LT aerial bunched cables of size Details
 8Tender for upgradation of TRCM panel Details
 8Tender for supply of critical valve cooling spares Details
 8Tender for asbestos sheet dismantling and new GI colour coated sheet fixing Details
 8Tender for empanelment of transportation agencies with rate contract for lifting Details
 8Tender for repairing and face lifting Details
 8Tender for repair and maintenance of damaged plant Details
 8Tender for insulation works of main plant piping, ducting and equipments Details
 8Tender for biennial contract for maintenance of aluminum partitions, false Details
 8Design, supply, installation, testing and commissioning of fresh air units Details
 8Tender for supply of lower journal bearing housing of HP803 bowl mills Details
 8Tender for supply of discharge chute SS for feeder of HP803 bowl mills Details
 8Tender for supply of variable load hanger assembly for condenser left and right outlet pipes Details
 8Tender for supply of constant load hanger assembly for HP803 bowl mills Details
 8Tender for supply of spares for making readiness of stand by scrapper feeder Details
 8Tender for supply of tapping channel cross arm Details
 8Tender for contract for mechanical maintenance, electrical maintenance and operation of ash handling plant Details
 8Tender for procurement of 33 kV, 20 MVAR capacitor bank with reactor, NCT and structures required Details
 8Tender for procurement of 132kV SF6 circuit breaker and 145kV isolator Details
 8Tender for procurement of 132kV SF6 circuit breaker at 132kV substation Details
 8Tender for repair and renovation works Details
 8Tender for erection of structures, equipments, earthing, control wiring, yard lighting Details
 8Tender for supply, erection, testing & commissioning of 66 kV line on D/C tower Details

8Tender for work of complete servicing /overhauling/fault attending /repairing / checking and supply of spare of various Details
 8Tender for annual rate contract for supply of spares of 11 kV class, VHA-12 type panels Details
 8Tender for annual repair and maintenance work of electric fencing, smoke detector and their associate saftey items installed Details
 8Tender for replacement of damaged/rusted pole Details
 8Tender for HT & LT line extension, improvement and maintenance works Details
 8Tender for supply of BM clamp 95 Sqmm, 120 Sqmm and 185 Sqmm Details
 8Tender for dismantling, fabrication and renewal of worn out 300 NB M.S seamless pipe and providing cement pedestal from clarified water pump house Details
 8Tender for HT & LT line extension, improvement and maintenance works Details
 8Tender for dismantling, fabrication and renewal of worn out 300 NB M.S seamless pipe Details
 8Tender for supply of steel and fabrication work of walk way for inspection and maintenance of various hoists installed Details
 8Tender for job work of routine, preventive maintenance, cleaning and readings of battery sets Details
 8Tender for estimate for 11 kV baifarcation feeder Details
 8Tender for supply of DC distribution board Details
 8Tender for supply of 30-V lithium-ion battery set for 33/11 kV substation Details
 8Tender for supply of 11 kV3 core 300 Sqmm and 33 kV 3 core 300 Sqmm HT XLPE cable Details
 8Tender for supply of 11 kV (9 kV) gapless type polymer lightening arrestor Details
 8Tender for procurement of 1.1 kV control cable and power cable Details
 8Tender for supply and erection of 45 degree fabricated ceramic coal bend for HP 803 bowl mills Details
 8Tender for earthwork excavation, stub setting, concreting, erection, stringing of panther conductor and earth wire Details
 8Tender for supply of caustic soda and HCL Details

 8
Tender for purchase of 400 kV and 220 kV isolators Details
 
8Tender for bi-annual rate contract for the work of erection of 66kV feeder bay equipment Details
 
8Tender for repair of civil structure foundations at varoius Details
 
8Tender for erection work of 66kV LILO line Details
 
8Tender for replacement of plugged eroded economizer coil assemblies Details
 
8Tender for complete preventive maintenance of LT breakers HT breakers HT panels complete service Details
 
8Tender for supply of clamps, control cables, power cables and other items at 132kV substation Details
 
8Tender for miscellaneous civil works at 33/11 kV substation Details
 
8Tender for extension of control room and other related civil works at 33/11 kV S/S Details
 
8Tender for miscellaneous civil works at at 33/11 kV substation Details
 
8Tender for construction of miscellaneous civil works at 33/11 kV substation Details
 
8Tender for strengthening work of conveyor gentry, junction tower and crusher house Details
 
8Tender for work of anticorrosive painting for the various structures, auxiliaries, tanks, piping, fence etc. Details
 
8Tender for supply of MS back clamp and MS stay clamp for 8 Mtr PSC pole Details
 
8Tender for supply of 11 kV and 22 kV fixed and moving contact Details
 
8Tender for supply of 350 NB seamless pipes of OD 355.6 mm and MS coupling set suitable Details
 
8Tender for supply of 400KV CVTs with standard accessories and fittings matching with existing CVT foundations Details
 
8Tender for purchase of spares of hydrogen generator energy systems Details
 
8Tender for supply of spares of ESP for 6 x 250 MW Details
 
8Tender for supply of complete ID fan hydraulic coupling and its spares Details
 
8Tender for purchase of spares For 3X1750 KVA DG sets Details
 
8Tender for purchase of seal oil pump and spares UT pumps system Details
 
8Tender for construction of transmission elements 400 kV transmission lines Details
 
8Tender for interlinking 1.7km HT line using HT covered conductor Details
 
8Tender for supply and installation of remote mounted smart positioner in SADC for coal elevations Details
 
8Tender for replacement of roof/cladding sheet of various Details
 
8Tender for supply of transformer oil Details
 
8Tender for work contract for operation and maintenance of HVAC system of main plant Details
 
8Tender for work contract for annual routine maintenance of turbine auxiliaries  Details
 
8Tender for procurement of split bearing equivalent to bearing CCK W33 along Details
 
8Tender for procurement of spares for degasser air blower Details
 
8Tender for land filling works for the new 33/11 kV substation Details
 
8Tender for augmentation by addition of 1x25MVA,132/33kV at 132kV S/Stn Details
 
8Tender for procurement of 200MVA, 400/220/20kV, 1 and 167MVA, 400/220/33kV, ICT along with new uninhibited high grade mineral insulating oil Details
 
8Tender for replacement of RCC structure by lattice type structure of various 220/132/110 kV equipments Details
 
8Tender for supply of spares & complete mechanism overhauling of 220kV circuit breakers at various Details
 
8Tender for supply of various size of ash pipes coupling Details
 
8Tender for work of in-situ repairing / overhauling / reconditioning of main steam stop valve, safety valves and other high pressure valves of boiler Details
 
8Tender for supply of 6.6KV, 261KW, HT motor for conveyor Details
 
You can also click on Tenders for more
 For reference purposes the website carries here the following newsclips:
8Green hydrogen: The future fuel driving industrial decarbonisation Details
 8Running on clean hopes, dirty fuel: India's renewable plans face key risks Details
 8Financial Briefs: India and overseas Details
 8Torrent Electricals to invest over 1,000 cr in housing wire segment Details
 8NCAER suggests 14K cr annual green grant for states to meet RE target Details
 8Indian Energy Exchange logs record trade volume of 12,664 MUs in July Details
 8The missing link in India’s battery waste management Details
 8With men driving India’s renewable energy push, what role do women play Details
 8Juniper green energy: 25 MW wind project in Gujarat Details
 8NTPC Wins SECI green ammonia Tender Details
 8
In green push, solar panels to be set up at Panchkula community centres Details
 
8Green hydrogen: The future fuel driving industrial decarbonisation Details
 
8Power stock to buy now for an upside of 32%; Recommended by Axis Securities Details
 
8Adani Group Denies BYD Tie-Up for battery manufacturing Details
 
8Energy dept’s nod to buy 630MW solar power leads to controversy Details
 
8GAIL India, RVUNL team up for 1 GW of wind, solar in Rajasthan Details
 
8Gentari signs 80MW wind PPA with AWS Details
 
8India’s Wind energy growth and wildlife challenges Details
 
8Avaada Electro Appoints Kaushal Shah as chief financial officer to accelerate global green manufacturing vision Details
 
8Indian Energy exchange trad volume jumps 25.5% YoY in July ’25 Details
 
8Parth Electricals IPO Raises Rs 13.8 Cr Details
 
8Vietnamese EV maker VinFast opens plant in Tamil Nadu; set to produce 50,000 EVs annually Details
 
8CIL plans big capex push for critical minerals foray Details
 
8India to open nuclear power sector to private companies with 100 GW Goal by 2047 Details
 
You can also click on Newsclips for more Details
8Mid afternoon coal generation fell below the technical minimum envelope while IEX average clearing price rose 17% (Rs 0.65/kWh) a counter intuitive decoupling.
Click on Details for more Details
230kV grid expansion project sees four contenders at technical bid stage
Four engineering and EPC firms have entered the race for a turnkey high-voltage AIS substation and bay extension package under an MNRE-KfW funded transmission upgrade. The technical bid opening for a 230/110kV AIS substation package revealed participation from both civil-heavy and equipment-focused firms, signalling a mixed competitive field. Technical bid opening for a 230/110kV AIS turnkey project shows healthy participation, underlining the continued draw of funded grid augmentation schemes. Details
Tariff race opens for decentralized solar push in Rajasthan
8Empanelled developers under a central solar program now enter the price bid stage for sub-station-linked projects in the state, with L1 selection rules and tariff ceilings set to test cost competitiveness.
8After qualification in the EoI stage, shortlisted players now have just days to lock in their tariff offers for multiple sub-station allocations in a city circle zone.
8The tender freezes plant locations and capacities for this phase, setting the stage for location-specific cost modelling and network integration planning.
8Pre-qualified RESCO players now face the decisive tariff test, with the lowest offers poised to secure long-term generation contracts under a flagship decentralised scheme. Details
8Find a snapshot of thermal, hydro, pumped storage, solar,
wind, BESS and T&D contracts related updates for the day
Click on Reports for more Details
Consultancy tender floats for long-haul coal delivery system
8A new thermal plant-linked tender seeks feasibility studies for a 40 km elevated pipe conveyor from upcoming coal blocks. The project hints at a shift away from rail-road dependence and could be a precursor to bundled EPC+logistics contracts in future phases.
8Originally closing mid-July, the consultancy tender for the elevated conveyor system was extended twice, now due by August 7. Extensions suggest deeper technical clarifications or a push for broader participation in this high-value logistics planning contract.
8The proposed study covers coal connectivity from WCL mines to a key thermal power plant. This signals renewed focus on dedicated, environment-friendly coal evacuation strategies amid capacity consolidation in central India. Details
Scope widens from powerhouse to rooftop solar base in thermal plant civil tender
8From turbine hall foundations to solar system supports, the package demands integration across power block sub-systems — a rare bundling that could stretch contractor resource planning.
 Inclusion of underground cooling water ducts and fire-fighting system foundations within powerhouse limits could significantly influence sequencing and excavation planning.
8The all-in-one structural and architectural package for a central India coal-based unit now has bids pushed to early August, indicating heavy front-end complexity and multiple interface points with other contractors. Details
Rajasthan’s first 1GWh+ grid storage bid stretches deadline amid pre-bid revisions
8A mega standalone battery energy storage procurement in the state has pushed bid submission to late August after major scope and location tweaks post pre-bid. Developers eye the reduced per-bidder cap and finalised substation list as key strategy shapers.
8From an initial early-August close, the bid window has now been pushed to 26 August, with technical opening on 27 August — a signal of prolonged clarification cycles and document redrafts.
8The latest amendments slash the maximum single-bidder allocation from 250 MW to 200 MW, potentially widening competition and altering consortium math in the upcoming tariff-based reverse auction.
8While the floor remains 50 MW × 2 hours, capacity increments must now be at least 50 MW / 100 MWh — tightening modular bidding strategies and site aggregation approaches. Details
Tight bid calendar sees three successive deadline extensions
8Initial submission was pushed from 9 July to 23 July, then again to 31 July and 6 August. The frequency of date shifts points to bidder queries and scope clarifications. The staggered response cycle may reflect coordination challenges across four distinct sub-packages.
8Although part of the scope lies in a dense urban footprint, the tender makes no allowance for gas-insulated switchgear or compact yard layouts. Air-insulated yard formats are assumed. This could restrict substation land optimization and signal limited flexibility in brownfield footprint planning.
8Uniform transformer sizing across all three new substations implies strategic modularity. The 40 MVA capacity is adequate for current load but suggests the substations are future-ready for rapid scaling. Design harmonization could reduce vendor divergence and transformer foundation redesigns.
8All new substation taps are derived from existing 66 kV SC lines—signaling a reliance on legacy corridors. This may expose the new assets to upstream contingency risks unless upstream redundancy is simultaneously addressed. No mention of 220 kV back-feeding or hybrid augmentation is noted. Details
Ninth extension issued for 1600 MW thermal switchyard EPC
8A large-scale switchyard package for a central India coal-fired project has now seen its ninth bid extension, pushing deadlines into mid-August. Despite a full-scope EPC format and a national promoter, bidder appetite seems cautious. Experts suspect ongoing clarifications and civil interface concerns may be the cause. Is technical ambiguity holding back large contractors.
8The project invites complete EPC responsibility—including design, supply, erection, testing, and commissioning—for a 400 kV AIS switchyard. With over 15 major equipment categories listed, the tender expects depth in both control and protection integration. Civil and electrical interface planning is critical given the clustered layout. Only seasoned integrators may qualify.
8With integrated supply, erection, and testing of a detailed protection system, the tender appears best suited for single-source OEM-backed bidders. Fragmented JV or consortium setups may find compliance difficult. The structure favors experienced turnkey switchyard integrators with full in-house capability.
8The project mandates supply and wiring of multiple interface panels—including synchronization, line protection, and busbar schemes—suggesting layered coordination between yard and control room assets. Experienced relay integrators will recognize the complexity here. This isn’t a supply-and-forget panel job. Details
Roorkee GIS package sees fifth extension amid bid hesitation
8A major substation EPC tender in northern India has now seen five start-date extensions, hinting at either tight qualification filters or tepid market appetite. The project, involving a 400/220 kV GIS build with full civil and control integration, may be pricing-in risk aversion among potential bidders.
8A high-voltage turnkey package involving control building, automation, and dual-voltage GIS bays sees sluggish bidder engagement. Market watchers note the strict commissioning history requirements and joint undertaking norms from OEMs as possible deterrents.
8With minimum average turnover set above Rs. 135 crore and access to Rs. 27 crore finance required at bidding stage, this tender raises the bar. These thresholds, combined with high-spec GIS mandates, may limit field to just 5–7 national players.
8Only firms with prior 400 kV or 220 kV GIS/AIS commissioning experience—certified by end users—are eligible to bid. This clause, in tandem with legally binding OEM tie-ups, keeps qualification tight for this 400/220 kV substation project. Details
8With technical qualification locked in for 230 players, the upcoming financial round is expected to drive tariffs down, testing developer margins in rural grid integration.
8The latest PM-KUSUM procurement in Rajasthan underscores developer preference for build-own-operate contracts backed by assured utility offtake.
8With technical evaluation wrapped up, the financial round could set new benchmarks for decentralised solar costs under the PM-KUSUM framework. Details
Northern Region Holds Strong: Uttar Pradesh Power Plants Stockpile for Over 40 Days
8Despite national variability, major plants like Harduaganj and Maqsoodpur in Uttar Pradesh report over 50 days of coal stock more than double the average reflecting robust fuel security amid monsoon logistics.
Chhattisgarh’s Private Players on the Brink: 5 Units Below 5 Days Stock
8Plants like Balco TPS and Adani Raigarh are skating dangerously close to operational thresholds, with coal supplies dipping as low as 4 days. The data signals rising stress in the western corridor’s private capacity.
Import Lagging, but No Crisis Yet: 98% of Power Plants Rely Entirely on Domestic Coal
8With indigenous supply powering nearly all 140+ thermal stations, India’s coal self-reliance holds yet the near-absence of imports could leave little cushion if domestic logistics falter.
Click on Details for more
Details
Pavagada Pushes Storage Frontier: 250 MW Solar + 1.1 GWh BESS Cleared for Grid-Linked Deployment
8Karnataka's solar heartland gears up for one of India’s largest co-located battery storage rollouts, blending TBCB solar capacity with a hybrid dispatch model using dynamic BESS scheduling.
No Compensation for Curtailment: KSPDCL Shifts Grid Management Burden to Developers
8RPDs will face zero deemed generation payouts if they fail to plan BESS dispatch or account for seasonal grid constraints making meticulous scheduling a regulatory necessity.
Only 83 MU Direct Injection Allowed Annually: Strict Caps & Dynamic Controls for Grid-Friendly Solar
8With annual limits and advanced PPC controls in place, developers must store 80% of solar output in batteries and tightly coordinate discharge through SLDC for real-time grid adaptability.
Click on Details for more Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8Coal and Coke
8LPG
8Ammonia
8All tankers
8Bulk and Dry cargo
Click on Reports for more. Details
Cooling tower EPC for 2×660 MW project sees strict design window and dual-unit staging
8The EPC scope for the NDCT, part of one of the latest thermal power tenders, includes staggered delivery targets—Unit1 civil handover in 30months and Unit2 trailing at 36. Design approvals and supply timelines are tightly gated, leaving limited float for delays in engineering resubmissions, a factor that sets this apart in the landscape of latest thermal power tenders.
8From its original 15July deadline, the NDCT bid saw three commercial corrigenda, moving successively to 25July, 1August, and finally 8August. The staggered extensions hint at active bidder interest and clarifications under negotiation, a dynamic increasingly seen in latest thermal power tenders with complex engineering scopes.
8In a departure from usual civil contracts, BHEL has stipulated that the NDCT contractor must arrange their own open and covered storage, with no laydown space provided within the project boundary. This self provisioning requirement reflects a tightening of execution discipline in latest thermal power tenders, where site logistics are being pushed back onto contractors. Details
 For reference purposes the website carries here the following tenders:
8Design/ engineering, supply, storage, erection, testing and commissioning works for Augmentation of transformation capacity Details
 8Tender for diversion of 400kV DC line Details
 8Tender for supply and retrofitment of VRLA battery banks at various substations Details
 8Tender for construction of transmission elements 400kV transmission lines Details
 8Tender for construction of additional divider dyke for capacity creation in lagoon-II Details
 8Tender for contract for silver alluminium painting with Primer coating on 11kv steel poles installed Details
 8Tender for construction of HT/LT line/sub-station Details
 8Tender for replacement of ACSR dog and rabit bare conductor by insulated covered conductor Details
 8Tender for procurement of different MS pipes Details
 8Tender for procurement of different knife gate valves Details
 8Tender for procurement of steel materials for structure renovation of stacker cum reclaimer Details
 8Tender for procurement of radiator for WDS 6R locomotive engine Details
 8Tender for annual repair and maintenance (civil and electrical works) of existing Details
 8Tender for operation and maintenance of PDFAC system and wet sluice system including materials Details
 8Tender for supply of splitter assembly for flue gas duct Details
 8Tender for dismantling hard facing and assembling of 1 meter length coal pipes Details
 8Tender for enhancement of power transformer 2x16 MVA into 2x16MVA+1x25MVA, 25 MVA power transformer Details
 8Tender for procurement of 200MVA, 400/220/20kV, 1 and 167MVA, 400/220/33kV, 1-ICT along with new uninhibited high grade mineral insulating oil Details
 8Tender for annual maintenance contract (AMC) for repairs, overhauling, servicing & alignment of 400kV center break type isolators Details
 8Tender for work of mechanical strengthening and stub strengthening of existing 66kV line Details
 8Tender for testing of various numerical and electromagnetic relays installed Details
 8Tender for procurement of load cells of weighbridges installed Details
 8Tender for blade vibration monitoring systems Details

8Tender for work of the re-strengthening of dry ash collector tank system hopper Details
 8Tender for repair and oil topup of transformers Details
 8Tender for ground improvement using geo-synthetics for tanker loading Details
 8Tender for testing and relocation of blade workstations with panels Details
 8Tender for civil structural and architectural works of transformer yard, power house Details
 8Tender for supply and installation of electrical appliances Details
 8Tender for supply of various consumable item Details
 8Tender for mapping survey and oxide layer testing of boiler tubes Details
 8Tender for procurement of fly ash conveying system Details
 8Tender for Bi-ARC for the emergency restoration of power of 66kV,132kV & 220kV transmission line on tower Details
 8Tender for miscellaneous maintenance works Details
 8Tender for procurement of float valves for seal oil system intermediate oil tank and vacuum tank Details
 8Tender for diversion of 220kV SC line Details
 8Tender for supply of media converters for HVDC MACH panels Details
 8Tender for supply of towers tower parts including stubs and nuts and bolts for various Details
 8Design, supply, installation, commission and maintenance of solar PV system Details

8Tender for procurement of spares of turbine bearings, pedestals, valves, servomotor, MS HRH strainers and deaerator etc.Details
 8Tender for work of in-situ metallography of tubes / pipes, headers, blades etc Details
 8Tender for supply of 2 KVA UPS with 12V 100 AH tubular batteries and stand under buyback Details
 8Tender for procurement of stay set complete Details
 8Tender for extension of oil testing laboratory at 220 kV GSS Details
 8Tender for construction of civil foundation for 1 Nos. 132 kV bay Details
 8Tender for construction of 1 Nos. 132 kV bay (solar bay) at 220 kV GSS Details
 8Tender for strengthening of court bridge Details
 8Tender for strengthening of concrete motorable bridge Details
 8Tender for strengthening of motorable bridge over power channel Details
 8Tender for strengthening of asan barrage bridge Details
 8Tender for repairing & maintenance of damaged lugs/LT XLPE cable Details
 8Tender for supply renewal of damaged insulations in flue gas duct Details
 8Tender for supply of 15000 Nos LT three phase channel cross arm Details
 8Tender for rectification replacement of defective tubes Details
 8Tender for supply of 20000 sets 11kV metal parts Details
 8Tender for erection of 110 kV DC line on DC tower by making LILO in 110 kV feeder Details
 8Tender for procurement of PSC pole stay clamp Details
 8
Tender for supply, erection and commissioning of new street light poles with cable laying Details
 
8Tender for procurement of spares for HT motors Details
 
8Tender for miscellaneous civil works Details
 
8Tender for construction of HT UG cable Details
 
8Tender for HT ABC stringing works and installation of transformer Details
 
8Tender for augmentation work for 40/50 20/25 MVA transformer at 132 kV GSS Details
 
8Tender for augmentation work for 31.5 20/25 MVA transformer Details
 
8Tender for augmentation work for 40/50 20/25 MVA transformer Details
 
8Tender for height rising work of 132 kV DC line Details
 
8Tender for requirement of various air nozzle tips installed in burner panel Details
 
8Tender for construction of 66 kV AIS substation Details
 
8Tender for upgradation of gantry crane Details
 
8Tender for supply of electrical line Details
 
8Tender for supply of electrical line materials Details
 
8Tender for routine maintenance work of milling system Details
 
8Tender for installation, testing and commissioning of new 5 MVA 33/11KV substation Details
 
8Tender for supply of 300 sets 11kv standalone complete set Details
 
8Tender for construction of control room with bore well, electrification Details
 
8Tender for renewal of various degree coals bends after dismantling the worn out bend of coal mill A B C D discharge pipe Details
 
8Tender for renewal of various degree coals bends after dismantling the worn out bend of coal mill Details
 
8Tender for applying two layers of ceramic wear coat eromat at inner surface of mill outlet coal bends Details
 
8Tender for reconditioning of hydraulic loading cylinder assembly with replacing of new cylinder piston rod Details
 
8Tender for strengthening of worn out portion of mill housing body by using M S Plates in coal mills Details
 
8Tender for providing foundation concrete for equipment plinth structure plinth and other civil works Details
 
8Tender for procurement of vibrating wire (VW) crack meter Details
 
8Design, engineering, procurement & construction (EPC) contract for development of 110 MW AC floating Details
 
8Tender for supply and delivery of 150 Nos 33kV top adaptor for PCC pole Details
 
8Tender for operation and maintenance contract of fly ash handling system and maintenance of ESPs Details
 
8Tender for annual maintenance work of 33/11 kV sub-station Details
 
8Tender for annual maintenance work of 33/11 kV sub-station Details
 
8Tender for supply and application of zinc rich paint for various conveyor gantry, junction tower and structure of coal handling plant Details
 
8Tender for work of up-gradation of wave Trap and bay strengthening in view of utilization of HTLS for associated end bays Details
 
You can also click on Tenders for more
 For reference purposes the website carries here the following newsclips:
8Bhupender Gupta gets 3-month extension for additional charge as CMD of SJVN Details
 8Empowering the Market: Experts discuss the impact of electricity derivatives Details
 8ACME Group secures SECI backing for green ammonia project under SIGHT initiative Details
 8India set to add 30 GW of storage by 2027, outpacing demand forecast Details
 8Waaree energies launches new 1.8 GW solar module facility in Gujarat’s Chikhli Details
 8Solar Surge: empowering farmers Details
 8Levelling Up: India Energy Stack seeks to unify the country’s power assets Details
 8India’s power transmission supply chain witnessing annual inflation of up to 20%: PowerGrid CMD Details
 8Power Generation company commissions first 80 MW unit of 240 MW kutehr hydro plant Details
 8Coal India targets 900MT supply for FY26, plans 16,000cr capex boost Details
 8Steady Growth in Hydro: Key trends and developments in the sector Details
 8PFC sanctions Rs 2790 crore to JKPCL to clear outstanding dues Details

 8
L&T Wins Contract for BESS-Integrated Solar Power Project Details
 
8Vikram Solar bags 250 MW solar module supply order from Bondada Group Details
 
8Solar power firms learn to live with red tape Details
 
8100 GW of solar again, and amendments to ALMM Details
 
8Transformers & Rectifiers Q1 Net Profit Triples to 67 Crore Details
 
8Union minister Meghwal inaugurates 500 kW rooftop solar plant in Delhi Assembly launches NeVa Details
 
8India set to ease entry of private firms into nuclear power generation Details
 
8Top 3 Green energy stocks in biomass energy sector to Keep an Eye On Details
 
8Reliance Power Plunges 5%; BSE POWER Index Up 0.1% Details
 
8Market coupling in power sector: Industry flags execution risks Details
 
You can also click on Newsclips for more Details
8Siemens Energy India secures the lowest bid for a 765kV single-phase reactor package under a nationwide bulk procurement programme by a central transmission utility. The win positions it strongly in Lot5 supply allocations, marking a significant milestone in the latest round of transmission equipment tenders in India.
 
8A central transmission giant has concluded a high-value bulk reactor package award, with the winning bidder undercutting three other majors in India’s transformer and reactor manufacturing space. This competitive outcome underlines the intensity of transmission equipment tenders in India, where aggressive pricing is reshaping market dynamics.
 
8In a tender featuring BHEL, CG Power, GE Vernova, and Siemens Energy, the German-engineered offering clinched L1 status for a nationwide 765kV reactor rollout. Such results are setting new benchmarks for transmission equipment tenders in India, both in terms of technical performance and cost competitiveness.
 
8The 110MVAR units under this award will be deployed to maintain voltage stability and reduce transmission losses on India’s backbone 765kV network. As more transmission equipment tenders in India move into bulk procurement mode, suppliers with proven scale and technology are gaining a decisive advantage. Details
8A major interstate transmission power projects in India milestone for Gujarat’s renewable corridor has closed with one of the lowest tariffs seen in recent months, edging out competition by a razor-thin margin.
8Competitive dynamics in the power projects in India space pushed the top bidder nearly Rs. 730million/year above the winner, underscoring aggressive positioning in the country’s renewable grid build out race.
8Late-stage augmentation, including a fourth 1,500MVA ICT and 220kV switchyard, was folded into the package raising engineering complexity and potential execution risks for this key power projects in India undertaking.
8The top two bids in the auction were separated by barely 5.84million/year, reflecting near parity in cost assumptions among leading players and showcasing how competitive pricing is shaping large scale power projects in India today. Details
Civil works award boosts east-zone transmission expansion
8Awarded package covers pile foundation construction for a double-circuit 400kV link, reinforcing evacuation from a large generation complex and enhancing inter-regional transfer capability.
8A domestic infrastructure player has edged out competition to win a major pile works package for a central-sector transmission scheme, valued at over Rs.44crore, with work spanning multiple tower locations.
8Lowest bidder confirmation clears the way for execution of pile foundations across a strategically important 400kV transmission line, enhancing long-term power transfer reliability. Details
8A single-vendor win in the latest Lot-5 bulk package signals strong pricing discipline and manufacturing readiness in India’s high-voltage equipment space. Bulk procurement drive for ultra-high voltage network expansion sees a winning bid for a 30-unit, 765kV, single-phase shunt reactor package. The deal locks in a substation-critical component at competitive pricing.
8With just two bidders in the fray, the winning OEM sealed the deal for a nationwide reactor deployment initiative under the latest package. Competitive edge in delivery capacity and cost efficiency helps domestic OEM secure the award for critical 765kV class assets.
8The 30-unit, 80MVAR reactor package win aligns with transmission build-out timelines aimed at integrating renewable energy hubs. Only two OEMs contested the high-capacity reactor package, with one securing L1 status and a contract worth over Rs. 3170 crore. Details
Bid date pushed third time as Roorkee grid LILO sees high bidder interest
8The deadline for submission has now shifted from 17 July to 14 August 2025, with technical opening on 18 August. The multiple extensions suggest serious reworking of pricing and scope evaluation by EPC players.
8A high-voltage interconnection scheme will combine multi-circuit tower lines with EHV underground XLPE cable to feed a new GIS substation. Execution will require specialized routing and termination interfaces on both ends.
8With overhead and 400 kV underground cable systems bundled in one turnkey scope, the project calls for tight inter-package interface coordination. Cross-bonded joint bays, sealing ends, and thermal backfill add to execution complexity.
8The bid guarantee reflects the high-value nature of the mixed-mode LILO scope. Copper-based cable core, with high-spec terminations, will test bidder pricing under metal volatility scenarios. Details
Multi-location turnkey scope spans 220KV, 110KV and distribution upgrades
8The package merges high-voltage transmission works with two separate 110kV substation builds, cutting across three districts. This bundling could favour large EPC players with multi-voltage capability and proven logistics planning.
8The latest North Karnataka package combines a digital switching station with over 25km of HPC-based 220kV transmission lines. The mix of double bus bar layout and conductor upgrades points to higher load handling and reduced transmission losses.
8220kV segments in the package will use high-performance conductors rather than standard ACSR, a move likely driven by thermal limits and right-of-way constraints. This choice could also mean fewer towers and faster execution. Details
Close-call bidding in high-capacity Northeast transmission award
8The winning bidder for a large-scale transmission package beat its nearest rival by just Rs.4.75 million, with the third bidder trailing by over Rs.250million.
8The award for a strategically important transmission corridor in the Northeast has gone to a private player, narrowly surpassing the PSU major’s offer.
8One of the closest BOOT tenders in recent memory has concluded with a private sector firm edging past competition in the Northeast transmission buildout programme. Details
Over 80 firms eye rural grid-solar contracts in Rajasthan
8A RESCO-mode solar push in Hanumangarh Circle has completed its technical scrutiny, revealing a crowded race for decentralised generation rights under PM-KUSUM.
Technical bid completion for a Rajasthan decentralised solar push confirms sector-wide interest, with more than 80 players eyeing RESCO revenues.
Details
Narrowest spread in recent LT transformer awards raises competition bar
8With top three bidders separated by under 2% in price, recent award points to intensifying fight for LV distribution contracts in Rajasthan’s power utility procurement cycle.
8Over three dozen firms competed for a single-phase CSP transformer package, underlining sustained vendor interest in aluminium-wound configurations despite cost compression.
8Utility procurement choices continue tilting towards aluminium winding, with large-capacity tenders now reinforcing this as the base specification for cost and supply security. Details
Advisory contract opens strategic gateway into India’s coal and mineral auctions
8In a 1-year rate contract, one of India’s largest state-owned mining entities seeks deep-dive consultancy support for coal and mineral block bidding across up to 10 auction tranches. The contract covers evaluation, due diligence, and real-time bid strategy—hinting at aggressive upstream positioning.
8The proposed study covers coal connectivity from WCL mines to a key thermal power plant. This signals renewed focus on dedicated, environment-friendly coal evacuation strategies amid capacity consolidation in central India.
8Clarifications confirm the consultant is not expected to handle legal vetting of contracts. However, they must flag policy risks, commercial caveats, and regulatory bottlenecks that could impact bidding viability or downstream utilization of blocks.
8The tender bars consortiums but permits partnering organizations, with prior approval. Confidentiality walls and conflict of interest disclosures will be scrutinized up to partner level, especially for firms serving other bidders in the same auctions. Details
 For reference purposes the website carries here the following tenders:
8Tender for restoration of erosion occurred to dividing wall Details
 8Tender for supply of NB60 stype tower with stub and cleat Details
 8Tender for supply of set of worm shaft & worm wheel gear along with worm shaft lock nut Details
 8Tender for supply of HT motors spares Details
 8Tender for construction of control room foundations, cable trench Details
 8Tender for procurement of spare parts of gear boxes installed Details
 8Tender for works contract for laying of 11kV 3x300 Sqmm XLPE UG cable Details
 8Tender for preventive maintenance and emergency breakdown works in 292 KMS of EHT lines Details
 8Tender for laying of 33kV,1x630 sq.mm XLPE UG cable Details
 8Tender for laying of 33kV,1x630 sq.mm XLPE UG cable from 110/33 kV SS Details
 8Tender for construction of a twin type RCC curing tank Details
 8Tender for replacement of PVC cable incoming service cable Details
 8Tender for construction of under ground LT and 11 kV line Details
 8Tender for construction of new 11 kV line Details
 8Tender for supply of various analytical instruments & its spares Details
 8Tender for repainting of 18 no dust extractors, 5 no wagon tipplers Details
 8Tender for providing and laying 20 mm thick open graded premix carpet including tack coat , seal coat Details
 8Tender for replacement of damaged corrugated asbestos sheets in wagon tippler Details
 8Tender for procurement of 47800 Nos. of 9 0m 300 Kg WL PSC poles Details
 8Tender for supply, fabrication erection of steel structures earthing steels Details
 8Tender for supply, erection, testing and commissioning of 10 ton capacity, electrical wire rope Details
 8Tender for supply of 400 kV CVT Details
 8Tender for supply of H.V. bushings of power transformers installed Details

8Tender for general civil maintenance work Details
 8Tender for misc. civil maintenance Details
 8Tender for construction of environmental radiation monitors (ERM) and automatic weather stations (AWS) and other associated works Details
 8Tender for comprehensive AMC of MC, CP, PA, EC and other AC equipment Details
 8Tender for supply and delivery of tools and plants for operation and maintenance of transmission lines Details
 8Tender for supply of PVC outer sheathed control cable for replacement of CVT control cable Details
 8Tender for requirement for supply installation and commissioning of fabric compensator for expansion joints Details
 8Tender for work of mechanical strengthening, stub strengthening and earthing work of 66 kV line Details
 8Tender for supply and installation of underground diesel storage tank Details
 8Tender for repairing work of cable trenches cover Details
 8Tender for repair and painting work of internal and outer surface Details
 8Tender for internal electrification renovation work of 30 no residences Details
 8Tender for online pressure testing and setting of safety valves using Details
 8Tender for supply & application of castable refractory for unit-3 bottom ash hopper Details
 8Tender for addition of 132/33kV, 20MVA transfomer Details
 8Tender for supply, installation, commissioning and AMC (5 years) of integrated solar street lights Details
 8Tender for services for installation of capacitor bank alongwith associated 33kV bays at various substations Details
 8Tender for laying of 33kV, 3x400 SQMM HTUG cable Details

 8Tender for supply of microprocessor base motor and feeder protection relay Details
 8
Tender for supply, erection, testing and commissioning of 220 kV and 33 kV bays with associated equipments for 100 MVA power transformers at various Details
 
8Tender for supply installation testing and commissioning of new 400kV 63kA for 1 sec 3150A circuit breakers outdoor SF6 type without PIR along with support structure and accessories etc Details
 
8Tender for standardization work of 11kV feeder Details
 
8Tender for supplying of aerial bunched cable Details
 
8Tender for creation of 220 kV transmission line Details
 
8Tender for construction of 66 kV and 132 kV transmission lines Details
 
8Tender for augmentation of 400 kV substation Details
 
8Design, engineering, supply, testing & commissioning including allied civil work of 30kWp capacity, 415 volts, 3 phase on-grid solar rooftop PV power plant Details
 
8Tender for work of 220 kV line and breaker isolator Details
 
8Tender for replacing of damaged sheet of boiler feed pump Details
 
8Tender for works contract for carrying out HT& LT DCW improvement Details
 
8Tender for work of erection and strengthening of H-frame lines Details
 
8Tender for estimate for additional of 3.15 MVA power transformer Details
 
8Tender for estimate for birfucation work of S/S Details
 
8Tender for installation, testing, erection and commissioning of 5 MVA 33 11 kV sub station Details
 
8Tender for supply of BIS certified energy efficiency level Details
 
8Tender for supply of 33/11 kV, 5.0 MVA power transformers Details
 
8Tender for procurement of various class OIP bushing for EHV grade transformers Details
 
8Tender for work of the re-strengthening of dry ash collector tank system hopper Details
 
8Tender for rate contract for complete overhauling/repairing of BFP cartridge Details
 
8Tender for annual work contract for O and M of HVAC air conditioning system Details
 
8Tender for work contract for operation and maintenance the road weighbridge Details
 
8Tender for work contract for overhauling of diesel engine installed in locomotive Details
 
8Tender for biennial work contract for picking of stones / shales and other foreign material from coal Details
 
8Tender for complete design supply testing installation and commissioning of SAS Details
 
8Tender for supply of throden bearing for jackwell pump Details
 
8Tender for supply and erection of Eco coil 8 Nos with supporting arrangement to renew heavily eroded Eco coil Details
 
8Tender for providing of insulation for flue gas duct Details
 
8Tender for works contract for carrying out HT& LT DCW improvement and capital extension works Details
 
8Tender for manufacture, supply, erection, testing and commissioning of 11 kV RMU Details
 
8Tender for replacement of damaged worn out obsolete railways track Details
 
8Tender for supply of automatic isoperibol bomb calorimeter Details
 
8Tender for procurement of various spares for RTUs in SS and FRTUs in RMU Details
 
8Tender for supply and erection of 1680 mtr of 250NB pipe Details
 
8Tender for providing and fixing of trip circuit supervision relay (TCSR) in control and relay panels at 220kV S/s Details
 
8Tender for replacement of weasel conductor 11 kV AAAC AL- 59, 99 Sq.mm Details
 
8Tender for replacement of weasel conductor Details
 
8Tender for replacement of weasel conductor 11 kV AAAC AL- 59, 99 Sq.mm Details
 
8Tender for up gradation of firewall system for ERP infrastructure Details
 
8Tender for work of erection of structures, equipments, earthing, control wiring Details
 
8Design, supply, installation, commission and maintenance of solar PV system Details
 
8Tender for work of replacement of equipments & other misc. various works Details
 
8Tender for work contract for routine, preventive & breakdown maintenance of instrument Details
 
8Tender for execution of supply and installation of fired type wedge connectors Details
 
8Tender for work of mechanical strengthening, stub strengthening and earthing work of 66 kV line Details
 
8Tender for supply of various size decking plates at coal handling plant Details
 
8Tender for work of various maintenance of drive system of conveyor belt of coal handling plant Details
 
8Tender for erection work of 66kV S/C line Details
 
8Tender for work of erection of 66kV S/C line on D/C towers Details
 
8Tender for BRC for the work of manual removal of bottom ash from bottom ash hopper of boiler Details
 
8Tender for supply of various auxiliary relays for various S/s Details
 
8Tender for rendering services for carpentary, masonry, plumbing works etc Details
 
8Tender for biennual contract for works of replacement of failed 167 MVA, 400/220/33kV ICT or 125MVA bus reactor or line reactor Details
 
8Tender for rate contract for attending emergency breakdown and planned outage works on various 400 kV lines Details
 
8Tender for annual maintenance contract (AMC) for the work of providing of hydra crane services Details
 
8Tender for extension of battery room by shifting existing Details
 
8Tender for work of renovation of 100 kV tap line Details
 
8Tender for procurement of 33kV CT & PT as a critical spare Details
 
8Tender for AMC for work of repairing/overhauling with spares, providing & fixing of 33kV poles Details
 
8Tender for rate contract for the work of loading, transportation, unloading & stacking of all types of EHV equipment / material Details
 
8Tender for biennial rate contract for attending emergency breakdown works & shutdown maintenance works in 132/220kV EHV substations Details
 
8Tender for procurement of mandatory & optional spares for 220kV GIS bays at 220kV GIS S/s Details
 
8Tender for work of augmentation by replacement of existing 132/33kV 2x25 MVA TF by 132/33kV 2x50MVA power transformer Details
 
You can also click on Tenders for more
 For reference purposes the website carries here the following newsclips:
8Kandla Port inaugurates green hydrogen facility Details
 8Is India’s energy storage market headed for oversupply Details
 8Solar Cell output set to reach 42 GW by 2026 Details
 8Coal Power trio: CIL, NLCIL & SCCL achieve 114% of Q1 capex target, signalling aggressive growth Details
 8
Why Suzlon energy share price is rising Details
 
8Gujarat commissions India’s 1st 1MW green hydrogen plant Details
 
8Ministry of coal awards 7 coal blocks in 12th round of commercial auction Details
 
8ACME Group gets LoA for green ammonia production project Details
 
8Tata Power Q1 net profit rises over 6 pc to Rs 1 262 cr Details
 
82 Green energy stocks in focus after India mandates new wind turbine norms Details
 
8New Delhi foresees 77,000 crore private investment into thermal power Details
 
8Waaree Energies opens 1.8 GW solar module plant in India Details
 
8Second unit of Telangana’s Yadadri thermal power plant inaugurated Details
 
8Coal India Production Drops 6% in Apr-Jul Details
 
8Graphite India’s Q1 net profit falls 44 pc, revenue down 9 pc Details
 
8Arunachal Pradesh To Add 15,000 MW hydropower generationcapacity Via 13 projects in next three years: CM Pema Khandu Details
 
8India has 29,277 EV charging stations, Karnataka leads: Minister Details
 
8India's stranded renewable projects surge past 50 GW amid delays: Report Details
 
8Record-Breaking output: NHPC’s tanakpur power station registers highest-ever july generation Details
 
8VOC Port becomes the first Indian port to produce green hydrogen and surpass 1 MW solar power Details
 
8Power Consumption in India grows marginally by 2.6% to 153.63 billion units in July amid heavy monsoon rains Details
 
8Transforming digital governance for India’s pharmacy sector: how dexian can power PCI’s digital reinvention Details
 
You can also click on Newsclips for more Details
Competitive hydel push intensifies in J&K with IPP-led 30 MW rollout
8A fresh RFQ opens doors to private developers for 18 micro and mini hydro projects across difficult Himalayan terrain. The initiative comes under IPP mode with JAKEDA laying strong emphasis on net worth benchmarks and EPC-led execution experience
8Developers must secure all clearances from DPR to environmental forest and power evacuation with no subsidy or facilitation beyond JAKEDA’s advisory role. IPP projects in this RFQ are fully privatized from conception to commissioning
8Bidders now face tighter linkages between their financial and technical scores and the number of projects they can win. Allocation flexibility exists but preference-based distribution hinges on evaluated capacity altering strategy for mid-sized players. Details
Himalayan hydro tunneling bid sees fourth deadline shift amid design-access disconnect
8With bids now pushed to 21 August, the civil tender for a 260 MW underground hydro project reveals deeper-than-expected site access bottlenecks. Temporary bridges and 6.5 km of new roads are still needed just to reach key tunnel portals an issue increasingly common in complex hydropower projects in India. Despite earlier reassurances, contractors warn of unrealistic power house timelines without frontloaded access works.
8The main civil package for this high-head, tunneling-led scheme part of the broader pipeline of hydropower projects in India demands precision staging of desilting chambers, pressure shafts, and twin caverns. With no critical path tag assigned to the power house, sequencing and site logistics become critical for contractors betting on adherence to the 44-month build schedule.
8Revised drawings now confirm just 4m vertical separation at key tunnel intersections, significantly raising excavation complexity. The design team has acknowledged the need for RCC lining, ramps, and enhanced supports to manage interference between legacy and new adits highlighting recurring technical hurdles seen in large-scale hydropower projects in India.
8Design drawings remain vague on exact bridge locations, with layout finalization deferred to post-award site surveys. This clause introduces considerable bid risk on foundation design and pricing for water crossings in Himalayan terrain a persistent challenge across many hydropower projects in India, particularly those involving remote access and tunneling. As developers rush to meet clean energy targets, such civil disconnects continue to delay execution of key hydropower projects in India. Details
8The latest renewable energy tenders in India revive asset buyback at scale pushing end-of-life handling, dismantling, and handover logistics onto the vendor. With multiple delivery locations and site-specific dismantling, contractors will face tightly defined risk corridors. Previous region-specific renewable energy tenders in India had limited this to selective sites.
8In a quiet but critical addition, the tender mandates delivery of spare Ni-Cd cells at each site. This move may preempt delays from isolated cell failures during the plant lifecycle. Contractors must align this with traceability and OEM warranty expectations. It’s a subtle shift from past renewable energy tenders in India that focused only on full battery strings.
8Compared to the previous NR-III SR-II tender, the new version expands geography, adds spares mandates, buyback, and introduces reverse auction. It marks a decisive shift from component-level upgrades to system-level lifecycle delivery. The overhaul could become a template for future renewable energy tenders in India and broader infra-standardization. Details
Strategic corridor for RE-powered ammonia gets infrastructure spine
8With high connectivity demand from multiple producers, the project builds dedicated bays and substations for industrial green molecule consumers. Transmission planners have locked spatial configurations to within 3 km for substations, hinting at tight corridor planning. Execution will involve inter-state connectivity with precise ownership transfer conditions critical for upcoming green ammonia projects in India.
8A high-voltage transmission backbone is being carved out to support upcoming green hydrogen and green ammonia projects in India, particularly in southern Tamil Nadu. The tender outlines interstate-level evacuation infrastructure tied to multiple industrial energy off-takers. The auction schedule has just been extended to mid-August, reflecting either heightened bidder interest or churn in clarifications.
8One hundred percent equity in a pre-formed SPV will be transferred to the successful bidder, who must then execute, own, operate, and finally transfer the assets after 35 years. REC remains the Bid Process Coordinator with CTU as the nodal agency. Pricing transparency will depend on how bidders value future operational liability an increasingly important factor in financing green ammonia projects in India.
8The extension to 14 August and beyond may indicate more than just logistical delays. With major hydrogen players already assigned connectivity, questions remain around tariff benchmarks, interoperability with other TBCB corridors, and long-term O&M commitments. The delay also pushes financial closure closer to year-end, raising implications for the rollout pace of green ammonia projects in India and associated grid assets. Details
8Find a snapshot of thermal, hydro, pumped storage, solar,
wind, BESS and T&D contracts related updates for the day
Click on Reports for more Details
Switching upgrade: ICT and reactor controls contract bagged for Rs.14.5 crore
8A key contract to supply Controlled Switching Devices for transformer and reactor bays in Northern India's transmission grid has been awarded. The Rs.14.55 crore deal underlines a push to mitigate switching surges across substations. Final award went to a public-sector-aligned vendor after limited bidding. Financial and technical terms signal focused standardization for EHV asset protection. Details
Single bidder secures Rs.46.9 crore grid upgrade package for 500 MW RE linkage
8A multi-location AIS substation extension contract involving new 220 kV bays and dual ICT augmentation has gone to a single L1 bidder. The Rs.46.9 crore award supports integration of 500 MW renewable capacity and strengthens N-1 readiness in two north Indian states. Despite its pan-regional scope only two firms submitted bids
8Only one technically qualified bidder remained in contention for this multi-scope substation job. The same firm secured the L1 position. As PGCIL continues to bundle cross-state work the number of eligible and willing EPC firms appears to be shrinking
8Two 220 kV line bays are now cleared for execution at a major pooling station enabling evacuation from a large-scale RE generator. The job is part of a bundled AIS extension contract targeting three sites. The limited bidding pool raises questions on vendor risk appetite in split-scope substation jobs. Details
Rs.431 million winning quote stuns rivals in 765 KV transmission auction
8The L1 bidder clinched the project with an annual transmission charge of Rs.431.11 million—less than half of the second-ranked offer at Rs.890 million. The dramatic tariff compression reflects either hyper-aggressive costing or structural design leverage. With just one bidder far below the curve margin realism will now face its first real test
8The final awarded tariff of Rs.431.11 million is a steep 52 percent below the L2 bidder’s Rs.890 million quote. This margin of difference in a single-element ISTS package suggests either a radically different cost model or willingness to bet on post-award scope leeway. EPC vendors will be watching delivery milestones closely
8Despite limited substation scope and a clear LILO route the final quote at Rs.431.11 million signals competitive heat even in minimal-transmission builds. With major line bay works handled by the generator the winning bidder appears to have optimized overhead execution and spare asset reuse assumptions to land this number. Details
NR-WR corridor stress triggers new 765 kV Prayagraj substation build-out
8VA major new substation with 2×330 MVAr bus reactors and multi-directional LILO bay provisioning is being fast-tracked in eastern Uttar Pradesh to ease chronic loading on the Vindhyachal–Varanasi axis. The 24-month BOOT project signals aggressive grid readiness for PSP-based inflows and N-1 contingency stability
8While Amendment 4 clarifies that backbone OPGW upgrades on Fatehpur-Varanasi and Fatehpur-Sasaram fall outside the current TSP’s scope bidders must account for interface equipment continuity. Failure to harmonize with parallel schemes could strain link budgets
8Amendment 4 revises communication specs with precision dual OPGW runs on LILO circuits repeater insertion beyond 225 km and FOTE upgrades at key nodes. The configuration tightens SCADA-integrated visibility in high-demand NR corridors
8The inclusion of 2 × 330 MVAr switchable line reactors at the Prayagraj end of the Vindhyachal D C link reflects a shift toward adaptive voltage control and load smoothing especially for PSP synchronizations. This level of control granularity is rare in recent NR-WR interconnection projects. Details
Power utility shifts to centralized PT specs for 66 KV NER substation revamp
8The latest transformer supply tender enforces internal technical specification NCN0166 replacing state-level legacy specs. This move consolidates design control across the northeastern grid network. The shift also restricts OEM flexibility and raises compliance hurdles for non-regular vendors
8Though earlier bids referred to PSPCL design benchmarks this one explicitly supersedes them with POWERGRID’s own NCN0166 spec. It reflects a deeper push toward pan-India standardization under a unified procurement regime. Details
400/220 KV transformer upgrade signals selective grid strengthening under RTM push
8The addition of a 500 MVA ICT at a key 765 400 220 kV substation underscores India’s real-time market readiness strategy. This brownfield augmentation is designed for quicker grid ramping tighter integration and targeted capacity relief
8Unlike GIS-heavy tenders this project relies on existing AIS bay interfaces to fast-track commissioning. A cost-efficient design with modularity and limited bay sprawl is central to this Real-Time Market deployment
8With no GIS shielding contractors must plan erection logistics around 400 kV live yard protocols. Safety management and crew sequencing become the make-or-break factor on timelines
8The specifications align with past NPCIL and PGCIL sourcing patterns—favoring domestic transformer makers compliant with nuclear-aligned engineering practices. Foreign vendors are unlikely to qualify on design deviations
8With the scope locked to a single ICT and intense SAS touchpoints industry veterans expect limited bidder turnout. The package design favors incumbents with prior bay control retrofit exposure. Details
Switchyard tender for 2400 MW plant sees fifth extension amid civil cost and cashflow tweaks
8The latest extension to early August follows a string of bidder clarifications around payment holdbacks tied to civil works percentages. Amendments reduce the structural works threshold from 25 percent to 13 percent easing pressure on cashflow-sensitive bidders
8Starting from February the bid has seen at least five pushbacks now ending on August 5. This extension streak reflects heavy bidder back-and-forth on payment structuring scope packaging and bid qualification formats
8Despite industry feedback NTPC will continue to hold civil-linked payment deductions unless bidders cross a now-revised minimum threshold. Contractors with equipment-heavy cashflow cycles will need to recalibrate their costing assumptions. Details

Multi-substation EPC tender for 110/11KV and 110/33KV package sees long extension window
8KPTCL’s composite substation package covering new 110kV-class installations at two southern Karnataka sites has seen its bid deadline pushed by over a year. The three-part tender includes transformer bays HT cabling and an alternate 66kV supply point
8One tender three sites and six 20 MVA transformers—KPTCL’s new EPC bundle merges 110/11kV and 110/33kV installations across Nekkilady and Kuthlur with backup interconnection at 66kV. Subcontracting scope could attract hybrid civil-electrical players
8In addition to standard substation build the package demands 66kV alternate sourcing works—hinting at grid redundancy planning in load centres. The build includes feeder cabling trenching SCADA-ready switchgear and HT protection relays
8Though designed for 110kV 66kV use hardware specs demand insulator strings and clamps suited for 220kV impulse withstands—indicating readiness for higher voltage retrofit or interconnects.

Details
MNRE Rebrands RLMM as ALMM(Wind), Expands Compliance Scope for Wind Turbine Makers
8The Revised List of Models and Manufacturers (RLMM) is now the Approved List of Models and Manufacturers (ALMM-Wind), introducing deeper documentation requirements and aligning with India’s localization and cybersecurity mandates.
Mandatory Inspections, Component List, and India-Based Data Control Tighten Wind Sector Norms
8A new clause makes MNRE inspection of component facilities mandatory, introduces a separate component ALMM, and imposes strict data localization and operational control within India, signaling strategic self-reliance in wind power.
New Exemptions Give Temporary Relief to Bidded, Captive, and Emerging Wind Projects
8Projects bid before July 31, 2025, captive/C&I projects commissioned within 18 months, and new entrants under 800 MW enjoy conditional exemption from the new ALMM(Wind) listing norms but under tight reporting rules.
Click on Details for more
Details
Patna Islanding Scheme Inches Closer to Implementation Amid Rising Urgency
8From awaiting administrative clearance in the 228th OCC to PSDF grant submission by July 18, the Patna Islanding Scheme moved forward yet remains under bureaucratic watch, as ERPC urges swift execution.
Kolkata Grid Vulnerability Triggers Fast-Tracked CLR Insulator Overhaul
8Frequent trippings in key 765/400 kV corridors around Kolkata led to PowerGrid committing to short- and long-term replacement of 4,701 CLR insulators, with testing mandates imposed amid Durga Puja deadline pressure.
Barh Unit-3 Declared Commercial, NKSTPP Evacuation Still in Limbo
8While Barh Unit-3 achieved CoD on July 1, the NKSTPP–Gaya line continues to face RoW and forest clearance delays. ERPC calls for a dedicated follow-up meeting as Bihar’s grid reliance peaks.
Click on Details for more
Details
PXIL Clears 16.34 Lakh RECs in July’s Second Trading Session
8Robust buy-side interest saw over 16 lakh RECs transacted at Rs 360 each, despite a massive oversupply of certificates in the market.
Legal Clearance Unlocks REC Trade Potential Post Court Directive
8Delhi HC’s withdrawal of sale restrictions on older RECs has opened the floodgates for market activity, with PXIL leveraging regulatory clarity to deepen trading volumes.
Non-Solar RECs Issued Before April 2017 See No Trades Despite Listing
8Certificates with a higher floor price of Rs 1,500/MWh found no buyers highlighting price sensitivity even in compliance-driven markets.
Click on Details for more
Details
SRPC Clears 400kV Somanahalli–Mylasandra Shutdown Amidst System Risk Warnings
8Despite concerns over low voltage and contingency overload risks in Bengaluru’s 220kV grid, SRPC has approved KPTCL's 4-month shutdown proposal with strict conditions and system preparedness mandates.
Execution Bottlenecks in Forest and Dense Urban Pockets Could Delay Tower Erection
8KPTCL faces serious access and logistical issues for tower erection across forested and populated areas, prompting SRPC to urge deployment of additional manpower and stricter sequencing of high-risk activities.
Contingency Planning and SPS Deployment Key to Prevent Grid Collapse in Bengaluru
8With Mylasandra Substation to be radially fed and ICTs already stressed, SRPC has mandated SPS readiness, 220kV radialisation, and relay adjustments to avoid cascade tripping during shutdown execution.
Click on Details for more
Details
West Bengal and DVC Emerge as Key Contenders for Unallocated Power from Patratu and Buxar Plants
8With most Eastern Region states opting out of their share, West Bengal and DVC have expressed willingness to avail significant portions of the 15% unallocated power from Patratu TPS and Buxar TPP. This signals a shift in regional demand patterns and may influence future allocation strategies within ERPC.
ERPC to Deliberate on SJVN Hydro Allocations and LPS Rule Implementation from August
8The Commercial Sub-committee is set to assess states’ willingness to procure power from SJVN’s upcoming hydro projects such as Luhri Stage-I, Sunni Dam, and Arun-III. Additionally, the panel will initiate implementation of revised Late Payment Surcharge (LPS) rules from August 1, 2025, enforcing stricter financial discipline across utilities.
Click on Details for more
Details
DAM Clears 155.7 GWh with Weighted MCP at Rs 3,295/MWh amid Robust Sell Surplus
8The Day Ahead Market witnessed aggressive sell-side participation with over 447 GWh offered, yet only around 35% of bids were cleared. This oversupply scenario kept the average market clearing price muted at approximately Rs 3.3/unit, even though prices peaked during early morning and evening blocks.
RTM Sees Peak Prices at Rs 9.1/unit Amid High Evening Demand; Day Clears 153 GWh
8Real Time Market prices showed high volatility throughout the day, reaching as high as Rs 9.12/unit during the 7–8 PM window due to tight demand. Despite this, the average price held steady near Rs 3.4/unit, with about 153 GWh of power successfully cleared for real-time scheduling.
GDAM Maintains Stability with 100% Clearance; Weighted MCP at Rs 3,238/MWh
8The Green Day Ahead Market displayed remarkable steadiness by clearing all market-coupled volumes. Balanced participation from solar and hydro sellers enabled full scheduling, with weighted MCP remaining stable at Rs 3.2/unit and minimal price volatility observed throughout the day.
HP-DAM Fails to Clear Any Volume as Zero Purchase Bids Persist
8High Price Day Ahead Market saw no activity for the entire trading day as there were no purchase bids despite a sizeable sell bid pool of 131 GWh. The lack of buyer interest indicates strong resistance to premium-priced procurement under current market conditions.
Click on Details for more
Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8Coal and Coke
8LPG
8Ammonia
8All tankers
8Bulk and Dry cargo
Click on Reports for more. Details
 For reference purposes the website carries here the following tenders:
 8Tender for Bi-ARC for erection of 66/132/220kV lines Details
8Tender for dismantling and eection testing commissioning work of ESP Details
 8Tender for supply of rewire able Details
 8Tender for work of providing services of health assessment of grounding system & soil resistivity measurement (earthing audit) of existing earth mat at various 132kV & 220kV S/s Details
 8Tender for procurement of isolator spares Details
 8Tender for laying of drinking water pipe line and fixing mini water filteration plant with allied works Details
 8Tender for day to day civil maintenance and miscellaneous civil works Details
 8Tender for improvement of existing drive arrangements in intermediate conveyors Details

 8Tender for supply, erection and commissioning of tertiary bay equipment including LT transformer Details
 8Tender for supply of spare AC filter capacitor Details
 8Tender for patrolling for power line crossing and jumper Details
 8Tender for erection of 33kV OH line Details
 8Tender for refurbishment or reconditioning or fabrication works of rotor assembly and various gearbox Details
 8Tender for repairing reconditioning rewinding of 6.6 KV HT motor Details
 8Tender for construction of coal sampling lab and AHP-3 and 4 transformers Details
 8Tender for routine breakdown capital maintenance work of compressed air system Details
 8Tender for annual contract for repair and maintenance work Details
 8Tender for repairing/retrofitting of evaporating cooling plant Details
 8Tender for complete work of repairing and overhauling including spares Details
 8Tender for supply of 612kV surge arrestor for 765 kV switchyard Details
 8Tender for procurement of lighting materials, cable lugs and other similar items Details
 8Tender for preventive / breakdown maintenance of duct and expansion joints of all three units Details
 8Tender for manufacturing of cement fly ash bricks Details
 8Tender for supply of 2KVA UPS system with battery sets and stand under buy back Details
 8Tender for procurement of spares for coal feeders Details
 8Tender for supply of telescopic earth rod Details
 8Tender for supply of stay set complete Details
 8Tender for dismantling of the existing wornout damaged iron steel structure Details
 8Tender for dismantling the existing wornout damaged 150 NB 200 NB pipes and bends of air lines sump pump lines Details
 8Tender for supply and erection of 350 NB cast basalt pipes Details
 8Tender for renovation & extension of existing excitation room of unit #3 & 4 for replacement of electrical panels during Details
 8Tender for work of overhauling and servicing of boiler feed pump (type-200 KHI) and booster Details
 8Tender for work of mechanical and stub strenghtning, painting work of 66kV line Details
 8Tender for work of 220kV bus strengthening conversation of existing 220 kV bus from twin zebra bus Details
 8Tender for repair of eroded guide vanes 60 Nos dismantled during annual maintenance Details
 8Tender for supply of spares battery cell for 220kV C/R and raw water at switchyard Details
 8Tender for laying of 11kV 3C300 sqmm XLPE cable Details
 8Tender for augmentation of capacity of PTR from (3X10) MVA to (4X10)MVA with allied works Details
 8Tender for biennial maintenance contract mandatory jobs and other jobs Details
 8Tender for service contract for overhauling / annual maintenance of PA FAN (1A and 1B) and FD fan Details
 8Tender for providing and fixing covering net over open approach channel (OAC) of CW system Details
 8Tender for dismantling of existing rail track, strengthening of track foundation Details
 8Tender for supply of HT cable Details
 8Tender for work of complete overhauling, routine, preventive and breakdown maintenance of air conditioning system Details
 8Tender for excavation & refilling of earth & laying of HT/LT power/ control cable Details
 8Tender for work of online preventive and breakdown maintenance for boiler, its mountings and accessories Details
 8Tender for routine, preventive and breakdown maintenance work of various TG auxiliaries installed Details
 8Tender for epoxy flooring of generator and turbine floor Details
 8Tender for work of unloading of EHV materials/equipments Details
 8Tender for AMC for repairs of 22kV CT and PT at various sub-station Details
 8Tender for work of supply, installation, testing and commissioning of ESE fast electrode L-CAT system at various 220/132 kV substations Details
 8Tender for work of erection, testing and commissioning in respect of balance work 3x33kV AIS line Details
 8Tender for supply of various consumable items at various s/s Details

 
You can also click on Tenders for more
 For reference purposes the website carries here the following newsclips:
8Navigating the ripple effects of renewable energy variability on grid stability Details
 8Commercial transportation of scientifically mined coal kicks off in Meghalaya today Details
 8Coal India records 20% YoY drop in Q1 PAT; net worth rises to Rs 1.07 lakh crore Details
 8How IPPs are revolutionizing India’s energy market Details
 8Wind turbine manufacturing: New norms mandate local sourcing, data control Details
 8Adani Power Q1 Results: Net profit falls 16% YoY to Rs 3,305 crore Details
 
8IREDA CMD Pradip Kumar Das charts roadmap to 485 GW at renewable energy summit Details
 
8Quality inspections critical to India's renewable energy ambitions Details
 
8IEA: Renewables will be world’s top power source ‘by 2026’ Details
 
8Smart grids for green future Details
 
8Arunachal emerges as India’s hydropower capital: CM Khandu Details
 
8Overdue oversight leaves Indian banks shackled to coal Details
 
8Suzlon secures 381 MW wind energy project from Zelestra India across three states Details
 
8MC Newsbreak Confirmed: Govt bars data sharing for wind turbines; mandates using domestic components Details
 
8India’s wind energy capacity crosses 51.67 GW; Gujarat leads among states Details
 
8Suzlon energy, inox wind shares rally up 6% today; what motilal oswal says Details
 
8NTPC Green further commissions 6 MW of Dayapar Wind Energy Project Details
 
8NTPC Reports 11% rise in Q1 FY26 consolidated profit despite dip in power generation Details
 
8Q-city near Bengaluru to power Karnataka’s quantum leap Details
 
8Industry and regulators align to accelerate large-scale green power access for India’s C&I sector via ISTS Details
 
8Godrej precision engineering: customised solutions for complex industrial needs Details
 
You can also click on Newsclips for more Details