All content in this website is sourced legitimately

Archives


All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.


Jun 2019

Yesterday for the first time, it was demonstrated live that a full charge of a two-wheel electric vehicle (EV) can be done in just five minutes.
8An electric scooter equipped with a new ultra-fast charging battery demonstrated that this technology can charge an electric vehicle in only five minutes.
8This proof-of-concept represents a major milestone for ultra-fast charging battery technology and its game-changing potential to accelerate the adoption of EVs.
Click on Reports for more Details
The website carries here a schedule of transmission line outages in India coming ahead
8The reason for the outage and the period of time are also documented
Click on Reports for more Details
The power minister has ordered resolution of all issues which have come in the way of a generating company procuring renewal energy from anywhere in the country against its own commitment to supply
8A timeline has been set to resolve all issues related to the subject so that such procurement can take off without any hurdle
Click on Reports for more Details
Is it true that current tariff regulations do not specify the location methodology of sampling and analysis of undisputed CGV (ARB) of coal?
8Independent third-party sampling is meant to be done at the receiving end as per certain conditions but this is not really happening on the ground, the complainant said.
8The charge, however, was found to be unwarranted
Click on Reports for more Details
Long term PPAs for procurement of hydel power seems not to be the order of the day
8A recent plan to procure power by a utility was curbed
8Then again, instead of going by the availability matrix to calculate capacity charges, the term now to be used is actual supply of power based on design energy for the month
8To avoid dispute a margin of plus, minus 10% is to be kept while using the word generation with respect to design capacity
Click on Reports for more Details
What is the eventual source wise mix of energy in 2050 in global electricity generation
814 different sources are taken into account, and their percentage share has been worked out in five-year installments beginning from now
8The calculations are carried here for different global warming scenarios, beginning from 1.5 degrees
8Also find out what are the investment costs vs accompanying savings in fuel use, under a transition model
Click on Reports for more Details
Even for a heavy duty player like Shapoorji Pallonji, staying put and expanding in the solar industry is turning out to be tougher than it should be
8The company seems to be struggling to put its act together, and to pull in other strategic investors
Click on Reports for more Details
How big a job creator is the renewable energy industry
8Clearly much bigger than the conventional power industry
8Find out more on where India figures in the picture
Click on Reports for more Details
A fresh ruling by the CERC has established the change of law process clearly for the Mundra power plant of the Adani Group
8Based on a Supreme Court direction, relief has been granted
Click on Reports for more Details
For reference purposes the website carries here the following tenders: 
8Tender for Erection of 33kV and 11kV Electrical equipment with associated other electrical works Details
8Tender for Laying of 33kv XLPE UG Cable Details
8Tender for Work contract for round the clock Complete Operation and Maintenance of Ash Handling Plant Details
8Tender for Work contract for operation & maintenance of Coal Mill Reject Handling System Details
8Tender for Supply of Vaccum Pump Spares Details
8Tender for RLA study of Boiler at TPS Details
8Tender for Work of carrying out RLA of Boiler Details
8Tender for Work of Running, Maintenance and Servicing of Valves and Hangers of TG Details
8Tender for Supply of 11KV & 33 KV Metering Unit Details
8Tender for Work Contract for overhauling of 04 Nos. Plough feeder with repairing of Plough feeder Blades Details
8Tender for replacement of cooling tower grids, V-bars, drift eliminators and related works of cooling tower Details
8Annual Operation & Maintenance Contract for Electrical Installations & DG sets Details
8Tender for Work Contract for overhauling with repair wherever required of Rotary Breaker Details
8Design, Supply, installation & commissioning of chlorine dioxide system Details
8Tender for Procurement of Non Magnetic Pulleys with plummer blocks for Conveyor Details
8Tender for the work of overhauling/servicing of 245KV SF6 gas breaker Details
8Supply, installation, testing & commissioning of Interface energy meter Details
You can also click on Tenders  for more
For reference purposes the website carries here the following Newsclips:
8Adani Green Energy raises Rs 402 cr through offer for sale Details
8Jharkhand: JREDA sets 5MW power target from solar rooftops this year Details
8PFC appoints Ravinder Dhillon as director projects Details
8FICCI recommends lower payment for upgrading stressed ‘power’ accounts Details
8Hydro power production not so ‘clean, green’ Details
8Kalpataru Power gains 2% after PhillipCapital initiates coverage, sees 37% upside Details
8Singareni Collieries Apr-May coal output at 11 MT Details
8Telangana govt to buy 2000 mw additional power from NTPC Details
8Power Minister RK Singh holds meeting with gencos to push clean energy Details
8Solar company says UK needs new policies to meet 2050 carbon target Details
8India sees rise in solar photovoltaic jobs: IRENA Details
8Power minister pitches for flexible generation to boost renewable energy Details
8Nagpur: No property tax on power infra Details
8Adani’s Australia mine project ready to go after getting final nod Details
You can also click on Newsclips for more
Details
What should be the mechanism for processing and reimbursement of admitted claims under Change in Law?
8Then gain, a question has arisen over what kind of jurisdiction regulators have to adjudicate a dispute surrounding a Change in law?
Click on Reports for more Details
Proportional–integral–derivative (PID) controllers are the gold standard to control the performance of a gas turbine engine meant to supply power
8But it is now noticed that such controllers have their limitations for various reasons and a model predictive control (MPC) system can produce better results.
Click on Reports for more Details
8Status update on construction of new substation in India Details Details
These are difficult times for solar and wind energy
8Here is a giant, with 2000 Mw of renewable capacity which is now on increasingly shaky ground despite strong backing from its promoters
8The journey undertaken by this company and the difficulties it is now facing epitomize what ails this industry as of today
8Will the situation turn better? Only time can tell
Click on Reports for more Details
Coal consumption grew by 8.7% in 2018.
8India accounted for 70% of the global increase in coal consumption last year
Click on Reports for more Details
A spate of coal projects are getting delayed for different reasons.
8And attendant power projects attached to this coal mines are left with no options but to look for extension of interim coal linkages
Click on Reports for more Details
For reference purposes the website carries here the following tenders: 
8Supply, Erection, Testing and Commissioning of Numerical Distance, Over-Current & Earth-Fault Protection Relays Details
8Tender for Service Contract for Air sealing in Boilers Details
8Tender for Round the clock Routine, Preventive and breakdown maintenance works of Bowl Mills Details
8Tender for supply of dry type transformer Details
8Tender for supply of various boiler tubes Details
8Tender for Insulation application work in boiler Details
8Tender for Construction of 33kV Feeder bay Details
8Tender for procurement of 33kV current transformers Details
8Tender for procurement of SF6 circuit breakers Details
8Supply, Erection, Testing & Commissioning of 02 Nos. 66 kV bays Details
8Tender for Repairing of Legs/Stubs and Supporting structure of equipment’s installed at 220kV Sub Stations Details
8Tender for Procurement of C&I instruments and pneumatic cylinders of Mill reject Handling system Details
8Tender for Procurement of turbine shaft seal assembly Details
8Tender for Procurement of Various type flexible coupling for lube oil pumps of ball tube mills Details
8Tender for supply of 400 kV SF6 Circuit Breakers with Pre Insertion Resistor (PIR) Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8Delhi's power demand on Wednesday touches 6904 MW, highest this summer Details
8Siemens supplies propulsion system to Indian Railways Details
8Offshore wind energy O&M spending to grow to 11 billion Euro by 2028 Details
8US excludes new panel technology from solar tariffs Details
8Chile to close eight coal-fired power stations Details
8Power PSU merger on top of Govt agenda Details
8Adani Enterprises wins final approval for long delayed Australian coal mine Details
8BSE’s India INX launches dedicated platform for trading green bonds Details
8Solar tariffs increase marginally in SECI auction Details
8Tangedco stops floating tenders for solar, wind farms Details
8Patna: Install solar plates on govt buildings from this year, says CM Details
8Hydropower construction taking a toll on HP: Report Details
8MERC hearing on solar rooftop metering soon Details
8Industrial growth at 6-month high on improved power, mining output Details
8Vedanta, JSW Energy bid low for stressed Odisha power project Details
8Chandigarh admin to install smart meters seek report on smart grid Details
8No power shortage in Madhya Pradesh, BJP misleading people: Congress Details
8Seven new countries to join Europe's largest intraday power market Details
You can also click on Newsclips for more
Details
Project Name: Pumped Storage Hydroelectric Project
8Project Cost: 3187 Crores
8Project Description: There is a delay in the floating of a bid for the selection of consultant for the preparation of a PFR and DPR for the proposed 780 MW (6x130 MW) greenfield pumped storage scheme for drawing additional benefits from an existing hydroelectric power project.
8Project Event: RFQ for an Expression of Interest (EoI) for PFR and DPR consultancy services are likely to be expected by August 2019.
8Expenditure Approval: Q4:2019
8RFQ Date: Aug:2019
8Release Date: Sep:2019
8Start Date: 2022
8Completion Date: 2027
Click here for more details
Details
Is coal dead? The answer is a 'no', going merely by the data
8Coal production grew last year at a pace double its 10-year average growth. Consumption growth was led by India (36 mtoe) and China (16 mtoe).
Click on Reports for more Details
For reference purposes the website carries here the following reports: 
8FGD phasing plan for the year of 2020: An update Details
8Details of proposed maintenance programme of generating units during June 2019 & July 2019 Details
8Transmission element outage planning for July 2019 Details
You can also click on Reports for more Details
In India, coal continue to stay the king
8India’s coal production is growing but domestic production alone cannot meet increased consumption, causing imports to increase.
8Given this situation, the Government of India announced a plan to increase domestic production with a production target of 1 500 million tonnes in fiscal 2022. 
Click on Reports for more.
Details
Even though coal went through a revival of sorts in production last year, greenfield projects are struggling to survive
8Questions about long term viability is preponderant.
8Will coal projects eventually get suffocated by a lack of funds, as big financial institutions, under pressure from shareholders and environmentalists, begin to turn off the tap?
Click on Reports for more Details
India's investment in Bhutan's hydropower sector has been beneficial for both countries
8But slowly yet inexorably odd questions are creeping up
8Has India been unmindful?
Click on Reports for more Details
Project Name: Maithon Thermal Power Station - Installation of FGD
8Project Cost: 800 Crores
8Project Description: Maithon Power Limited, a JV of Tata Power Limited and Damodar Valley Corporation has floated a tender for installation of a wet limestone based flue gas desulphurization main package in a 1050 (2x525) MW thermal power station located at the Nirsa village, in Dhanbad district of Jharkhand. Maithon Power Limited is going on with the evaluation of bids. 
8Project Event: Award of FGD is likely to be expected by July 2019.
8Expenditure Approval: Q1:2018
8RFQ Date: May:2019
8Release Date: July:2019
8Start Date: Q4:2019
8Completion Date: 2023
Click here for more details
Details
For reference purposes the website carries here the following tenders: 
8Tender for Biennial job contract for overhauling maintenance of APH Details
8Tender for supply of MS ERW pipe and MS bend for OH of AHP Details
8Tender for Supply of Coal Mill Grinding Elements Details
8Tender for Overhauling of Non Pressure Parts of Boiler Details
8Tender for overhauling of boiler Non-pressure parts Details
8Tender for overhauling of boiler Non-pressure parts (APH, Air/Flue duct) Details
8Tender for the work of enabaling 132kV line bay & 132kV Bus section bay Details
8Annual Maintenance Contract for maintenance during scheduled outage and for attending breakdown at various 220 kV & 132 kV EHV sub-station Details
8Tender for Construction of 132 kV DC line Details
8Supply of fully automatic Oil Tan delta & Resistivity testing kit with accessories Details
8Tender for the supply of Various types of Sacrificing Heating Elements for Air Pre Heater Details
8Tender for the supply of Inner cone assembly with access door and inside ceramic lining suitable for XRP 803 mills Details
8Tender for Chlorine Di-oxide plant package Details
8Tender for Round The Clock Routine/Preventive & Breakdown Maintenance Of Generator Seal Oil System & Hydrogen Gas System Details
8Tender for annual contract of rewinding & repair work of LT motors Details
8Tender for Supply and ETC for Upgradation of PLC of belt conveyor system of CHP Details
8Tender for raising the height of 132kV S/C line Details
8Annual Contract for routine operation in shift and routine/capital/ breakdown maintenance work of 6.6kV SWGR of main plant area Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8Britain to become first G7 country with net zero emissions target Details
8Project awards to induce 11-12 Gw renewable energy addition in FY20 Details
8Coimbatore: Farmers flay power transmission project Details
8How PFC got record $5 bn demand against $1 bn overseas bond sale Details
8World's 100 big cities represent 10% global emissions: Study Details
8Govt’s 100-day plan aims to re-energize India's power sector Details
8No tariff hike for Odisha's power consumers in 2019-20, says OERC Details
8All debt obligations of Reliance Group will be met: Anil Ambani Details
8Subsidy proposals this week to set up 5,000 e-charging stations Details
8Govt mulling payment security mechanism to tackle solar power dues Details
8Odisha CM meets PM Modi, reiterates demand for revision of coal royalty Details
8OPINION: Coal price slump in Asia even as demand grows shows supply is the issue Details
8Solar focus in Finance Minister Sitharaman's first pre-Budget meeting Details
8BSES commissions charging station for electric vehicles in Delhi Details
8Mumbai: Electricity firms issue safety advisory Details
8Chandigarh seeks progress report on pending power projects Details
You can also click on Newsclips for more
Details
Land developers in Haryana will soon have it easy when it comes to getting an electricity connection
8The upfront deposits sought from developers are being relaxed
Click on Reports to know more Details
Is the diesel generator market in terminal decline?
8Here is gen set company with sterling credentials
8But the outlook is poor as of now
Click on Reports for more Details
Project Name: Kotli Bhel Greenfield Hydroelectric Project Stage-IA
8Project Cost: 2074.02 crores
8Project Description: The owner has elicited environment clearance, forest clearance and techno-economic clearance for a 195 MW (3x65 MW) greenfield hydro power project. A detailed project report using its in-house resources has been prepared and approved. The company is going to carry out Hydrometeorology data collection at the project site using its in-house design team and data collection work is expected to be initiated soon. 
8Project Event: RFQ for carrying out of the civil works at the project site is expected by Sep 2019.
8Expenditure Approval: Q3:2019
8RFQ Date: Sep:2019
8Release Date: Sep:2019
8Start Date: 2021
8Completion Date: 2025
Click here for more details

Project Name: Greenfield Thermal Power Project
8Project Cost: 6749.18 Crores
8Project Description: BHEL has been hired as the EPC contractor and it has now commissioned the last 250 MW unit of the 750 MW (3x250 MW) thermal power project.
8Project Event: RFQ for design, engineering, supply, erection, and commissioning of a wet FGD system is expected by August 2019.
8Expenditure Approval: Jan:2018
8RFQ Date: Sep:2019
8Release Date: Sep:2019
8Start Date: Q3:2008
8Completion Date: Nov:2019
Click here for more details
Details
For reference purposes the website carries here the following tenders: 
8Tender for Purchase of 66 KV capacitive Voltage transformer Details
8Tender for Round the clock operation and maintenance of Ash handling plant and Coal Mill Reject Handling System Details
8Tender for Biennial term contract for coal handling plant maintenance Details
8Tender for Biennial maintenance contract for mechanical maintenance of main plant boiler Details
8Supply of spares for repairs, retrofitting and servicing/alignment of 220kV Isolators Details
8Tender for Overhauling and Maintenance of Hydro generating Unit Details
8Tender for Dismantling of existing systems, Supply, Erection, Testing & Commissioning of new Control & Monitoring System (SCADA) Details
8Tender for Procurement of spares of electrical actuators Details
8Biennial Maintenance Contract for Boiler & Auxiliaries including Rotary Equipments, Associated Ducts & Dampers, Fuel Oil System Details
8Tender for Round the clock running/preventive/break down maintenance work of MAX-DNA DCS controlled C&I equipment of Boiler & Turbine Details
8Supply, Erection and Commissioning of New Steam and Water Analysing System Details
8Tender for Supply of Various sizes of Conveyor Belt Details
8Tender for Supply of 4500 Nos of 9.00m PSC poles Details
8Tender for Supply of 2000 Nos of 9.00m RCC Square Section poles Details
8Tender for Supply of 9000 Nos of 7.50m PSC poles Details
8Design, Manufacture, Inspection and Testing before dispatch and Supply of Nylon Conveyor belts for Coal Handling Plant Details
8Tender for Work of Overhauling of Wobbler Feeders at CHP Details
8Tender for Procurement of 600NB & 300NB MS Pipe Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8Coal India to soon name merchant banker for Australian buy. Details
8BHEL bags Rs 440 cr order from NPCIL. Details
8China to reduce output at coal mines at risk of 'bumps' by 20% Details
8Coastal Gujarat Power looks to raise Rs 1,300 crore via bond sale Details
8Oberoi, Trident to run fully on solar power in Gurugram Details
8IL&FS board extends date for filing claims Details
8CII, SIAM urge government to hold talks before finalizing EV policy Details
8Dull summer demand casts shadow on Indian Energy Exchange’s earnings Details
8CPWD to install ‘solar trees’ in residential complexes of central government employees Details
8Govt to ask RBI to remove priority lending limit for renewable energy sector Details
8RPP Infra Projects wins Rs 47 crore contract from BHEL Details
8Ministry seeks removal of priority lending limit for renewable energy to boost financing Details
8Suzlon may default on Rs 1.2k-cr FCCBs due July Details
8Reliance Power shares hit 10% lower circuit limit on Rs 3,559 crore Q4 loss Details
8Companies may soon be invited to set up battery plants Details
You can also click on Newsclips for more
Details
A change in law relief was granted towards installation and operation of FGD in terms of additional capital cost, O & M expenses and additional auxiliary power consumption.
8However the state utility had denied payment of compensation for auxiliary consumption over energy charge while allowing for capacity charge
8Was the utility justified in doing so?
Click on Reports for more Details
With the demand for quick communication, there is now a rush of new OPGW/OFC links
8Here is a list of new links which are proposed
Click on Reports for more Details
Thus far, key policy measures that Incentives for promotion of electric vehicles are largely fiscal, such as demand incentives in the form of subsidies on the purchase price of electric vehicles, and preferential tax structures on manufacturing and sales of electric vehicles.
8A lesser discussed incentive mechanism involves manufacturers introducing electric vehicles into their fleets and receiving a certain percentage of compliance flexibility with their greenhouse gas-based corporate average fuel  consumption (CAFC) standards.
Click on Reports on how this new route can help push electric vehicles in the Indian market Details
8The Supreme Court judgement that a state commission has jurisdiction only where generation and supply takes place within the state, otherwise the central commission has the authority to adjudicate upon the dispute as per the Section 79 (1) (f) of the Electricity Act, 2003 seems to be having ripple effects everywhere.
Click on Details for more Details
The state utility has the right to challenge an order under the Consumer Grievance Redressal Form in an appropriate court of law.
8But if a stay is not granted, can it not abide by such order?
Find out more Details
Project Name: Super-Critical Expansion Thermal Power Project: Installation of WFGD
8Project Cost: 400 crores
8Project Description: Rajasthan Rajya Vidyut Utpadan Nigam Limited has floated tender for installation of two wet limestone-based FGDs in the under construction brownfield 1320 MW (2x660 MW) thermal power complex at its existing 1000 MW (4x250 MW) thermal power station located at Chhabra village, in the Baran district of Rajasthan. RVUNL is going to open technical bid by mid July. 
8Project Event: Award of FGD is likely to be expected by Oct 2019
8Expenditure Approval: Q4:2018
8RFQ Date: June:2019
8Release Date: June:2019
8Start Date: Q1:2020
8Completion Date: 2022
Click here for more details
Details
Project Name: Thermal Power Station - FGD Addition
8Project Cost: 250 crores
8Project Description: NTPC has been hired as a DPR consultant for preparing tender documents for installation of the wet flue gas desulphurisation system in a 500 MW expansion unit out of 1340 MW (4x210 MW+1x500 MW) thermal power complex. Tender is getting delayed due to pending approval from the state government
8Project Event: RFQ for design, engineering, supply, erection, and commissioning of a wet FGD system is expected by August 2019.
8Expenditure Approval: Q1:2018
8RFQ Date: August:2019
8Release Date: August:2019
8Start Date: 2020
8Completion Date: 2022
Click here for more details
Details
For reference purposes the website carries here the following tenders: 
8Tender for Procurement of different types of 145kV Current Transformer Details
8Tender for Work contract for overhauling & servicing of 6.6kV, 360KW Glandless Boiler circulating Water motor pump Details
8Tender for Procurement of mill spares for milling system Details
8Tender for Breakdown and shutdown maintenance works in Ash slurry disposal pumps Details
8Supply and Erection of Damper assembly full Unit with frame for FD Fan Details
8Tender for Renewal of weakened steam supply pipe line and its drains of Water Wall Soot Blowers Details
8Tender for Dismantling of the existing Cast Basalt lined pipe Details
8Tender for service rate contract for rectification of oil leakage problems of Transformers Details
8Tender for Modification work of existing 132kV S/C Line Details
8Tender for Procurement of 1100 MT Sulphuric Acid for thermal power project Details
8Tender for Procurement of 600 MT Alumino Ferric for thermal power project Details
8Supply, erection and commissioning of 69.3 KM 11kV outgoing feeders Details
8Supply, erection and commissioning of 11kV overhead line Details
8Supply, erection and commissioning of 11kV outgoing feeders using ACSR conductor Details
8Tender for construction of 220kV LILO Details
8Tender for Consultancy Services for Renovation and Modernization & Retrofitting in respect of Pulverized Coal Fired Details
8Tender for Procurement of 11KV & 33KV Metering Cubicles Details
8Tender for the Work of attending to resolving the Fuse-Off-Call Complaints & LT/HT line Breakdowns for restoration of Electrical Power Supply Details
8Supply, Erection /installation, Testing & Commissioning of DG Sets Details
8Tender for Purchase of LV distribution panel Details
8Supply, installation, testing and commissioning of 1No. 50MT Hydraulic Power Press Details
8Supply of Hydraulic ladder for carrying out emergency and essential maintenance and routine inspection works at 220kV and 110kV yard Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8Delhi: Discoms seek tariff hike, public hearing on July 10 Details
8Stalin against spent fuel storage facility at KNPP Details
8Centre writes to Andhra Pradesh government; requests not to re-open PPAs of renewables Details
8CIL eyes stakes in Australian coal assets Details
8BoB puts Bhushan Power, 66 others accounts on block as NCLT process gets delayed Details
8AAP challenges Congress to show single state where power tariffs lower than Delhi Details
8Power minister RK Singh confident of achieving 175 GW of renewable energy target Details
8BHEL bags Rs 530 crore orders for setting up Solar PV power plants Details
8AAP urges Navjot Singh Sidhu to scrap MoUs with private power firms Details
8Gadkari against haste in rolling out e-vehicles Details
8Power regulators may be told not to lower tariffs of stressed plants Details
8UP first state to invite EoIs to set up EV charging stations Details
8Reliance Power books impairment, arm defaults on loan repayment Details
8Stressed power assets: Smaller banks hit most by RBI’s revised note on NPAs Details
8Consultations on EVs with all stakeholders must before firming up any plan: CII Details
8L&T power arm bags orders in Middle East, Uttar Pradesh Details
You can also click on Newsclips for more
Details
For reference purposes the website carries here the following reports: 
8GE Company: General electric’s investors misjudged the company’s ability to navigate the transition and lost hundreds of billions Details
8ADB: Investor presentation June 2019 Details
8GHG mitigation policies in major emitting countries: An overview of recently adopted policies June 2019 Details
8CCI approves Acquisition of the electrical and automation business of Larsen & Toubro Limited by Schneider Electric India Private Limited and MacRitchie Investments Pte. Ltd Details
8What about emissions from an electric mobility future? Details
8How is India enabling the electric transition ? Details
8State-wise power procurement volume/cost/average cost per unit for FY 2018-19 Details
8ABB: ABB’s transformer and high-voltage technology essential part of the world’s largest super grid Details
8The Influence of changing hydropower potential on performance parameters of pumps in turbine mode: An analysis Details
8Five reasons gas is not a bridge to a safe climate:
 -Gas breaks the carbon budget
 -Coal-to-Gas switching doesn’t cut it
 -Low-cost renewables can displace coal and gas
 -Gas is not essential for grid reliability
 -New gas infrastructure locks in emissions Details

You can also click on Reports for more Details
For reference purposes the website carries here the following tenders: 
8Tender for Construction of 132/33kV Substation with SAS on turn-key basis Details
8Tender for supply of 245kV Current Transformers with Terminal connectors and Junction Boxes Details
8Tender for the supply of 7.2KV, 10KA, Polymeric Surge Suppressor Details
8Tender for Procurement of 110V 120AH battery set with stand and Accessories Details
8Tender for Repair of damaged/eroded portion of Spillway of Bay Details
8Supply, erection, testing & commissioning of 132/33kV substation Details
8Tender for manufacture, Galvanising, Testing & Running Supply of approx 5500 MT of 220 KV & 132 KV Transmission line Tower parts Details
8Design, Engineering, Manufacture, Supply, Testing and Commissioning of OPGW alongwith hardware & Accessories Details
8Tender for AMC for CHP Mechanical Maintenance Details
8Supply, Installation, Testing & Commissioning of Dry type Station & Unit Auxiliary Transformers Details
8Tender for Round the Clock Running Maintenance, Preventive Maintenance & Breakdown Maintenance of MAX DNA DCS control system Details
8Tender for Bi-Annual Maintenance Contract for attending emergency/breakdown maintenance work at various 220kV & 132kV Substations Details
8Tender for the work of Constructing 13.75km of HT ABC Details
8Tender for providing services for routine electrical maintenance work Details
8Supply, Erection, Testing and Commissioning of 2 X 2, LED Type Video Wall System for SCADA System Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8Asia set to power growth of global gas industry: IEA Details
8New NPA resolution norms to be issued within 3-4 days: Shaktikanta Das Details
8Solar and Wind Energy Policy Roundup from May 2019 Details
8Private thermal power plant utilisation rises in May on election demand growth Details
8Coal India may miss output target Details
8Yasasu sets a new model for waste to energy plant with Net Metering Details
8Non-stop power supply, sector’s sustainablitity main challenges before new govt Details
8Maharashtra to Procure 500 MW of Wind Power at a Ceiling Tariff of Rs2.52/kWh Details
8GIPCL commissions 75 MW solar power project in Gujarat Details
8May spot power price falls 29% to Rs 3.34 per unit Details
8CCI asks Schneider to reserve a part of L&T's capacity for third party firms Details
8China adds 5.2 GW of solar power capacity in Q1 Details
8GE lost billions by 'misjudging' renewables: Report Details
8Japan plans carbon emission cuts by promoting renewables, nuclear Details
8Bengaluru working on plan to buy 300 electric buses Details
8Nitin Gadkari for wider stakeholder talks on EV adoption Details
8Punjab in a fix over 9% annual growth of power subsidy bill Details
You can also click on Newsclips for more
Details
Project Name: Thermal Power Plant - FGD Addition
8Project Cost: 500 crores
8Project Description: A tender has been floated for the installation of a wet scrubber based (Limestone/Ammonia) FGD System in the 1400 MW (2x700 MW) Super Thermal Power complex. The owner has concluded the Qualification round. Company is going to open technical bid by mid of June. 
8Project Event: Award is expected in September, 2019
8Expenditure Approval: Q2:2017
8RFQ Date: Q3:2019
8Release Date: Q3:2019
8Start Date: 2021
8Completion Date: 2023
Click here for more details

Project Name: Thermal Power Station - FGD Addition
8Project Cost: 600 crores
8Project Description:  RFQ for a lump-sum turnkey contract for a wet flue gas desulphurisation system in the 1720 MW (7x210 MW + 1x250 MW) thermal power station involving design, engineering, manufacture, civil works with a new chimney, erection of all mechanical, C&I systems, electrical equipment, and systems, testing, commissioning, and performance guarantee testing of wet limestone FGD system has been floated and pre bid meeting has also been concluded. Technical evaluation of bid is expected by June end and soon it is going to open its price bid too.
8Project Event: Award of FGD is likely to be expected by Q4 2019
8Expenditure Approval: 2018
8RFQ Date: Q3:2019
8Release Date: Q3:2019
8Start Date: 2021
8Completion Date: 2023
Click here for more details
Details
 For reference purposes the website carries here the following reports:
8Triveni Turbines: Going from good Details
8A Survey on Microgrid Energy Management Considering Flexible Energy Sources Details
8GMR Warora Energy Limited: Rating downgraded Details
8DC Grid for Domestic Electrification in India: It is better than AC grid? Details
8What the full scope and meaning of a Change in law in the PPA: A complete analysis Details
8Are claims for compensation really admissible under a Change of Law in a PPA? Details
8Coal Power: Proponents have consistently opposed carbon tax but that stand may ultimately backfire Details
8Australian thermal coal vs. Indian coal: How big is the quality difference? Details
8NPTC: Moving away from coal? Details
8The Adani Group is betting big on renewables Details
8India has under-estimated the quantum of non-performing loans in the power sector. The figure can be staggering higher  Details
8 EOI out for energy storage services for up to 500 MW Details
8Coal India: Better grades and lower CoP drive performance Details
8Outage of generating units and transmission lines: Lots of them coming up Details
You can also click on Reports for more Details
For reference purposes the website carries here the following tenders: 
8Supply, Erection, Commissioning & Testing of Low Impedance Bus Bar Protection Relays Details
8Tender for procurement of 33kV current transformers Details
8Tender for procurement of 220kV Circuit breaker Details
8Tender for the work of detailed survey of various EHV lines Details
8Supply of Hydraulic Pumps for Clinker Grinder & FBAD Systems of Boiler Details
8Tender for Refurbishment of Rotor Blades Details
8Tender for Work of Counter Poise & Pipe type tower earthing for various EHV Lines Details
8Tender for Procurement of 33/11KV transformer Details
8Tender for Procurement of LT cables& Aerial bunched Cables Details
8Tender for Supply of Sulphuric Acid for TPP Details
8Tender for Procurement of LV components for HVAC & air washer system Details
8Tender for Overhauling and oil replacement of 100 MVA ICT at TPS Details
8Tender for supply of distribution transformers Details
8AMC services for maintenance of generators and its auxiliaries Details
8Supply, erection & commissioning of Pulse Jet Ventilation Module Details
8Tender for Rate contract for Electrical O&M Support service in shift operation,Preventive Maintenance including Opportunity based Shutdown/Breakdown Maint. and overhauling of Electrical equipments Details
8Tender for Evacuation of Ash from different filled up ash ponds of TPS Details
8Supply and installation of automatic solar operated radar type water level recorder Details
8Tender for Annual maintenance contract for servicing/maintenance of battery sets & chargers Details
8Tender for Work Contract for Annual Maintenance of 220/132/110KV Transmission Lines Details
8Tender for Procurement of 4000 Nos of Three phase four wire static meters Details
8Tender for Procurement of 500Nos. of return rollers Details
8Tender for Procurement of 11kV XLPE Flat Strip armoured AL Cable Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8India to be a large market for storage batteries in two years: Khurshed Daruvala Details
8India needs a solar manufacturing strategy Details
8EESL, Ahmedabad Municipal Corp enter 10-year deal to build EV infra Details
8Renewables sector awaits a multi-pronged policy to resume strong growth trajectory Details
8NTPC likely to generate higher operating profit in FY20: Fitch Ratings. Details
8Solar energy target a tough task in Chandigarh. Details
8Coal India targets 660 MT output, lines up Rs 10K cr capex in FY20. Details
8GMR Infra subsidiary pursues power discoms for early recovery of dues Details
8Mega power infra for KLIP Details
8Goa: Electricity regulator asks power dept to explain wrong solar bills Details
8Elections pulled down India’s solar power installations by a half in Jan-March 2019 Details
8Maharashtra: MSEDCL starts supplying solar power to farmers Details
8Telangana has become second-largest producer of solar power: Spl chief secy Details
8Global climate goal measures an 'enormous challenge', says Equinor Details
8Goldman Sachs and SSG in talks to buy RattanIndia Power bad loans Details
8Rs 8,000 cr NTPC-SJVN merger push likely in Modi govt’s 1st 100 days Details
8Centre seeks proposals for 5,000 electric buses Details
8Spot electricity price drops to Re 1 at power exchange on higher supply Details
8Hiccups in Tata-backed Resurgent Power’s bid to acquire Prayagraj Details
8Uttarakhand power transmission utility, IMP lock horns over malfunctioning transformers Details
8Need proactive policy to boost electric-powered public transport Details
You can also click on Newsclips for more
Details
For reference purposes the website carries here the following tenders: 
8Tender for Biennial contract for electrical and C&I cabling works Details
8Supply, Dismantling, Erecting, Testing and commissioning of 33kV outdoor type Vacuum Circuit Breaker Details
8Tender for Procurement of Cable Fault Locator Details
8Tender for Overhauling of Boiler pressure Parts Details
8Tender for laying of 33kV UG Cable (6.670 KM) Details
8Tender for laying of 33kV UG Cable (3.425 KM) Details
8Tender for laying of 33kV UG Cable Details
8Tender for Work contract for Comprehensive Annual Maintenance Contract for continuous ambient air quality monitoring station Details
8Tender for Work of boiler tube coating by wear resistant Tungsten carbide coating by HOVF process Details
8Tender for Procurement of critical spares of CT make-up Pump and Raw water in-plant Pump Details
8Tender for work of construction of 220kV transmission line Details
8Tender for Procurement of 11/0.4KV distribution transformers Details
8Tender for Breakdown maintenance of Air Pre Heater Details
8Supply, Installation, Testing and Commissioning of engine suitable for 1000KVA DG set Details
8Tender for the balance work of shifting of 220KV D/C line Details
8Tender for Operation, monitoring and maintenance works in the 11 KV Construction Power Supply system & LT power supply networks Details
8Design, Engineering, Manufacture, Supply, Erection, Supervision of Erection, Testing and Commissioning of Single Phase Generator Transformers Details
8Tender for Execution of Electromechanical works of Small Hydro Electric Project Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8Greenko gets $495 mn more from GIC, ADIA; reaches an enterprise value of $6 bln Details
870% of India's top 100 corporates are moving towards renewable energy Details
8Tariff for EV Charging in Chandigarh Set at Rs 4/kWh Details
8Mahindra Susten and Mitsui to co-invest in distributed solar power projects in India Details
8NTPC to piggyback ISA to expand solar footprint Details
8Increasing share of renewables in energy sector poses regulatory challenge: Moody's Details
8Short-term power price down 19% in April Details
8GE Power India wins contract worth Rs 738.3 crore Details
8Mahindra Susten, Mitsui to jointly develop solar power projects in India Details
8Underutilised funds: CERC plans to review PSDF norms Details
8India to maintain its level of thermal coal imports: Fitch Details
8Coal supply improved, govt steps eased power plants’ stress Details
8Solar power firms in doldrums in Telangana on Rs 2,000 crore govt dues Details
8Fund manager Glennmont raises 850 mln euros for clean energy investment Details
8Increased power supplies keep prices under control: IndRaIncreased power supplies keep prices under control: IndRa Details
You can also click on Newsclips for more
Details
For reference purposes the website carries here the following tenders: 
8Tender for Operation and Maintenance of Hydro-Mechanical Equipments Details
8Tender for service contract for maintenance and overhauling of valves and heat exchangers Details
8Tender for Job Contract for Overhauling of Milling area equipments Details
8Tender for Contract for repairing of faulty thyrister block Details
8Tender for Procurement of Vertical Turbine Pump along with Motor and starter Details
8Tender for Procurement of Boiler Circulating Water Pump/ Motor spares Details
8Tender for Procurement of spares of 200NB segregating slide valves for Ash Handling Details
8Tender for repair of single phase generator transformer Details
8Tender for Shifting of transformers, HT and LT poles and lines Details
8Supply, Installation and commissioning of online coal analyser Details
8Tender for Procurement of electrical actuator Details
8Tender for Supply of HT fasteners Details
8Tender for Procurement of Spare Part of Power Cable Reeling Drum and Control Cable reeling Drum for stacker reclaimer installed at CHP Details
8Tender for increasing capacity at 132kV substation Details
8Tender for Transportation of Coal via Rail-Cum-Road (RCR) mode from Mine to Plant Details
8Annual rate contract (ARC) of Turbo Generator (TG) associates and its auxiliaries equipments Details
8Tender for Day to day operation & maintenance of Pumps and Valves Details
8Supply, erection, testing and commissioning of 245 KV, 3150 A spring operated SF6 circuit breaker Details
8Tender for Transportation of ROM Coal from Mine to Plant through RCR Mode Details
8Tender for strengthening of single conductor by twin conductor Details
8Tender for Establishment of 33 kV & 22 kV bays at various Substations Details
8Tender for the Work of supply ,installation and commissioning of portable & programmable battery charger system Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8PFC will continue its focus on renewable biz: Rajeev Sharma Details
8We are examining the suggestion to merge Renewable and Power Ministries: RK Singh Details
8Odisha seeks help for power work in Puri Details
8Modi 2.0 can reduce power sector stress: These energy reforms must top priority list Details
8N-power generation advantages highlighted Details
8Appellate Tribunal for Electricity rules in favour of Adani Group Details
8BJP seeks Guv's intervention as power cuts leave Jammu residents fuming Details
8Why Punjab consumers pay 20% more than power regulator-fixed tariff Details
8TPDDL claims Rs 7 cr dues from NMC, DSIIDC Details
8Coal India production declines 1.1% to 46.59 MT in May Details
8Power producers want CIL to step up coal supply through rail wagons to reduce transportation cost Details
8SCCL aims for Rs 50,000 crore turnover Details
8Adani Green Energy bonds subscribed three times Details
8OPINION: Will Modi spur global inaction into action on climate-change? Details
8R K Singh takes charge as minister with focus on 24X7 Power for All Details
8Visakhapatnam plans e-vehicles for city to fight climate change Details
8With $51m raised, Ather plans new Scooter plant and charging infra Details
8GE says French plant set for layoffs will not close down Details
8Madhya Pradesh: Discoms seek power tariff hike, domestic users to be worst hit Details
8Gujarat: Essar to pay penalty in tranches, others in one go Details
8Panaji: Quelossim locals object power tariff hike move Details
You can also click on Newsclips for more
Details