All content in this website is sourced legitimately

archiveForm.jsp
Archives
All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.
Year: Month:

Oct 2018
Oct 22 : Coal based power generation will remain in demand

Domestic coal supply to the power plants has grown to double digits(11%) since July 2017.
8Since, July 2017 coal-based power generation has increased by 5% which is higher than conventional power generation growth of 4%.
8A generation capacity of 8710 MW has been commissioned in 2017-18 which shows uprising specific consumption of coal.
8Coal imports to increase by at least 15-20 MT in FY19.
Click on Reports for more.
  Details

Oct 22 : An emission control equipment coming ahead: RFQs for supply of FGD by the end of Oct, 2018

Project Name: Thermal Power Station - FGD Addition
8Project Cost: 500 crores
8Project Description: The power generating company along with DPR consultant is carrying out the detailed project activities for installation of a wet flue gas desulphurization system at its 1000 MW unit thermal power complex. A pre-feasibility report has already been prepared. Further bids are expected soon.
8Project Event: RFQ for design, engineering, supply, erection, and commissioning of a wet FGD system is expected by the end of October 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: 26/Oct/2018
8Release Date: 28/Oct/2018
8Start Date: Q3:2019
8Completion Date: Q1:2021
Click here for more details
  Details

Oct 22 : Coal power plants face a double whammy

The specific challenge in transporting coal from mines to demand centers and lack of availability is working into the power sector in two insidious ways.
8In Maharashtra, for example, the state genco's 10GW owned coal generation capacity is operating just at 50-60% PLF.
8Low PLF is forcing the state discom to purchase power from the exchange.
8Power exchange prices have been doubled up in September due to lack of coal in merchant plants, forcing discoms to pay higher.
8This state of affairs has extended to other states as well.
Click on Reports for more.
  Details

Oct 22 : A Greenfield Hydro-power plant: Get the latest report

Project Name: Greenfield Hydroelectric Power Project
8Project Cost: 810 crores
8Project Description: The civil package contractor is undertaking the removal of slide deposit in the desilting tank area for owner's 84 MW greenfield hydroelectric power station. Moreover, open excavation of the diversion channel is in progress. The H&M package contractor has signed a contract agreement on September 2018. Mobilization of hydro-mechanical equipment is to start by the next month. Further bids are expected soon.
8Project Event: RFQ for the erection of hydro-mechanical equipment is expected by December 2018.
8Expenditure Approval: Oct/2017
8RFQ Date: Dec/2018
8Release Date: Dec/2018
8Start Date: Q2:2018
8Completion Date: Q4:2021
Click here for more details
  Details

Oct 18 : Download Tenders and Newsclips

For reference purposes the website carries here the following tenders: 
8Annual contract for repair / reconditioning of various components installed at Ash Handling Plant Details
8Annual contract for repair/ reconditioning of valves Details
8Tender for Supply of H.T. fasteners Details
8Supply, Installation Testing and Commissioning of 11 KV Medium Voltage Covered Conductor Details
8Tender for supply of 11 KV 36 KN Strain disc hardwares suitable Details
8Tender for Second circuit stringing of 220 kV line Details
8Tender for The work of replacement of damaged /broken disc Insulators Details
8Tender for Annual Rate Contract for work of attending emergency breakdown & shutdown work on 220/132 kV EHV lines Details
8Tender for Supply of 9000 nos. 8.00m PSC poles Details
8Tender for Replacement of conductor, H/W & Insulators of 66 kv line Details
8Tender for Procurement of Spares of various sizes Control valves Details
8Tender for Construction of Misc. Civil works at 220kv S/S Details
8Tender for Preventive maintenance works of Main boiler Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips: 
8Coal shortage hits power sector again; how India can get its production right Details
8A sound policy regarding electric vehicles can be a game changer Details
8NTPC prepares war chest to bid for stressed assets; shortlists 8-9 projects Details
8Andhra Pradesh conserving power worth Rs 1,000 cr annually by energy efficiency Details
8ABB wins Rs 115-crore order to sell transformers to Indian Railways Details
8Can the CESC demerger unlock value for investors? Details
8Karna CM writes to Goyal on coal shortage in thermal plants Details
8EDF says protests could hit its coal power plants until 2019 Details
8New research punctures electric cars' greenhouse gas claims Details
8U.S. greenhouse emissions fell in 2017 as coal plants shut Details
8UK's Contour Global in talks to buy Iberdrola's solar power plant Details
8Siemens may have to share big Iraq power contract with GE Details
8How far away are we from commercial fusion energy? Details
You can also click on Newsclips for more
  Details

Oct 17 : Supply and erection of a wet FGD in a thermal power station: RFQs ahead

Project Name: Thermal Power Station: FGD Addition
8Project Cost: 308 crores
8Project Description: The power generating company along with DPR consultant is carrying out the detailed project activities for installation of a wet flue gas desulphurization system at its 500 MW expansion unit thermal power complex. A pre-feasibility report has already been prepared. Further bids are expected soon.
8Project Event: RFQ for design, engineering, supply, erection, and commissioning of a wet FGD system is expected by the end of October 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: 26/Oct/2018
8Release Date: 28/Oct/2018
8Start Date: Q3:2019
8Completion Date: Q1:2021
Click here for more details
  Details

Oct 17 : A Chimney package for FGD is in pipeline: RFQs in Nov, 2018

Project Name: Thermal Power Station: Chimney Package for FGD
8Project Cost: 110 crores
8Project Description: Promoter is planning to come out with a bid for chimney package for installation of FGD in the 3000 MW thermal power station. An IFB for limestone handling, crushing and gypsum storage package for the FGD system bids have been floated. Further bids are expected soon.
8Project Event: RFQ for the design and construction of RCC chimney package for implementation of an FGD is expected by November 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: Nov/2018
8Release Date: Nov/2018
8Start Date: Q3:2019
8Completion Date: 2021
Click here for more details
  Details

Oct 17 : Download Tenders and Newsclips

For reference purposes the website carries here the following tenders: 
8Design, Supply, Erection & Commissioning of Screw Air Compressor Details
8Supply, laying, testing and commissioning of 220KV cable system on turnkey basis Details
8Supply & erection work of DC new Tower Details
8Tender for the work of Erection of 66 KV D/C LILO line Details
8Tender for Procurement of LT AC 3-phase, 4-Wire CT operated Static, DLMS Compliant, Energy Meters Details
8Tender for work of replacement of existing old control and relay panel Details
8Tender for work of Stub-Strengthening of heavily-rusted Tower Details
8Tender for Supply of Boiler Tube Shield  Details
8Tender for Procurement of knife edge Gate Valve Details
8Tender for supply of 11 KV 30 KN Strain disc hardwares Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8Maharashtra cabinet nod for 1 lakh solar pumps at Rs 3,435 crore Details
8Bhushan Power lenders are said to back JSW’s $2.7 billion offer Details
8Magenta Power updates EV charging stations with new billing meters, to expand chargers to more highways Details
8Edelweiss-backed fund buys Essel Infra’s power assets for 6,000 cr Details
8SJVN pays total dividend of Rs 864.56 cr for 2017-18 Details
8India will add 8.5-GW renewable energy in FY19, says ICRA Details
8First stubble-to-coal plant misses deadline Details
8Coal scam: Court allows Naveen Jindal to travel abroad Details
8After four decades, Badarpur thermal plant shut for good Details
8Tangedco breathes easy as imported coal arrives at port Details
8Centre, states must cooperate in improving coal production, supply: Goyal Details
You can also click on Newsclips for more
  Details

Oct 17 : Hydro PSU forays into super critical power

A hydro-based public sector power company is foraying into greenfield supercritical thermal power projects.
8All the statutory clearances have been applied for.
8Investment approval has also been granted.
8The project, however, has been stuck at the CCEA approval stage for now
Click on details to know the fact behind.
  Details

Oct 16 : A thermal power maintenance project: RFQs coming ahead

Project Name:  Thermal Power Station Maintenance Project
Project Cost: 8 crores
Project Description: Promoter has planned a 20- day scheduled annual overhaul in the 1500 MW thermal power station. The major scope of work includes boiler inspection, checking of boiler pressure parts and replacement of basket for the regenerative air preheater. A bid is expected soon.
Project Event: RFQ for the required overhauling works is expected by the end of October 2018.
Click here for more details
  Details

Oct 16 : Islanding Scheme is coming up in 2x210 MW IB Thermal Power Station: A boon in the transmission network

Islanding schemes are implemented to isolate the healthy subsystems following a large-scale disturbance.
8The new system will help out under contingency conditions that will prevent from total block out by avoiding the effect of cascade tripping of all generating stations in the power system.
8Also, fast restoration of supply can be achieved.
8Various methodology for islanding scheme is proposed in the OPGC's  2x210 MW operational IB thermal power plant in Odisha and for 2x660 MW expansion project which is under construction.
Click on the Reports to know more.
  Details

Oct 16 : Domestic coal shortage still pertains in the power plants

The major coal producers CIL and SCCL cumulative reported a less production of coal in Q3 2018.
8The supply chain issues due to inadequate rail-connectivity for coal evacuation and rake availability continues to be the major factor impacting the availability of coal.
8The scarcity of coal has compelled the merchant to raise the power tariffs.
 Click on Reports to find out more.
  Details

Oct 16 : Imported coal will continue to remain in demand in the power sector

Coal imports grew by 14% during the past months at 95.2 MT.
8Australia, South Africa and Indonesia are the major countries supplying imported coal.
8Not only the IPPs, but captive units under steel and cement sectors use thermal coal as feedstock and coking coal as raw material are major drivers of demand for imported coal.
8Coal import trend is expected to rise as power, cement, and steel industry are expected to witness improvement in demand and capacity utilization.
Click on Reports for more.
  Details

Oct 16 : Download Tenders and Newsclips

For reference purposes the website carries here the following tenders: 
8Design, Engineering, Manufacturing, Supply, Installation and Commissioning of Grid Connected 70 MW Solar PV Project Details
8Annual Contract for the operation and maintenance work of 400 KV/220 KV/33 KV Switchyard Details
8Tender for Maintenance work of Heavy Mobile Equipment Details
8Design, Manufacturing and Supply of Power Transformers Details
8Procurement, Erection, Testing & Commissioning of 245 KV Capacitor Voltage Transformers Details
8Procurement, Erection, Testing & Commissioning of 400 KV Current Transformer Details
8Annual Contract for maintenance of wagon tipplers & Associated Equipments Details
8Annual Contract for maintenance of Conveyor System Details
8Tender for Procurement of Vertical Turbine CT Drain Pumps and Drain Sump Pump Details
8Tender for Chemical Treatment of Cooling Water Details
8Tender for the work of fabrication & Installation of Model Parts for 3D Comprehensive Model for Spillway and Power Intake Details
8Annual Rate Contract (ARC) for Supply of FR Grade Conveyor Belt Details
8Tender for Annual maintenance of Ash pond Details
8Tender for the Supply of Relay Details
8Tender for procurement of ACSR Raccoon Conductor Details
8Tender for the supply of square type coal nozzle tip including hard facing Details
8Tender for procurement of 11 KV 45 KN Polymer Composite (B&S) Disc Insulators Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8Tapping sunshine: Tata Power aims to grow solar rooftop business four-times in four years Details
8Sajjan Jindal keen to buy out stressed hydroelectric plants Details
8Sterlite Power expects renewable energy to boost private participation as tussle over project allocations continues Details
8Saudi Arabia, BP eye major Indian solar play Details
8E-vehicle charging points in Bengaluru high-rises? Details
8Sterlite Power commissions 3,000 cr project in Jammu and Kashmir Details
8India to achieve 76% of renewable energy target by 2022: Wood Mackenzie Details
8MCL would achieve coal output target of 162.6 mt: Piyush Goyal Details
8India coal import forecast raised by 6MT in 2018 on local supply crunch Details
8Coal crisis intensifies with rising demand, poor evacuation at ports Details
8HSBC UK Pension Scheme to invest 250 mln pounds in wind and solar Details
8Spain's Iberdrola sells British power assets to Drax for 800 million euros Details
8States to get Rs 100 Cr award for being efficient under Saubhagaya scheme Details
8Power demand matches summer’s as temp rises in Mumbai Details
8CIL says supplies up 9%; Power Co's report low stock Details
You can also click on Newsclips for more
  Details

Oct 16 : A Greenfield Thermal Power Project in Pipeline

Owner plans to set up a greenfield super-critical thermal power project.
8Currently, EPC bidding process is going on.
8The long-term coal linkage has been approved.
8Project is suffered due to delay in investment approval from the PIB.
8A pre-bid meeting was held. Major EPC players have participated in the process.
8Piling works are going on at the site location.
8Project Cost: 15010 crores
8Project Event: RFQ for the township package is expected by November 2018.
RFQ for the design, engineering, procurement, construction and commissioning of merry-go-round rail track system is expected by November 2018.
8Expenditure Approval: Q4:2018
8RFQ Date: Nov/2018
8Release Date: Nov/2018
8Start Date: 2019
8Completion Date: 2024
Click here for more details
  Details

Oct 15 : Download Tenders and Newsclips

For reference purposes the website carries here the following tenders: 
8Supply, Installation, Testing and Commissioning of Energy Management System (EMS) Details
8Tender for Erection (Mechanical/Instrumentation) & Commissioning of ETP & STP Details
8Tender for Procurement of ST Cooling Tower Fill Pack and Drift Eliminator Details
8Annual rate contract of Dozer on hire for coal stockyard management Details
8Tender for Overhauling of ID fan & Coal Pipe Details
8Tender for Running and Breakdown Maintenance of ESP Details
8Tender for Requirement of Various types and sizes of Lugs & Cable Glands Details
8Tender for work of renovation of broken / rusted leg earthing to the towers of various Lines Details
8Tender for the Work of construction of 1X132kV End Bay Details
8Supply & Delivery of FRP Blades with Hub Assembly Details
8Supply, Installation and Commissioning of 60 kw roof top solar Plant Details
8Supply of Governor Main distribution Valve Details
8Tender for Overhauling of boiler pressure parts Details
8Supply and drawing of 33kV ACSR Conductor Details
8Tender for Supply of Earthing Coil set Details
8Supply of LT Guy Grip & Thimble Details
8Supply, Erection and Commissioning of 25 meter high mast Lighting System Details
8Supply of 245KV Potential Transformer Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8Ex Ostro Energy CEO, COO to start renewable energy firm. Details
8Power plants wants PFC, REC to fund green compliance Details
8Delhi court grants bail to Naveen Jindal, others in coal scam case Details
8RP Sanjiv Goenka's CESC alters demerger plans as WBERC plays spoilsport Details
8JSW Energy puts solar power plans on backburner over policy uncertainties Details
8India needs to make a smooth and viable transition from coal, says IPCC report Details
8EESL inks MoU with DoP for distribution of energy-efficient appliances Details
8Govt to give priority to state power producers for coal supply; pvt plants in lurch Details
8Getting clearances major hindrance for hydro projects: Arunachal Pradesh CM Pema Khandu Details
8Jaiprakash, RKM, 5 others bag 1,900 MW power supply deals Details
8Musk rejoices as Tesla’s Model 3 passes 1,00,000 units produced mark Details
8Under pilot project, 1.2 Lakh houses in Tamil Nadu to get smart meters Details
8Gurugram asks EESL for 18,000 more street lights for dark stretches Details
8Maharashtra CM to inaugurate three schemes of state power utility Details
8TN plans to construct Anamalayar hydro dam under 60-yr old PAP Details
8Gujarat moves SC to ensure power plans not disrupted Details
8Adani Electricity offers subsidised tariff for Navratri, Durga Puja pandals Details
You can also click on Newsclips for more
  Details

Oct 15 : Dismantling of a old thermal power station: RFQs for the services expected in Q1, 2019

Project Name: Thermal Power Plant - Dismantling Project  
8Project Cost: 210 crores
8Project Description: The Supreme Court of India mandated to shut down the owner's 850 MW operational thermal power plant with the commissioning of 400/220 kV sub-station. The sub-station will take the load off the TPS. The high-level committee of the owner is in discussion to dismantle the whole plant. Moreover, plans to implement a solar PV plant is still under a shadow. Further bids are expected soon.
8Project Event: RFQ for dismantling services of various equipment is expected by the Q1 2019.
8Expenditure Approval: Q4:2017
8RFQ Date: Q1:2019
8Release Date: Q1:2019
8Start Date: Q3:2019
8Completion Date: Q3:2020
Click here for more details
  Details

Oct 15 : Greenfield hydel power project delays due to pending TEC

Owner along with an EIA consultant was accorded the environmental clearance in a 105 MW greenfield hydroelectric power project.
8The project is getting delayed due to pending techno-economic clearance from the CEA.
8The forest clearance is also outstanding at the state forest department.
8The project has been renamed due to protests among the local.
8Pre-construction activities are yet to start.
8Further RFQs are expected soon.
8Project Cost: 1150 crores
8Project Event: RFQ for supply and erection of civil works and H&M works are expected by the Q1 2019.
8Expenditure Approval: Q1:2019
8RFQ Date: Q1:2019
8Release Date: Q1:2019
8Start Date: 2020
8Completion Date: 2025
Click here for more details
  Details

Oct 12 : BHEL muscled out in an FGD contract: Know more

Owner along with an EPC contractor is carrying out the mechanical completion activities in a 660 MW super-critical brownfield thermal power complex at the existing 1200 MW facility.
8Boiler light up is expected in November 2018.
8Tractebel Engineering Pvt Ltd has carried out the project engineering consultant works for implementation of an FGD.
8The pre-bid meeting for the FGD was held on September 2018. 
8Major EPC contenders have been shortlisted in the technical bid.
8However, BHEL failed to qualify the techno-commercial part of the bid.
8A price bid is expected soon.
8Project Cost: 9450 crores
8Project Event: RFQ for the price bid of the shortlisted contenders is expected by November 2018.
8Expenditure Approval: 2014
8RFQ Date: Nov/2018
8Release Date: Nov/2018
8Start Date: 31/Dec/2014
8Completion Date: Dec/2018
Click here for more information
  Details

Oct 12 : Work Contract for LT motors at CHP area in a thermal power station

Owner plans a work contract for LT motors in an 840 MW thermal power station.
8Click on details to know the key contacts   Details

Oct 12 : Civil works and construction of RCC chimney for an FGD is coming: RFQs in Nov, 2018

Project Name: Thermal Power Station - Installation of FGD
8Project Cost: 1050 crores
8Project Description: A JV company is evaluating pre-qualification bids of an EoI for installation of a wet limestone based flue gas desulphurization main package in a 1200 MW thermal power station. Also, the owner is on the lookout for financial institutions to fund the project. Further bids are expected soon.
8Project Event: RFQ for the civil works and design & construction of RCC chimney for implementation of wet limestone-based FGD is expected by November 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: Nov/2018
8Release Date: Nov/2018
8Start Date: Q2:2020
8Completion Date: Q3:2022
Click here for more information
  Details

Oct 12 : NTPC & PFC: What does it look like from the other side

There is always the other side to the picture on NTPC and PFC, very different from how we see them.
8There is a perception that NTPC has a history of brutal evictions for the construction of its power plants and coal mines.
8Virtually all of the company’s coal plants violate India’s air pollution standards and the ash residue from its power stations contaminates local water supplies, putting enormous health burdens on communities living nearby.
8Its safety record is also abominable as evidenced in 2017, when an explosion at one of NTPC’s plants killed 43 people and injured over 100 more.
8The other company is Power Finance Corporation.  Under the control of the Ministry of Power, PFC sets up shell companies to finance, plan and facilitate so-called “Ultra Mega” coal power projects in India. These shell companies acquire the necessary land, obtain permits and financing for the projects that are then sold to other power companies in a bidding process. PFC was thus responsible for financing a large part of the Indian coal boom, which led to the tripling of India’s coal-fired capacity between 2007 and 2017.
8A 2017 report by India’s Comptroller and Auditor General (CAG) states that PFC’s lending to these coal projects was not properly vetted.
8As a consequence, PFC is now burdened with non-performing loans, which were sunk into stranded coal assets. PFC nonetheless currently still has 8,000 MW of new coal projects under development.
 Click on Reports for more   Details

Oct 12 : Global warming: What kind of disruptions to expect?

The global average decarbonisation rate is less than half of what is needed.
8So where does this leave us?
8The gaps between current progress, the Paris Agreement’s national targets and the two degrees global goal indicate the potential for major disruptions
Read more on the subject   Details

Oct 12 : LNJ Power Ventures Ltd: A lot of trouble

LNJ Power Ventures Limited 20 MW wind power project located in Jaisalmer, Rajasthan sems to have run into trouble
8And it is not just sub-par generation that is troubling the unit
8Know more on why the O&M subcontractor is facing an uphill task as well
Find out more   Details

Oct 12 : Coal India: Capex flows

Rs 17,000 crore of capex is envisaged for 2018-19 for Coal India and NLCIL
8The capex is low in progressing as of now
8But it is likely to pick up speed as the year flows by
8Also get the data on spot e-action rates and quantity.
8Know more on CIL's RFQ for linkages for IPPs without PPAs
Click on Reports for more     Details

Oct 12 : Massive power capacity coming up

A captive power plant is coming up
8Phase-I 217 MW
8Phase-II 168 MW Power generated
Click on Reports for more   Details

Oct 12 : Download Tenders and Newsclips

For reference purposes the website carries here the following tenders: 
8Supply, Installation, Erection, Testing & Commissioning of 11 Nos. 245KV Class Isolators Details
8Tender for supply of various size and type of steel material to power stations Details
8Tender for Drawing HT ABC and Pole erection in IPDS at various locations Details
8Tender for Supply of three Phase Relay Test Kit Details
8EOI for Electrical Power Supply Package for FGD (Flue Gas Desulphurization) System Details
8Tender for Erection of 33/11 KV Substation structure Details
8Tender for Round the clock Routine, Preventive and Breakdown Maintenance of complete 0.4 KV Switchgear & ESP System Details
8Tender for Supply of Sulphuric Acid for TPP Details
8Construction of 132/33 KV Substation with SAS on turn-key basis Details
8Tender for Construction of 1 No. T/F Plinth Details
8Supply of Complete Assembly of Conveying Air Blower & Spares Details
8Tender for Preventive and Breakdown Maintenance works of HP 803 Bowl Milling system Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8US announces measures to prevent nuclear technology exports to China Details
8Why bids for CESU Odisha have lit up the power sector Details
8Olectra-BYD to invest Rs 700 cr for electric buses in Uttarakhand Details
8JSW Energy eyes stressed hydro assets;to revive Kutehr project Details
8Chinese solar projects facing closure amid subsidy backlog: Govt report Details
8SECI’s manufacturing-linked solar bids put off, for fourth time Details
8India may miss its target to conduct 10 Gw wind auctions in FY19: Ind-Ra Details
8Hyderabad: New power plants to provide 10,000 jobs, says Telangana Genco's CMD Details
8No loss in skipping tender route for coal purchase: Tangedco Details
8Gujarat to seek SC stamp on rescue plan for power plants Details
8Government lists projects won by Anil Ambani under UPA's watch Details
8BMW ramps up investment in China to meet electric vehicle demand Details
8Discom blames coal companies for load shedding Details
8Expect higher coal imports this year: Care Ratings Details
You can also click on Newsclips for more
  Details

Oct 11 : Implementation of a De-NOx system is in pipeline: RFQs coming ahead

Project Name: Ultra Mega Thermal Power Project: Implementation of De-NOx
8Project Cost: 2450 crores
8Project Description: A subsidiary company is planning the implementation of a De-NOx abatement system at its existing 2400 MW ultra mega power plant. Currently, a bid for project engineering consultant has been floated for pre-order activities, detailed design, review engineering and all the systems required for the proposed De-NOx system. Further bids are expected soon.
8Project Event: RFQ for supply, transportation, construction and commissioning of a De-NOx system is expected by the end of October 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: 26/Oct/2018
8Release Date: 28/Oct/2018
8Start Date: 2020
8Completion Date: 2022
Click here for more information
  Details

Oct 11 : Annual Maintenance Contract for HT/LT motors in a thermal power station

Owner plans an AMC for HT/LT motors at the switchyard in a 500 MW thermal power station.
8Click on details to know the key contacts   Details

Oct 11 : Download Tenders and Newsclips

For reference purposes the website carries here the following tenders: 
8Supply, Installation, Erection, Testing and Commissioning of Current Transformer Details
8Design, Supply, Installation, Testing & commissioning of 132 kV, 2X15 MVAR Capacitor Banks Details
8Design, Supply, Installation, & commissioning of 800KWp solar roof top System Details
8Design, Supply, Installation, Testing & commissioning of 132 kV, 2X15 MVAR Capacitor Banks along with Associated HV Bays & civil works Details
8Tender for the work of Erection of 66kV H frame link line Details
8Tender for the work of Erection of 66kV Equipment, Structures, Control Wiring & Yard Lighting etc Details
8AMC of Station Lighting System Details
8AMC Services for Electrical Maintenance of Hydro Electric Project Details
8Procurement, Erection, Testing & Commissioning of 420 KV SF6 Circuit Breaker Details
8Tender for Construction of 132/33 KV GIS sub-station Details
8Tender for Construction of 132/33/11 KV GIS sub-station Details
8Tender for Supply of Stranded wire GI 7/3.15 mm Details
8Tender for Supply of HT and LT Stay Insulator Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8Tata Power among bidders in race for Odisha’s CESU Details
8Demand up, but power sector woes to continue Details
8Let’s keep the renewables story going Details
8Emission control: Banks wary of funding thermal power plants Details
8France's EDF wants to dominate electric vehicle charging market Details
8France's ASN to rule on EDF reactor lifespans by end 2020: ASN nominee Details
8Coal shortage hits aluminium units Details
8State power firms get priority as coal supplies worsen Details
8PTC India inks new pacts for 200 Mw power supply to Bangladesh for 15 years Details
8Indo-US nuclear deal helped fuel domestic power plants, gave India access to critical tech: Experts Details
8Maharashtra CM tries to delink load shedding from coal crisis Details
8Banks may not take a decision on stressed power plants by October 15 Details
8Bharat Forge, NTPC joint venture initiates liquidation under IBC Details
8Weaker solar radiation, poor ratings of discoms keep solar tariff above Rs 3/unit in UP Details
8Carbon sink' Bhutan counts cost of plans for green future Details
You can also click on Newsclips for more
  Details

Oct 11 : Supply of a new screw air compressor is coming up in a thermal power plant: RFQs in Nov, 201

Project Name: Thermal Power Plant: Renovation & Modernisation Project       
8Project Cost: 3 crores
8Project Description: National Thermal Power Corporation Limited is getting delayed in coming out with RFQs for the supply of a new screw air compressor in place of its existing old reciprocating instrument air compressor in the Stage-II plant in its 3000 MW thermal power complex due to decision pending at the Western Region headquarter of the owner. A further bid is expected soon.
8Project Event: RFQ for supply, erection, and commissioning of a new screw air compressor is expected by the November 2018, instead of May 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: Nov/2018
8Release Date: Nov/2018
8Start Date: Q1:2019
8Completion Date: Q2:2019
Click here for more information
  Details

Oct 10 : Requirement of a 16 MVA power transformer in a coal mining project: Know more

A major power company plans for the requirement of a power transformer at its ongoing coal mining project.
8Click on details to find out the key contacts.   Details

Oct 10 : Maintenance Contract in a hydro power station: RFQ in Oct, 2018

8Project Name: Hydroelectric Power Plant: Maintenance Contractor Project
8Project Cost: 3 crores
8Project Description: Owner is further getting delayed in coming out with bids for a biennial maintenance contract for electrical works and for the 400 kV switchyard and its associated system due to decision pending at owners hydro region headquarters in the 1000 MW hydropower station. Further bids are expected soon.
8Project Event: RFQ for an electrical maintenance job contract is expected by the end of October 2018
RFQ for maintenance job contract of 400 kV switchyard and it's associated system is expected by the end of October 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: 24/Oct/2018
8Release Date: 26/Oct/2018
8Start Date: Q1:2019
8Completion Date: Q1:2021
Click here for more information
  Details

Oct 10 : Installation of WFGD in a super-critical thermal power project: Latest progress report

Project Name: Super-Critical Thermal Power Plant: Installation of FGD
8Project Cost: 1450 crores
8Project Description: A subsidiary company is planning the installation of a wet flue gas desulphurisation (WFGD) system at its existing 1980 MW supercritical thermal power project. The feasibility study and report has been prepared by Tata Consulting Engineers. An EPC package bid is expected soon.
8Project Event: RFQ of an EPC package comprising the design, manufacture, transportation, supply, erection, and commisioning of a wet flue gas desulphurization (WFGD) system is expected by December 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: Dec/2018
8Release Date: Dec/2018
8Start Date: 2020
8Completion Date: 2023
Click here for more information
  Details

Oct 10 : Clean energy: "Catalytic" funding is the new innovation but will it ever take off?

That clean energy suffers from a funding deficit is now a well known fact
8Margins are thin and any disturbance, either by way of delay in payments or a hike in interest rates, can cause large scale disability.
8Indian lending institutions capacity to fund the sector is limited to a cap of around between $6-10 billion whereas the need is for around $15-20 billion a year to achieve India's clean energy targets by 2022.
8So new funds are needed, and what is now being mooted is "catalytic funding" that channels in private sector resources in an innovative manner
Click on Reports for more   Details

Oct 10 : Uttar Pradesh Power Corporation: Hazardous counter-party risk

Find out why Uttar Pradesh Power Corporation constitutes a high counter-party risk
8Payments against sales are meant to come in within 60 days but are delayed well beyond this stipulated period
8So much so that private sector power generators are currently in extreme distress
Click on Reports for more   Details

Oct 10 : Wind power: Generators run up overdue receivable of 230 days in Maharashtra

Which are the best states to be in, if you are a wind power generator.
8Some of the obvious choices may seem good on paper but not in reality
8In Maharashtra, for example, the overdue receivables now run to around 230 days as on August, 2018
Click on Reports for more   Details

Oct 10 : BF Utilities: Runs into trouble with original service provider

BF Utilities Ltd seems to have run into trouble with its original service provider for its wind farm
8This forced the company to start the facility with the help of another service provider, leading to some confusion
Click on Reports for more   Details

Oct 10 : New captive power plants coming up

The website carries here a set of new captive power plant opportunities
8Despite the bridging of the demand gap, power intensive companies need to set up captive power units, along with waste heat recovery units, to take care of their requirements
Click on Reports for more   Details

Oct 10 : Hydel power promoter: Are you looking for a deep pocketed investor?

If you have a hydel power project capable of a reasonable IRR and looking for funding, here is a multinational with a big bank balance you can tap
8The company has inserted a growth team in India
8And is actively looking for good renewable investments
Click on Reports for more     Details

Oct 10 : Download Tenders and Newsclips

For reference purposes the website carries here the following tenders: 
8EOI for Appointment of Project Engineering Consultant (PEC) for FGD implementation Details
8EOI for Appointment of Project Engineering Consultant (PEC) for Implementation of NOx abatement System Details
8EOI for FGD (Flue Gas Desulphurization) System Main Package at TPP Details
8Supply & Retrofitting of 630A ACBs Details
8Annual Maintenance Contract for LT Motors Details
8Annual Maintenance Contract for Hoist and EOT Cranes Details
8Procurement of 0.85 MMT of Import Coal for Power Plants Details
8Annual Maintenance Contract of Coal Mill, APH, ESP and Rotary parts of Boiler Details
8Tender for the supply of 100A 415V Rewireable Porcelain Fuse units Details
8Tender for the work of Drawal of 33 KV 400 Sq mm XLPE cable Details
8Annual Rate Contract for preventive / routine / breakdown maintenance of TG & its Auxiliaries Details
8Purchase of Spares for Replacement of Service Seal of 01 No. MIV at Power Station Details
8Rate Contract for Different maintenance jobs at Coal Conveying System Details
You can also click on Tenders for more
 For reference purposes the website carries here the following Newsclips:
 
8SFIO narrows on five IL&FS firms for fund diversion, mismanagement Details
 
8Rising electricity demand in India leading to costlier coal imports: ICRA Details
 
8Gujarat ideal destination for investment in Renewable Energy: Saurabhbhai Patel Details
 
8US keen to invest in India`s infra, port, solar sector development : OPIC Details
 
8Opinion | Solar alliance can match OPEC only if ground rules are modified Details
 
8Aluminium industry seeks immediate coal supplies to power up plants Details
 
8ReNew Power to quote tariffs sustainable in the long run: Chief Sumant Sinha Details
 
8Panel proposes relief for mega Rs 50,000 cr power projects Details
 
8Would like to invest in India's hydro power plants, says chief of Russia's sovereign wealth fund Details
 
8Chennai Central to get solar power panels, save Rs 1.5 crore per annum Details
 
You can also click on Newsclips for more
  Details

Oct 09 : ARC maintenance project: RFQs in Q1, 2019

Project Name: Thermal Power Project: Annual Rate Contract
8Project Cost: 4 crores
8Project Description: Promoter is planning to come out with an annual maintenance contract for the coal handling and ash handling plant in a 600 MW thermal power plant. The contract tenure will be for 12 months. A bid is expected soon.
8Project Event: RFQ for an annual rate maintenance contract for  the CHP and AHP is expected by the Q1 2019.
8Expenditure Approval: Q1:2018
8RFQ Date: Q1:2019
8Release Date: Q1:2019
8Start Date: Q3:2019
8Completion Date: Q3:2020
Click here for more information
  Details

Oct 09 : A Thermal power expansion project: Latest progress report

Project Name: Thermal Power Station Brownfield Project
8Project Cost: 5450 crores
8Project Description: The EPC contractor is carrying out the geotechnical investigations in the owner's super-critical 800 MW thermal power expansion project at its existing thermal power complex. Extension of validity of EC was granted. Further bids are expected soon.
8Project Event: RFQ for boiler pressure parts is expected by November 2018.
 RFQ for pile test, piling and pedestal works is expected by November 2018.
8Expenditure Approval: Q3:2017
8RFQ Date: Nov/2018
8Release Date: Nov/2018
8Start Date: Q3:2018
8Completion Date: 2023
Click here for more information
  Details

Oct 09 : Download Tenders and Newsclips

For reference purposes the website carries here the following tenders: 
8Tender for the work of replacement of 22/33kV Current Transformer Details
8Tender for Procurement of LT Power Cables for Power Station Details
8Tender for Supply of MS flat Details
8Supply of 1750 nos 11kV DROP OUT Fuse Details
8Tender for Electrical Overhaul works Details
8Annual Maintenance Contract for HT/LT Transformers Details
8Supply, Erection, Testing and Commissioning of 132KV Hybrid Modules including Civil works on turnkey basis Details
8Tender for the Work of Supply, Installation, Testing & Commissioning of Microprocessor Based MFM meters Details
8Tender for Raising of existing 66 KV SC Line Details
8Tender for Supply of Steel Cord Conveyor Belt with one Steel Breaker Details
8Supply, Erection and Commissioning of New Steam and Water Analysing System (SWAS) Details
8Procurement of 40 Nos. of Bottom discharge Hopper Wagons Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8Coal India, NLC India ink pact to set up JV for power generation Details
8Parts of Maharashtra to face load-shedding in festive season Details
8Daily average power price at record Rs 8.95/unit on IEX Details
8India lacks ecosystem for electric cars: Volkswagen official Details
8India has opportunity to develop more sustainable energy industry: IPCC report co-author Details
8Suzlon aims to reduce 40-50% of debt through asset monetisation by March Details
8Bionergy signs pact to acquire assets of Skeiron in Andhra, Karnataka Details
8L&T Construction bags orders worth Rs 1,881 crore Details
8NTPC signs Rs 5,000-crore term loan agreement with SBI Details
8Increase in power demand met by improved hydro and nuclear generation in August 2018: India Ratings Details
8BHEL bags Rs 2,900 cr orders from NTPC for emission control equipment Details
8Badarpur thermal power plant to shut down by October 15 Details
8Solar pumps, e-vehicles and artificial ponds top state’s green agenda Details
8Bioenergy set to grow fast in next five years Details
8KSEB starts measures to install rooftop solar panels Details
8No new coal expansion if India serious about keeping temp rise below 1.5 degrees: Greenpeace Details
You can also click on Newsclips for more
  Details

Oct 09 : China and India account for half of the growth in global energy demand

The world economy continues to grow, driven by increasing prosperity in the developing world.
8Over 80% of the expansion in world output is driven by emerging economies, with China and India accounting for over half of that expansion.
8China and India each account for around a quarter of the increase in world energy over the Outlook, although this masks sharply contrasting trends. 
8China’s energy growth slows significantly as it transitions to a more sustainable pattern of economic growth. In contrast, the slowing in India’s demand growth is less pronounced, underpinned by robust economic growth. As a result, by the second half of the Outlook, India emerges as the world’s largest growth market for energy.
8Africa continues to be weighed down by weak productivity, accounting for nearly half of the increase in global population but less than 10% of world GDP growth.
Click on Report for more
  Details

Oct 08 : An O&M contract for C&I equipment

Owner plans to come with an O&M contract of C&I equipment in a 440 MW thermal power station.
8Click in details to get key contacts.   Details

Oct 08 : Consultancy services for an FGD is ahead: RFQs in Dec, 2018

Project Name: Thermal Power Plant - FGD Addition
8Project Cost: 400 crores
8Project Description: A subsidiary company is getting delayed in coming out with RFQs for an FGD due to pending insolvency case with the NCLT for a 600 MW sub-critical thermal power complex. Currently, office buildings are being relocated for the creation of space for an FGD. Further bids are expected soon.
8Project Event: RFQ for pre-award consultancy services for preparation of a feasibility report is expected by the December 2018.
8Expenditure Approval: Q1:2019
8RFQ Date: Dec/2018
8Release Date: Dec/2018
8Start Date: 2020
8Completion Date: 2022
Click here for more information
  Details

Oct 08 : RFQ for E&M works bid is delayed in a hydel project: Know more

8Project Name: Greenfield Hydroelectric Power Project
8Project Cost: 1450 crores
8Project Description: Owner is getting delayed in coming out with an RFQ for electro-mechanical works due to the delay in preparation of the bid documents in a 150 MW greenfield hydroelectric plant. Major contenders have been shortlisted for the civil and H&M works bid. Further bids are expected soon.
8Project Event: RFQ for engineering, procurement, construction and commissioning of electro-mechanical works is expected by the end of October 2018, instead of September 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: 24/Oct/2018
8Release Date: 27/Oct/2018
8Start Date: Q2:2019
8Completion Date: Q4:2023
Click here for more information
  Details

Oct 08 : Download Tenders and Newsclips

For reference purposes the website carries here the following tenders: 
8Tender for Work of replacement of existing 160 kN glass insulator strings by 160 kN DC composite long rod insulators Details
8Tender for Work of construction of LILO on 132kV Line Details
8Tender for Supply of SF6 Gas Cylinder with Gas Details
8Tender for Repairing of Ventilation Duct System Details
8Tender for Construction of Earth Mat at 33/11 KV Sub/Station Details
8Tender for Installation of different electrical equipments at the Switch Yard Details
8Tender for Procurement of Seal Assembly for Pulveriser Hot Air Gate Details
8Tender for Procurement of 11KV vertical type Group operating switches Details
8ARC of Electrical System/ Equipments (HT/LT Switchgear, HT/LT Motors, Illumination System, Power and Control cables etc.) Details
8Tender for the procurement of Grinding Roller Tyres for Pulverized Coal Mill Details
8Tender for procurement of Iron and Steel materials Details
8Tender for supply of LED Light Fittings Details
8Tender for supply of 2000 Nos. of 9.00m RCC Square Section Poles Details
8Tender for supply of 9000 Nos. Of 8.00m PSC Poles Details
8Tender for supply of Synthetic washable Air inlet filter element Details
8Tender for Overhauling of HP Valve & Actuator Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8 Bioenergy leads growth in renewable energy consumption to 2023: IEA Details
8Massive societal changes needed to meet lower global warming target world needs: U.N. Details
8Ahead Of Polls, Over 12 Lakh Farmers To Get Free Electricity In Rajasthan Details
8Indian renewable energy sector will lead world in clean energy: Goyal Details
8Power producers book 87% CIL coal in first 10 days of bids Details
8Electric Vehicles' charging station pilot run conducted in Kolkata Details
8Power loom weavers in Guj demand cheap power, subsidy on lines of Maha Details
8Delhi CM Arvind Kejriwal writes to BJP CMs on power tariffs Details
8UP govt to start 2 power plants before 2019 Lok Sabha polls Details
8BHEL plans to roll out e-buses by March under new e-mobility portfolio Details
8Catalytic financing can scale up clean energy market: Report Details
8Rooftop solar panels on govt buildings from November Details
8Floating solar power plant at Irai in Maharashtra may be dropped Details
8Orange Renewable a done deal, Greenko in final talks to acquire Tanti Co Details
8RE Invest changes focus, no investments sought this time Details
8Spot power bids hit ceiling as states rush for purchase ahead of elections Details
8Deadly heatwaves could hit India: Climate change report Details
8India's coal import rises 35 per cent to 21.1 million tonnes in September Details
You can also click on Newsclips for more
  Details

Oct 05 : Major EPC players have been shortlisted for installation of an FGD unit: Find out who

Project Name: Thermal Power Project: Installation of FGD
8Project Cost: 866 crores
8Project Description: Owner is going on with final estimation for an EPC contract for Air Quality Control System including an FGD package in the 1320 MW thermal power station. Big EPC contractors have been shortlisted in the techno-commercial part of the bid. Further bids are expected soon.
8Project Event: RFQ for a letter of intent by the owner is expected by November 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: Nov/2018
8Release Date: Nov/2018
8Start Date: Q3:2019
8Completion Date: Q2:2021
Click here for more information
  Details

Oct 05 : Renovation of the fire protection system in a thermal power station: RFQs in Q1, 2019

Project Name: Thermal Power Project: Renovation & Modernisation
8Project Cost: 2 crores
8Project Description: Promoter is planning the renovation and modernization of the fire protection system in the 4000 MW thermal power station. The owner is going on with the bidding process for the renovation of the fire protection system in the Stage-I thermal power complex. A further bid is expected soon.
8Project Event: RFQ for the renovation of the fire protection system in the Stage-II is expected by the Q1 2019.
8Expenditure Approval: Q1:2018
8RFQ Date: Q1:2019
8Release Date: Q1:2019
8Start Date: Q3:2019
8Completion Date: Q1:2020
Click here for more information
  Details

Oct 05 : Download Tenders and Newsclips

For reference purposes the website carries here the following tenders: 
8Supply of Radar Type Level Measurement Transmitter Details
8Tender for Supply of MCC Panels Details
8Tender for Purchase of Vespel Pin (SP-21) Details
8Bi-Annual Maintenance Rate Contract for servicing & overhauling of OLTC of various capacities ICT & Power T/F Details
8Tender for Routine/Breakdown/Capital Maintenance works of Ash Handling Plant system Details
8Tender for Work of Dismantling, Shifting, Erection, and Commissioning of 22KV 5.4MVAr Capacitor Bank Details
8Tender for Supply, Installation, Commissioning and 5 years Comprehensive Maintenance of Grid Tied Rooftop Solar Power plant Details
8Design, Engineering, Manufacturing, Supply, Installation, testing & commissioning of Digital AVR System Details
8Bi-Annual Rate Contract(ARC) for maintenance of 300NB Ash slurry pipe lines Details
8Supply, Design, Installation, testing and commissioning of Rack & Pinion type Stack Elevator Details
8Tender for Overhauling of Boiler Non-pressure parts Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
821 IORA countries adopt the Delhi Declaration on Renewable Energy; to tie up with ISA members Details
8ISA receives $9 mn fund approval for 2019-20, finalises 5 new programmes Details
8PowerGrid sees 50,000-cr opportunity in green transmission corridors Details
8Himachal offering land at Re 1/sq.m for renewable projects: CM Details
8CESC considering business model for e-charging stations in Kolkata Details
8UDAY scheme can be model about massive rotation of capital: Michael Eckhart Details
8High demand pushes cost of power to hit a new high on exchange Details
8CR developing new station to boost WCL’s coal supply Details
8Wind turbines contribute to climate change: study Details
You can also click on Newsclips for more
  Details

Oct 04 : Civil works requirement for an FGD unit is ahead: RFQs in Nov, 2018

Project Name: Greenfield Super Thermal Power Project
8Project Cost: 13000 crores
8Project Description: The project proponent along with the steam generator contractor and turbine generator contractor is carrying out erection works in a 1320 MW super-critical greenfield thermal power plant. Recently, an EPC contract for installation of FGD has been awarded. The unit-1 is expected to get commissioned by Q1 2019. Further bids are expected soon.
8Project Event: RFQ for civil, structural, architectural and piling works for the FGD system is expected by November 2018.
8Expenditure Approval: Nov/2013
8RFQ Date: Nov/2018
8Release Date: Nov/2018
8Start Date: Oct/2014
8Completion Date: Q1:2019
Click here for more information
  Details

Oct 04 : Replacement of a new HP heater with an old one is coming: RFQs in Nov, 2018

Project Name: Thermal Power Station Stage-II Project
8Project Cost: 166 crores
8Project Description: Owner is going on with the bidding process for procurement of gearboxes for cooling tower fans in the 3000 MW thermal power complex. Also, the owner is preparing the bid document for replacement of the old high-pressure heater with a new one. Further RFQs are expected soon.
8Project Event: RFQ for a new high-pressure heater is expected by November 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: Nov/2018
8Release Date: Nov/2018
8Start Date: Q1:2019
8Completion Date: Q3:2019
Click here for more information
  Details

Oct 04 : Pending Long Term PPAs delaying 800 MW & 600 MW hydropower projects

A hydropower company is planning to install two hydropower projects with capacities of 800 MW and 600 MW each at a cost of Rs. 8000 crores and Rs. 6200 crores respectively.
8EC was granted in 2011.
8But, due to delay in signing of PPAs with the state government, the publication of a tender for the main plant packages are under a shadow.
8Where is the truth lying for such a delay?
Click on Reports for more.
  Details

Oct 04 : 2000 MW hydro project: Pending PPA a major concern

A major hydropower generation company is undertaking construction activities in a 2000 MW at a cost of Rs. 19000 crores hydel project.
8The project has got the environmental nod in 2003, but it has suffered several hindrances due to delay in transfer of forest land, local protests, slope failure in the powerhouse, and a case pending in NGT.
8One major concern is the pending long-term PPA with the state government.
Click on Reports for more.
  Details

Oct 04 : Download Tenders and Newsclips

For reference purposes the website carries here the following tenders: 
8Tender for Procurement of 1100V, 4x120 sqmm LT UG XLPE Alu. Power Cable Details
8Tender for the Work of restringing of existing Wolf Conductor of 132 kV line Details
8Tender for Purchase of 210 KN Disc Insulators Details
8Tender for the work of Repairing of both side damage RR drain with cement plastering on Penstock Details
8Tender for the Work of Erection of 66KV S/C line with ACSR Panther Conductor Details
8Tender for the Work of Erection of 66KV S/C Line on D/C Panther Tower with ACSR Panther Conductor Details
8Tender for Erection work of 66kV LILO at 220kV S/S Details
8Tender for Procurement of Spare Parts of L&T make Rotary Breaker for CHP Details
8Tender for Strengthening work of old 132KV S/C Line by converting to 66KV Details
8Tender for the Work of Shifting of 132KV D/C Line Details
8Annual Maintenance Contract for Emergency Breakdown work for 400 KV Lines Details
8Supply, Installation, testing and commissioning of Relay testing Kit Details
8Tender for manufacture, testing, supply and delivery of 3 Ph, 4 wire CT/PT operated, DLMS compliant 11 KV Bulk Consumer Meter Details
8Tender for the Procurement of bearings for Mill Gear Boxes of HP 803 Bowl Mills Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8Trump nominates coal, nuclear bailout supporter to U.S. power agency Details
8Country’s tallest hybrid concrete tubular Wind Turbine Generator commissioned by Suzlon Details
8IFC extends 1,000-crore loan to Aditya Birla Finance Details
8Honouring PM Modi is a fitting tribute to making our planet clean, says Sushma Swaraj Details
8Softbank’s Masayoshi Son promises free solar power Details
8Coal scam: Court imposes Rs 2 lakh fine on accused for violating bail condition Details
8OPINION: It’s action time for the International Solar Alliance Details
8IITs the new talent pool for electric vehicles sector Details
8States ask for subsidies, support, protection, right policies to boost clean energy in India Details
8Acme solar mulls putting 650 MW of capacity up for sale Details
8Indian Railways officials inspect wind energy project in Jaisalmer Details
8Mumbai: BEST plan to get 40 electric buses scrapped Details
8French solar company Neoen to raise 640 mln euros in IPO Details
8NLC India jumps on buyback plan Details
8Citibank warns of ‘wave of project bankruptcies’ in wind, solar Details
8Vladimir Putin arrives in India today: S-400 defence system, nuclear plant deal on cards Details
8Private players want committee on power transmission reconstituted Details
You can also click on Newsclips for more

  Details

Oct 03 : Download Tenders and Newsclips

For reference purposes the website carries here the following tenders: 
8Supply, Erection, Testing & Commissioning of Balance work of 220kV D/C line Details
8Supply of Nylon/Nylon Fiber conveyer belt Details
8Tender for Erection of Electrical Switch Yard of 33/11 KV Sub Station Details
8Tender for Supply of 1800mm belt width, 800KN/M, 4Ply Nylon / Nylon Conveyor Belt for Internal Coal Handling System Details
8Supply, Installation, Testing and Commissioning of new distribution panel Details
8Supply of Mill Classifier Outlet Box with Ceramic Lining for Coal Mills Details
8Supply, Erection, Testing & Commissioning of Balance work of 220kV D/C BECL - Botad line on tower with ACSR Zebra Conductor Details
8Construction of 12 Nos of 132/33 KV Transformer Bays on turnkey basis Details
8Tender for Dry Cooling System with Adiabatic Cooling System Details
8Design, Supply & Erection of FRP Walkway Platform in Cooling Tower Details
8Tender for Round the clock daily routine maintenance work of Main Boiler & its associated auxiliaries Details
8Tender for Supply of Single Tension Clamp Details
8Tender for Civil works for Construction of Capacitor Bank Details
8Tender for Supply of VRLA 760Ah Battery Bank Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8Gujarat invites tenders for 700 MW solar projects sans ceiling tariff Details
8Acute coal crisis in Maharashtra may lead to power shortage like last year Details
8World Bank to assist State in transforming health sub-centres Details
8SoftBank to offer free power from solar plants in India: Masayoshi Son Details
8Power tariff soars to a decade high of Rs 18/unit in spot market Details
8Record spot electricity prices may hold a silver lining for stressed power plants Details
8India-Led Solar Alliance Will Outshine OPEC, Says PM Modi Details
8Scientists to publish report on feasibility of climate targets on Oct. 8 Details
8Coal India posts 10.6% rise in H1FY19 production Details
8Poland's power from coal seen down at 50 percent by 2040 - government official Details
8Government asks CIL to supply rakes to power sector on priority basis Details
8SCCL produces 28.5 MT coal in first half of FY 2018-19 Details
8Indian solar industry can attract $70-80 bn investment: Modi Details
8Opinion | Power sector: going beyond insolvency Details
8Cost structure, reneged contracts cast shadow on solar programme Details
8Solar alliance must be agile, results-oriented Details
8For Make in India to succeed, we need to compete with Chinese imports Details
8PM Narendra Modi to open International Solar Alliance assembly Details
8Solar power plants of 620 MW capacity get operational at Bhadla park Details
8Climate goals mean Europe will overtake US in electric cars Details
You can also click on Newsclips for more
  Details

Oct 01 : R&M of ESP and ducts is coming up in a thermal power station

Owner plans R&M of ESP and associated ducts in a 500 MW thermal power station.
8A bid is expected soon.
Click on details for more
  Details

Oct 01 : A greenfield hydel project is getting delayed: RFQs for civil and H&M works expected in Q1, 2019

Project Name: Greenfield Hydroelectric Project
8Project Cost: 1662 crores
8Project Description: A subsidiary company is getting delayed in the process of the public hearing for a 180 MW (3x60 MW) greenfield hydroelectric project. The company needs to grant a fresh TOR for the EC. The final EIA report is getting prepared. Further bids are expected soon. 
8Project Event: RFQ for civil and hydromechanical works expected by the Q1 2019.
8Expenditure Approval: Q2:2019
8RFQ Date: Q1:2019
8Release Date: Q1:2019
8Start Date: 2020
8Completion Date: 2024
Click here for more information
  Details

Oct 01 : A Solar-Wind-Pumped Storage hybrid greenfield project is in pipeline: RFQs ahead

Project Name: Greenfield Integrated Renewable Energy: Standalone Pumped Storage Project
8Project Cost: 6124 crores
8Project Description: A wholly owned subsidiary company along with an EIA consultant is planning the implementation of a greenfield integrated renewable energy project comprising wind-solar-pumped storage hybrid power project. The pumped storage project envisages capacity of 1200 MW, solar plant of 1000 MW and wind plant of 550 MW. TOR has been amended in capacity from 1000 MW to 1200 MW. Collection of three season baseline data for preparation of draft EIA report is under process. Further bids are expected soon. 
8Project Event: RFQ for drilling and drifting activities for pre-construction activities is expected by the Q1 2019.
8Expenditure Approval: Q2:2019
8RFQ Date: Q1:2019
8Release Date: Q1:2019
8Start Date: 2020
8Completion Date: 2023
Click here for more information
  Details

Oct 01 : Download Tenders and Newsclips

For reference purposes the website carries here the following tenders: 
8Annual electrical maintenance contract of TPP Details
8Annual maintenance contract of Boiler and Auxiliaries Details
8Tender for Purchase of upper and lower rotating labyrinth of runner for Power Station Details
8Supply of Valves for Power Station Details
8Tender for FGD System Package Details
8Procurement, Erection, Testing & Commissioning of 400 KV Capacitor Voltage Transformers Details
8Supply, Installation& Commissioning of Level Monitoring System for Automation of Turbine Pit Pumps through Laser Sensor Details
8Tender for Purchase of Power Cable Details
8Tender for Civil package required for Transmission & Distribution Division Details
8Tender for Supply Of Earthing Pipe Details
8Supply and Delivery of Grinding Ring & Hi-Chrome Balls Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8Edelweiss arm eyes Rising Sun’s 140MW solar assets Details
8No takers for solar power? Power minister warns that states are not buying even at lowest rates! Details
8Kalpataru Power firms up after winning orders Details
81.5 million powermen to go on strike against 'privatisation' policies Details
8Indo-French nuclear deal: 10 years after its signing, power project yield little success Details
8Firms close to PM Modi to benefit from Electricity Act amendments, says Arvind Kejriwal Details
8Uttarakhand receives investment proposals worth whopping Rs 74,000 crore, confirms CM Trivendra Singh Rawat Details
8Coal India’s supply to power sector rises 12% to 197 MT in April-August Details
8Power tariff soars to a decade high of Rs 17.61/unit in spot market Details
8Saudi shelves $200 bln SoftBank Solar project: WSJ Details
8Gas-based power plants seek more gas from ONGC's Deepwater Wells Details
8ABB plans to make EV chargers in India by year-end Details
8PSPCL sells power, earns over Rs 400 cr in one month Details
8Long road ahead for Asian drivers revving up to go electric Details
8Exempt state from electricity tariff policy 2016, say farmers Details
8Tata power discom claims annual loss of Rs 150 crore due to power theft Details
8CIL to undertake "challenge" of 700 mn-tn output aim for FY'20 Details
8No 5% regulatory surcharge on FPPCA charges for Chandigarh: JERC Details
8Tamil Nadu sugar mills want to produce thermal power Details
8Make solar power structures mandatory in new buildings: HC Details
You can also click on Newsclips for more
  Details

<< Back