Rs. 1650 crore 765kV D/C transmission line project: RFQ ahead
May 09: 8The erection of the lattice tower is yet to be started.
8Application are pending at the Ministry of Highway for the transmission line.
8RFQ for the 765 kV GIS S/S works package is likely to be floated in July 2023.