Rs 287.59 crore hydroelectric project: Civil work package-1 in Q2, 2020
Jan 17: Project Name: Hydroelectric Greenfield Project
8Project Cost: Rs 287.59 crores
8Project Description: The promoter's 52 MW (2x26 MW) greenfield hydroelectric plant has been held up on account of a delay in signing of the power purchase agreement. EIA and EMP studies under progress by a consultant R.S Enviro Technology Pvt. Ltd. The preparation of DPR is also under progress. EC has not been granted yet . Forest clearance is pending at DFO. RFQ for civil work package-1 is likely to be floated in Q2 2020.