Greenfield Super Thermal Power Project: Bridge & Roof holds up progress
Apr 09:
Project Name: Greenfield Super Thermal Power Project 8Project Cost: 12000 crores 8Project Description: National Thermal Power Corporation Limited has successfully commissioned one of the 800 MW units out of 1600 MW (2x800 MW) Stage-1 greenfield super-critical thermal power plant at the Dongargaon village, situated in the Narsinghpur district of Madhya Pradesh. The BTG and ESP contractor BHEL is carrying the balance works in unit-2 (800 MW). The project is getting affected due to slow progress in works of the civil contractor, Bridge & Roof Company Limited. Meanwhile, ISGEC Heavy Engineering Ltd has been selected as an EPC contractor for the FGD. The design and drawing of the two FGDs needed are under approval. .Further bids are expected soon. 8Project Event: RFQ for the civil works for the FGD system is expected by June 2019. RFQ for the piling and pedestal works for the FGD system is expected by November 2018. Click here for more details, including key contacts