FGD installation: RFQ in Q3, 2018
Jun 11: 8Project Name: Thermal Power Station - Installation of FGD
8Project Cost: 750 crores
8Project Description: The owner has completed the site survey activities for installation of Wet Flue Gas Desulphurisation (WFGD). Preparation of feasibility report is ongoing. Tenders for the same is expected soon. The project requirements are: absorber system, gas to gas heat exchanger, spray headers and nozzles, mist eliminators & washing, agitators, quenching spray system, slurry re-circulation pumps, oxidation blower, gypsum bleed pumps, limestone grinding system, limestone slurry pumps, vacuum belt filter system, auxiliary absorbent slurry pumps with drive motor, piping, valves, auxiliary absorbent tanks, limestone storage tank, limestone silos, process water storage and pumping system, booster fans, ducting, dampers along with supports, slurry piping along with associated valves, low height wet chimney, FGD control room, dozers, wet ball mills, bucket elevator, gypsum dehydration, piles, spray headers, cooling water tank, process water tank, emergency slurry tank, among others.
8Project Event: RFQ for installation, supply, erection and commissioning of Wet Flue Gas Desulphurization unit is expected by the Q3 2018.
8Expenditure Approval: Q1:2018
8RFQ DateQ3:2018
8Release Date: Q3:2018
8Start Date: Q3:2019
8Completion Date: Q2:2021