Equipment required in a gas based power plant: RFQs in Oct, 2018
Sep 21: Project Name: Gas Power Station - Supply of Cooling Tower Fill Pack and Drift Eliminator
8Project Cost: 15 crores
8Project Description: Promoter is getting delayed in coming out a bid for supply of a cooling tower fill pack and a drifts eliminator system in a 720 MW gas power station due to non-approval from the C&M group committee. A Notice Inviting Tender is expected soon.
8Project Event: RFQ for the supply of a cooling tower fill pack and drifts eliminator system is expected by October 2018, instead of Sep 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: Oct/2018
8Release Date: Oct/2018
8Start Date: Dec/2018
8Completion Date: Q2:2019