A Ultra Super-critical thermal power plant is coming up: RFQs in Nov, 2018
Sep 20:
Project Name: Brownfield Thermal Power Project 8Project Cost: 8957 crores 8Project Description: The project proponent has been accorded environmental clearance in September 2018 for a 1600 MW brownfield ultra super-critical technology thermal power plant in the existing premises of old Thermal Power Station. The RFQs are getting delayed due to pending clearance from the state's high-level clearance committee. Further bids are expected soon. 8Project Event: RFQ for raw water, make-up water system, and associated civil works package are expected by November 2018, instead of June 2018. RFQ for the make-up water pipes package is expected by November 2018, instead of June 2018. 8Expenditure Approval: Q3:2018 8RFQ Date: Nov/2018 8Release Date: Nov/2018 8Start Date: 2019 8Completion Date: 2023 Click here for more information