Rs 170 crore Construction of 220 kV D/C T/L: Pooling station works package in Q4 2022
Sep 26: 8FC stage -2 has been granted by the DFO.
8The Engineering works are in progress for S/S works.
8Land acquisition has been completed for all locations and the fabrication works for the lattice tower are in progress.
8RFQ for the pooling station works package is likely to be floated in Q4 2022.