Rs 312 crore construction of 132 kV D/C Transmission Line: P/S works package in December 2022
Sep 22:
8The identification of private land has been completed and the acquisition of private land is in progress. 8Forest clearance stage-1 was pending at the DFO. 8Approval from PTCC, civil aviation, and defense is in the process. 8Sev Engineering works are in progress for the 132 kV GIS S/S. 8RFQ for the P/S is likely to be floated in December 2022. Click here for more details