Rs 325 crore Construction of 400 kV DC T/L: ACSR moose conductor works package in October 2022
Sep 21: 8NOC from the Inland Waterway Authority of India has been granted.
8Forest clearance stage -1 and stage 2 have been granted by the DFO.
8Engineering works are in progress for the S/S works.
8Approval from civil aviation, defense, and PTCC have been granted.
8Fabrication, erection and installation works for P/S is yet to be started.
8RFQ for the ACSR moose conductor works package is likely to be floated in October 2022.