Rs 550 crore greenfield hydroelectric power project: HM works package in Q4 2022
Sep 20: 8Forest clearance stage -1 has been accorded by the DFO but stage -2 is pending at the nodal office.
8EC for the same has been granted by the MoEF.
8Pre-bid meetings for the same are yet to be conducted for the civil works package.
8RFQ for the HM works package is likely to be floated in Q4 2022.