Rs 450 crore construction of 765 kV D/C Transmission Line: P/S works package in Q4 2022
Sep 19: 8A Land acquisitions have been completed. Erection and installation works are in progress for the S/S.
8Fabrication of the lattice tower has been completed and stringing works are yet to be started.
8RFQ for the P/S works package is likely to be floated in Q4 2022.