Sep 19: 8Erection of TG for units -1 and 2 have been completed and the PG test is yet to be conducted.
8 Stacker reclaimer works have been completed.
8The erection of the absorber system and ball mill work is in the advanced stage for completion.
8RFQ for the DeNOx system package is likely to be floated in October 2022.