Rs1800 crore greenfield hydroelectric project : HM works package in Q4 2022.
Sep 14: 8DPR is completed and it has been approved by the CEA.
8EC has been granted by the MOEF.
8After several meetings with State Government, the interstate boundary issue have been resolved.
8The civil works contractors have completed the mobilization of equipment at the site.
8Bidding is in progress for the civil works package(lot-2).
8RFQ for the HM works package is likely to be floated in Q4 2022.