Sep 12: 8Forest clearence stage-1 and stage-2 have been granted by DFO.
8Techno Electric has been selected for sub-station works.
8Approval from PTCC, Defence, and civil aviation is in progress.
8RFQ  for the P/S works is likely to be floated in October 2022.
 