Rs 500 crore hydel project: RFQ for the EIA consultants is likely to be floated by Q3 2020.
Feb 24:
Project Name: Greenfield Hydroelectric Power Project 8Project Cost: 550.00 crores 8Project Description: The owner is preparing the DPR for a greenfield 78 MW (3x29 MW) hydel power project located at Beri Nichali village in the Mandi district of Himachal Pradesh. Techno-economic clearance is pending. Further, the owner will look out for financial institutions to fund the project. Currently, geotechnical investigations are in process.RFQ for the EIA consultants is likely to be floated by Q3 2020. Further bids are expected soon. 8Project Event: RFQ for the EIA consultants is likely to be floated by Q3 2020. 8Expenditure Approval: 2020 8RFQ Date: Q3:2020 8Release Date: Q3:2020 8Start Date: 2021 8Completion Date: 2025 Click here for more details