All content in this website is sourced legitimately

Page No: 1
Rs 500 crore hydel project: RFQ for the EIA consultants is likely to be floated by Q3 2020.
Feb 24: Project Name: Greenfield Hydroelectric Power Project
8Project Cost: 550.00 crores
8Project Description: The owner is preparing the DPR for a greenfield 78 MW (3x29 MW) hydel power project located at Beri Nichali village in the Mandi district of Himachal Pradesh. Techno-economic clearance is pending. Further, the owner will look out for financial institutions to fund the project. Currently, geotechnical investigations are in process.RFQ for the EIA consultants is likely to be floated by Q3 2020. Further bids are expected soon. 
8Project EventRFQ for the EIA consultants is likely to be floated by Q3 2020.
8Expenditure Approval: 2020
8RFQ Date: Q3:2020
8Release Date: Q3:2020
8Start Date: 2021
8Completion Date: 2025
Click here for more details


**********************************

Back  |  Top