Feb 13:
Project Name: Greenfield Thermal Power Station Project Cost: Rs 31000 crore 8Project Event:RFQ for the supply, erection, installation, electrical, mechanical, testing and commissioning of coal handling plant (CHP) and ash handling plant (AHP) is likely to be floated in Q2 2020. RFQ for switchyard package for all units is likely to be floated in Q3 2020. Further RFQs are expected soon. 8Expenditure Approval: Q2: 2014 8RFQ Date: Q2:2020 8Release Date: Q2:2020 8Start Date: 2019 8Completion Date: 2024 Click here for more details