Jan 13:
Project Name: Greenfield Standalone Pump Storage Project 8Project Cost: 1347.63 crores 8Project Description: Pre- Feasibility report is completed and it is prepared by in house resources. Detailed topographical surveys and geotechnical investigations will be initiated during the feasibility studies. TOR is prepared and it is submitted. RFQ for EIA consultant is likely to be floated on Q2 2020. Further bids are expected soon. 8Project Event:RFQ for EIA consultant is likely to be floated on Q2 2020. 8Expenditure Approval: Q3:2020. 8RFQ Date: Q2:2020 8Release Date: Q2: 2020 8Start Date: 2021 8Completion Date: 2025 Click here for more details