RFQ for supply, testing, and commissioning of all boiler pressure parts is expected by  Q4 2019
Jul 08: Project Name: Thermal Power Station Brownfield Project
8Project Cost: 4500 crores
8Project Description: The EPC contractor has already floated the tenders for civil, structural and architectural works for main plant area and BOP including FGD,SCR
8Project Event: RFQ for supply, testing, and commissioning of all boiler pressure parts is expected by  Q4 2019.
8
Expenditure Approval:  Q3:2017       
8RFQ Date: Q4:2019
8Release Date:Q4:2019
8Start Date: 2020
8Completion Date: 2024