Software updates: Power projects
Jul 02: Project Description: Tenders for  Air pre heater tubes of stage -1 Boiler and supply of attachment and fins with soot blower spares for boiler have been floated
8
Project Event: RFQ for material handling, erection, testing and commissioning of the FGD system is expected by Nov 2019. RFQ for the main civil, piling, structural, and architectural works of the FGD system is expected by March 2020
8
Expenditure Approval: Feb 2005      
8RFQ Date: Q4:Nov 2019
8Release Date:Q4: Nov 2019
8Start Date: 2005
8Completion Date: 2022
Click here for more details
Project Name: Greenfield Thermal Power Project
8Project Cost: 4997.93Crores
8Project Description: The  DPR work of this project  is under process and it is expected to complete by Sept 2019.  
8
Project Event: RFQ for an EPC contractor package is expected by the Q4 2019.
8Expenditure Approval: Q2:2019         
8RFQ Date: Q4:2019
8Release Date:Q4:2019
8Start Date: Q3:2020
8Completion Date: Q4:2024
Click here for more details