Jul 02:
Project Description: Tenders for Air pre heater tubes of stage -1 Boiler and supply of attachment and fins with soot blower spares for boiler have been floated 8Project Event:RFQ for material handling, erection, testing and commissioning of the FGD system is expected by Nov 2019. RFQ for the main civil, piling, structural, and architectural works of the FGD system is expected by March 2020 8Expenditure Approval: Feb 2005 8RFQ Date: Q4:Nov 2019 8Release Date:Q4: Nov 2019 8Start Date: 2005 8Completion Date: 2022 Click here for more details Project Name: Greenfield Thermal Power Project 8Project Cost: 4997.93Crores 8Project Description: The DPR work of this project is under process and it is expected to complete by Sept 2019. 8Project Event:RFQ for an EPC contractor package is expected by the Q4 2019. 8Expenditure Approval: Q2:2019 8RFQ Date:Q4:2019 8Release Date:Q4:2019 8Start Date: Q3:2020 8Completion Date: Q4:2024 Click here for more details