Apr 12:
Project Name: Thermal Power Plant - Installation of FGD 8Project Cost: 400 crores 8Project Description: The DPR consultant NTPC is carrying out the detailed project report for implementation of 4 wet flue gas desulphurisation units in the UPRVUNL's thermal power station. Site surveys have been carried out. NTPC is busy in preparing the technical drawings and design of the WFGDs. As of now, NTPC has not confirmed whether to go for a gas-gas heater or a wet stack system in the FGD. 8Start Date: 2020 8Completion Date: 2022 Click here for more details